20250819_SOW_EEPZ245434.pdf
PDF 613 KB Posted
- Attached to
- EEPZ245434 - B730 Renovate SAPR Space
- Solicitation number
- EEPZ245434
About this file
This Design-Build Statement of Work (SOW) details a renovation project for the Sexual Assault Prevention and Response (SAPR) space in Building 730 at Columbus Air Force Base, Mississippi. The project involves renovating existing 14 CS space to create a shared conference room and Integrated Prevention Workforce (IPW) storage room, with a total period of performance of 90 days. Key renovation activities include demolishing and removing existing communication outlets, electrical components, and mechanical systems, and installing new interior walls, lighting fixtures, electrical receptacles, HVAC diffusers, and other systems to support the new space configuration.
The renovation requires comprehensive design and construction services, including developing detailed construction documents, obtaining necessary permits, and executing the work in compliance with Air Force, state, and federal regulations. The contractor must provide a Quality Control Plan, submit design documents at various stages (35%, 65%, 95%, and 100%), and ensure all work meets strict safety, environmental, and technical standards. The project emphasizes preservation of existing infrastructure, minimizing disruption to base operations, and maintaining high standards of workmanship across electrical, mechanical, and architectural systems.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DESIGN-BUILD STATEMENT OF WORK
PROJECT NUIMBER: EEPZ245434
RENOVATE SAPR SPACE, B730
COLUMBUS AFB, MISSISSIPPI
19 AUGUST 2025
COLUMBUS AFB, MS PROJECT NUMBER: EEPZ245434
TABLE OF CONTENTS
NOMENCLATURE
1.1 ACRONYMS & ABBREVIATIONS
1.2 BASIC TERMS
DESCRIPTION OF PROJECT
2.1 SUMMARY
2.2 BACKGROUND
2.3 SCOPE OF PROJECT
2.4 GOVERNMENT FURNISHED EQUIPMENT/MATERIALS
2.5 SALVAGE
DESIGN REQUIREMENTS
3.1 SUMMARY
3.2 NATURE/EXTENT OF DESIGN
3.3 RESPONSIBILITY
3.4 DESIGN STANDARDS
3.5 DRAWINGS
3.6 DESIGN SUBMITTALS
3.7 DESIGN REVIEWS
3.8 CONFERENCES
ADMINISTRATION OF CONSTRUCTION
4.1 PERFORMANCE CAPABILITIES
4.2 COMMENCEMENT, PROSECUTION & COMPLETION
4.3 SCHEDULING
4.4 MANAGING
4.5 MATERIAL SUBMITTALS AND SHOP DRAWINGS
4.6 WORK BY GOVERNMENT
4.7 PRE-FINAL AND FINAL INSPECTION
4.8 WARRANTY
4.9 CONTRACTOR OFFICE
4.10 CONSTRUCTION SITES
4.11 CONSTRUCTION EQUIPMENT
4.12 AVAILABILITY OF UTILITY SERVICES AT JOB SITES
4.13 TEMPORARY UTILITIES
4.14 CONSTRUCTION SECURITY
QUALITY REQUIREMENTS
5.1 QUALITY CONTROL PLAN
5.2 TESTING AND INSPECTION SERVICES
5.3 MANUFACTURERS' FIELD SERVICES
5.4 PRODUCT REQUIREMENTS
5.5 CLOSEOUT PROCEDURES
SAFETY, HEALTH AND ENVIRONMENTAL PROTECTION
6.1 SAFETY AND HEALTH
6.2 GENERAL
6.3 HAZARDOUS MATERIAL
6.4 PROJECT EXECUTION
6.5 HAZARDOUS WASTE GENERATION/DISPOSAL
6.6 RECYCLING
6.7 PROHIBITED MATERIAL/ACTIONS
6.8 SPILLS AND CLEANUP
6.9 AIR CONSIDERATIONS
6.10 AFFIRMATIVE/GREEN PROCUREMENT/BIO-BASED/ENERGY
6.11 ASBESTOS/LEAD BASED PAINT
6.12 DRINKING WATER
6.13 EMS
6.14 HISTORICAL AND CULTURAL ARTIFACTS
6.15 NATURAL RESOURCES
6.16 NOISE
6.17 PESTICIDES/FERTILIZERS
6.18 STORM WATER PROTECTION
6.19 REQUEST FOR CE SERVICE/ACTION/CLEARANCE; AF FORMS 332/813
6.20 TANKS
6.21 LIMITS AND EXCEPTIONS
6.22 LEGAL AUTHORITY
NOMENCLATURE
1.1 ACRONYMS & ABBREVIATIONS
AF Air Force AFI Air Force Instruction AFM Air Force Manual AFUE Annual Fuel Utilization Efficiency AHU Air Handling Unit ATFP Anti-terrorism/Force Protection BCE Base Civil Engineer CAD Computer Assisted (or Aided) Design CAFB Columbus Air Force Base CDs Construction Documents CEPM Civil Engineering Project Manager CES Civil Engineering Squadron cfm cubic feet per minute CFR Code of Federal Regulations CHW Chilled Water CMI 14CES Construction Manager Inspector CO Contracting Officer COR Contracting Officer Representative Comm Communications CPM Contractor’s Project Manager CSS Contractor’s Site Superintendent DP Design Professional EMCS Energy Management & Control System EMI Electromagnetic Interference EPA Environmental Protection Agency ETL Engineering Technical Letter FAR Federal Acquisition Regulation FCU Fan Coil Unit FM Factory Mutual
FOD Foreign Object Debris fps feet per second
ft. foot or feet GFCI Government Furnished Contractor Installed gpm gallons per minute Hazmat Hazardous Materials HMW Hazardous Material or Waste HTW Hazardous and Toxic Waste HVAC Heating, Ventilating and Air Conditioning NEC National Electrical Code NTP Notice to Proceed O&M Operation and Maintenance OSP Originally Specified Product PDF Portable Document Format PE Professional Engineer Ph Phase (electrical) PM Project Manager psi pounds per square inch QCP Quality Control Plan RFP Request for Proposal SOW Statement of Work TI Technical Instruction TL Technical Letter TM Technical Manual UFC Unified Facilities Criteria UPS Uninterruptible Power Supply VAV Variable Air Volume V Volts W Watts
1.2 BASIC TERMS
The following table provides many of the meanings of words or phrases commonly used in this document.
