This document is a Statement of Work (SOW) for the Dog Kennels SAW361-SAW364-RR476 Repair Project. The contractor shall provide all material, labor, equipment, and supervision to remove old epoxy and install new epoxy coating in the specified areas of buildings SAW361, SAW364, and RR476 located at MCB Camp Lejeune. The work must be performed per the manufacturer's specifications and the attached flooring specification. The contractor shall take necessary precautions to protect property, repair any damage, and properly dispose of all debris. The work hours are 0730 to 1800 Monday through Friday, with scheduling for weekends and holidays available upon request. The contractor shall submit the manufacturer's product specifications for approval. A warranty is required per the attached Combined Division 01 Specifications. This project is associated with Solicitation Number N4008524R2826 issued by the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MACC # 24-0418

Project # 24M049CN Maximo #5372395

TITLE: Dog Kennels SAW361-SAW364-RR476 Repair Project

ATTACHMENTS: Flooring Specification (3), MCO 5585.5a Kennel Flooring Guidance (2), Division 1 MACC Specifications

SCOPE OF WORK: The contractor shall provide all material, labor, equipment, and supervision required to accomplish the following:

GENERAL DESCRIPTION: This scope of work is to be accomplished at Building SAW361, SAW364 on Saw Mill Road, MCB Camp Lejeune and RR476 at MARSOC Compound off NC Hwy. 210. The contractor shall remove all old epoxy in specified areas and install new epoxy PPG WB Urethane Gloss Gray-A 00462398, PPG 2550 WB Urethane Gloss Catalyst -B 00462418 or comparable product that meets or exceeds specs.

All work should be performed per manufacturer’s specifications.

General Specifications: The contractor shall follow the general specifications unless noted in the project area description section. All measurements on the attached sketches are for reference use only. The contractor shall take their own field measurements in determining required material and costs. All work performed shall meet or exceed Division 01 MACC Specifications

PROJECT AREA DESCRIPTIONS:

1. SAW361 (11,265 SF Prep / Install)

2. SAW364 (11,265 SF Prep / Install)

3. RR476 (11,440 SF Prep / Install)

PROCEDURE

1. Installation:

a. The contractor shall remove existing epoxy. Repair any masonry where new epoxy is to be installed and maintain proper slope to any drains. All work should be performed per manufacturer’s specifications and the kennel flooring guidance in the attached MCO 5585.5a.

2. Preparation:

a. The contractor shall take the necessary precautions to prepare and protect personal property, government property, and work areas during the accomplishment of work for this scope.

3. Flooring Specification:

a. See attached specification. PPG Flooring 2550 Waterborne Urethane

Coating or equivalent.

SPECIAL CONDITIONS

1. Clean all over-spray, drips, splatters, and spills resulting from accomplishing work for this project.

2. Repair, refinish areas damaged or disturbed by new work to be provided under this contract.

3. Properly remove, haul, and dispose of all debris. The contractor shall not utilize the dumpster provided by Camp Lejeune for the occupants.

SCHEDULING AND ACCESS:

The Primary Point of Contact for these buildings are as follows:

1. Building SAW361, SAW364 - John Salvetti 910-4513915

2. Building RR476 - GySgt Gonzalez - 910-440-0387

3. This schedule is event driven and may be deviated from if both the occupants and contractor are in agreement. Once the work has been started this project shall be worked continuously during schedule. Working hours to ensure timely completion.

Working hours are from 0730 to 1800 Monday through Friday. Scheduling work for weekends and holidays can be arranged with the occupants upon request.

HAZARDOUS MATERIALS: None Identified

ENVIRONMENTAL REQUIREMENTS: None Identified

SUBMITTALS:

The contractor shall submit to the contracting officer, the manufacturer’s product specifications, complete with technical products data being used for this project. Submittal should be marked with project numbers.

WARRANTY:

Flooring contractor shall provide per the attached Combined Division 01 Specifications.