This document is an Addendum to a State and Local contract opportunity for the new construction of Enlisted Barracks 5 (EB5) in Hermiston, Oregon. The project, overseen by SERA Architects, Inc., involves the full construction of a 21,505 square foot, 2-story EB5 building, including site work, utilities, landscaping, building foundations, structure, envelope, roofing, interiors, MEP systems, and low voltage/AV. This Addendum modifies the original project manual and drawings, providing clarifications and changes to various specification sections and drawing sheets.
The key changes include updates to metal fabrications, metal stairs, tiling, television mounts, fire alarm system, earthwork, drawings, and structural elements. Specific updates are provided for elements such as insulation values, light bollard foundations, mirror sizes, and coordinating grid numbers between architectural and structural drawings. An IT fiber map is also added to clarify existing and new scope for fiber and conduit, including locations of existing junction/pull boxes.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM No. 02 - Page 1 of 3
Addendum 2- EB5
Project Name OMD EB5 Project # 2201032 Project Address
78798 Ordnance Rd Hermiston, OR 97838
Company SERA Architects, Inc.
Address 600 SW 10th Ave
Suite 500 Portland, OR 97205
Addendum # 02
Date of Issuance
08 September 2023
To: All Contract Document Holders
This Addendum forms a part of the Contract Documents and modifies the original Project Manual and Drawings, dated 07 07 2023 as noted below. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject bidder to disqualification.
SPECIFICATION SECTION ATTACHMENTS:
01 10 00-Summary, 05 50 00- Metal Fabrications, 05 51 00-Metal Stairs, 09 30 00-Tiling, 11 52 70-Television Mounts, 28 31 66-Interior Fire Alarm and Mass Notification, Non-Addressable, 31 20 00-Earth Moving
DRAWING ATTACHMENTS
1. Drawing Sheet G002
2. Drawing Sheet G051
3. Drawing Sheet G101
4. Drawing Sheet LP101
5. Drawing Sheet LP102
6. Drawing Sheet LI101
7. Drawing Sheet A002
8. Drawing Sheet A051
9. Drawing Sheet A202
10. Drawing Sheet A301
11. Drawing Sheet A451
12. Drawing Sheet A502
13. Drawing Sheet A701
14. Drawing Sheet A702
15. Drawing Sheet A703
16. Drawing Sheet A704
17. Drawing Sheet A901
18. Drawing Sheet S101
19. Drawing Sheet S101S
20. Drawing Sheet S102
21. Drawing Sheet S103
22. Drawing Sheet S502
23. Drawing Sheet E002
1 of 3 4
ADDENDUM No. 02 - Page 2 of 3
PROJECT MANUAL
Division 01 – GENERAL REQUIREMENTS
01 10 00 - Summary
1. Clarify: Paragraph 1.05.A.
DIVISION 05 - METALS
05 50 00-Metal Fabrications
1. Delete: Paragraph 2.01.B.
2. Clarify: Paragraph 2.05.A and B.
05 51 00-Metal Stairs
1. Clarify: Paragraph 2.04.A.
2. Clarify: Paragraph 2.05.A.
3. Clarify: Article 2.06.
DIVISION 09 - FINISHES
09 30 00-Tiling
1. Change: Sub-Paragraph 2.02.A.1
2. Change: Paragraph 2.02.B.
DIVISION 11 - EQUIPMENT
11 52 70 – Television Mounts
1. Change: Sub-Paragraph 2.02.A.1.
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 31 66 – Interior Fire Alarm and Mass Notification System, Non-Addressable
1. ADD: New Section supplemental to 28 12 10 provided to capture new cybersecurity requirements for facility related control systems.