All directives, informative, etc. statements are directed to the Contractor even if the term “contractor” or the contractor name is not included (e.g. “Provide a nail.” is equivalent to “The contractor shall provide a nail.” And “remove” is equivalent to “The Contractor shall remove”). Also, the Contractor shall ably and competently execute all directives including all directly or indirectly related tasks required to safely and legally perform the directive (e.g. “remove debris from CAFB” includes “safe and legal removal, disposal and obtaining all necessary permits, etc.)
A device, equipment or system referred to in the singular (e.g. “the pump”, or “the ___ system”) includes all related devices, elements and components required to Provide (see below in this table) that device, equipment, or system.
The Term Shall Mean (*=Shall in Addition Mean) Approved (by CAFB) *without waiving or suspending the full force of Contractor obligation to fulfill the CDs Aspect Distinct feature or element of the project CAFB Government contracting Authority on Columbus Air Force Base
Construction Documents
Drawings, specifications and their references including all Design Criteria and Design & Construction Requirements for this Project.
Contractor The Design-Build entity holding a current Government contract including all personnel in direct or indirect employ of same entity servicing same contract including partners, consultants, subcontractors, suppliers, and manufacturers.
Design Professional (Abbreviated: DP) Professionals including Architects, Engineers and Landscape Architects licensed to practice in one or more states of the U.S.
Day Calendar day unless noted otherwise.
DP Licensed Design Professional fully responsible for all professional design on this project.
Engineer DP For example (e.g.) One among many possible examples Government Columbus Air Force Base Contracting Officer Including [Includes] Including, but not limited to [Includes, but is not limited to] Provide Furnish and install complete, functional, and ready for use without added government action Provision Furnishing & installation complete, functional, and ready for use without added government action Will, must, shall & similar Terms are mandatory directives whereby ‘Term’ = ‘Term + to CAFB satisfaction’ Work The whole or any part, product, system or subsystem of this project Replace Demolish and dispose of existing element. Provide new element of equal or greater value.
Review Review and, if and when acceptable to the government, approval Subcontractor Subcontractor and all personnel in Subcontractor’s direct or indirect employ on any given
Project including suppliers and manufacturers
DESCRIPTION OF PROJECT
2.1 SUMMARY
The Contractor must provide all plant, labor, equipment, transportation, and tools required to complete a renovation of the existing 14 CS space in B730 to accommodate colocation of Sexual Assault, Prevention, and Response (SAPR) and Integrated Prevention Workforce (IPW) offices. Renovation of the space includes minor HVAC, fire protection and sprinkler, and interior finishes work, replacing lighting fixtures, building a shared conference room, and building a storage room for IPW. Perform all work according to this Statement of Work (SOW), the Concept Design Drawings, and all related AF requirements and other codes and references.
2.2 BACKGROUND
Renovate existing 14 CS space in B730 to accommodate colocation. This project will create a shared conference room and IPW only storage room within existing rooms 121F and 122 to meet part of the colocation model outlined in the Integrated Response Co-Location Pilot.
2.3 SCOPE OF PROJECT
COMMUNICATIONS:
2.3.1 Demolish existing communication outlets and receptacles at locations that conflict with demolition of existing walls and other actions because of this project. Test before demolition to ensure power is disconnected. Keep existing conductors. Cap, pull, coil, and tie existing conductors up overhead (above suspended ceiling system) for future use. Keep existing junction boxes, conduit, and runways in place, unless locations conflict with demolition of existing walls and other actions because of this project.
2.3.2 Demolish and remove existing communication faceplates and jacks within existing rooms 121F and
122. Furnish and install new faceplates and jacks in existing locations. Components shall match throughout and be white. Keep existing outlet boxes, conduit, and conductors. Components shall be compatible and reconnect with existing conductors. Contractor shall test and modify the system as required.
ELECTRICAL:
2.3.3 The existing light switch location within existing room 121F shall remain. Keep existing electrical box, conduit, and conductors in place. Demolish the existing light switch and cover. Furnish and install a new light switch and cover, both shall be white. Rewire the existing lighting circuit so that the light switch will control the lights only within the new shared conference room. Contractor shall test and modify the system as required.
2.3.4 The existing light switch location within existing room 122 shall remain. Keep existing electrical box, conduit, and conductors in place. Demolish the existing light switch and cover. Furnish and install a new light switch and cover, both shall be white. Rewire the existing lighting circuit so that the light switch will control the lights only within the new IPW storage room. Contractor shall test and modify the system as required.
2.3.5 Demolish existing power outlets and receptacles at locations that conflict with demolition of existing walls and other actions because of this project. Test before demolition to ensure power is disconnected. Keep existing conductors. Cap, pull, coil, and tie existing conductors up overhead (above suspended ceiling system) for future use. Keep existing junction boxes, conduit, and runways in place, unless locations conflict with demolition of existing walls and other actions because of this project.
