2021 Consolidated Projects Combined Specifications R1 6-17-2021.pdf

PDF 4 MB Posted

Attached to
VTANG 2021 Consolidated Construction Projects Federal contract opportunity
Solicitation number
W50S9C-21-B-0004
Issued by
Department of the Army Vermont Army National Guard

About this file

This federal solicitation seeks bids for construction projects at the Vermont Army National Guard facilities. Work includes concrete demolition and replacement; installation of three new roll up doors; communication conduit and boxes; roadway and parking lot line striping; HVAC equipment installation, maintenance and repair; fire hydrant maintenance; asphalt and concrete repairs; hangar trim removal and gutter installation; electrical work; and overhead door replacement. The solicitation also includes VAV control valves, balance valves and piping for HVAC equipment. The Department of the Army and Vermont Army National Guard are the agencies involved. The response date is not provided.

View the file

Other files for this federal contract opportunity

Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2021 Consolidated Projects Rev. 6-17-2021

-Specifications-

CURZ192314 B312 Vehicle Lift Concrete Repair

A SELECTIVE DEMOLITION

1 Concrete Slabs-on-grade: Saw-cut perimeter of area to be demolished, and then break up and remove.

2 Contractor shall use a wet saw and minimize concrete dust when cutting any concrete on the project site.

B DISPOSAL OF DEMOLISHED MATERIALS

1 Do not allow demolished materials to accumulate on-site.

2 Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

3 Flushing of concrete trucks is restricted to the location specifically designated for this purpose by the Contracting Officer’s Representative.

C DUST AND DEBRIS CONROL

1 Provide protective measures to control accumulation and migration of dust and dirt in all work areas.

2 Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

D PREPARATION

1 Remove all wood and wood scraps, sawdust, hardened concrete, construction debris, ice, snow, and other foreign materials from and between forms and from other areas in which concrete will be placed.

2 Thoroughly clean all areas to receive concrete to ensure proper placement of concrete.

3 Verify that Contracting Officer’s representative has completed all tests and inspections and they pose no objections to the placement of concrete.

E INSTALLATION

2021 Consolidated Projects Specifications Vehicle Lift Concrete Repair

1 Accurately position reinforcement and firmly support with approved devices and wire together to prevent displacement or distortion.

2 Place dowels and anchor them into position.

3 Provide proper cover around reinforcement, as indicated on the Drawings, or in conformance with ACI requirements when not shown.

4 Placement of reinforcement after concrete has been placed is prohibited.

F PLACING CONCRETE

1 Consistency and Quality of Concrete - Mix, transport, and place concrete so as to maintain proper consistency, to avoid segregation, and to insure placement in final position before initial set takes place. Re-tempering of concrete is prohibited. Control the rate of placement so that the concrete remains plastic and flows readily into spaces between the reinforcing bars, and can be worked into corners and around inserts without forming voids.

2 Vibration - Unless otherwise specified or directed by Engineer, vibrate all reinforced concrete. Use only approved mechanical vibrators operated by experienced operators.

Apply vibrators at uniformly spaced points not further apart than the visible effectiveness of the machine. Vibrate concrete sufficiently to produce satisfactory consolidation without causing objectionable segregation. Manually shake reinforcing bars to insure bond with the concrete. It is prohibited to use vibrators to transport concrete in the forms and to insert them into lower layers of concrete that have begun to set.

G FINISHING CONCRETE

1 General – Surfaces shall be brought to accurate lines and levels to receive subsequent finishes.

2 Deposit concrete and bring to approximate final grade. Bring surface to required grade using a straight edge.

3 Float and trowel the concrete after it has sufficiently set so that water and excess fine material is not brought to the surface.

4 Do not sprinkle dry cement or mixture of dry cement and sand on the surface to absorb moisture.

5 Tamp, where necessary, to achieve proper consolidation.

6 The surfaces shall be given two steel trowelings. The finished surface shall be free of trowel marks.

7 The finish shall be protected, and curing shall start immediately and be maintained for at least 7 days.

8 If correction of surface defects is required, submit to Contracting Officer’s Representative the measures and methods proposed.

H CURING CONCRETE

1 General - Cure concrete using the following methods or combinations thereof. Modify or augment these methods, or adopt additional protective measures, when required to compensate for changes in humidity, temperature, wind, or other conditions. Minimum curing period shall be 7 days.

2 Water Curing - Water curing during cold weather concreting is not permitted. Water curing is mandatory for all slabs-on-grade and structural slabs. Continuously keep concrete surfaces wet by covering with water, by continuous fog spraying, or by covering with burlaps, cotton mats, or other approved material thoroughly saturated with water and kept wet by intermittent hosing. Protect water cured concrete against freezing for the full curing period specified.

