This procurement plan memo, dated April 2, 2026, is prepared by the Contracts Administration and Materials Management (CAMM) section for the Orange County Transportation Authority (OCTA) regarding RFP 250257 for towing and recovery services. The RFP seeks qualified contractors to provide towing and recovery services on an as-needed basis to support OCTA's operational requirements. The contract term is three (3) years, with an initial term budget of $435,000. The procurement plan does not specify explicit response dates, due dates, site visits, or bidder's conference information within the provided document.
The contract will be structured as a time and expense agreement with firm-fixed hourly rates, appropriate for the as-needed nature of these services. Evaluation criteria are weighted as follows: Qualifications of the Firm (30%), Work Plan (25%), Cost (25%), and Staffing/Project Organization (20%), with emphasis placed on demonstrated experience, equipment capability, and reliable response procedures to minimize safety risks and service disruption. The funding source is Local Measure M, and an independent cost estimate has been received. Prevailing wage requirements apply to this procurement. The internal evaluation team consists of Trevor Worthy, Casey Gladding, Kevin Levan, and Jason Morris. No Disadvantaged Business Enterprise (DBE) goal is noted in the plan.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Revised: 07/20/2010
INTEROFFICE MEMO
Date: April 2, 2026
To: Christine Herrera, Contracts Analyst, Maintenance Resource Management (MRM)
From: Trevor Worthy, Senior Contract Administrator, CAMM
Subject: Procurement Plan for Release, Selection and Award RFP 250257 “Towing and Recovery Services”
Please review the procurement plan for the subject RFP and advise your concurrence with the evaluation criteria and contract elements. Include suggested evaluation team members and/or comments. Thanks.
Procurement Type: RFP IFB
A Request for Proposals (RFP) is issued as the nature of the procurement demands that evaluation criteria, in addition to price, be used to select a firm.
Evaluation Criteria:
PROPOSAL WEIGHT
Qualifications of the Firm 30% Staffing/Project Organization 20% Work Plan 25% Cost 25% Justification:
The criteria are structured to select a contractor that can safely and reliably support OCTA’s towing and recovery needs. Greater weight is placed on qualifications and work plan to ensure demonstrated experience, proper equipment, and effective response procedures. Staffing is weighted to evaluate coverage and operator capability. Cost is weighted at 25% in accordance with requirements; however, due to the safety-sensitive and operational nature of these services, experience and reliability are prioritized to reduce risk and service disruption.
Procurement Plan, RFP 250257
Revised: 0720/2010
Contract Type: Time & Expense CTO-Based Firm Fixed Price
Justification (Explain the rationale for using the particular contract type):
A time and expense contract is appropriate for this procurement as firms are required to provide services on an as-needed basis at a firm-fixed hourly rate.
Retention: Yes No N/A
Prevailing Wages: Yes $ No N/A
Liquidated Damages: Yes $ No N/A
Procurement Schedule: Attached
Internal Evaluators:
Trevor Worthy, Senior Contractor Administrator, Contracts Administration and Materials Management
Casey Gladding, Section Manager II, MRM
Kevin Levan, Section Manager II, Maintenance-Specialty Shops Administrator
Jason Morris, Section Manager II, Facilities Maintenance-Santa Ana
Contract Term: Three (3) year term
Funding Source: Local Measure M Federal (CMAQ)
Dollar Amount: Initial Term $435,000 Option Term
Independent Cost Estimate Received: Yes No
Requisition Received: Yes Req. R001064
DBE Goal: Yes No
Procurement Plan, RFP 250257
Revised: 0720/2010
Project Manager Concurrence:
Christine Herrera, Contracts Analyst, Maintenance Resource Management Date
CAMM Section/Department Manager Concurrence:
Georgia Martinez, Department Manager, Contracts and Procurement Date
4/7/2026