23. Attachment 15 Traffic Control Plan.pdf

PDF 142 KB Posted

Attached to
Go Big G-Z Stewardship IRSC - Region 6, Fremont-Winema NF, Chiloquin RD
Solicitation number
12363N22Q4111
Issued by

About this file

This solicitation is for a Go Big G-Z Stewardship Integrated Resource Service Contract (IRSC) to be awarded by the USDA Forest Service. The contractor will complete forest restoration treatments across approximately 30,000 acres located near Chiloquin and Sprague River, Oregon by December 2030. Work will include layout, timber removal, road maintenance and reconstruction to increase the pace and scale of wildfire risk reduction efforts. The contractor will first develop an implementation plan detailing all needed activities by treatment area. Pricing will be firm-fixed using a "Stepladder Pricing" approach established at award based on complexity levels. The contract will be a commercial services agreement awarded using best value procedures.

View the file

Other files

File Type Posted
A003_SiteVisitNotes.pdf PDF
A003_SOI_Notes_GoBig G-Z IRSC.pdf PDF
InsectDiseaseRiskPotentialAssessment.pdf PDF
A003_SF30_GoBig G-Z IRSC_12363N22Q4111.pdf PDF
A003_Appendix A_GoBig G-Z.pdf PDF
A002-SF30_GoBig G-Z IRSC 12363N22Q4111.pdf PDF
A002_GoBig G-Z IRSC_SOI_Notes.pdf PDF
Go Big_GIS Data.zip ZIP file
A001_QandA 06012023.pdf PDF
Go Big_GIS Stands.zip ZIP file
A001-SF30_Go Big G-Z IRSC 12363N22Q4111.pdf PDF
A001_Appendix B.pdf PDF
Go Big_GIS Layerfile.zip ZIP file
21.Attachment14_FirePlan.doc DOC document
2.Appendix A_GoBig G-Z IRSC.pdf PDF
7.CAM-ContractAreaMap_GoBig G-Z IRSC.pdf PDF
19.Attachment12_FreWinCommercialRoadUseRules_20220203.pdf PDF
24.Davis-Bacon Construction WD #OR20230001.pdf PDF
10.Attachment3_NEPA Documents_GoBig G-Z.zip ZIP file
9.Attachment2_HarvestCardTemplate_GoBig G-Z.doc DOC document
16.Attachment9_TimberCruising in the PNW.pdf PDF
11.Attachment4_WildlifeRetention.pdf PDF
17.Attachment10_Additional PDCs.pdf PDF
15.Attachment8_Hessburg.pdf PDF
14.Attachment7_R6 TatumAid.pdf PDF
6.CAM-VicinityMap_GoBig G-Z IRSC.pdf PDF
1.Solicitation_GoBig G-Z IRSC_12363N22Q4111.pdf PDF
26.Industry Q&A to the G-Z IRSC Model.pdf PDF
12.Attachment5_Prescriptions.pdf PDF
4.Appendix C_RoadMtce_GoBig G-Z IRSC.pdf PDF
18.Attachment11_Additional PDCs Map.pdf PDF
3.Appendix B_Scaled_GoBig G-Z IRSC.pdf PDF
20.Attachment13_Shapefile_GoBig G-Z IRSC.zip ZIP file
8.Attachment1_ForestProductAccountabilityActionPlan.pdf PDF
5.Appendix D_RoadPlanTemplates_GoBig G-Z IRSC.pdf PDF
25.PreSolicitationMeeting Q&A_GoBig G-Z.pdf PDF
23.SCA Wage Determination-OR#1977-0079_Rev71.pdf PDF
22.Attachment15_TrafficControlPlan.pdf PDF
13.Attachment6_FSM & FSH.pdf PDF
13. Attachment 6 FSM & FSH.pdf PDF
9.Attachment2_HarvestCardTemplate_GoBig G-Z.doc DOC document
Go Big G Z IRSC PreSolicitation Meeting Q and A.pdf PDF
22. Attachment 14 Fire Plan.doc DOC document
6.CAM-VicinityMap_GoBig G-Z IRSC.pdf PDF
3.Appendix B_Scaled_GoBig G-Z IRSC.pdf PDF
19. Attachment 12 FreWinCommercialRoadUseRules_20220203.pdf PDF
8.Attachment1_ForestProductAccountabilityActionPlan.pdf PDF
21. Davis-Bacon Construction WD #OR20230001.pdf PDF
4.Appendix C_RoadMtce_GoBig G-Z IRSC.pdf PDF
15. Attachment 8 Hessburg.pdf PDF
Show 40 more

Latest 50 of 64 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Name: Go Big G - Z IRSC Stewardship

TRAFFIC CONTROL PLAN AND SPECIFICATIONS PURSUANT TO B6.33 SAFETY

Unless otherwise agreed in writing in accordance with B6.33Safety, the following measures are required to provide adequate warning of hazards for users of roads and trails adjacent to Contractor’s Operations.