3 Curing Compounds - The use of curing compounds is not permitted during hot weather concreting, when they are incompatible with subsequent coatings, and when they may release pollutants, contaminants, or toxic materials. Curing compounds shall be used on walls.

I CURING COMPOUND

1 Submit product data and manufacturer’s instructions for concrete curing compound.

J HARDENING/SEALING CONCRETE

1 Apply approved concrete hardening compound to new concrete per manufacturer’s instructions.

2 Hardening compound shall be compatible with any curing compounds used.

K FLOOR HARDENER COMPOUND

1 Provide a colorless aqueous solution containing zinc silicofluoride, magnesium silicofluoride, or sodium silicofluoride. These silicofluorides can be used individually or in combination. Proprietary hardeners may be used if approved in writing by the Contracting Officer.

L PATCHING CONCRETE

1 Mortar - Mortar for patching shall be of the same materials and proportions used for the concrete, except that the coarse aggregate shall be omitted and a sufficient amount of white cement shall be substituted for the grey cement in order to produce a patch whose color matches the color of the surrounding surfaces. Mortar shall not be thicker than 1 part cement to 3 parts sand. Keep mixing water to a minimum. Re-temper mortar, without addition of water, by occasional mixing to prevent setting. Using mortar which has begun to set or is more than 1 hour old is not permitted.

2 Application of Mortar - Thoroughly compact mortar into place and screed to leave the patch slightly higher than the adjacent surface. Leave undisturbed for one or two hours to permit initial shrinkage before being finally finished to match adjoining work. Patches exceeding 1" in depth shall be filled to within 1" of the surface and, after sufficient time has elapsed for shrinkage, final patching shall proceed. Keep all patches wet for at least 5 days.

M PROTECTION

1 Protect concrete form damage to sun, rain, flowing water, weather and mechanical injury.

A LIFT ANCHOR SYSTEM

1 Concrete Anchors: Adhesive or expansion anchors fabricated from corrosion-resistant materials with allowable load capacities in accordance with ICC-ES AC193 and ACI 318 greater than or equal to the design load as determined by testing per ASTM E488/E488M conducted by a qualified testing agency.

B CONCRETE

Mix properties:

28 day compressive strength (psi) 4,000 Max. Water-cement ratio (lb./lb.) 0.45 Entrained Air Content (%) 0-2 Slump (inches) 2-4

C CEMENT

1 Portland Cement – ASTM C150, Type 1 unless otherwise specified

D AGGREGATES

1 Fine Aggregates - ASTM C33

2 Coarse Aggregate – ASTM C33, ¾” maximum for structural concrete

E REINFORCEMENT

1 Reinforcing Bar – ASTM A-615, Grade 60. Stirrups and ties shall be Grade 40.

2 Reinforcing Wire – ASTM A82.

3 Wire Fabric – ASTM A-185

4 Supporting Devices – Galvanized or non-rusting type. Use of plastic tipped accessories in concrete exposed to weather, water or view.

F FABRICATION

1 Accurately fabricate to details and dimensions shown on the Drawings.

2 Reinforcing bars shall be bent cold and shall not be bent or straightened in a manner which will injure the material's properties.

3 Bend all reinforcement in accordance with ACI 318.

G ADMIXTURES

1 Concrete for interior slabs that are to receive a steel trowel finish shall have no entrained air.

2 Water Reducing Retarder - ASTM C-494 - Quantity of retarder to be added per sack of cement shall be as recommended by the approved manufacturer for general use and as required to suit actual ambient or mix temperatures.

3 No other admixtures are permitted without the prior acceptance of Contracting Officer’s

Representative.

4 Admixtures shall be compatible with one another and with aggregates, cement, finishing materials, and other materials which may be affected thereby.

H EPOXY RESIN

1 Provide epoxy-resin materials that consist of two-component materials conforming to the requirements of ASTM C881/C881M, Class as appropriate for each application temperature to be encountered, except that in addition, the materials meet the following requirements:

a Material for use for embedding dowels, reinforcing and anchor bolts be Type IV, Grade 3.

I MORTAR MATERIALS

1 Portland Cement: ASTM C 150/C 150M, Type I or II, except Type III may be used for cold-weather construction.

J Aggregate for Mortar: ASTM C 144.