2.3.6 Design, furnish and install new power receptacles, outlet boxes, junction boxes, conduit, conductors, and faceplates as necessary to supply the new interior wall separating the new shared conference room and new IPW storage room with power, see concept drawing for locations. Components shall match throughout and be white. Design shall ensure new receptacles are connected to the best option existing circuit and follow applicable UFCs, and local, state, and national codes. Design and approval to be completed by Electrical P.E. Install outlet boxes, conduit, and conductors within the new interior wall to have an uninterrupted, flat wall surface. Install receptacles and faceplates to be flush to the new interior wall.
2.3.7 Demolish and remove existing power receptacles and faceplates within existing rooms 121F and
122. Furnish and install new receptacles and faceplates in existing locations. Components shall match throughout and be white. Keep existing outlet boxes, conduit, and conductors. Components shall be compatible and reconnect with existing conductors. Contractor shall test and modify the system as required.
2.3.8 Demolish existing 2’x4’ light fixtures and associated fixtures whips up to the junction boxes in existing rooms 121F and 122.
2.3.9 Design, furnish, and install new 2’x2’ flat panel LED light fixtures with new fixture whips in the new shared conference room and new IPW storage room. Recess mount the light fixtures in the new suspended ceiling system. Light fixtures shall comply with ASHRAE 90.1 power and lighting standards.
Ensure light fixtures comply with base, local, and national emergency lighting codes. Light fixtures shall have necessary seismic support.
2.3.10 Place new light fixtures in locations necessary for optimal lighting qualities for essential daily functions and occupant comfort. Light fixtures shall be placed in locations that ensure minimal disruptions (i.e. relocating, demolishing, performance, etc.) to existing HVAC, fire detection and suppression, and electrical systems. Design and approval to be completed by Electrical P.E. Contractor shall test and modify the system as required.
2.3.11 Provide photometric analysis of all renovated lighting systems detailing compliance with all applicable codes and standards. See UFC 3-530-01 for details on the required photometric analysis.
Photometric analysis is to be provided at the 35% design.
2.3.12 Demolish existing occupancy sensors and accompanying power pack relays within existing rooms 121F and 122.
2.3.13 Design, furnish, and install new white ceiling occupancy sensors and accompanying power pack relays within the new shared conference room and new IPW storage room. Components shall be compatible and reconnect with the existing lighting circuits and new light switches of each room. Design and approval to be completed by Electrical P.E. Contractor shall test and modify the systems as required.
2.3.14 All new cover plates, receptacles, light switches, and any other similar devices shall be white. All existing shall be replaced with new and be white. Install throughout so that they all match.
2.3.15 Electrical wires and any other electrical components shall not be placed directly on the suspended ceiling system grid and tiles.
FIRE PROTECTION:
2.3.16 Design, furnish, and install a new non-load bearing interior wall separating the new shared conference room and new IPW storage room in accordance with NFPA 101.
2.3.17 Relocate smoke detectors, ADA compliant fire strobes and alarms, and mass notifications that obstruct locations of the new interior wall, new flat panel LED light fixtures, suspended ceiling system, and new HVAC components. Extend items to include the new shared conference room and new IPW storage room. Furnish and install items in accordance with NFPA 101 and Air Force Occupational Safety and Health Standards 91-118, reusing existing components to the maximum extent possible and reprogram fire control panels accordingly (if applicable). If these items are required in additional areas and/or existing items cannot be relocated to extend in these additional areas, furnish and install smoke detectors, ADA compliant fire strobes and alarms, and mass notifications to match those existing within the project’s construction areas. If this occurs, furnish and install conduit, wiring, associated components, and anything else required to install fire protection, identification, and alert systems. Primary and secondary power for the smoke detectors must be provided from the fire alarm control panel. The facility’s fire alarm system must always remain operational throughout this project.
2.3.18 Design, furnish, and install all piping, components, and appurtenances necessary to modify the existing wet-pipe sprinkler system and add fire protection to the new shared conference room and new IPW storage room. Reuse existing water mains and lines where possible but perform all modifications and additions necessary to add wet-pipe sprinkler protection. Reprogram fire control panels accordingly (if applicable). Design, furnish, and install the system in accordance with NFPA 13, UFC 3-600-01, and all appliable codes and standards to ensure all components of the system are designed and installed as required. Install sprinkler heads to match the existing sprinkler heads within the project’s construction areas. Coordinate all fire protection work with the Government and Emergency Services to ensure proper disconnection, draining, testing and any other necessary components and aspects of the existing and new sprinkler systems to perform the modifications.
2.3.19 Furnish and install emergency exit signs and egress lighting in accordance with NFPA 101.
Extend emergency exit signs and egress lighting to include the project’s construction areas.
2.3.20 If any existing components of the fire alarm system require relocation or any modification, it is the responsibility of the contractor to perform whatever work is necessary. Coordinate all fire alarm work with the Government and Emergency Services to ensure proper disconnection and storage of all components. The Contractor must furnish and install all components, detectors, sensors, conductors, and anything else necessary to extend the fire alarm into the new shared conference room and new IPW storage room. Any damage to fire alarm or fire suppression components caused by Contractor will be fixed or replaced at the Contractor’s expense.
MECHANICAL:
2.3.21 Demolish the CyberTWO Series Dual Circuit – Vertical Floor Mounted Precision Air Conditioner by Stulz Air Technology Systems, Inc. and associated hardware and components in existing room 121F.
Disconnect all field connections (electrical, water, and refrigerant) from the conditioner unit. Follow all warnings and cautions provided in the installation, operation, and maintenance manual.
