This document contains a schedule of items for the Renovation of Sabino Canyon Recreation Area Pavement project. The work involves repaving and repairing several miles of existing pavement on roads 100, 100A, 100B, and 100D within the recreation area. The base bid includes clearing, grading, installing erosion controls, repaving over 5 miles of roadway with 3 inches of asphalt, and repairing existing pavement. There are also three additive bid items which provide for repaving additional segments of road 100 and 100A, as well as adding intermittent concrete ditch lining on road 100. Temporary traffic control is required for all work. The solicitation number for this federal contract opportunity is 127EAX21R0033 and it was issued by the Department of Agriculture Forest Service Southwestern Region. Bids are due by September 15, 2021. The construction value is estimated between $1,000,000 and $3,000,000.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

v0: 3/25/2021Renovation of Sabino Canyon Recreation Area Pavement
SCHEDULE OF ITEMS
BASE BID ITEMS
Method ofEstimatedEstimated
Pay ItemDescriptionMeasureQuantityPay UnitUnit CostTotal
151.01MobilizationLump Sum1EA
152.04Slope and reference staking, roadway existing ('subgrade') surface and finish stakes per table 152.-1Mile5.81EA$0.00
152.06Clearing and grubbing limits--flaggedMile6.55EA$0.00
157.13Soil Erosion & Pollution Control including ditch and inlet wattlesMile5.55EA$0.00
201.03Clearing and grubbing, 6-feet wide per road shoulder, each side, dispose off National Forest LandMile6.55EA$0.00
202.04Special clearing and grubbing, ditchlines, cutslopes as indicated by CORACRE1EA$0.00
301.01Aggregate surface course, per 703.05 and gradation per Table 703-3, compaction method per 301.05, primarily for shouldingTon1436EA$0.00
303.07Roadway reconditioning, per 303.07--Ditch, Shoulder, Road (approx 2.85 miles)Mile2.85EA$0.00
304.01Full Depth Reclamation (approx 2.85 miles)SY33440EA$0.00
403.01Hot asphalt concrete pavement, 3-inch compacted depth, PAG Residential 1/2-inch mix.Ton6080EA$0.00
414.13Crack sealant, completeTon10.5EA$0.00
418.04Asphalt Pavement Full Depth Patch, Type 2 (FDP-2).SY250EA$0.00
602.11Install 24-inch Corrugated galvanized steel 16 gauge drainage pipe, including sawcut and patch w/3-inch hot mix, junction Road 100A & 100B on 100BFoot60EA$0.00
634.01Pavement markings, thermoplastic, type H, with glass beads, WHITEFoot2800EA$0.00
634.02Pavement markings, thermoplastic, type H, with glass beads, YELLOWFoot3200EA$0.00
635.01Temporary traffic control--Sabino Road 100--One Lane or Delay Public Access--During survey, veg, crack, fog workDay28EA$0.00
635.02Temporary traffic control--Sabino Road 100--Full Closure--During ditch, shoulder, milling, paving workDay30EA$0.00
635.03Temporary traffic control--Lower Sabino/Bear Roads 100A, B, D--During survey, veg, crack, fog workDay14EA$0.00
635.04Temporary traffic control--Lower Sabino/Bear Roads 100A, B, D--During ditch, shoulder, milling, paving workDay14EA$0.00
635.05A PAIR of Variable Message Sign sized for 45 mphDay75EA$0.00
635.06Variable Message Sign sized for 25 mphDay75EA$0.00
637.01Field OfficeDay75EA$0.00
SUBTotal NO MOB$0.00
BASE BIDSUBTOTAL WITH MOB$0.00
ADDITIVE BID ITEM #1
Road 100 from MP 0.000 to 0.740
151.12MobilizationLump SumEA
152.14Slope and reference staking, roadway existing ('subgrade') surface and finish stakes per table 152.-1Mile0.74EA$0.00
304.11Full Depth Reclamation (approx 0.740 miles)SY9117EA$0.00
403.11Hot asphalt concrete pavement, 3-inch compacted depth, PAG Residential 1/2-inch mix.Ton1661EA$0.00
406.11Fog Seal @ 0.06 gal/sy on new matTon11.85EA$0.00
406.12Fog Seal @ 0.12 gal/sy on old matTon20.53EA$0.00
635.13Temporary traffic control--Lower Sabino/Bear Roads 100A, B, D--During survey, veg, crack, fog workDay8EA$0.00
635.14Temporary traffic control--Lower Sabino/Bear Roads 100A, B, D--During ditch, shoulder, milling, paving workDay8EA$0.00
SUBTotal NO MOB$0.00
TOTAL WITH MOB$0.00

SUBTOTAL WITH MOB $0.00

ADDITIVE BID ITEM #2
Road 100A from MP 0.000 to 0.540
151.22MobilizationLump SumEA
303.27Roadway reconditioning, per 303.07--Ditch, Shoulder, RoadMile0.54EA$0.00
304.21Full Depth Reclamation (approx 0.540 miles)SY6653EA$0.00
403.21Hot asphalt concrete pavement, 3-inch compacted depth, PAG Residential 1/2-inch mix.Ton1210EA$0.00
406.21Fog Seal @ 0.06 gal/sy on new matTon1.79EA$0.00
635.23Temporary traffic control--Lower Sabino/Bear Roads 100A, B, D--During survey, veg, crack, fog workDay5EA$0.00
635.24Temporary traffic control--Lower Sabino/Bear Roads 100A, B, D--During ditch, shoulder, milling, paving workDay5EA$0.00
SUBTotal NO MOB$0.00
TOTAL WITH MOB$0.00

SUBTOTAL WITH MOB $0.00

ADDITIVE BID ITEM #3
Road 100 Intermittent Concrete Ditch Lining MP 3.50 to 3.78, to match adjacent area
151.32MobilizationLump SumEA
608.31Type 4 Concrete Paved Waterway--concrete ditch apron--4-inch slab depth--WWF reinforcement--Adobe integral colorSY600EA$0.00
303.33Ditch Reconditioning--clean interior of grated cross drainsLump Sum5EA$0.00
635.32Temporary traffic control--Sabino Road 100--Full Closure--During concrete apron and cross drain workDay7EA$0.00
SUBTotal NO MOB$0.00
TOTAL WITH MOB$0.00

SUBTOTAL WITH MOB $0.00