The document is a comprehensive set of Technical Specifications for the 99th Street Path Construction project between Westfield Boulevard and Haverstick Road in Carmel, Indiana, prepared by the City of Carmel Engineering Department. The project involves constructing a multi-use path on the north side of 99th Street, including storm sewer construction, with specific technical requirements for various aspects of the work. The project has a substantial completion deadline of 60 days after the actual start date, with an earliest start date of May 26, 2025, and a latest substantial completion date of October 31, 2025. Liquidated damages of $1,000 per day will be assessed for missed substantial completion deadlines, and $500 per day for missed final completion deadlines.
The technical specifications provide detailed guidance on numerous construction elements, including utility coordination, erosion control, material testing, traffic maintenance, road closure procedures, and specific requirements for water utility work, fire hydrant installations, valve adjustments, and as-built documentation. The contractor will be responsible for coordinating with multiple utility companies, including AT&T, Centerpoint Gas, Duke Energy, and others, and must follow strict requirements for capturing point feature locations, preparing as-built drawings, and meeting Carmel Water Utility's specific standards. The project will require careful attention to existing conditions, protection of infrastructure, and compliance with local and state specifications, with no separate payment for many incidental works, which are to be included in other pay items.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL SPECIFICATIONS
TS 1 GOVERNING DOCUMENTS
TS 2 COMPLETION DATES AND LIQUIDATED DAMAGES
TS 3 HOLIDAYS WHEN WORK IS NOT PERMITTED
TS 4 WORK SCHEDULE SUBMITTAL
TS 5 CONSTRUCTION WORK HOURS
TS 6 COOPERATION WITH UTILITIES
TS 7 EROSION CONTROL SUBMITTAL
TS 8 LIMITATIONS OF OPERATIONS
TS 9 EXISTING CONDITIONS
TS 10 PROTECTION OF EXISTING STRUCTURES AND PIPE
TS 11 RIGHT-OF-WAY CLEARING
TS 12 MAINTAINING TRAFFIC
TS 13 ROAD CLOSURE
TS 14 ROAD CLOSURE NOTIFICATION
TS 15 MATERIAL TESTING
TS 16 UNDISTRIBUTED ITEMS
TS 17 OPEN BURNING OF NATURAL GROWTH
TS 18 STREET CLEANING
TS 19 TRANSPORTATION OF SALVAGEABLE ITEMS
TS 20 PROJECT CONTRACT DOCUMENTS
TS 21 SAW CUTTING
TS 22 HMA – HOT MIX ASPHALT
TS 23 PAVEMENT SMOOTHNESS
TS 24 TOP SOIL
TS 25 COORDINATION WITH OTHER PROJECTS
TS 26 CONCRETE SIDEWALK, 4”
TS 27 ADJUSTING RINGS
TS 28 STRUCTURE CASTINGS AND HOODS
TS 29 EXISTING STRUCTURE ADJUSTMENT
TS 30 WATER UTILITY STANDARD DETAILS & REQUIREMENTS
TS 31 MAILBOX ASSEMBLY
TS 32 PAYMENT FOR DRIVES
TS 33 ASPHALT MATERIAL THICKNESS AND CONFORMANCE
TS 34 GRADING BEHIND WALK
TS 35 MATERIAL ACCEPTANCE
TS 36 FINAL CLEANUP
TS 37 STANDARD DRAWINGS
TS 38 CONSTRUCTION NOISE
TS 39 HMA SURFACE COURSE
TS 40 EROSION CONTROL GUARANTEE
TS 41 SOD AND LANDSCAPE MAINTENANCE AND WARRANTY PERIOD
TS 42 GEOGRID
TS 43 RIGHT OF ENTRY
TS 44 PLAN MEASURED QUANTITIES
TS 45 EXCESS MATERIAL - DISPOSAL
TS 46 RESTORATION OF DISTURBED AREAS
TS 47 PIPE REMOVAL
TS 48 MANHOLES AND CULVERTS - EXISTING
TS 49 RESETTING STREET SIGNS
TS 51 WATERING REQUIREMENTS FOR NEWLY PLANTED TREES
TS 52 LIGHT RELOCATE
TS 53 ADA CURB RAMPS
TS 54 CONCRETE CURB; CONCRETE CURB & GUTTER
TS 55 AS-BUILT PLANS
TS 57 TEMPORARY EROSION AND SEDIMENT CONTROL
TS 59 CONCRETE CAP ADJACENT TO CURB AND GUTTER
TS 62 PIPE CULVERT EXTENSION & PIPE END SECTION
TS 63 INSPECTION HOLE
TS 64 ADJUST FLUSHING STATION PIT AND INSTALL CASTING
TS 65 SANITARY SEWER LATERAL PIPE ADJUSTMENT
TS 66 METER PIT RELOCATION & ADJUST TO GRADE
TS 67 FIRE HYDRANT ASSEMBLY
TS 68 ADJUST VALVE TO GRADE (CARMEL WATER)
TS 69 ADJUST VALVE TO GRADE & REPLACE VALVE BOX (CARMEL WATER) .. 28
TS 70 ADJUST VALVE TO GRADE (TRICO FM VALVES)
TS 71 EXISTING CONDITIONS
TS 72 TRANSPORTATION OF SALVAGEABLE ITEMS
TS 73 COORDINATION WITH PUBLIC
TS 74 OTHER SPECIAL CONDITIONS AND REQUIREMENTS
TECHNICAL SPECIFICATIONS
TS 1 GOVERNING DOCUMENTS
The applicable sections of the following documents shall apply except as modified elsewhere herein:
1) Indiana Department of Transportation (INDOT) Standard Drawings and Standard
Specifications – Latest Edition.
2) INDOT Supplemental Specifications
3) City of Carmel General Conditions for Construction Contracts Unless otherwise specified within the Contract Documents, whenever any specification, standard, reference material, manual or other similar document is incorporated by reference into any of the contract documents, it shall be deemed to be the latest edition of said item including any and all supplemental addendum, which was in effect on the date of the bid opening for this project.
