This document outlines oversight and performance metrics for the operation and maintenance of High Speed Transport vessels. The Navy's Military Sealift Command will monitor two key performance requirements through routine onboard condition inspections and an annual contractor performance assessment. Metrics include maintaining ships in a readiness state to perform assigned missions, managing reimbursable costs within budgets, tracking the number of days vessels are ready for tasking, comparing planned and completed maintenance, and ensuring all civilian mariner billets are filled. Noncompliance will be addressed using contractual remedies. The related federal contract opportunity is for the operation and maintenance of the High Speed Transport vessel USNS GUAM, with worldwide performance and a solicitation released by the Navy's Military Sealift Command.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT F - OVERSIGHT AND METRICS
In successfully providing these services to the Fleets, there are two basic performance requirements for MSC’s ships: 1) keep the vessel in a readiness state that allows it to perform any mission assigned to it by the Fleet Commander, and 2) perform assigned missions.
Accordingly, in measuring the extent to which a contractor meets the Performance Work Statement (PWS), MSC monitors and measures both the condition/readiness of the vessel, and the performance of specific missions/tasks.
MSC will routinely conduct Onboard Condition Inspections (OCI) (normally conducted annually) to monitor performance elements through ship visits and site audits as outlined in the Performance Work Statement.
On an annual basis, the contractor’s performance will be evaluated for its Contractor Performance Assessment Reporting System (CPARS) rating. This evaluation will use, primarily, the metrics below. The results of these metrics will be communicated to the contractor as part of contract administration and any discrepancies or issues will be addressed using the contract remedies available.
Requirements Metric Cost: The metric will be used to manage reimbursable expenses within established ship operating budgets.
Differences between expected/budgeted and actual costs.
Schedule/Performance: This metric will be used to determine MSC primary output of Ships Ready for Tasking (RFT), the key indicator of MSC readiness. COMSC is responsible to deliver MSC ships RFT and to maintain this readiness during operational fleet time.
The RFT metric is a cumulative total of calendar days that a ship is deemed RFT or Not Ready for Tasking (NRFT) in the preceding rolling 12 month period compared to an accepted baseline established by MSC.
Inspection: This metric will track planned maintenance against performed maintenance, supplemented by periodic inspections of actual vessel condition.
The difference between Shipboard Automated Maintenance Module (SAMM) System planned maintenance completion levels for ships and actual completion levels.
The COMSC Class Manager will track findings of annual vessel condition inspections to identify degraded or poor vessel condition and the operating contractor’s corrective action.
Manning & Training: This metric will be used to ensure fully trained mariners are aboard ship in accordance with the PWS.
Difference between offered/required civilian mariner shipboard billets versus those that are currently emcumbered.