250063_ATT 8_Liquidated Damages.pdf

PDF 82 KB Posted

Attached to
WWYK250063 - INSTALL REACT VII FACILITY, B9001, POST V19
Solicitation number
FA813727R0002
Issued by

About this file

This is a Liquidated Damages assessment document for federal contract WWYK250063, which concerns the installation of a REACT VII Facility at Building B9001, POST V19. The document establishes a daily liquidated damages rate of $227.75 per calendar day for contractor delays in completing work on this delivery order, in accordance with FAR 36.206 and DFARS 236.206.

The liquidated damages calculation is composed of two components: engineering labor costs totaling $122.36 per day and government labor costs totaling $105.39 per day. The engineering component includes 0.5 hours from an Engineering Manager ($28.85), 1 hour from a Project Manager ($36.06), 1 hour from an Engineering Tech/Inspector ($28.52), 0.5 hours from Project Engineers ($19.23), and 0.5 hours from Clerical staff ($9.71). The government component includes 0.5 hours from a FAS GS-12/5 employee ($19.60), 1 hour from Legal GS-13/5 ($46.60), and 1 hour from Contracting GS-12/5 ($39.19). The document indicates that the contractor maintains complete control over work pace and that the assessment rate is reasonable given the project requirements. A signature block for the Contracting Officer and date field are provided but remain unsigned.

View the file

Other files

File Type Posted
250063_ATT 13_Prebid RFI Responses Round 1.pdf PDF
250063_ATT 4_ODS.pdf PDF
2026 TAFB Mechanical Standard_signed.pdf PDF
2026 TAFB FIRE PROTECTION STANDARD.pdf PDF
SOW Att 04_Automated Casting Cell.pdf PDF
SOW Att 02a_Controlled Area Training.pptx PPTX presentation
250063_ATT 10_Submittal Register.pdf PDF
23 00 00.pdf PDF
08 11 13.pdf PDF
08 33 23.pdf PDF
10 22 13.pdf PDF
10 44 16.pdf PDF
07 21 16.pdf PDF
00 71 00.pdf PDF
01 33 00.pdf PDF
01 50 00.pdf PDF
ufc_3_260_01_2019_c1.pdf PDF
EM_385-1-1.pdf PDF
dafi21-101_afmcsup_afmcgm2023-01.pdf PDF
ufc_3_601_02_2021.pdf PDF
tinkerafbi13-204.pdf PDF
afman32-7003.pdf PDF
afman91-203_oc-alcsup.pdf PDF
afi48-104.pdf PDF
dodio-2000.16v1_afi10-245-o.pdf PDF
007200_Attch7b_Monthly Hazardous Usage Report.pdf PDF
007200_Attch9_EMS Awareness Training.pdf PDF
JOIST SPECIAL INSPECTIONS.xlsx XLSX spreadsheet
250063_ Redline A-502.pdf PDF
HE05IN_Dimension_Drawing.pdf PDF
lrad331965pd_spec.pdf PDF
ELECTRICAL COMBINED.pdf PDF
4500-MUG.pdf PDF
220042 As Built Drawings.pdf PDF
Site Visit Meet Up Location.png PNG image
SOW Att 05_SMS Builder Equipment List_v0 2023 0817.xlsx XLSX spreadsheet
250063_ATT 10_Submittal Register.xlsx XLSX spreadsheet
23 08 00.pdf PDF
21 13 13.pdf PDF
23 07 00.pdf PDF
23 36 00.00 40.pdf PDF
23 05 48.00 40.pdf PDF
10 14 00.10.pdf PDF
08 81 00.pdf PDF
28 31 76.pdf PDF
06 41 16.00 10.pdf PDF
01 42 00.pdf PDF
01 33 16.00 10.pdf PDF
HAZMAT Reporting at Tinker AFB FEB 2025.pdf PDF
afi91-202_afmcsup.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT NUMBER & TITLE: WWYK250063 - INSTALL REACT VII FACILITY, B9001, POST V19

FACILITY/USER DAMAGES Impact / Day Daily Consideration of Delivery Extension -$

ENGINEERING TITLE Hrs RATE TOTAL Engineering Manager 0.5 57.69$ 28.85$ Project Manager 1 36.06$ 36.06$ Engineering Tech, Inspector 1 28.52$ 28.52$ Project Engineers 0.5 38.46$ 19.23$ Clerical 0.5 19.41$ 9.71$

SUBTOTAL 122.36$

GOVERNMENT TITLE Hrs RATE TOTAL

FAS (GS-12/5) 0.5 39.19$ 19.60$

Legal (GS-13/5) 1 46.60$ 46.60$ Contracting (GS-12/5) 1 39.19$ 39.19$

SUBTOTAL 105.39$

TOTAL AMOUNT OF LIQUIDATED DAMAGES PER DAY - PHASE 1 227.75$

Contracting Officer (Signature)

Contracting Officer (Print)

Date:

LIQUIDATED DAMAGES

In accordance with FAR 36.206 and DFARS 236.206, liquidated damages (LDs) will be assessed for each calendar day of delay required to complete work on the subject contract/delivery order. As a minimum, LDs in the amount of $227.75 for each day thereafter will be changed based upon the following:

a. The contractor has complete control of the pace of work.

b. The contract provides for LDs for delay of work for each calendar day of the contract.

c. Considering the requirement, the rate of assessment is reasonable.

Sheet1