TS 2 COMPLETION DATES AND LIQUIDATED DAMAGES
Substantial Completion: 60 days after actual start date Final Project Completion: 30 days after Substantial Completion Earliest Start Date: May 26, 2025 Latest Substantial Completion Date October 31, 2025
All contracts shall be calendar day contracts and shall include all days in the number of days provided for completion including weekend days and holidays, even if these days are identified as non-work days within the contract documents.
Substantial Completion is defined as set forth in Article 1 of the Standard General Conditions.
Substantial Completion is further defined to include the completion of the HMA Surface and permanent pavement markings.
Liquidated damages of $1,000 per day shall be assessed for every day beyond the agreed upon Substantial Completion date, listed above, that the project does not meet the completion requirements.
Liquidated damages of $500 per day shall be assessed for every day beyond the agreed upon Final Completion date, listed above, that the project does not meet the completion requirements.
TS 3 HOLIDAYS WHEN WORK IS NOT PERMITTED
The CONTRACTOR may not perform work on the following days unless requested and approved or permitted by the ENGINEER or OWNER:
Sundays (unless otherwise approved by City Engineer) New Years Day Memorial Day Independence Day Labor Day Thanksgiving Day Christmas Day
TS 4 WORK SCHEDULE SUBMITTAL
The CONTRACTOR shall provide a critical path work schedule for the entire project with the Post-Bid documents. This schedule shall be submitted to and approved by the ENGINEER prior to the start of construction and shall be updated as necessary. No work will be allowed until this schedule is submitted and approved; however, the CONTRACTOR will not be granted any time extension due to this delay.
TS 5 CONSTRUCTION WORK HOURS
The CONTRACTOR shall perform all construction activities between the hours of 7:00 am and 7:00 pm unless receiving prior approval from the ENGINEER.
TS 6 COOPERATION WITH UTILITIES
It shall be the CONTRACTOR’S responsibility to have all utilities located before construction in a particular area. The CONTRACTOR shall coordinate with all utilities in the adjustment of these facilities and in order to avoid damage to any facilities. Damage to any of the existing public utility facilities during the project caused by the CONTRACTOR'S operations or equipment, shall be repaired by the CONTRACTOR at no expense to the Contract. This includes sewer, water, gas, electric, telephone, cable, etc.
and includes facilities within proposed storm sewer trenches. However, if any utilities are exposed and must be relocated for construction to continue, this work shall be performed by the utility, or the CONTRACTOR shall be reimbursed at an agreed upon price to perform such work. If the utility performs the work, the CONTRACTOR shall coordinate with the utility in order to expedite said work.
The status of all utility companies and organizations potentially involved with the work to be performed are described below as know at the time this contract was prepared.
(Note: Below information will be updated prior to letting)
The facilities of AT&T exist within the project limits but are not expected to be affected by the proposed construction. If questions arise, Brad Bailey of the utility may be contacted at 317-610-5422, mobile 317-459-4769 or bb3525@att.com.
The facilities of City of Carmel exist within the project limits but are not expected to be affected by the proposed construction. If questions arise, John Duffy of the utility may be contacted at 317-571-2451, mobile 317-339-8472 or jduffy@carmel.in.gov.
The facilities of Centerpoint Gas exist within the project limits but are not expected to be affected by the proposed construction. The utility has an active 4-inch steel medium pressure main, an active 4-inch plastic medium pressure main, an active 2-inch steel medium pressure main, an active 2-inch plastic medium pressure main and service throughout the project area. Although no conflicts are anticipated, the Utility is in the process of performing test holes to confirm depths. There will be various service lines retired in place and reinstalled. If questions arise, Chad Miller of the utility may be contacted at 317-979-3291, mobile 317-776-5590 or Chad.R.Miller@centerpointenergy.com.
The facilities of Duke Energy Distribution exist within the project limits but are not expected to be affected by the proposed construction. The utility has OH primary 3∅ 12.47 kV, 1∅ 7.2 kV, and UG secondary 120/240 V facilities in the project area. It’s anticipated that there are no conflicts with the utility and the Contractor shall work around existing poles. If questions arise, Dan Weirauch of the utility may be contacted at 765-438-0139 or Daniel.weirauch@duke-energy.com.
The facilities of Metronet exist within the project limits but are not expected to be affected by the proposed construction. If questions arise, Lori Kemper of the utility may be contacted at 812-213-1050 or lori.kemper@metronet.com.
The facilities of Marathon Pipeline exist within the project limits but are not expected to be affected by the proposed construction. The utility has an 8-inch high pressure petroleum products pipeline that traverses parallel to 99th Street on the north side. If questions arise, Zach Rich of the utility may be contacted at 463-203-2363 or zjrich@marathonpetroleum.com.
The facilities of TriCo Regional Sewer Utility exist within the project limits but are not expected to be affected by the proposed construction. The utility has air release valves at Sta. 14+09 and Sta. 34+00 LT., Line ‘B’. The utility has a Manhole at Sta. 21+28 LT., Line ‘B’ and a Flushing Station at Sta. 28+05 LT., Line ‘B’. If necessary, manhole castings and air release valves are to be adjusted to grade by the contractor using traffic grade castings. New manhole adjusting rings and cover shall be adjusted a maximum height not to exceed 12-inches on existing structure. If additional height is required, barrel rings are to be used. If questions arise, Ryan Hartman of the utility may be contacted at 317-844- 9200. ryan.hartman@trico.eco.
The facilities of Spectrum (Brighthouse) exist within the project limits but are not expected to be affected by the proposed construction. The utility has passive and active aerial and underground coax and fiber facilities within the project limits. The facilities enter the project aerially from Haverstick Road, crossing 99th Street from south to north, then continues west on the north side of 99th Street on Duke poles. At Duke pole #060-356- CML, approximate Sta. 23+50.02 Lt., Ln. ‘B’, the utility risers down and continues heading west underground out of the project area. If questions arise, Byron Posey of the utility may be contacted at 317-538-2016 or Byron.posey@charter.com.