1 For mortar that is exposed to view, use washed aggregate consisting of natural sand or crushed stone.

2 For joints less than 1/4 inch (6 mm) thick, use aggregate graded with 100 percent passing the No. 16 (1.18-mm) sieve.

End Sect

MUNS IDS Infrastructure

CURZ202310 MUNS IDS Infrastructure

A ELECTRICAL METALLIC TUBING (EMT)

1 Description: NFPA 70, Type EMT steel electrical metallic tubing complying with

ANSI C80.3 and listed and labeled as complying with UL 797.

2 Fittings:

a Description: Fittings complying with NEMA FB 1 and listed and labeled as complying with UL 514B.

b Material: Use steel or malleable iron. Do not use die cast zinc fittings.

3 Connectors and Couplings: Use compression (gland) or set-screw type.

a Do not use indenter type connectors and couplings.

4 Damp or Wet Locations (where permitted): Use fittings listed for use in wet locations.

B ACCESSORIES

1 Conduit Joint Compound: Corrosion-resistant, electrically conductive; suitable for use with the conduit to be installed.

2 Pull Strings: Use nylon cord with average breaking strength of not less than 200 pound-force.

3 Modular Seals for Conduit Penetrations: Rated for minimum of 40 psig; Suitable for the conduits to be installed.

C GRAVEL SUBBASE

1 704.05 Crushed Gravel for Sub-base. Crushed gravel for sub-base shall consist of material reasonably free from silt, loam, clay, or organic matter. It shall be obtained from approved sources and shall meet the following requirements:

a Grading. The crushed gravel shall be uniformly graded from coarse to fine and shall meet the requirements of the following table:

Table 704.05A – Crushed Gravel for Sub-base

Grading Sieve Designation

Percent by Weight Passed Square Mesh Sieves

4 inch 95-100 Coarse No. 4 25-50

No. 100 0-12 No. 200 0-6

MUNS IDS Infrastructure a Percent of Wear. The percent of wear of the crushed gravel shall be not more than 40 when tested in accordance with AASHTO-T-96.

b Fractured Faces. At least 30 percent, by weight, of the material coarser than No.

4 sieve shall have at least one fractured face.

B BITUMINOUS CONCRETE

1 Furnish all labor and material required to complete all paving.

a Base Course Type II 3” thick b Top Course Type II 2” thick

C WETHER LIMITATIONS

1 Bituminous material shall not be applied between November 1 and May 1. The courses shall not be placed when the ambient air temperature at the paving site in the shade and away from artificial heat is below 5C for courses 35 mm or greater in compacted thickness or below 10C for courses less than 35 mm in compacted thickness.

2 Bituminous material shall not be placed on a wet or frozen surface or when weather or other conditions would prevent the proper handling, finishing, or compacting of the material, unless otherwise approved by the Contracting Officer’s Representative.

3 Bituminous wearing course materials shall not be applied before May 15 or after

October 15.

4 When it is in the public interest, the Construction Contracting Officer’s Representative may adjust the ambient air temperature requirements or extend the dates of the paving season.

D CONDITION OF EXISTING SURFACE

1 The existing surface shall be cleaned and sprayed with Emulsified Asphalt, RS-1, before placing of the bituminous mixture except that when the surface to be paved is placed in the same construction season, the asphalt treatment will not be requirement unless ordered by the Contracting Officer’s Representative. The emulsion shall be applied under pressure at the rate of 0.05 to 0.14 L/m5. The application shall be made just prior to the placement of the bituminous concrete mixture but shall progress sufficiently ahead of the paving so that the surface to be paved will be tacky.

E PLACING AND FINISHING

1 The bituminous mixture, at the time of discharge from the haul vehicle, shall be within 6EC of the compaction temperature for the approved mix design.

F COMPACTION

1 The specific gravity of the compacted pavement will not be less than 92 % and not more than 96% of the average daily maximum specific gravity of the type mix designated.

G TOPSOIL

1 All topsoil shall be of good, rich, uniform grade without admixture of subsoil material.

It shall be free from hard clods, stones, stumps, roots or similar substances 1 inch or more in diameter, debris, or other material deleterious to planting operations or plant growth.

H LAWNS

1 Grass Seed: Clean material guaranteed to be 95% free from seeds other than those listed, and to have a minimum germination rate of 85%. Provide as follows:

Seed: Mix 6 lbs per 1,000 square feet 39.55% min. (98/85) KY Bluegrass Germ: 85% 19.82% Min. Touchdown KY Bluegrass Germ: 80% 19.78% Min. Famous KY Bluegrass Germ: 78% 19.29% Min. Futura 3000 Per Rye Germ: 90% 0.43% Max. Crop 1.05% Max. Inert 0.08% Max Weed

I MULCH

1 Straw mulch shall be spread at a rate of 2 tons/acre.

J LAWN GUARANTEE

1 If at the end of three weeks a satisfactory stand of grass has not been produced, the

Contractor shall renovate and reseed the lawn or unsatisfactory portions thereof immediately, or if after October 15th, during the next planting season following the requirements of this specification. A satisfactory stand is defined as a lawn or section of lawn 1,000 square feet or large that has:

a No bare spots larger than one square foot.

b Not more than 10 percent of total area with bare spots larger than six inches square.

