About this file
This is Construction Bid Addendum No. 1 issued by the Michigan Department of Technology, Management and Budget's State Facilities Administration, Design and Construction Division for HVAC Renovations at the Saginaw Correctional Facility (File Number 472/22064.CTS). The addendum, issued on January 28, 2025, clarifies that there is a mandatory pre-bid meeting scheduled for Friday, January 31, 2025 at 10:00 am. The bid opening date is set for February 12, 2025. Matrix Consulting Engineers, Inc. is serving as the Professional on the project, with Chris Schanbeck as the Project Director.
The addendum is to be distributed through www.michigan.gov/SIGMAVSS and must be acknowledged by bidders in the Bid Summary and Bid Form, with failure to acknowledge potentially resulting in bid rejection. The document is signed by Devon Pung of Matrix Consulting Engineers and approved by Project Director Chris Schanbeck.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 (Rev 12/17)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
CONSTRUCTION BID ADDENDUM NO. 1
This form identifies an Addendum to Bidding Documents, and incorporates interpretations or clarifications, modifications, acceptance of proposed “or equal” materials, and other information into the Bidding Documents. Addenda will be numbered by the Professional and distributed through www.michigan.gov/SIGMAVSS as an attachment.
TO:
ALL BIDDERS
DATE ISSUED
1/28/2025
PROJECT NAME
Saginaw Correctional Facility – HVAC Renovations
FILE NUMBER
472/22064.CTS
PROFESSIONAL
Matrix Consulting Engineers, Inc.
PROJECT DIRECTOR
Chris Schanbeck
BID OPENING DATE:
2/12/2025
ADDENDUM ITEMS: (attach additional sheets and drawings if required)
1. Project Advertisement Clarification: Mandatory pre-bid meeting is, Friday, January 31, 2025 at 10:00 am.
ACKNOWLEDGMENT: This Addendum must be acknowledged by the Bidder in the space provided in the Bid Summary and Bid Form. Failing to acknowledge Addenda may be cause for the Bid to be rejected. Addenda will become part of the Contract Documents.
PROFESSIONAL: Devon Pung, Matrix Consulting Engineers DATE: 1/28/2025
APPROVED BY: Chris Schanbeck PROJECT DIRECTOR: Chris Schanbeck DATE: 1/28/2025 http://www.michigan.gov/SIGMAVSS
File details come from the government source that posted it. Updated .