The facilities of Zayo exist within the project limits but are not expected to be affected by the proposed construction. The utility has buried fiber optic and plastic ducts with composite handholes at the northeast corner of 99th Street and Westfield Boulevard.
If questions arise, Waylon Higgins of the utility may be contacted at 765-341-1199 or Waylon.higgins@zayo.com.
TS 7 EROSION CONTROL SUBMITTAL
Prior to commencing work, the Contractor shall prepare and submit to the Engineer for approval an erosion control plan that includes, at a minimum, the following items:
1. Locations of all proposed soil stockpiles, borrow areas, or disposal areas.
2. Locations of all proposed vehicle and equipment parking areas, vehicle and equipment fueling locations, placement of the site construction trailers, location of all on-site batch plants, and designated concrete truck washout areas.
3. Proposed construction sequence and phasing of erosion control measures.
4. Location of all construction entrances where vehicles and equipment will enter and exit the site.
5. Material handling and spill prevention plan, which shall include a list of expected materials that may be present on the site during construction operations, as well as a written description of how these materials will be handled to minimize the potential that the materials may enter storm water runoff from the site.
6. Statement that the erosion control measures for the project will be inspected, at a minimum, on a weekly basis and within 24 hours of every ½ inch rain event.
The Engineer will submit the Erosion Control Plan to:
soil.water@hamiltoncounty.in.gov and
Mark McCauley, Resource Conservationist Hamilton County SWCD 1717 Pleasant Street Noblesville IN 46060
(317) 773-2818 mark.mccauley@hamiltoncounty.in.gov
Ground disturbing activities shall not commence until the Hamilton County Soil and Water Conservation District (SWCD) has reviewed and approved the Erosion Control Plan.
Method of Measurement. This work will not be measured for payment.
Basis of Payment.
This item includes all costs required to prepare the Erosion Control Plan as described.
Preparation of the Erosion Control Plan will not be paid for directly, but such cost shall be included in the cost of the other pay items.
Temporary erosion control measures will be paid for with the pay items included in the itemized bid. No direct payment will be made for notifications or preparation of amendments to the SWPPP, but such cost shall be included in the cost of other pay items.
TS 8 LIMITATIONS OF OPERATIONS
When in the judgment of the OWNER, the CONTRACTOR has obstructed or closed a greater portion of the work than is necessary for proper construction, or is carrying on operations to the prejudice of the work already started, the OWNER may require the CONTRACTOR to finish that portion of the work which is in progress before any additional portions are started. Work shall be conducted with minimum inconvenience to traffic.
Except as hereafter specified, no loads of material for any construction shall be dispatched from cars or plants so late in the day that it cannot be placed, finished and protected within the Specification limits and provisions in the daylight hours of that same day.
TS 9 EXISTING CONDITIONS
The CONTRACTOR shall verify the elevations and measurements of all points where new construction is to match existing conditions prior to the commencement of any construction activities. No direct payment shall be made for this work but the cost thereof shall be included in the costs of the other items of the contract.
TS 10 PROTECTION OF EXISTING STRUCTURES AND PIPE
On this project there are existing storm drainage and sanitary sewer structures that are to remain in place. The CONTRACTOR shall take care that these structures are not damaged.
If any of these structures are damaged, the CONTRACTOR shall be required to repair them at his own expense.
TS 11 RIGHT-OF-WAY CLEARING
Clearing Right-of-Way shall be in accordance with the requirements of Section 201.
Cavities formed by the removal of shrubs, trees and/or stumps and located outside of proposed pavement areas shall be backfilled and compacted with approved material. Such compaction shall comply with Section 211.04. A minimum of three (3) inches of the backfilled area shall be topsoil in accordance with TS 24. No direct payment shall be made for this work, but the cost thereof shall be included in the costs of the other items.
The cost of removal of items within the right-of-way or as directed by the ENGINEER, that are not quantified in the plans, will not be paid for, but shall be included in the lump sum price for Clearing of Right-of-Way.
TS 12 MAINTAINING TRAFFIC
Maintenance of traffic shall be the sole responsibility of the CONTRACTOR. Access and traffic to all businesses, residences, for all postal deliveries and all emergency traffic such as police, fire, medical, etc. within the project limits, shall be maintained at all times.
Unless otherwise directed, or permitted, the work specified shall be arranged and prosecuted in accordance with all applicable provisions of Sections 104.04, 107, 801 and as set out in INDOT Standard Specifications.
The names and telephone numbers of the CONTRACTOR'S superintendent and one other responsible employee shall be furnished at the pre-construction conference. These employees shall be on call and available at nights, weekends, or during other non-working periods to repair or replace all traffic control devices, which may become damaged or inoperative.
In the event the CONTRACTOR desires not to perform traffic maintenance in accordance with the sequence of operations as called for within the Contract Documents, CONTRACTOR shall submit his alternate plan in writing to the ENGINEER and obtain acceptance at least 1 week prior to the commencement of any construction activities.
Open trenches, if permitted by the ENGINEER, shall be spanned per current OSHA requirements and with the concurrence of the ENGINEER.
Any trenching areas adjacent to a sidewalk shall be barricaded.
The CONTRACTOR shall be prepared to have all construction signs erected for the project as specified by the ENGINEER.
All temporary traffic control devices not listed separately or adjustments, labor, materials, etc., necessary for the maintenance of traffic as called for within the Contract Documents, or as permitted by the ENGINEER shall be included in the lump sum price for ‘Maintenance of Traffic’, as set out in the itemized proposal.