End Section.

PROJECT MANUAL

B-140 RADIO ROOM

HVAC

VERMONT AIR NATIONAL GUARD

BURLINGTON, VERMONT

CURZ 212306

MARCH 3, 2021

B140 RADIO ROOM HVAC PROJECT DIRECTORY

PROJECT DIRECTORY

CONTRACTING OFFICER:

Department of Army & Air Force Vermont Air National Guard 45 NCO Drive, Suite A South Burlington, VT 05403

Attn: James Belaski

(802) 660-5361

CONTRACTING OFFICER'S

REPRESENTATIVE:

2d Lt Dayton Brown

158 CES/CEE VTANG

30 Falcon Street So. Burlington, VT 05403

Attn: Dayton Brown

(802) 660-5336

B140 RADIO ROOM HVAC

GENERAL

PROJECT DIRECTORY

LOCATION MAP

TABLE OF CONTENTS

ASBESTOS INSPECTION REPORT

DIVISION 7 - THERMAL AND MOISTURE PROTECTION

078413 PENETRATION FIRESTOPPING

079200 JOINT SEALANTS

DIVISION 23 - HEATING, VENTILATING AND AIR CONDITIONING

230500 COMMON WORK RESULTS FOR HVAC

230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT

230516 EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING

230519 METERS AND GAGES FOR HVAC PIPING

230548 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT

230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC

230719 HVAC PIPING INSULATION

230800 COMMISSIONING OF HVAC

230993 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

232300 REFRIGERANT PIPING

233100 HVAC DUCTS AND CASINGS

233300 AIR DUCT ACCESSORIES

236213 PACKAGED AIR-COOLED REFRIGERANT COMPRESSOR AND CONDENSER UNITS

238124 COMPUTER ROOM AIR CONDITIONERS - FLOOR MOUNTED

238127 SMALL SPLIT-SYSTEM HEATING AND COOLING

238415 STEAM HUMIDIFIERS

DIVISION 25 - INTEGRATED AUTOMATION

250000 INTERGRATED AUTOMATION

250912 VARIABLE-FREQUENCY MOTOR CONTROLLERS

250913 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

250923 DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC

DIVISION 26 - ELECTRICAL

260100 BASIC ELECTRICAL REQUIREMENTS

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS

260534 CONDUIT

260535 SURFACE RACEWAYS

260536 CABLE TRAYS FOR ELECTRICAL SYSTEMS

260537 BOXES

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

262416 PANELBOARDS

262717 EQUIPMENT WIRING

262726 WIRING DEVICES

262818 ENCLOSED SWITCHES

264300 SURGE PROTECTIVE DEVICES

CROTHERS

Environmental Group, LLC

29 Duncan Road - Morrisville, Vermont 05661 802-888-1936 info@crothersenvironmenta/.com

../ AIHA

ORGANIZATIONAL

MEMBER

RENOVATION INSPECTION FOR THE PRESENCE OF

ASBESTOS-CONTAINING MATERIALS

Site Location:

Vermont Air National Guard, Building 140 Burlington, Vermont

Report Prepared For:

Smith Alvarez Sienkiewycz Architects 117 St. Paul Street #3 Burlington, Vermont

Inspection Dates:

May 20 and June 27, 2016

INDOOR ENVIRONMENTAL SPECIALISTS

Renovation Asbestos Inspection Report and Limited Lead Screening Summary VTANG, Building 140- Burlington , Vermont

July 11, 2016

TABLE OF CONTENTS

1.0 Summary

1.1 Asbestos-Containing Materials

2.0 Disclaimers

3.0 Asbestos-Containing Materials

3.1 Scope of Work

3.2 Bulk Sample Inventory and Analytical Results

3.3 Inventory of Confirmed Asbestos-Containing Materials

3.4 Asbestos-Containing Materials Abatement Cost Estimates

4.0 Renovation Requirements

4.1 Non-Friable Asbestos-Containing Materials

4.2 Regulations

4.3 Vermont Department of Health

4.4 Occupational Safety and Health Administration

4.5 Asbestos Hazard Communication Requirements

5.0 Lead-in-Paint

5.1 Lead Paint Sampling

5.2 Lead-in-Paint Summary

6.0 Qualifications/Signatures

VTANG, Building 140- Burlington , Vermont

1.0 Summary

Crothers Environmental Group, LLC (Crothers) is pleased to provide Smith Alvarez Sienkiewycz Architects with an asbestos inventory and limited lead survey for Building 140 of the Vermont Air National Guard base located in Burlington, Vermont. The site contains a structure with a footprint of approximately 16,500 square feet. The facility has a ground floor and basement level. The facility is scheduled for renovation.

