25-00001 Amend. 1 .docx

DOCX document 37 KB Posted

Attached to
Sowing and Growing 85, 000 Ponderosa Pine Seedlings
Solicitation number
25-00001
Issued by
Adams County, Asotin County, Benton County, Chelan County, Clallam County, Clark County, Columbia County, Cowlitz County, Douglas County, Ferry County, Franklin County, Garfield County, Grant County, Grays Harbor County, Island County, Jefferson County, King County, Kitsap County, Kittitas County, Klickitat County, Lewis County, Lincoln County, Mason County, Okanogan County, Pacific County, Pend Oreille County, Pierce County, San Juan County, Skagit County, Skamania County, Snohomish County, Spokane County, Stevens County, Thurston County, Wahkiakum County, Walla Walla County, Whatcom County, Whitman County, Yakima County, Asotin City, Clarkston City, Clarkston Heights-Vineland CDP, West Clarkston-Highland CDP, Benton City, Chelan City, Chelan Falls CDP, Clallam Bay CDP, Lewisville CDP, Rock Island City, Pacific Beach CDP, Whidbey Island Station CDP, Mercer Island City, Pacific City, Bainbridge Island City, Kingston CDP, Kitsap Lake CDP, Kittitas City, Klickitat CDP, Okanogan City, Anderson Island CDP, Fort Lewis CDP, Fox Island CDP, Herron Island CDP, Ketron Island CDP, North Fort Lewis CDP, Raft Island CDP, Stevenson City, Hat Island CDP, Lake Stevens City, Snohomish City, Spokane City, Spokane Valley City, Puget Island CDP, Garfield Town, Yakima City, Washington

About this file

This document is an Amendment (No. 1) issued by the Washington Department of Fish and Wildlife (WDFW) for Invitation for Bid (IFB) No. 25-00001, addressing a procurement for sowing and growing 85,000 Ponderosa Pine seedlings. The amendment primarily resolves a technical issue regarding attachment accessibility, with the agency reattaching Appendices A, B, C, and D to the solicitation. The procurement covers seed propagation across multiple Washington State counties, including Franklin, Grant, Grays Harbor, Chelan, and Yakima, with a proposal submission deadline of May 5, 2025, representing a procurement timeline of approximately six weeks.

The contract opportunity requires a specialized nursery contractor capable of cultivating seedlings while maintaining their unique genetic and environmental characteristics, with seeds previously collected by WDFW from specific locations where the seedlings will ultimately be planted. While the exact budget is not specified, the volume of seedlings suggests a potentially significant contract value. The procurement appears focused on environmental restoration or habitat reconstruction, with an emphasis on qualitative factors beyond pricing. The specialized nature of the contract implies a need for contractors with extensive botanical and agricultural expertise, particularly in coniferous tree propagation, though no explicit set-aside designations are detailed in the documentation.

View the file

Other files

File Type Posted
25-00001 Appendix D.doc DOC document
25-00001 IFB Amend. 1.pdf PDF
25-00001 Appendix C .doc DOC document
25-00001 IFB Ponderosa Pine Seedlings 3.20.25.docx DOCX document
Appendix A- .docx DOCX document
25-00001 Appendix B.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Washington Department of Fish and Wildlife Request for Qualifications/Quotation

IFB No.:
25-00001

Title:

Sowing and Growing 85,000 Ponderosa Pine Seedlings

Date issued:
March 31, 2025
Amendment No:
1

1. This amendment provides answers to questions posed by prospective vendors regarding unable to open attachments in this procurement.

Question 1: In reviewing this WEBS opportunity (25-00001 IFB Ponderosa Pine Seedlings), I am unable to view or download the Appendices, as the .doc files don't seem to be clickable. Will these appendices be added as attachments in the Amendments section of the Solicitation Details page?

Answer: I have reattached the documents in the Solicitation Amendment section.

All other terms, conditions, and specifications remain unchanged. Attachments: Appendix A, Appendix B, Appendix C, Appendix D image1.jpeg

File details come from the government source that posted it. Updated .