TS 13 ROAD CLOSURE
It will be necessary to close E. 99th Street to westbound traffic for the construction of the project. Westbound traffic shall be detoured via Haverstick Road, E 96th Street and Westfield Road. E. 99th Street will be open to eastbound traffic (one-way) as shown in Plans. The CONTRACTOR shall minimize the duration of road closure by constructing as many off-road items as reasonable while the mainline remains open. Road and driveway cuts may be plated or topped with Compacted Aggregate Base No. 53 and opened to local traffic. The cost of this work will not be paid for directly but shall be included in the cost of Maintaining Traffic.
The lane closure shall be limited to 30 days. No additional closures will be allowed.
Liquidated damages of $1,000 per day shall be assessed for every day beyond the agreed upon closure days.
Flagman shall be used during work activities, and road cuts shall be plated at night as needed.
TS 14 ROAD CLOSURE NOTIFICATION
The CONTRACTOR shall post an advance closure construction sign that notifies the traveling public of a road closure and the duration of the closure at least 14 days in advance of the road closure, unless otherwise approved by the ENGINEER. The advance closure construction sign legend shall generally state that the named road or street will be closed on or after a specific date for a number of days. The signs shall be placed as shown on the plans or as directed by the ENGINEER.
The advance closure construction signs shall be in accordance with Section 801 of the INDOT Standard Specifications and paid for at the contract unit price per each for
Construction Sign, A.
TS 15 MATERIAL TESTING
The ENGINEER will be responsible for compaction testing and concrete testing for the project. The CONTRACTOR shall be responsible for lime stabilization proctor testing.
The cost of material testing shall be included in the cost of other pay items. Asphalt materials shall be provided as shown on the plans; certifications and acceptance shall be in accordance with Section 402 of the INDOT Standard Specifications.
TS 16 UNDISTRIBUTED ITEMS
Quantities of undistributed items needed in addition to those shown on the itemized proposal and approved by the ENGINEER will be paid for at the contract unit price for the quantity used on the project. In addition, there shall be no adjustment in the contract unit price if quantities are less than those shown on the itemized proposal and the item can be deleted entirely without impact to the contract amount. All work involving undistributed items shall be performed only at the direction of the ENGINEER.
TS 17 OPEN BURNING OF NATURAL GROWTH
Open burning of natural growth is not permitted on this contract.
TS 18 STREET CLEANING
The CONTRACTOR shall provide effective dust control throughout the project. Loader-mounted pick-up, power sweepers, or other types of pull type models shall be used for street cleaning. Street cleaning shall also be performed prior to the pre-final meeting as directed by the ENGINEER.
Street cleaning will not be paid directly, but shall be included in the cost of various items of the contract regardless of the amount of times this operation is reasonably requested.
Naturally occurring conditions, out of the control of the owner, that cause more dust control than normal shall not be a valid reason for request of payment for dust control.
TS 19 TRANSPORTATION OF SALVAGEABLE ITEMS
Existing traffic control devices, signs, pipe, end sections, castings and manhole covers, etc.
specified to be removed will be salvaged and stockpiled at the job site by the CONTRACTOR. The CONTRACTOR shall deliver those items designated by the ENGINEER, to the City of Carmel or appropriate owner. The remainder of the items shall become the property of the CONTRACTOR.
TS 20 PROJECT CONTRACT DOCUMENTS
The documents related to the proposed improvements of this project include:
Final Plans Project Manual City of Carmel Standard Drawings INDOT Standard Specifications City of Carmel General Conditions for Construction Contracts
TS 21 SAW CUTTING
In all areas where proposed construction matches existing conditions, full depth saw cutting shall be required.
No direct payment will be made for saw cutting but the cost thereof shall be included in the costs of the other items.
TS 22 HMA – HOT MIX ASPHALT
This work shall consist of courses of HMA at the locations shown in accordance with Section 401 of the INDOT Standard Specifications, latest edition. For all local (non-federal aid) projects, acceptance and testing requirements for all HMA mixtures shall be in accordance with Section 402, unless indicated herein.
HMA paving operations in street approach areas shall utilize the mainline HMA pay items.
An asphalt tack coat shall be applied between each course of HMA material or as directed by the ENGINEER. Asphalt tack coat shall also be applied in areas of surface milling and asphalt overlay.
If no Asphalt for Tack Coat item is provided in the itemized proposal, then the cost shall be included in the costs of the HMA items.
TS 23 PAVEMENT SMOOTHNESS
The pavement smoothness will be accepted by means of a 16 ft long straightedge.
The 16 ft long straightedge shall be used on all full width pavement lanes, overlays that are preceded by milling, all full width pavement lanes shorter than 250 ft, on tapers, within 50 ft of bridge ends, and within 50 ft of an existing pavement, which is being joined. The 16 ft long straightedge will be furnished and operated by the CONTRACTOR in the presence of the ENGINEER for the City of Carmel.
All wavelike irregularities and abrupt changes in profile caused by paving operations shall be corrected.
Each finished course of base and intermediate shall be subject to approval. The pavement smoothness shall be checked on any new intermediate course located immediately below a surface course and the surface course as directed by the ENGINEER.
If grinding of the intermediate course is used for pavement smoothness corrections, the grinding shall not precede the surface placement by more than 30 calendar days if open to traffic.
When the 16 ft straightedge is used on a surface course, the pavement variations will be corrected by grinding with a grooved type cutter, or removal, and surface replacement. The ENGINEER and the City of Carmel shall determine the limits of the correction area. In no case shall the width of correction be less than the original paved lane width in that area.
When the 16 ft straightedge is being used on an intermediate course, all areas having a high or low point deviation in excess of 1/4 in. shall be corrected by means of grinding with a grooved type cutter or an approved alternate method.
Corrections for pavement smoothness shall not be paid for but will be at the cost of the
CONTRACTOR.
TS 24 TOP SOIL
Description
This work shall consist of the testing, placement, and installation of topsoil in accordance with these requirements, the INDOT Standard Specifications, and as indicated on the plans.