1) Ensure that the water to the 0.25-inch cold water supply line is shut-off before disconnecting from the system. Furnish and install a cap for the supply line. Test the capped fitting for proper seal and function of the supply line.
2) The Government shall lead the evacuation and storage of refrigerant. Refrigerant lines shall be abandoned in place appropriately. Contractor shall coordinate work with the Government to synchronize work on the system.
3) Disconnect all electrical field connections up to the unfused disconnect switch in existing room 121F. Keep the unfused disconnect switch and associated components in its entirety.
2.3.22 Demolish the SCS Series Remote Air Cooled Condenser by Stulz Air Technology Systems, Inc.
and associated hardware and components on the exterior mechanical ground pad. Disconnect all field connections (electrical and refrigerant) from the condenser unit. Follow all warnings and cautions provided in the installation, operation, and maintenance manual
1) The Government shall lead the evacuation and storage of refrigerant. Refrigerant lines shall be abandoned in place appropriately. Contractor shall coordinate work with the Government to synchronize work on the system.
2) Demolish the condenser unit, wire, refrigerant piping, conduit, and additional associated hardware and components up to 6” underground. Abandon the rest in place. Furnish and install one (1) properly sized end cap at the end of the conduit. Backfill the excavated area.
2.3.23 Keep existing warmer/cooler temperature adjustment sensors and accompanying components.
Reuse existing components to the maximum extent possible. Furnish and install conduit and anything else necessary if more materials are needed to extend existing components. Move and extend to new locations if the existing sensors are obstructed by the new interior wall, new flat panel LED light fixtures, and suspended ceiling system. Perform the same at locations that conflict with any other new construction actions. Contractor shall use best practice location placement, coordinate work with EMCS.
2.3.24 Demolish existing supply air diffusers, return air grilles, transfer air grilles, and accompanying branch ducts in rooms 121F and 122 that are obstructed by the new interior wall, new flat panel LED light fixtures, and suspended ceiling system. Demolition shall occur up to the existing branch(es) coming from the accompanying VAV box.
2.3.25 Design, furnish, and install new supply air diffusers, return air grilles, transfer air grilles, branch ducts, and any other components necessary to supply the new shared conference room and new IPW storage room with HVAC capabilities. Components shall match throughout and be white.
2.3.26 Design and size the new branch ducts necessary for a complete and functional system, while achieving occupant comfort. Supply air diffusers, return air grilles, transfer grilles, and branch ducts shall be placed in locations that ensure minimal disruptions (i.e. relocating, demolishing, performance, etc.) to existing and new HVAC, fire detection and suppression, and electrical systems. Install the new supply air diffusers, return air grilles, and transfer air grilles at locations that best serve each room and occupants.
Fit the new branch ducts to be supplied by the best option VAV box. Run the new branch ducts to their accompanied diffuser and grille. Ensure the new diffusers, grilles, and branch ducts connect to and operate the existing VAV box and associated thermostat control.
2.3.27 Furnish and install new balancing dampers throughout the new shared conference room and new IPW storage room.
2.3.28 Relocate existing thermostat and accompanying components for VAV-1-08 from its existing location in room 122 to a new location within the new shared conference room. Contractor shall use best practice of location placement. Reuse existing components to the maximum extent possible, extending them to the new location. Furnish and install conductors, conduit, and anything else necessary if more materials are needed to extend existing. Furnish and install material necessary to patch and repair existing walls as necessary at the existing and new thermostat locations.
2.3.29 Thermostat should be wall-mounted and have a set point coordinated with EMCS. The users in the facility should retain the ability to adjust the temperature up or down 2 degrees from the set point.
2.3.30 All new ductwork and piping shall not be placed directly on the existing suspended ceiling system grid and tiles.
2.3.31 All new ductwork and piping must be insulated.
2.3.32 Test, adjust, and balance the HVAC system at each unit and in each renovated room as required and necessary. Provide a complete TAB report of the system details including but not limited to those specified in UFC 1-200-02 and UFC 3-410-01. It is the responsibility of the Contractor to obtain this independent, third-party service.
INTERIOR CONSTRUCTION, FINISHES, AND ASSEMBLIES:
2.3.33 Furnish and install all materials necessary to repair all existing interior walls, except those to be demolished, throughout the project’s construction area. Areas of insignificant damage such as holes smaller than 4” square, pinholes, cracks and chips, paint peels, among others, shall be repaired with like materials of existing to match existing. All areas needing repair shall use wall surface preparation materials to provide an uninterrupted, flat wall surface transition with existing.
2.3.34 Furnish and erect all materials required to construct the new wall separating the new shared conference room and new IPW storage room. This includes, but is not limited to, galvanized metal studs and wall braces, framing, furring channels, gypsum wall board, among others. The new wall studs and wallboards shall be terminated at the height of the existing walls.
2.3.35 Demolish an area on the wall between existing rooms 121F and 122 to prepare for one (1) 6’-0” Wide x 7’-0” High cased opening leading into the new IPW storage room, see concept drawing for location. Consult with a licensed structural engineer prior to demolition. Furnish, patch, and repair the wall and floor as required to match existing surfaces. Furnish and repair the area as necessary to prevent a gapped transition between existing room 122’s floor and new IPW storage room’s floor. Make the floors leveled (have zero slope, have no height difference).
2.3.36 Rekey the existing door handle of exterior door 106. Ensure the door handle prevents facility entry from the outside but always allows for egress to the outside.