DIVISION 31 – EARTHWORKS
31 20 00-Earth Moving
1. Change: Sub-Paragraph 1.01.B.1.
DRAWINGS
G002
1. DELETE Section 01 10 00 from delegated design and deferred submittals table
G051
2. CHANGE Allowable area calculations
3. CHANGE Energy conservation building envelope requirements per ASHRAE 90.1-2019
G101
1. ADD Occupant load summary for levels 1 and 2
2. ADD Common path of egress travel on opposite side of building on level 1 and 2
3. CHANGE Common path of egress travel distance and code section to 1030.8
LP101
1. CHANGE Work limit line adjusted to show stormwater basin west of Elm Street is not in project scope
2. CHANGE Cobblestone size to PER CIVIL. Refer to civil drawings for cobble size
3. CHANGE Thornless honey locus tree size to 2” caliper on PLANTING SCHEDULE
4. DELETE Kinnikinnick from PLANTING SCHEDULE
LP102
1. DELETE Synthetic grass surfacing edge detail
2 of 3 4
ADDENDUM No. 02 - Page 3 of 3
LI101
1. CHANGE Work limit line adjusted to show stormwater basin west of Elm Street is not in project scope
A002
1. CHANGE Typical exterior wall detail to have R13.3 continuous XPS rigid insulation
2. CHANGE FC6 Floor-Ceiling Assembly at I-Joists to have hat channel furring
A051
1. ADD surface concrete pads for all light bollards
2. CHANGE Light bollards not to overhang adjacent sidewalk
3. CHANGE Keyed Note S31 for 24” Conc. pole Base & refer to struct.
4. DELETE Precast base from Site pole lighting verbiage in legend
A101 & A102
1. CLARIFY General Note E includeded describing the Campus Standard Access Control System
2. CLARIFY Card Reader clarification in Floor Plan Legend
A103
3. ADD Solar ready zones on roof plan
4. ADD Solar ready zone hatch to legend
5. ADD Section callout for detail 5/A502 at Stairs 1 & 3 on Attic Plan
A202
1. ADD Trim line showing location of 1x4 painted trim to cover top plate in public spaces
2. ADD Trim line type to legend
3. CHANGE Note C3 to reference trim detail
A301
1. CHANGE Exterior double door E107 panel types to remove glazing lites
A451
1. CHANGE Wall section stair and wall section window typical to show chair rail with clear stain finish at level 2
A502
1. CHANGE Typical guardrail detail to align with Pacific Stair R400
A601
1. ADD Detail callout for resilient flooring to resilient flooring transition between restrooms, typical
2. CHANGE Mirror size in men’s and women’s restrooms to (3) 18”x30” at 69” AFF
A603
1. CHANGE Mirror size in Sr. Leader’s restrooms to 18”x30” at 69” AFF
A701
1. CHANGE Light bollard detail to show concrete pad, anchorage kit by manufacturer, and fixture head not to overhang adjacent sidewalk
2. CHANGE Soffit detail to have R13.3 continuous XPS rigid insulation
3. CHANGE CMU wall footing detail to have fluid applied waterproofing in a location that allows for a continuous membrane
A702
1. DELETE Plan section at recessed jamb detail
A703
1. DELETE Duplicate section at HM door head detail
3 of 3 4
ADDENDUM No. 02 - Page 4 of 3
A704
1. CHANGE Detail section at rake to include fiber cement soffit
2. CHANGE Detail section at ridge to show correct specification section for plywood
A801
1. ADD Resilient flooring to resilient flooring transition detail
2. ADD Bullnose tile detail
A901
1. CHANGE Exterior double door E107 panel types to be full metal with no glazing
A921
1. ADD Senior Leader’s Quarter spaces to finish schedule
2. CLARIFY Circulation 209 space included in finish schedule as separate line item
3. CHANGE 09 30 00 Tiling finishes to Dal Tile manufacturer in arctic white and desert gray
4. CLARIFY Storage and circulation spaces by separating into individual spaces in finish schedule to clearly define flooring finish in each space
5. CLARIFY Stair spaces in finish schedule by referring to the stair areas labeled on floor plans with additional remarks on where to specifically apply flooring finishes
S101
1. CHANGE Grid numbers coordinated to match architectural
S101S
1. CHANGE Mech. yard slab pulled out to 4” from bldg. edge to accommodate 4” slab edge insulation
2. CHANGE Mech yard slab extended south to better accommodate equipment clearances.
S102
S103
S501
1. ADD Light Pole Foundation Detail 16/S501
S502
2. ADD Missing sheet of masonry details included.
E002
1. CHANGE anchorage kit at concrete walk in lieu of direct burial anchors at G1 fixtures.
EB5FiberMap
1. ADD IT Fiber Map clarifying Existing and New scope for fiber and conduit including locations of existing junction pull boxes.
END OF ADDENDUM ‘02’