This is a Procurement Plan memorandum from the Orange County Transportation Authority (OCTA) Contracts Administration and Materials Management (CAMM) department outlining the procurement strategy for RFP 250080, "Detail Bus and Streetcar Cleaning and Pesticide Application Services." The RFP seeks qualified contractors to provide detailed bus cleaning and pesticide application services on an as-needed basis according to the bus maintenance department fleet schedule. The contract term is three years for the initial term with one optional two-year renewal term. No specific response dates, due dates, site visits, or bidder conferences are referenced in this procurement plan document.
The contract will be awarded on a time and expense basis at firm-fixed hourly rates, with an initial term budget of $1,465,000 and a first option term budget of $1,120,000, funded through local sources with Requisition R000703. An independent cost estimate has been received. Evaluation will be based on four criteria: Qualifications of the Firm (30%), Staffing/Project Organization (20%), Work Plan (25%), and Cost (25%). There are no prevailing wage requirements, liquidated damages provisions, retention requirements, or Disadvantaged Business Enterprise goals associated with this procurement. The evaluation team includes Ellis Hoskin (Senior Contract Administrator), Christine Herrera (Contracts Analyst), Nancy White (Senior Business Unit Analyst), Joe Nakaishi (Section Manager II, Facilities Maintenance-Garden Grove), and Jason Morris (Section Manager II, Facilities Maintenance-Santa Ana).
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INTEROFFICE MEMO
Procurement Plan, RFP 250080
Date: November 3, 2025
To: Christine Herrera, Contracts Analyst, Maintenance Resource Management (MRM)
From: Ellis Hoskin, Senior Contract Administrator, CAMM
Subject: Procurement Plan for Release, Selection and Award RFP 250080 “Detail Bus and Streetcar Cleaning and Pesticide Application Services”
Please review the procurement plan for the subject RFP and advise your concurrence with the evaluation criteria and contract elements. Include suggested evaluation team members and/or comments. Thanks.
Procurement Type: |X| RFP |_| IFB
A Request for Proposals (RFP) is issued as the nature of the procurement demands that evaluation criteria, in addition to price, be used to select a firm.
Evaluation Criteria:
| PROPOSAL |
| WEIGHT |
| Qualifications of the Firm |
| 30% |
| Staffing/Project Organization |
| 20% |
| Work Plan |
| 25% |
| Cost |
| 25% |
Justification:
Qualifications of the firm criterion is weighted at 30 percent as the proposing firms must demonstrate a proven history in successfully completing similar projects and having the required licensing and experience in the application of pesticides and detail bus cleaning requirements. Staffing and project organization criterion is weighted at 20 percent as the firm must demonstrate the proposed key personnel have specific skillsets in order to complete the services required in the scope of work. Work Plan is weighted at 25 percent to ensure proposals address each section of the work plan in sufficient detail to demonstrate a clear understanding of the scope of work and must demonstrate the firm’s understanding and ability to provide extensive cleaning and pesticide bait application. Cost and price criterion is weighted at 25 percent to ensure OCTA receives fair and competitive pricing for the services provided.
Contract Type: |X| Time & Expense |_| CTO-Based |_| Firm Fixed Price
Justification (Explain the rationale for using the particular contract type):
A time and expense contract is appropriate for this procurement as firms are required to provide services on an as-needed basis per the bus maintenance department fleet schedule at a firm-fixed hourly rate.
| Retention: |
| |_| Yes |
| |X| No |
| |_| N/A |
| Prevailing Wages: |
| |_| Yes |
| $ |
| |X| No |
| |_| N/A |
| Liquidated Damages: |
| |_| Yes |
| $ |
| |X| No |
| |_| N/A |
Procurement Schedule: |X| Attached
Internal Evaluators:
Ellis Hoskin, Senior Contractor Administrator, Contracts Administration and Materials Management
Christine Herrera, Contracts Analyst, MRM
Nancy White, Senior Business Unit Analyst, MRM
Joe Nakaishi, Section Manager II, Facilities Maintenance-Garden Grove
Jason Morris, Section Manager II, Facilities Maintenance-Santa Ana
Contract Term: Three (3) year initial term with one, two (2)-year option term
Funding Source: |X| Local |_| Measure M |_| Federal (CMAQ)
Dollar Amount: |X| Initial Term $1,465,000.00 |X| First Option Term $1,120,000.00
Independent Cost Estimate Received: |X| Yes |_| No
Requisition Received: |X| Yes Req. R000703
DBE Goal: |_| Yes |X| No
Project Manager Concurrence:
| __________________________________________ | ______________ |
| Christine Herrera, Contracts Analyst, Maintenance Resource Management | Date |
CAMM Section/Department Manager Concurrence:
| __________________________________________ | ______________ | |
| Georgia Martinez, Department Manager, Contracts and Procurement | Date |
Revised: 07/20/2010 Revised: 0720/2010 image1.png
File details come from the government source that posted it. Updated .