2.3.37 Demolish the one (1) interior door, doorframe, and associated hardware between existing room 121F and existing corridor 121. Repair the wall as necessary to prepare for one (1) new 3’x7’ opaque interior door (that meets current ASHRAE 90.1 standards), doorframe, kickplate, and associated hardware to be installed. Furnish and install these items. Match to existing fully opaque interior doors of IPW offices for uniformity. The doors, doorframes, and hardware shall be prefinished by the manufacturer and approved by the Base Architect. Sand and prep the surrounding wall surfaces to receive one (1) coat of primer and two (2) coats of paint. Paint the surrounding wall surfaces to match the existing color. Furnish and install cove base on the corridor side to match the existing cove base of the coordior. Furnish and install door trim on the hallway side to match the existing door trim that was demolished for uniformity with existing interior doors of IPW offices.
2.3.38 Demolish existing raised floor system in existing room 121F. Furnish and install new 2’ x 2’ steel raised floor system with steel, high pressure laminate panels in the new shared conference room. The new raised floor systems includes floor panels, pedestals, stringers, and any other components necessary for a complete, useable system. Sweep concrete floor to remove any debris prior to installing the raised floor system and associated components. Raised floor system shall be a height equal to existing corridor 121’s floor and existing room 122’s floor. Contractor to field verify. Raised floor system shall be leveled (have zero slope) and maintain necessary design load (live and dead) calculations. Raised floor panel’s color should conform to base standards and match color selected by the Base Architect.
2.3.39 Furnish and install transition strips between the new shared conference room and existing corridor
121. Locate the transition strips under the interior door to create a smooth floor material transition. Use best practice given assembly/installation constraints of the new raised floor system.
2.3.40 Furnish and install transition strips between existing room 122 and the new IPW storage area.
Locate transition strips at the cased opening to create a smooth floor material transition. Use best practice given assembly/installation constraints of the new raised floor system.
2.3.41 Demolish the existing suspended ceiling grid system and tiles throughout existing rooms 121F and
122. Replace with new.
2.3.42 Furnish and install new tegular 2’-0” x 2’-0” suspended ceiling grid system and 5/8” acoustical ceiling tiles throughout. The new suspended ceiling shall maintain existing ceiling height. Grid system and tiles shall match throughout and be white. Color to be approved by the Base Architect. Tiles are not to be vinyl coated.
2.3.43 Demount TV, wood-backing, and associated hardware from the wall in existing room 121F.
Salvage these items. Protect and store these items throughout the duration of this project. Coordinate storage location with the Government. Furnish materials necessary to patch any holes, scratches, etc.
created from original installation. Sand and prep surface prior to re-installation. Install these items on the same wall they were dismantled from after construction is completed. Ensure the TV is leveled (have zero slope) and operates correctly once re-installed. Paint the wood-backing Sherwin Williams’ Accessible Beige, or approved equal. Color should conform to base standards and be approved by the Base Architect. Cover the TV and associated hardware prior to painting.
2.3.44 Paint interior walls and trims within the new shared conference room and new IPW storage room.
Paint color(s) shall be Sherwin Williams’ Accessible Beige, or approved equal. Color should conform to base standards and be approved by the Base Architect. Interior walls will be painted to match the color selected by the Base Architect. At a minimum, painting should include one (1) coat of primer, two (2) coats of paint, sanding and prepping of all surfaces, and placing drop cloths on the floor.
2.3.45 Demolish existing cove base throughout existing rooms 121F and 122. Furnish and install all new 4” rubber cove base throughout the new shared conference room and new IPW storage room. Rubber cove base color shall conform to base standards and be approved by the Base Architect.
2.3.46 All new walls and existing patched and repaired walls shall achieve a level 4 finish.
2.3.47 All new and modified existing interior and exterior door hardware must be Best 7-pin core compatible.
2.3.48 Sweep, remove debris, and damp mop the newly installed hard surface floors throughout the project’s construction areas. Sweep, remove debris, and damp mop the existing hard surface floors that received construction foot traffic. All clean-ups shall be performed at the completion of all construction activities.
SAFETY
2.3.49 Design, furnish and install wiring, alarm trigger, and any other components necessary for a complete, useable electronic duress alarm notification system. See UFC 4-022-01 for details on the required design guidelines. Coordinate all duress alarm work with the Government to ensure proper connection to base security personnel, testing, and any other necessary components and aspects to perform installation. Contractor shall coordinate with the Government for location placement of the duress alarms throughout the project’s construction area.
2.4 GOVERNMENT FURNISHED EQUIPMENT/MATERIALS
The Government will not furnish equipment and materials as part of this project.
2.5 SALVAGE
The Government will not salvage anything as part of this project.
DESIGN REQUIREMENTS
3.1 SUMMARY
Design will consist of all site investigations and design work associated with preparing complete contract documents for this project as described in this SOW. The design documents must be developed from the functional and technical data contained in this SOW and include construction drawings, schedules, and design analysis. The Contractor will also be required to submit design documents for review as described in Paragraph 3.6 as well as final contract documents. The Contractor will be required to attend review and conference meetings as needed and requested by the Government.
3.2 NATURE/EXTENT OF DESIGN
This project requires the services of licensed Design Professionals. The project requires structural design and details for the demolition and construction of interior walls. Mechanical design and details are required for this project with new diffusers, grilles, ductwork, piping, etc. being installed. Electrical design and details including variable frequency drives, power, conduit, circuit breakers, wiring, etc. are required.
Professionally sealed drawings are required. Design/shop/coordination drawings, materials and equipment submittals, and final as-built record drawings are required for this project. Contractor must maintain accurate redline As-Builts throughout construction and must submit final As-Built drawings (with any of the redline changes updated on the drawings) upon project completion (see paragraph 4.7.2 for more information).
