About this file
The document is a Supplemental Qualifications of Bidders file for the Collier County North County Regional Water Treatment Plant (NCRWTP) Nanofiltration System Upgrades project (Bid No. 24-8279) in Florida. The document outlines specific qualification requirements for potential installers bidding on the project, mandating that bidders demonstrate recent experience in membrane system installation and commissioning. Specifically, installers must have installed membrane elements at a minimum of five municipal locations in Florida with a production capacity of at least 3.0 million gallons per day (mgd) within the past five years, and must have fabricated, assembled, and commissioned complete nanofiltration or reverse osmosis membrane trains at a minimum of three municipal locations in the United States with a similar production capacity.
The qualification requirements are designed to ensure that bidders have substantial, recent experience in municipal water treatment system upgrades, particularly in nanofiltration and reverse osmosis technologies. Bidders are required to provide five reference projects of similar magnitude completed in the last five years, which can be used to meet the two primary qualification criteria. These references will be verified by calling the provided references, and bidders must complete Form 5 – Statement of Experience of Bidders to document their qualifications. The stringent requirements aim to select an installer with proven expertise in complex water treatment system installations and upgrades.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
24-8279 Collier NCRWTP Nanofiltration System Upgrades
SUPPLEMENTAL QUALIFICATIONS OF BIDDERS
The reference projects submitted by the Installer shall clearly demonstrate experience within the last five (5) years to meet the qualifications listed below (to be verified by calling references). Reference projects submitted shall include:
1. The INSTALLER shall have installed membrane elements at a minimum of five (5) municipal locations in Florida with a minimum production capacity of 3.0 mgd within the past five years
2. The INSTALLER shall have fabricated, assembled and commissioned complete nanofiltration or reverse osmosis membrane trains at a minimum of three municipal locations within the United States with a minimum production capacity of 3.0 mgd within the past five years.
Additionally, five (5) reference projects of similar magnitude completed in the last five
(5) years must be provided per Form 5 – Statement of Experience of Bidders. These projects can meet the two (2) qualifications above.
File details come from the government source that posted it. Updated .