The inspections were conducted on May 20 and June 27, 2016 by Christopher Clement, a Vermont-licensed Asbestos Site Inspector and Lead Inspector/Risk Assessor.

1.1 Asbestos-Containing Materials

The inspection was conducted to comply with renovation requirements set forth by the Vermont Regulations for Asbestos Control (V.S.A Title 18, Chapter 26), the U.S. Environmental Protection Agency Asbestos NESHAP Regulation (40 CFR Part 61 Subpart M) and the Occupational Safety & Health Administration (29 CFR 1926.1101 Construction Standard for Asbestos).

An asbestos-containing material is defined as any material containing greater than 1% asbestos.

The following materials were found to contain asbestos in concentrations greater than 1 %:

• Black mastic

2.0 Disclaimers

1) Some suspect asbestos-containing materials may be present in locations such as behind walls, in chases, above rigid ceilings, inside crawl spaces, etc. that were not observed or accessible to the Inspector. In the event suspect materials not identified in this report are discovered during renovation activities, the discovered material must be presumed as asbestos-containing and treated accordingly.

2) This inspection did not include any materials that may be underground (i.e. cement water and sewage pipes, buried trash and debris, etc.

3.0 Asbestos-Containing Materials

3.1 Scope of Work

Crothers was retained to collect bulk samples of suspect materials from the interior and exterior of the facility that may be disturbed during renovation activities. Since this was a renovation inspection, destructive sampling was not conducted of walls, ceilings and floors. If additional suspect materials are discovered during the renovation that are not reported, CEG should be notified.

VTANG, Building 14 0 - Burlington, Vermont

Jul y 11, 2016

3.2 Bulk Sample Inventory and Analytical Results

Ninety-five (95) bulk samples were collected (including layers) and delivered to Crothers Environmental Group, LLC Laboratory Division. Proper chain-of-custody procedures were followed during transport of samples. Crothers is a Vermont-licensed asbestos laboratory. All samples, unless noted, were analyzed by Polarized Light Microscopy "PLM" in accordance with EPA test method 40 CFR Part 763, Subpart F. The analyst visually estimates the percentages of identified asbestos. In the event that a sample appears to contain 2% asbestos or less, the analysis is repeated utilizing the point count method (a more statistically reliable method at lower concentrations).

The following table provides asbestos bulk sampling information:

May 9, 2016 sampling

Sample Number

Homogeneous Material Sample Location Analytical

Result

222179-3 12 x 12" beige floor tile MDF room 025 - center NAD

222179-4 Yellow mastic MDF room 025 - center NAD

222179-5 12 x 12" beige floor tile & yellow mastic

MDF room 025 - northeast corner NAD

222179-6 Light grey cove base & yellow mastic

Radio room 026 - east side NAD

222179-7 Light grey cove base & yellow mastic

Radio room 026 - west side NAD

222179-8 12 x 12" light grey floor tile & yellow mastic

Radio room 026 - west side r NAD

222179-9 Yellow mastic & black mastic Radio room 026 - east side D

5 % Chrysotile Asbestos

222179-10 12 x 12" light grey floor tile Radio room 026 - east side NAD

July 11, 2016 Renovation Asbestos Inspection Report and Limited Lead Screening Summary VTANG, Building 140 - Burlington, Vermont

3.3 Inventory of Confirmed Asbestos-Containing Materials

Homogeneous Area/Material

Material Condition

Material Location

Approximate II Quantitv II

Black Mastic Good Radio Room #026 350ft2 I

VTANG, Building 140 - Burlington, Vermont

4.0 Renovation Requirements

4.1 Non-Friable Asbestos-Containing Materials

Non-friable ACM or PACM is an asbestos-containing material that when dry cannot be crumbled, pulverized, or reduced to powder by hand pressure. The following materials were identified as non-friable ACM:

◇ Black flooring mastic

4.2 Regulations

The following regulatory agencies have regulations in effect when removing/disturbing non-friable

ACM:

4.3 Vermont Department of Health

The Vermont Regulations for Asbestos Control (VRAC) requires that all non-friable asbestos-containing materials that will be disturbed by renovation or demolition activities be properly removed prior to disturbance. VRAC Section 6 only requires minimal abatement procedures when removing non-friable materials. Vermont certified abatement personnel are not required. In short, the removal procedures include but do not limit:

◆ adequately wetting the material;

◆ removing the material in as large of sections as feasible; and ◆ properly packaging, labeling and disposing of the material.