The services of a Qualified Fire Protection Engineer (QFPE), as defined in UFC 3-600-01, are required for this project and all applicable design documents and shop drawings must be stamped by the QFPE. Provide a Life Safety Plan for this facility to ensure means of egress are sufficient for occupant load. The QFPE must be involved in every aspect of design, construction, and testing/commissioning as it relates to fire protection and life safety. This includes, but is not limited to, building code analysis, life safety code analysis, design of automatic fire alarm, detection and suppression systems, water supply analysis, a multi-discipline review of the entire project, construction inspections, and witnessing of fire protection acceptance testing/commissioning. Applicable design documents and shop drawings requiring QFPE shall be provided at the 35% design.
Provide psychrometric/load design analysis of all renovated HVAC systems detailing the systems’ compliance with all applicable codes and standards. See UFC 3-401-01 for details on the required HVAC design analysis. Psychrometric/load design analysis is to be provided to the Government at the 35% design.
Base temperature set points for administrative areas are 76°F cooling and 68°F heating. Users in administrative areas are to have a ±2°F adjustment through warmer cooler adjust thermostats. HVAC systems for administrative areas are to be designed to meet 74°F cooling and 70°F heating.
Provide a complete sequence of operations for HVAC systems including, but not limited to, start up, occupied operation (heating and cooling), unoccupied operation (heating and cooling), nighttime setback, pump operation, boiler operation, and chiller operation.
Test, adjust, and balance the HVAC system within the space as required and necessary. Provide a complete TAB report of the system, details including but not limited to those specified in UFC 1-200-02 and UFC 3- 410-01. It is the responsibility of the Contractor to obtain this independent, third-party service.
Provide photometric analysis of all renovated lighting systems detailing compliance with all applicable codes and standards. See UFC 3-530-01 for details on the required photometric analysis. Photometric analysis is to be provided at the 35% design.
3.3 RESPONSIBILITY
3.3.1 Contractor must perform all services, including travel, required to prepare and to furnish complete design documents consisting of drawings, analysis, and addenda as required, for the construction of the project in accordance with this SOW.
3.3.2 Record drawings (attached) are provided to the Contractor as a courtesy at the discretion of the Government, but their accuracy is not guaranteed. The Contractor is responsible for doing his own field investigations of the utilities, existing conditions, and other items in the area.
3.3.3 The Government may provide conceptual drawings to the Contractor, but their accuracy is not guaranteed. The Contractor must do his own field investigations of the utilities, existing conditions, and other items in the area and base his design accordingly.
3.3.4 Although the sizing and specification of major equipment is suggested by this SOW, the Contractor is responsible for all remaining design and coordination to provide an acceptable final product that meets intent of this SOW. Contractor is responsible for ensuring constructability and code compliance.
3.3.5 The Contractor must immediately notify the contracting officer and secure any documents found with “Classified”, “Controlled Unclassified Information” (CUI) or personal information. The Contracting Officer will direct disposition of these documents.
3.4 DESIGN STANDARDS
All design and construction must be accomplished in accordance with applicable UFC’s, ETL’s, (UFC’s and ETL’s may be found on-line at www.wbdg.org.) local and national codes, Columbus AFB Installation Facility Standards (IFS) and all Appendices (Special Construction, Mechanical, and Electrical) and other guidance as modified by this SOW. The IFS document may be found at the following location:
https://www.wbdg.org/airforce/ifs/columbus-afb-ifs. The list of documents includes, but is not limited to, the latest editions of the following
• UFC 1-200-01 DoD Building Code (General Building Requirements)
• UFC 1-200-02 High Performance and Sustainable Building Requirements
• UFC 3-401-01 Mechanical Engineering
• UFC 3-410-01 Heating, Ventilating, and Air Conditioning Systems
• UFC 3-410-02 Direct Digital Control for HVAC and Other Building Control Systems
• UFC 3-410-04 Industrial Ventilation
• UFC 3-450-01 Noise and Vibration Control
• UFC 3-501-01 Electrical Engineering
• UFC 3-520-01 Interior Electrical Systems
• UFC 3-530-01 Interior and Exterior Lighting Systems
• UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings
• UFC 4-022-01 Entry Control Facilities Access Control Points
• NFPA 101
• NFPA 72
• NEC 70
• ACGIH: Industrial Ventilation Manual
• Columbus AFB IFS
• CAFB Base Standards
The Contractor must submit a written request for approval of any deviations from the Government's established standards. No deviations from the Government's established standards will be permitted unless the Contracting Officer has issued prior written approval of such deviation.
https://www.wbdg.org/airforce/ifs/columbus-afb-ifs
3.5 DRAWINGS
Drawings under this Contract must be well prepared, complete, and accomplished in accordance with the best professional practice to show clearly and concisely the type and extent of work to be performed.
3.5.1 Drawings must be drawn to appropriate scales and dimensioned completely and accurately.
Lettering must be large enough to ensure legible half-size reduction and each dimensioned drawing must have a graphic scale. Use of fractions less than 1/8-inch for building dimensions must be avoided. Use standard building material indications and symbols for architectural items and for mechanical, electrical and plumbing equipment.