Materials A. Materials shall be in accordance with Section 914.01 of the INDOT Standard
Specifications as follows:
1. 914.01 Special Topsoil for Roadside Development This topsoil shall consist of loose friable soil, free of refuse, stumps, large roots, rocks over 2 in. in diameter, brush, weeds, or other material which would be detrimental to the proper development of vegetative growth. It shall be capable of supporting normal vegetation as demonstrated by the growth of healthy vegetation on it. It shall not be taken from a source known to contain any of the noxious weeds defined as such in the Indiana State Seed Law, IC 15-4-1. 10 Topsoil shall have a pH value of 6.2 to
7.4. Testing for pH value shall be performed in accordance with AASHTO T 289.
Agricultural limestone may be added to topsoil in order to raise the pH to meet specification requirements.
2. Topsoil Source: Import topsoil or manufactured topsoil from off-site sources as necessary. Obtain topsoil displaced from naturally well-drained construction or mining sites where topsoil occurs at least 4 inches deep; do not obtain from bogs or marshes. On site soil may be used.
3. Topsoil test results shall be supplied to the ENGINEER.
B. Materials that do not meet these requirements shall not be incorporated into the work as topsoil.
C. The ENGINEER and CONTRACTOR shall consult and agree on suitability of onsite topsoil generated from common excavation stripping operation and incorporate the approved material into the project. When or if this suitable material is exhausted, only then, or as directed, can the Pay Item for Topsoil can be utilized to import Topsoil to the project.
Construction Requirements A. If existing soil suitable for amendment, as determined by the ENGINEER, is not available in sufficient quantities onsite, Topsoil shall be furnished at the contract unit price for Topsoil.
B. Topsoil is to be placed on all plant beds, disturbed areas, and seeded or sod areas to a minimum depth of three (3) inches or as directed by the ENGINEER. The ENGINEER may authorize an additional excavation in areas designated to be seeded, sodded, or landscaped. Payment for additional cut, beyond the finished grade, required to place topsoil at the ENGINEERS direction will be made at the contract unit price for Common Excavation
C. In addition to B. above, topsoil is to be placed in medians and roundabout islands at a minimum depth of one (1) foot or as directed by the ENGINEER.
Method of Measurement Topsoil will be measured by the cubic yard in accordance with Article 211.09.
Basis of Payment The accepted quantities of topsoil will be paid for at the contract unit price per cubic yard.
Payment will be made under:
Pay Item Pay Unit Symbol
Topsoil CYS
TS 25 COORDINATION WITH OTHER PROJECTS
The CONTRACTOR shall coordinate construction with the activities of other projects in the area. Adjacent activities and maintenance of traffic shall be coordinated with the other projects. The referenced projects will be under the jurisdiction of the City of Carmel.
TS 26 CONCRETE SIDEWALK, 4”
This work shall consist of the installation of concrete sidewalk at the proposed locations or as directed by the ENGINEER in accordance with Section 604 of the INDOT Standard Specifications and Carmel Standard Drawings 10-18 and 10-19. All concrete sidewalks shall be placed on prepared compacted material in accordance with INDOT Specification 207.02.
The costs for concrete, excavations, labor, equipment, backfill material, joint placement, any bed course material used for leveling, preparation of a compacted subgrade, and any necessary incidentals with concrete sidewalk installation shall be included in the cost of ‘Sidewalk, Concrete, 4 in.’.
When unsuitable material prevents achieving the desired compaction, these areas shall be excavated and replaced with Compacted Aggregate Base, No. 53 to the desired compaction at the direction of the ENGINEER. The costs for excavation, material, placement, and compaction shall be included in the pay item Compacted Aggregate Base, No. 53.
The costs for removal and disposal of existing sidewalk shall be included in the pay item Clearing of Right of Way unless a specific pay item is included in the itemized proposal.
TS 27 ADJUSTING RINGS
No brick or block shall be used in the construction of a manhole or when adjusting the elevation of the frame and cover.
When one solid riser or barrel section cannot be used, the final adjustments in elevation of the frame and cover shall only be accomplished by the use of precast concrete adjusting rings as shown in the Plans, and conforming to ASTM C-478. Not more than twelve (12) inches of total adjusting rings shall be allowed per structure.
Joints between adjusting rings and casting shall be sealed utilizing one of the following elements:
1. An approve rubber gasket manufactured and installed in accordance with
ASTM C443, latest edition
2. Trowelable grade butyl rubber
3. A .5 inch diameter non-asphaltic mastic (Kent Seal or approved equal) conforming to AASHTO M-198 and Federal Specification SS-521-A.
TS 28 STRUCTURE CASTINGS AND HOODS
Any manhole lids that will be within any portion of a bituminous recreational path or concrete walkway shall be Neenah Casting Catalog #R-1714, Special “C” Cope Lid 1 Neenah - NF-17140023 Type "C" lid design with permagrip texture with four lift holes, or approved equal.
All catch basins and modified structures with a sump present shall have “Snout Oil- Debris Hoods” as manufactured by:
Best Management Products, Inc.
53 Mt. Archer Rd.
Lyme, CT 06371
(860) 434-0277, (860) 434-3195 FAX
Toll Free: (800) 504-8008 or (888) 434-0277 Web Site: www.bmpinc.com
OR
Pre-Approved Equal
No direct payment will be made for the castings and catch basin hoods but the cost thereof shall be included in the costs of the other items or the structure item.
TS 29 EXISTING STRUCTURE ADJUSTMENT
Adjustments to existing structures shall be performed as shown on the plans in accordance with Section 720.04 of INDOT Standard Specifications. Adjustments to sanitary structures shall be made in accordance with the Specifications of Clay Township Regional Waste District or appropriate owner.
Payment for the adjustments shall be made in accordance with Section 720.06.