The material cannot be sanded, sawn, chipped, ground, abraded or drilled.

4.4 Occupational Safety and Health Administration

(V)OSHA classifies these materials as Class II. This regulation is more stringent than VRAC, requiring the supervision by a competent person, specifically trained in a training course that meets the EPA's Model Accreditation Plan (Title 40 CFR 763, Asbestos-Containing Materials in Schools;

Final Rule and Notice) or a supervisor or project designer or its equivalent. Employees must also be trained, medically monitored and etc. Unless a negative exposure assessment has been carried out, full procedures are required under this regulation.

4.5 Asbestos Hazard Communication Requirements

This section applies to the communication of information concerning asbestos hazards in construction & general industry to facilitate compliance with OSHA 1926.1101 (construction) and 1910.1001 (general industry). Building owners are often the only and/or best sources of information concerning the presence of previously installed ACM. Therefore they, along with employers of potentially exposed employees, are assigned specific duties for hazard communication.

VTANG, Building 140- Burlington, Vermont

Building and/or facility owners shall notify the following persons of the presence, location and quantity of ACM or presumed asbestos-containing materials (PACM), at the work sites in their buildings and facilities. Notification shall be either in writing, or shall consist of a personal communication between the owner and the person to whom notification must be given or their authorized representatives:

• Prospective employers applying or bidding for work whose employees reasonably can be expected to work in or adjacent to areas containing such material;

• Employees of the owner who will work in or adjacent to areas containing such material; and

• On multi-employer worksites, all employers of employees who will be performing work within or adjacent to areas containing such material.

5.0 Lead-in-Paint

5.1 Lead Paint Sampling

A limited screening for lead-in-paint was conducted throughout the facility to determine whether it is likely that contractors would come into contact with lead during the course of the renovation. Note:

this does not exclude OSHA standards and lead-safe work practices should still be utilized when applicable.

EPA identifies lead-based paint as a surface coating containing greater than 1.0 mg/cm2 of lead or greater than 0.5% by weight. Testing was performed by Christopher Clement, a Vermont-licensed Lead Inspector and Risk Assessor, using the RMD Model LPA-1 XRF, Serial No. 3315. The XRF analyzer is designed to measure the lead content of surface coatings on a variety of building surfaces, substrates, and components . The measurement is rapid, nondestructive, and (according to the manufacturer) is capable of detecting lead concentrations that occur within numerous layers of various surface coatings.

5.2 Lead-in-Paint Summary

No detectable levels of lead were discovered on any of the tested surfaces. Therefore, we do not find a significant lead hazard, and the likeliness of workers coming into contact with lead during this renovation project is very low. However, if the contractor believes that lead-containing coatings are going to be disturbed by renovation, they are encouraged to refer to OSHA guidelines.

VTANG, Building 140- Burlington, Vermont

6.0 Qualifications/Signatures

Crothers Environmental Group, LLC Project#:

Vermont Licensed Asbestos Consulting Entity:

Entity Certificate#:

Vermont Licensed Asbestos Inspector:

Asbestos Inspector Certificate #:

Vermont Licensed Asbestos Laboratory:

Vermont Licensed Lead Inspector/Risk Assessor:

Lead Inspector/Risk Assessor Certificate #:

CEG222179

Crothers Environmental Group, LLC

CE475400

Christopher Clement

AI032436

RA853038

Inspection Dates: May 20 and June 27, 2016

Report Date: July 11, 2016

29 Duncan Rd - Morrisville, VT 05661

802-888-1936 PLM Bulk Sample Laboratory Report info@crothersenvironmental.com

Client: S.A.S Architechts

Project: VTANG Building 140

CEG: 222179

Date Received: May 20, 2016

Date Reported: June 10, 2016

Lab ID# Sample ID#: Description/ Sample Location Analyst Description Asbestos Type & Percent

