210364_Attach6_Liquidated_Damages.pdf
PDF 149 KB Posted
- Solicitation number
- WWYK210364
About this file
This document is a Liquidated Damages form for Project WWYK210364, titled "Construct Loading Dock & Dock Leveler, B3113". The document details the calculation of daily liquidated damages at $227.75 per calendar day of contract delay, broken down by engineering and government personnel hourly rates. The engineering personnel calculation includes roles such as Engineering Manager, Project Manager, Engineering Tech/Inspector, Project Engineers, and Clerical staff, totaling $122.36. The government personnel calculation includes FAS (GS-12/5), Legal (GS-13/5), and Contracting (GS-12/5) roles, totaling $105.39. The liquidated damages assessment is based on the contractor having complete control of work pace, the contract providing for damages for each calendar day of delay, and the assessment rate being deemed reasonable.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT NUMBER & TITLE: WWYK210364 Construct Loading Dock & Dock Leveler, B3113
FACILITY/USER DAMAGES Impact / Day Daily Consideration of Delivery Extension -$
ENGINEERING TITLE Hrs RATE TOTAL Engineering Manager 0.5 57.69$ 28.85$ Project Manager 1 36.06$ 36.06$ Engineering Tech, Inspector 1 28.52$ 28.52$ Project Engineers 0.5 38.46$ 19.23$ Clerical 0.5 19.41$ 9.71$
SUBTOTAL 122.36$
GOVERNMENT TITLE Hrs RATE TOTAL
FAS (GS-12/5) 0.5 39.19$ 19.60$
Legal (GS-13/5) 1 46.60$ 46.60$ Contracting (GS-12/5) 1 39.19$ 39.19$
SUBTOTAL 105.39$
TOTAL AMOUNT OF LIQUIDATED DAMAGES PER DAY - PHASE 1 227.75$
Contracting Officer (Signature)
Contracting Officer (Print)
Date:
LIQUIDATED DAMAGES
In accordance with FAR 36.206 and DFARS 236.206, liquidated damages (LDs) will be assessed for each calendar day of delay required to complete work on the subject contract/delivery order. As a minimum, LDs in the amount of $227.75 for each day thereafter will be changed based upon the following:
a. The contractor has complete control of the pace of work.
b. The contract provides for LDs for delay of work for each calendar day of the contract.
c. Considering the requirement, the rate of assessment is reasonable.