TS 30 WATER UTILITY STANDARD DETAILS & REQUIREMENTS
Water utility standards for installation & relocations can be found at:
http://www.carmel.in.gov/services/wateroperations/waterops.html
TS 31 MAILBOX ASSEMBLY
The mailbox work shall consist of the placement of mailbox assemblies, or the relocation of mailbox assemblies at the location as shown on the Plans or as directed.
Procedure Existing mailboxes shall be removed as discussed herein. Mailboxes that are to be relocated shall be removed and reset as shown on the Plans or as directed. Mailboxes that are to be salvaged and delivered to the apparent owner shall be removed and stored until such time as they are delivered to the apparent owner. If the apparent owner of the mailbox assembly refuses to take possession, the existing mailbox and assemblies shall be removed. Mailboxes, which must remain in service between removal and erection of the new assembly, shall be securely mounted in a temporary manner. All mailbox assemblies that are to be relocated or salvaged shall be carefully handled. Any such materials damaged by the Contractor or allowed to be damaged while in storage shall be repaired or replaced by the Contractor at no additional cost.
Mailbox assemblies shall be of the type and size and shall be placed as shown on the Plans or as directed in accordance with INDOT Section 611. Coordinate with the local postmaster to installation requirements.
Measurement and Payment Mailbox Assemblies will be measured and paid per each at the bid unit price. The item mailbox assembly shall include: wood or pipe posts, support hardware, mailbox, removal of existing mailbox and its assembly, and any other material required to complete the work as shown or as directed.
Removal of mailboxes will not be measured or paid separately, but shall be included in the cost of clearing and other items.
Project Specification Information Mailbox assembly shall be an all-in-one mailbox, newspaper compartment, and post assembly. Mailbox shall be constructed of durable heavy-duty plastic and of a neutral color. Mailbox shall have front and back doors for mail retrieval. Two inch address numbers will be installed on both sides of mailbox. Mailbox assembly shall be a Mailmaster Plus, manufactured by The Step 2 Company or approved equal.
TS 32 PAYMENT FOR DRIVES
When the existing drive is concrete or asphalt, the existing drive shall be sawed at the line where the new construction shall match the existing material. If no removal item is provided, no direct payment shall be made for the sawing or removal of any type of drive, but the cost thereof shall be included in the price bid for the type of driveway or approach being placed.
TS 33 ASPHALT MATERIAL THICKNESS AND CONFORMANCE
All pavement thickness and miscellaneous item(s) thickness shall be constructed to reasonably close conformance to the specified thickness. Payment will be made according to exact thickness provided, but not in excess of the specified thickness as shown in the plans.
Bituminous Materials
Thickness:
The total asphalt pavement thickness shall be constructed to reasonably close conformance as specified in Contract Documents. Thickness shall be controlled by controlling the rate of application of the bituminous mixture. The mixture shall be placed at the weight per square yard designated by the plans. The rate application shall not exceed the designated rate by more than five (5) percent. No payment will be made for any material placed in excess of this five (5) percent tolerance. Additionally, the OWNER may core the overlay to verify yields.
TS 34 GRADING BEHIND WALK
All grading behind walks and curbs is to be completed as shown on the plans and cross sections or as directed by the ENGINEER. Quantities of earth placement or removal in these areas are included within section volumes; therefore, this work shall not be paid for separately, but the cost shall be included within the item Common Excavation.
TS 35 MATERIAL ACCEPTANCE
All aggregate, concrete, and bituminous materials used for the project shall be produced from an approved source. The Contractor shall submit the names and addresses of the suppliers of these materials for the project to the ENGINEER at the pre-construction conference. Prior to delivery the Contractor shall submit to the ENGINEER a copy of the certification for each material supplier.
TS 36 FINAL CLEANUP
The Contractor shall clean up all areas, including inlets, storm pipes, and streets, within the construction area as well as areas disturbed outside the construction areas at the completion of the project. This work shall be done at the satisfaction of the City of Carmel. The areas disturbed outside of the construction area shall be seeded at no cost to this project.
TS 37 STANDARD DRAWINGS
See City of Carmel Standards/Details. These can be accessed at www.carmel.in.gov at the Carmel Technical Standards and Standard Drawings link in the Construction Trades drop down menu on the Engineering Main Page.
TS 38 CONSTRUCTION NOISE
The CONTRACTOR shall be required to limit construction noise by maintaining his equipment in proper working order, thereby minimizing the effect of construction noise in the project area.
TS 39 HMA SURFACE COURSE
Prevailing Specifications: INDOT 401, 402
Additions:
The HMA surface course shall not be placed until all new pavement areas within the project limits, including mainline, approaches and areas of incidental construction, have been completed and are ready, in the opinion of the ENGINEER, for the HMA surface course.
TS 40 EROSION CONTROL GUARANTEE
Prevailing Specifications: INDOT 621
Additions:
The Contractor shall guarantee a stand of grass; and if through the actions of the elements, the seasons, animals, or man the seed does not grow; shall reseed, re-fertilize, and do that which is required to produce an abundant and uniform growth of grass on the areas requiring seeding in this contract. Final acceptance of the project will not be made until the requirements of this special provision have been attained.
TS 41 SOD AND LANDSCAPE MAINTENANCE AND WARRANTY PERIOD
Prevailing Specifications: INDOT 621
Section 621.10 Watering Sod
Delete the following: Sod shall be maintained for a minimum of four weeks from the time it is laid before being accepted.
And replace with: Sod that is not irrigated permanently shall be watered and maintained for a minimum of 90 days from the time the sod placement for the entire project is complete before being accepted. Any sod that is not accepted at the end of the 90 day watering and maintenance period shall be replaced at no additional cost to the contract and maintained for another 90 day maintenance period and this maintenance period and replacement shall continue until all sod has been accepted.