414092

222179-3 12" x 12" beige floor tile/ MDF room 025 / Center Beige

NAD

414093

222179-4

Yellow mastic/ MDF room 025 / Center

Yellow

414094

222179-5

12" x 12" beige floor tile& yellow mastic/ MDF room

025 / NE corner

Beige/ Yellow

414095

222179-6

Light grey core base & yellow glue/ Radio room 026 /

East side

Grey/ Yellow

A - NAD / B - NAD

414096

222179-7

Light grey core base & yellow glue/ Radio room 026 / west and south sides

414097

222179-8 12" x 12" light grey floor tile & yellow mastic/ Radio room 026 / West side

414098

222179-9 Yellow mastic and black mastic/ Radio room 026 / East side

L"1 Yellow/ Black

- (l- _m A - NAD / B - 5% Chrysotile Absestos

414099

222179-10

12" x 12" light grey floor tile/ Radio room 026 / East side

Grey

802-888-1936 info@crothersenvironmental.com PLM Bulk Sample Laboratory Report info@crothersenvironmental.com

Client: S.A.S Architechts

Project: VTANG Building 140

CEG: 222179

Date Received: May 20, 2016

Date Reported: June 10, 2016

11 ꞏ----

Asbestos PLM Analyst

Vermont License#: PB032436

Asbestos Analysis of Bulk Materials were conducted in accordance with EPA Test Method 600/R-93/116 Utilizing Polarized Light Microscopy

(PLM) and Dispersion Staining Techniques. Reported results are visual estimates only unless the analyst visually estimates an asbestos content of 2% or less; at which point the sample is analyzed utilizing the point count method. Samples were received in good condition unless otherwise noted.

Client: S.A.S. Architects

Project: VTANG - Building 140 - Colchester, Vermont

CEG: 222247

Date Received: June 27, 2016

Date Reported: July 6, 2016

Crothers Environmental Graup, LLC

Lab ID# Sample ID#: Description / Sample Location Analyst Description Asbestos Type & Percent

414534 222247-1 Carpet glue/ Room 10 entryway Yellow No Asbestos Detected {NAO)

414535

222247-2

2 x 2' Pin & worm ceiling tile/ Middle left corner of room 10

NAO

414536

222247-3

611 Cove base/ Hallway adjacent to room 5

Grey NAO

414537

222247-4

611 Cove base/ Hallway adjacent to room 6

414538

222247-5

Carpet & glue/ Doorway to room 6

Yellow NAO

414539

222247-6

2 x 4' Pin & worm ceiling tile/ Room 33 - Center left wall

Grey NAO

414540

222247-7

12 x 12" Floor tile/ Entryway to room 6 Grey NAO

414541

222247-8

12 x 12" Floor tile/ Entryway to janit or's closet

414542

222247-9

12 x 12" Floor tile/ Behind door in room 34 Dark grey NAO

414543

222247-10

12 x 12" Floor tile/ Behind door in room 34

Dark grey

414544 222247-11 Cove base/ Behind door of room 10 Black NAO

414545 222247-12 Cove base/ Middle left center of room 10 (by closet) Black NAO

Client: S.A.S. Architects

Project: VTANG - Building 140 - Colchester, Vermont

CEG: 222247

Date Received: June 27, 2016

Date Reported: July 6, 2016

Crothers Environmental Graup, LLC

Asbestos PLM Analyst

Vermont License #: PB032436

Asbestos Analysis of Bulk Materials were conducted in accordance with EPA Test Method 600/R-93/116 Utilizing Polarized Light Microscopy

(PLM) and Dispersion Staining Techniques. Reported results are visual estimates only unless the analyst visually estimates an asbestos content of 2% or less; at which point the sample is analyzed utilizing the point count method. Samples were received in good condition unless otherwise noted.

PENETRATION FIRESTOPPING

Section 078413 - Page 1

SECTION 078413 - PENETRATION FIRESTOPPING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes through-penetration firestop systems for penetrations through fire-resistance-rated constructions, including both empty openings and openings containing penetrating items.

B. Related Sections include the following:

1. Division 21 Sections fire-suppression piping penetrations.

2. Divisions 22 and 23 Sections duct and piping penetrations.

3. Divisions 26 and 27 Sections cable and conduit penetrations.

1.3 PERFORMANCE REQUIREMENTS

A. General: For penetrations through fire-resistance-rated constructions, including both empty openings and openings containing penetrating items, provide through-penetration firestop systems that are produced and installed to resist spread of fire according to requirements indicated, resist passage of smoke and other gases, and maintain original fire-resistance rating of construction penetrated.

B. Rated Systems: Provide through-penetration firestop systems with the following ratings determined per UL 1479:

1. F-Rated Systems: Provide through-penetration firestop systems with F-ratings indicated, but not less than that equaling or exceeding fire-resistance rating of constructions penetrated.