3.5.2 The Contractor will use paper sheets, 24" x 36". Each sheet will be numbered consecutively beginning with "1 of (x) Sheets" and continue to the last sheet. Number individual drawing sheets as follows:
Drawing Sheet Subject Notation Additional Sheets
Cover (Title Sheet, Map and Index)
T1 and following
Civil/Site Work C1 and following Demolition D1 and following Landscaping L1 and following Architectural A1 and following Structural S1 and following Plumbing P1 and following Mechanical M1 and following Electrical E1 and following
Note: All sheet subjects above may not be necessary for this project
3.5.3 Drawings must be prepared electronically in both AutoCAD (Release 2020) and PDF formats.
3.6 DESIGN SUBMITTALS
3.6.1 DELIVERY: Deliver two (2) hard copies of each submittal and one (1) digital copy via DoD SAFE containing each drawing sheet in PDF file format directly to the CO, along with AF Form 3000. For uploading to DoD SAFE, the Contractor must request an upload link from the CO and then upload the files using the details in the subsequent email from DoD SAFE. For the final design submittal (As-Builts in most cases), the contractor is to provide, in addition to the hard copies and digital copies via DoD SAFE, containing the PDF file as well as the associated CAD files in AutoCAD (Release 2020) .dwg file format. Hard copy submittals must be delivered to:
14th Contracting Squadron 495 Harpe Blvd, Suite 293 Columbus, MS 39710
3.6.2 SUBMITALS AT INTERMEDIATE STAGES OF DESIGN COMPLETION: To facilitate review and feedback throughout the design process, designs are submitted at various stages of completion as follows:
1) 35% DESIGN SUBMITTAL: Contractor must submit 35% design documents within 14 days after Notice to Proceed (NTP). The 35% design must include complete and thorough detailing to leave no question as to how demolition and construction is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “35% REVIEW SET” and the date.
2) 65% DESIGN SUBMITTAL: Contractor must submit 65% design documents within 14 days after receipt of the “Approved” 35% design. The 65% design must include complete and thorough detailing to leave no question as to how demolition and construction is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “65% REVIEW SET” and the date.
3) 95% DESIGN SUBMITTAL: Contractor must submit 95% design documents within 07 days after receipt of the “Approved” 65% design. The 95% design (essentially complete design and drawings, pending review and acceptance by Government as the 100% APPROVED CONSTRUCTION SET) must include complete and thorough detailing to leave no question as to how assembly is intended. All design documents must be clearly annotated (in both title block and revision block of drawings) with “95% REVIEW SET” and the date.
4) 100% DESIGN/APPROVED CONSTRUCTION SET: Contractor must submit the 100% DESIGN APPROVED CONSTRUCTION SET within 07 days after Contractor receipt of the “Approved” 95% design. The construction set must incorporate and/or address any Government comments on the 95% design and should leave no question to how demolition and construction will be done. If professionally stamped and sealed drawings are required for this project (paragraph 3.2), the approved construction set must include all stamped drawings. All final design documents must be clearly annotated (in both title block and revision block of drawings) with “APPROVED CONSTRUCTION SET” and the date.
5) For each holiday or extraordinary event in a submittal period, increase the required days for submittal by one day for each day in the event. Deliver no submittals within (before or after): one week of Thanksgiving; two weeks of Christmas; or one week of New Year’s Day. Extraordinary Events include: unscheduled holidays for base personnel; base-wide training exercises; etc. The Government may prohibit work during such events.
3.6.3 PARTIAL SUBMISSIONS: Partial submissions normally will not be accepted. However, under some circumstances, to expedite project execution, the Government may accept design/shop drawings or material submittals for major elements or long-lead-time equipment for review and approvals prior to 95% design submittal. Government approval of such items does not relieve the Contractor of his responsibility to ensure a complete, constructible, code-compliant design.
3.6.4 CONSTRUCTION PRIOR TO 100% DESIGN: Construction may not commence until Government approves the 100% design. Exception: To expedite contract completion, Contractor may petition CO for an Interim Notice to Proceed with specific elements of construction. Government review does not constitute approval or acceptance of any variations from this SOW, the Contractor’s Proposal, or the Contract unless authorized in writing by the CO. The Interim Notice to Proceed, if exercised, will in no way mitigate the responsibility of the Contractor to provide a complete, constructible, code-compliant design.
All drawings, specifications, design analyses and other project materials become the property of the Government.
3.7 DESIGN REVIEWS
3.7.1 DESIGN PHASE REVIEWS: Government review of each XX% design submittal (where XX = 95 or 100 as required per 3.6.2) will require up to fourteen (14) days after Government receipt. The Government will determine the sufficiency of each XX% design submittal as follows:
1) Approved as Submitted. If design is sufficient to proceed without correction to the next phase submittal, one (1) copy of AF FORM 3000 marked "Approved" will be returned to the Contractor.
Contractor must advance to the next stage design submittal.
2) Approved - Except as Noted. Design submittals that have only minor errors or deficiencies will be marked in red to indicate necessary corrections. Marked materials, along with one (1) copy of AF FORM 3000 indicating "Approved - Except as Noted" will be returned to the Contractor.
Contractor must revise the design documents, making the necessary corrections, and advance to the next stage design submittal.
3) Disapproved. Design submittals that are incomplete or require more than minor corrections will be marked in red to indicate necessary corrections. Marked materials, along with one (1) copy of AF FORM 3000 marked “Disapproved” will be returned to the Contractor. Contractor must revise the design documents, making the necessary corrections, and re-submit as the current stage “XX% Design – 2nd (or subsequent) Submittal”.