The 90 day water and maintenance period shall exclude the winter months of December through March. Therefore, any maintenance days that overlap the winter months as defined herein shall be applied to the following year and beginning on April
1. Irrigated sod shall have the same requirements for the sod only and the actual irrigation system will be covered under the project Maintenance Bond for any deficiencies in the materials or craftsmanship.
Additions to INDOT Section 621:
Any and all supplemental specifications or technical specifications herein or as part of the landscape plans.
Warranty Bond: Upon completion of the installation and initial inspection of any living landscape material, a properly executed Warranty Bond with a surety shall be supplied in the amount of the material being warranted. The intent of the Warranty Bond shall be to permit the final acceptance of the contract and payment of the retainage.
TS 42 GEOGRID
This work shall consist of furnishing and installing Tensar BX 1300 Geogrid, or an approved equal, in accordance with Section 214 of the latest version of the Indiana Department of Transportation Standard Specifications. The geogrid shall be placed on compacted subgrade and installed in accordance with manufacturer’s recommendations and specifications. The subgrade shall be compacted to 95% modified proctor prior to placement of geogrid.
Basis of Payment
The cost of all work and materials, including grading, subgrade compaction, placement of geogrid, proof rolling, and any and all necessary incidentals shall be included in the cost of Geogrid or the associated pay item(s).
TS 43 RIGHT OF ENTRY
The CONTRACTOR shall receive permission from property owners prior to constructing drives or yard grading or doing any work for their convenience outside of the right-of-way or construction limits provided. A minimum of 48 hour notice of any request to encroach private property shall be provided. Copies of signed Right of Entry forms shall be supplied to the ENGINEER.
TS 44 PLAN MEASURED QUANTITIES
Item “Common Excavation” and/or “Borrow” shall be measured per plan quantity in the itemized proposal unless otherwise approved by the Owner or Engineer.
TS 45 EXCESS MATERIAL - DISPOSAL
All excess material (waste) shall be removed from the project site. Whether a private or public waste site is utilized, such disposal shall comply with all Federal, State and local ordinances and permit requirements. A copy of all permits obtained or applied for shall be submitted to the ENGINEER prior to the commencement of any construction activities.
TS 46 RESTORATION OF DISTURBED AREAS
Cavities formed by the removal of shrubs, trees and/or stumps and located outside of proposed pavement areas shall be backfilled and compacted with "B" Borrow. Such compaction shall comply with Section 211.04. The top six (6) inches of the backfilled area shall be top soil in accordance with Section 914.01.
Any roots remaining after all the removal of any designated item shall be removed to a depth of 6 inches below the surface of the surrounding ground area.
Backfilled areas and the surrounding ground areas are to be raked to the satisfaction of the ENGINEER and sodded. All work shall be in accordance with Section 621.
No direct payment shall be made for this work, but the cost thereof shall be included in the costs of the other items.
TS 47 PIPE REMOVAL
If no Pipe or Structure Removal Pay Item is provided but is indicated in the plans and required for the improvements, the removal will not be paid for directly, but shall be included in the cost of Clearing Right of Way or other items. If pipe removal, not indicated on the plans, is required to make the proposed improvements, then it shall also be considered as a part of Clearing of Right-of-Way.
TS 48 MANHOLES AND CULVERTS - EXISTING
The breaking of manhole or culvert walls shall be done so as to insure no damage to existing pipes. The Contractor, at no cost to the OWNER, shall make any necessary repairs to manholes or pipes if damage is caused.
All existing concrete manholes shall be core drilled as specified by the ENGINEER. All breaking into manhole, pipe, concrete, etc. required for construction of the sewer shall be included in the cost of other items.
TS 49 RESETTING STREET SIGNS
The resetting of street signs as shown in the plans will not be paid for directly but the cost shall be included in the cost of other items. The CONTRACTOR shall be responsible for maintaining and storing all signs that are removed from their respective places during construction. Any sign, post, hardware, etc. damaged after the sign has been removed shall be replaced and paid for by the CONTRACTOR before being reset at the end of the project.
TS 51 WATERING REQUIREMENTS FOR NEWLY PLANTED TREES
The watering of newly planted trees as part of the plant material maintenance and warranty shall be as follows:
1. 15 gallons per week for rootballs up to 36” diameter.
2. 55 gallons per week for tree spaded rootballs up to 90” diameter.
3. Watering and documentation of the watering shall take place during the first year after installation and documentation or records shall be provided to the City of Carmel department managing the project.
TS 52 LIGHT RELOCATE
The items “Light, Relocate” shall include all materials and labor to relocate existing light poles and bases as shown in the plans. The foundation is to be poured level and surrounding ground shall be graded up to within 1" of the top of the concrete. All miscellaneous lighting equipment, wiring & conduit necessary for the installation of the light poles shall not be paid for directly, but the cost shall be included in ‘Light Relocate’.
TS 53 ADA CURB RAMPS
Detectable Warning Elements for all ADA curb ramps shall be red brick truncated dome pavers that comply with INDOT Standard Specification 905.05, or an approved equal by the OWNER or ENGINEER. Detectable Warning Elements shall be installed in accordance with INDOT Standard Drawing No. E 604-SWCR-14, or latest detail, and shall have G2 Gator-Maxx (beige color) or approved equal polymeric sand swept joints. 6-inch wide return curb, flush only when required, shall be constructed around the brick area.
Design of the return curb to be approved by OWNER prior to installation. The ADA ramps and detectable warning elements shall be similar in size and shape to the areas shown in the plans or construction documents; however, the exact dimensions shall be determined or approved in the field by the ENGINEER. The cost of all labor, materials, equipment and incidentals associated with this work shall be included in the cost of Curb Ramp, Concrete and Detectable Warning Surfaces, as measured and paid by INDOT Standard Specifications, latest edition.
TS 54 CONCRETE CURB; CONCRETE CURB & GUTTER
Concrete Curb & Concrete curb & gutter shall be placed as described in the construction plans. All Labor, equipment, and materials required for installation of the curbing shall be included within the lineal foot unit price of said item.