Part I. Signing and Other Warning Methods:

(a) Signs. The following signs are required when Contractor’s Operations are in progress adjacent to or on Forest Service controlled roads and trails:

MINIMUM LETTER

SIZE AND LEGEND

MINIMUM SIZE AND

SHAPE WHEN AND WHERE REQUIRED

1. LOGGING 24" x 36" (rectangle) Min. 100 ft. outside of any continuous OPERATIONS work areas, on roads listed in C5.31# NEXT <> MILES and trails listed in Part II.

(4" letters)

2. LOGGING

OPERATIONS

(4" letters)

30" x 30"(diamond) To be used in conjunction with "Logging Operations Next <> Miles" and where work area is not continuous.

3. FOR LOGGING

USE ONLY

(4" letters)

30" x 30"(diamond) Required where roads listed in C5.31# and temporary roads intersect with C5.31# roads. Install a cross ditch to discourage use when sign is covered or removed for extended periods.

4. TRUCKS

(4" letters)

30" x 30"(diamond) At critical intersections on roads listed in C5.31# when traffic is heavy or otherwise exceeds volumes stated in Part II below.

Remove or cover when the sign is not applicable.

5. END 24" x 36" (rectangle) Use in conjunction with "Logging LOGGING Operations Next <> Miles" and "Logging OPERATIONS Operations."

(4" letters)

6. TREE 30" x 30"(diamond) Required 200 feet in advance of danger FELLING area where timber is being felled adjacent AHEAD to all roads, including temporary roads, (4" letters) and trails.

7. ROAD 30" x 30"(diamond) Required at least 200 feet in advance of MACHINERY Contractor road maintenance operations AHEAD on roads listed in Schedule C5.31#.

(4" letters)

Page: 1

Contract Name: Solomon DxP IRTC Stewardship Page: 2

TRAFFIC CONTROL PLAN AND SPECIFICATIONS PURSUANT TO B6.33SAFETY (continued)

All signs shall meet requirements as specified in Parts 1 and 6 of the Manual of Uniform Traffic Control Devices (MUTCD).

Sign borders and lettering shall be black. Borders are 7/8 inch wide, inset 5/8 inch from outside Solomon of sign. All sign backgrounds shall be orange, except that signs that need to be seen both day and night shall be retroreflective orange or illuminated.

Signs shall be installed on posts, with a 5 foot minimum height above road surface, or on temporary supports complying with MUTCD standards.

All signs are to be removed or covered when operations are interrupted for seasonal nonuse or other extended periods.

Contractor shall furnish flag personnel and advance warning signs when cable or helicopter logging above roads or trails, felling adjacent to roads or trails, where logs being bucked may roll into roads or trails, and in areas where fallout from blasting may occur. Except as identified in Part II, Contractor may temporarily block roads listed in C5.31# and temporary roads in lieu of furnishing flag personnel. On roads controlled by other jurisdictional authorities, Contractor shall receive approval from that authority for Contractor’s safety measures and traffic control plans before commencement of operations.

(b) Barricades. On roads listed in C5.31#, if Contractor’s Operations cause the traveled way or road shoulders to be constricted overnight, or longer, by such obstructions as decked logs, parked equipment, or piled slash, Contractor shall place barricades on both sides of the encreaching obstruction to safely channel traffic around such obstructions. Barricades shall remain in place until the obstruction is removed.

Barricades shall be Type II and meet specifications in MUTCD, Part 6. Barricades must be at least 3 feet high. Rails must be at least 2 feet long. Striping shall be alternating orange and white, sloping at a 45 degree angle, and reflectorized. For rails 2 feet to 3 feet long, striping shall be 4 inches wide. For rails longer than 3 feet, striping shall be 6 inches wide. Two rails, 8-12 inches in width, must face each direction.

(c) Other Traffic Control Methods. The posting of CB channel signs may be authorized.

On roads listed in C5.31#, Contractor may be authorized to install temporary gates, barricades (except cables), or natural barriers. The devices must be installed with the necessary hazard markers, be reasonably passable by Forest Service, and be removed to acceptance of the subdivision being served by the road.

Contract Name: Go Big G - Z IRSC Stewardship Page: 3

Part II. Specific Requirements:

Contractor and Forest Service agree to the above stated requirements of the Traffic Control Plan:

Name Name

Contractor Title Forest Service Title

Date Date