4) Disapproved – Major Deficiency. Examples include, but are not limited to, design submittals that fall significantly short of indicated level of completion, grossly deviate from or misinterpret the SOW, or contain errors of a nature or quantity that indicate failure of Contractor to review submittals for completeness, correctness, and coordination between trades. For such submittals, the Government will not complete a comprehensive review or provide an exhaustive list of needed corrections. Rather, one (1) copy of AF FORM 3000 marked “Disapproved – Major Deficiency” along with general reason(s) for disapproval will be returned to the contractor. The CO will issue a written warning to the Contractor that any subsequent grossly incorrect/incomplete submittals constitute evidence of inability to complete the project and may result in declaring the Contractor “In Default.” Contractor must correct deficiencies and resubmit as current stage “XX% Design – 2nd (or subsequent) Submittal”.
3.7.2 100% DESIGN REVIEW: The Government will have fourteen (14) days to verify that all review comments have been addressed and no unapproved changes have been made. Upon Government approval of the 100% design documents, the Contractor may begin construction.
3.7.3 IMPACT OF REVIEW ON PERIOD OF PERFORMANCE: Contract completion time includes time for Government review of drawings, specifications, and material submittals. Unless otherwise noted, the Government will use no more than 14 calendar days for review of each design submittal and each subsequent re-submittal of “Disapproved” submittals (paragraph 3.7.1, c or d). There will be no increase in the period of performance for review of re-submittals.
3.7.4 RESPONSE TO REVIEW COMMENTS: The Contractor is required to respond to all review comments and submit their annotated comments as a design analysis appendix in the subsequent design submittal. All comments must either be accepted and incorporated into the next design submittal or satisfactorily rebutted.
3.7.5 DESIGN ACCOUNTABILITY: The Contractor is solely responsible for accurately designing and constructing everything necessary to provide a fully functional product. Government approval of any design or design-related submittal does not waive or remove full liability from the Contractor to provide a design, facility, or final product that meets the intent of this SOW, performs as intended, and adheres to all applicable codes and standards.
3.8 CONFERENCES
3.8.1 PRECONSTRUCTION CONFERENCE: A Preconstruction Conference (Pre-Con) will be held at the Contracting Office as indicated.
3.8.2 COORDINATION/REVIEW CONFERENCES: Coordination/review conferences may be held from time to time as required. The Contractor may request such conferences when it is deemed necessary by both parties to clarify the work or expedite the preparation of plans, specifications or construction.
3.8.3 REVIEW/CONFERENCE MINUTES: The Contractor will be responsible for making memoranda of record of any conversations and minutes of any meeting with Government personnel concerning this project and forward one copy of these memoranda/minutes to each party concerned and one copy to the Contracting Officer within seven (7) days. The final version of the meeting minutes will be approved and filed at the CO’s discretion. Each copy will be numbered consecutively and chronologically.
3.8.4 MEETING LOCATIONS: Meetings will be held in person at Columbus Air Force Base. Contractor transportation costs for attending all conferences/reviews and meetings must be included in the Contractor’s Proposal. There will be no teleconferences unless permitted otherwise by the Contracting Officer.
End of Design Requirements
ADMINISTRATION OF CONSTRUCTION
4.1 PERFORMANCE CAPABILITIES
4.1.1 One week prior to the start of work under this contract, Contractor must submit in writing to the CO for review and possible approval the names and credentials of Contractor Project Manager, Contractor Site Superintendent, and Quality Control Manager. Subsequent proposed changes of approved personnel must be submitted in writing to and receive prior approval from the CO before working on the project.
Each of these personnel may upon CO approval hold additional onsite duties which must not diminish their required performance. Contractor must demonstrate to the Government’s satisfaction that proposed personnel exceed education, technical and experience levels of personnel described in this Contract including the following:
1) Contractor Project Manager (CPM) - Provide management of the prime contract to include subcontract purchasing and administration, review of material submittals and shop drawings. CPM must have full authority to develop cost proposals, negotiate with Government and subcontractors, sign awards and modifications, supervise project superintendents, attend weekly CO/CE/PM Contractor status meetings as well as pre-performance site visits, pre-final and final inspections.
The CPM must have a minimum of 5 years previous experience as primary contract manager or equivalent experience as a primary estimator and negotiator with a contracting firm engaged in similar multi-discipline commercial construction projects. CPM must also have not less than 5 years’ experience managing subcontractors.
2) Contractor Site Superintendent (CSS) - Provide on-site construction superintendent(s) to oversee all work under this contract. Site supervision must be daily (constant throughout each day) and includes submission of detailed weekly progress reports, scheduling and coordination of subcontractors and material suppliers, and attendance at all construction progress meetings, CO site visits, and pre-final and final inspections. Superintendents must have a minimum of 5 years previous experience as a project superintendent (exclusive of time employed as a tradesman or working foreman) for a general contracting firm overseeing one or more multi-discipline commercial construction projects. The superintendent must be available within 15 minutes during all normal working hours, except for such incidental errands as required by his duties. The superintendent must be responsible for the proper coordination and timeliness of the work, and for the proper workmanship of all trades; therefore, his absence from the project site without a suitable substitute Contractor representative must be considered as damaging to the Government.
3) Quality Control Manager (QCM) - Provide quality control management for the project. QCM must continually (constant throughout each day) ensure full compliance with all safety requirements, verification that work and materials in place and stored on site are in accordance with the approved construction documents, shop drawings and material submittals. QCM must submit daily status reports recording activities at each project site, prepare and coordinate material submittal sheets and shop drawing submittals, schedule and coordinate testing procedures, prepare quality control reports for construction progress and other required meetings, and attend all pre-final and final inspections. QCM must have a minimum of five years’ experience in Quality Control Management of multidiscipline construction projects.
4.1.2 Contractor must have additional personnel including management, technical, service, labor or subcontractor, available as necessary to fulfill all construction contract requirements.