TS 55 AS-BUILT PLANS
Storm Sewers - Storm sewer as-built plans shall be submitted to the City of Carmel Engineering Department upon the completion of the project per the City of Carmel GIS submittal requirements. Submittal requirements can be found at http://www.carmel.in.gov/index.aspx?page=800. Submittal questions should be directed to Shane Burnham with the Engineering Department at (317) 571-2459 or sburnham@carmel.in.gov.
Street Lights – Street Light as-built plans shall be submitted to the City of Carmel Engineering Department upon the completion of the project per the City of Carmel GIS submittal requirements. Submittal requirements can be found at http://www.carmel.in.gov/index.aspx?page=800. Submittal questions should be directed to Shane Burnham with the Engineering Department at (317) 571-2459 or sburnham@carmel.in.gov.
Roadway Construction – The contractor shall use the PDF contract plans and add legible notation for elevations, dimensions, and other information that was built and accepted by the engineer that differs from the contract plans. The contractor shall submit the completed as-built plans to the Engineer for approval.
The cost of as-built plans shall not be paid for separately but shall be included in the lump sum cost of “Construction Engineering”.
TS 57 TEMPORARY EROSION AND SEDIMENT CONTROL
Temporary erosion and sediment control measures in the plans shall be constructed and paid for in accordance with the 2024 INDOT Standard Specifications Section 205.
TS 59 CONCRETE CAP ADJACENT TO CURB AND GUTTER
A concrete cap shall be placed next to curb and gutter, as shown on plans, as per Carmel Standard Drawing 10-28. The cost of all materials, labor, equipment, and incidentals necessary to construct the concrete cap in accordance with Standard Drawing 10-28 shall be included in the cost of “Concrete Class A”.
TS 62 PIPE CULVERT EXTENSION & PIPE END SECTION
This work includes extending existing pipe culvert under Haverstick Road, at approximately Sta. 26+16, as shown in plans. The CONTRACTOR shall match existing pipe size. All the work and material required to extend the pipe culvert shall be included in the cost of “Pipe, Type 2, Circular, 30 in”. The pipe end section required shall be paid as “Pipe End Section, Dia 30 in”.
TS 63 INSPECTION HOLE
This work shall consist of digging inspection holes in accordance with 105.03, to verify the exact location of underground utilities that are in potential conflict with the proposed construction.
Materials Materials, tools, equipment, labor and incidentals shall be provided as required.
Construction Requirements Utility locates and coordination shall be in accordance with 105.06 and 107.20.
Once utility locates are marked in the field, inspection holes shall be dug at critical locations as agreed upon by the Department along the marked locates where the utility is within 2 ft of the proposed construction. The inspection holes shall be dug to a depth to either the underground utility or to a depth 1 ft below the proposed construction elevation, whichever is shallower. The inspection hole shall be as large as necessary to search for the marked underground utility within 2 ft horizontally of each side of the marked locate. If the utility is found, as directed, outside the 2 ft horizontal distance from the locate mark, then it shall be considered as an additional inspection hole.
The results of inspection holes shall be plotted on the plan sheets and provided in .pdf format to the Engineer within seven calendar days of completing the inspection holes. The results shall include the utility owner, type, size and material of the utility, station, offset and elevation of the top of the utility. If a utility is not found for a particular inspection hole, then the information shall include the station, offset, elevation and dimensions of the inspection hole.
Once the Contractor no longer requires the inspection hole to remain open, it shall be backfilled and compacted with B borrow in accordance with 211. If the inspection hole is to remain open beyond the day that it was dug, it shall be marked and protected to provide warning that the hole exists.
Method of Measurement Inspection holes for underground utility verification will be included in other pay items.
Basis of Payment Inspection holes for underground utility verification will be included in other pay items.
Payment will be included in other pay items The cost of digging, backfilling, B borrow, measuring, preparing and submitting results, coordination, and all necessary incidentals shall be included in the cost of inspection holes.
TS 64 ADJUST FLUSHING STATION PIT AND INSTALL CASTING
TriCo has a flushing station that will be in the path (Sta 28+02.86). This flushing station is a water meter pit with lid. The CONTRACTOR shall contact TriCo (Ryan Hartman or Arron Strong: Office 317-844-9200) upon stone placement. The CONTRACTOR shall coordinate with TriCo to install a road grade manhole casting over the station pit that meets ADA compliance.
Materials
The manhole casting shall be a Neenah Foundary Company R-1714 casting.
Adjust Flushing Station Pit and Install Casting shall measured by the EA.
Adjust Flushing Station Pit and Install Casting shall include all necessary materials to adjust flushing station pit to grade and install new casting complete in place. This includes but not limited to labor, manhole casting, excavation, backfill, equipment, and restoration.
Adjust Flushing Station Pit and Install Casting ....................................... EA
TS 65 SANITARY SEWER LATERAL PIPE ADJUSTMENT
There are sanitary laterals within the project limits. The contractor shall lower the sanitary lateral in case conflicts with proposed construction arise. At least one week in advance of the sanitary lateral lowering, the Contractor shall contact Ryan Hartman of the Clay Township Regional Waste District and the sanitary lateral owners to coordinate. The lowered section of the sanitary lateral shall be 1.25” diameter DR-11 HDPE pipe.
Connections shall be fusion connections and not pressure fittings. The excavation shall be backfilled with the same material as the storm sewers. The cost of the labor, materials, equipment, and incidentals associated with lowering the sanitary lateral shall be paid for with the undistributed item "Sanitary Sewer Service Adjustment" per LFT lateral as required. An assumed undistributed quantity amount of 100 LFT has been provided.
TS 66 METER PIT RELOCATION & ADJUST TO GRADE
A. Description: This item is for relocations of water meter pits that need to be relocated.
This item shall include all costs to furnish all labor, materials, tools, and equipment,…