24M049CN Dog Kennels SAW361-SAW364-RR476 Repair Project PD.pdf
PDF 136 KB Posted
- Attached to
- Dog Kennels SAW361-SAW364-RR476 Repair Project
- Solicitation number
- N4008524R2826
About this file
This document is a Project Description for the Dog Kennels SAW361-SAW364-RR476 Repair Project. The contractor shall provide all material, labor, equipment, and supervision required to remove old epoxy and install new epoxy in the kennel areas at Building SAW361, SAW364 on Saw Mill Road, MCB Camp Lejeune and RR476 at MARSOC Compound off NC Hwy. 210. The facility/activity will remain in operation during construction, and the contractor shall conduct operations to minimize interference. One person may fill the roles of Superintendent, Quality Control Manager, and Safety & Health Officer if qualified.
The related federal contract opportunity is Solicitation Number N4008524R2826 for the Dog Kennels SAW361-SAW364-RR476 Repair Project, issued by the Department of the Navy Naval Facilities Engineering Command. Only General MACC Contractors listed on the General Requirements cover page may submit a proposal for this ROICC Camp Lejeune area of responsibility project.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT DESCRIPTION
The contractor shall provide all material, labor, equipment, and supervision required to accomplish the following: This scope of work is to be accomplished at Building SAW361, SAW364 on Saw Mill Road, MCB Camp Lejeune and RR476 at MARSOC Compound off NC Hwy. 210. The contractor shall remove all old epoxy in specified areas and install new epoxy in the kennel areas as specified.
SPECIAL SCHEDULING
The facility/activity will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the facility/activity. The furniture and other objects in the room are to be moved by the contractor.
SUPERVISION
One person may fill the roles of Superintendent, Quality Control Manager, and Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.