The provided document is an appendix to a draft Request for Proposal (RFP) for a Non-Temporary Storage Contract (NTSC) for the storage of household goods (HHG) belonging to Department of Defense (DoD) Service Members, DoD Civilians, and U.S. Coast Guard Members.
The key requirements outlined in the document include: the contractor shall maintain storage facilities within 100 miles of specified major installations in the South Central region, with a capacity up to 27 million gross pounds of HHG annually for each installation. The contractor shall also maintain additional regional support storage facilities to provide the required storage capacity. All storage facilities must comply with the Performance Work Statement requirements. The government may direct changes to the location, proximity, and capacity requirements during contract performance.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HTC711-XX-R-R0XX
Appendix B.4 (South Central Region)
B4-1
Region 4 (Central [South]) Major Installations Proximity Requirements
B4.1. The Contractor shall maintain storage facilities within 100 miles of each of the major installations listed below in Region 4:
• Little Rock AFB, Arkansas
• Barksdale AFB/Ft. Johnson, Louisiana
• Kirtland AFB, New Mexico
• Ft. Sill/Tinker AFB, Oklahoma
• Ft. Bliss, Texas
• Ft. Cavazos, Texas
• JB San Antonio, Texas
B4.2. The Contractor shall maintain regional support storage facilities, in addition to the location requirements identified in B4.1, to provide the requisite storage capacity for shipments from the outlying areas.
B4.3. The Contractor shall maintain storage facilities with capacity up to 27 million gross pounds of HHG annually for each of the major installations identified in B4.1.
B4.4. All storage facilities shall also comply with all requirements identified in the Performance Work Statement.
B4.5. The Government may direct changes to the location and proximity requirements identified in paragraph B4.1. and the capacity requirements identified in Paragraph B4.3 during contract performance to be mutually agreed upon by the Government and the Contractor in advance.