This document is an Appendix B.3 to a draft Performance Work Statement for a federal contract solicitation. It outlines the regional storage facility requirements for the Northeast region under the Non-Temporary Storage Contract (NTSC).
The key details are:
- The contractor must maintain storage facilities within 100 miles of several major military installations in the Northeast region, including Scott AFB, Ft. Campbell, Hanscom AFB, Joint Base McGuire-Dix-Lakehurst, Ft. Drum, Wright Patterson AFB, and Ft. McCoy.
- The contractor must also maintain additional regional support storage facilities to provide the required storage capacity of up to 20 million gross pounds of household goods annually for each major installation.
- All storage facilities must comply with the overall Performance Work Statement requirements.
- The government may direct changes to the location, proximity, and capacity requirements during contract performance, to be mutually agreed upon.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HTC711-XX-R-R0XX
Appendix B.3 (Northeast Region)
B3-1
Region 3 (Northeast) Major Installations Proximity Requirements
B3.1. The Contractor shall maintain storage facilities within 100 miles of each of the major installations listed below in Region 3:
• Scott AFB, Illinois
• Ft. Campbell, Kentucky
• Hanscom AFB, Massachusetts
• Joint Base McGuire-Dix-Lakehurst, New Jersey
• Ft. Drum, New York
• Wright Patterson AFB, Ohio
• Ft. McCoy, Wisconsin
B3.2. The Contractor shall maintain regional support storage facilities, in addition to the location requirements identified in B3.1, to provide the requisite storage capacity for shipments from the outlying areas.
B3.3. The Contractor shall maintain storage facilities with capacity up to 20 million gross pounds of HHG annually for each of the major installations identified in B3.1.
B3.4. All storage facilities shall also comply with all requirements identified in the Performance Work Statement.
B3.5. The Government may direct changes to the location and proximity requirements identified in paragraph B3.1. and the capacity requirements identified in Paragraph B3.3 during contract performance to be mutually agreed upon by the Government and the Contractor in advance.