2. T-Rated Systems: For the following conditions, provide through-penetration firestop systems with T-ratings indicated, as well as F-ratings, where systems protect penetrating items exposed to potential contact with adjacent materials in occupiable floor areas:

a. Penetrations located outside wall cavities.

b. Penetrations located outside fire-resistance-rated shaft enclosures.

C. For through-penetration firestop systems exposed to view, traffic, moisture, and physical damage, provide products that, after curing, do not deteriorate when exposed to these conditions both during and after construction.

1. For piping penetrations for plumbing and wet-pipe sprinkler systems, provide moisture-resistant through-penetration firestop systems.

B140 RADIO ROOM HVAC PENETRATION FIRESTOPPING

Section 078413 - Page 2

2. For floor penetrations with annular spaces exceeding 4 inches (100 mm) in width and exposed to possible loading and traffic, provide firestop systems capable of supporting floor loads involved, either by installing floor plates or by other means.

3. For penetrations involving insulated piping, provide through-penetration firestop systems not requiring removal of insulation.

D. For through-penetration firestop systems exposed to view, provide products with flame-spread and smoke-developed indexes of less than 25 and 450, respectively, as determined per ASTM E 84.

1.4 QUALITY ASSURANCE

A. Installer Qualifications: A firm with FM4991 certification experienced in installing through-penetration firestop systems similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful performance.

Qualifications include having the necessary experience, staff, and training to install manufacturer's products per specified requirements. Manufacturer's willingness to sell its through-penetration firestop system products to Contractor or to Installer engaged by Contractor does not in itself confer qualification on buyer.

Section 078413 - Page 3

B. Installation Responsibility: Assign installation of through-penetration firestop systems in Project to a single qualified installer.

C. Fire-Test-Response Characteristics: Provide through-penetration firestop systems that comply with the following requirements and those specified in Part 1 "Performance Requirements" Article:

1. Firestopping tests are performed by a qualified testing and inspecting agency. A qualified testing and inspecting agency is UL, or another agency performing testing and follow-up inspection services for firestop systems acceptable to authorities having jurisdiction.

2. Through-penetration firestop systems are identical to those tested per testing standard referenced in "Part 1 Performance Requirements" Article. Provide rated systems complying with the following requirements:

a. Through-penetration firestop system products bear classification marking of qualified testing and inspecting agency.

b. Through-penetration firestop systems correspond to those indicated by reference to through-penetration firestop system designations listed by the following:

1) UL in its "Fire Resistance Directory."

1.5 DELIVERY, STORAGE, AND HANDLING

A. Deliver through-penetration firestop system products to Project site in original, unopened containers or packages with intact and legible manufacturers' labels identifying product and manufacturer, date of manufacture, lot number, shelf life if applicable, qualified testing and inspecting agency's classification marking applicable to Project, curing time, and mixing instructions for multi-component materials.

B. Store and handle materials for through-penetration firestop systems to prevent their deterioration or damage due to moisture, temperature changes, contaminants, or other causes.

Section 078413 - Page 3

1.6 PROJECT CONDITIONS

A. Environmental Limitations: Do not install through-penetration firestop systems when ambient or substrate temperatures are outside limits permitted by through-penetration firestop system manufacturers or when substrates are wet due to rain, frost, condensation, or other causes.

B. Ventilate through-penetration firestop systems per manufacturer's written instructions by natural means or, where this is inadequate, forced-air circulation.

1.7 COORDINATION

A. Coordinate construction of openings and penetrating items to ensure that through-penetration firestop systems are installed according to specified requirements.

B. Coordinate sizing of sleeves, openings, core-drilled holes, or cut openings to accommodate through-penetration firestop systems.

C. Do not cover up through-penetration firestop system installations that will become concealed behind other construction until each installation has been examined by Contracting Officer.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Available Products: Subject to compliance with requirements, through-penetration firestop systems that may be incorporated into the Work include, but are not limited to, those systems indicated in the Through-Penetration Firestop System Schedule on Drawings that are produced by one of the following manufacturers:

1. Reserved.

2.2 FIRESTOPPING, GENERAL

A. Exposed Penetration Firestopping Systems: Flame-spread and smoke-developed indexes of less than 25 and 450, respectively, per ASTM E 84.

1. Sealant shall have a VOC content of 250 g/L or less.

B. Compatibility: Provide through-penetration firestop systems that are compatible with one another;

with the substrates forming openings; and with the items, if any, penetrating through- penetration firestop systems, under conditions of service and application, as demonstrated by through-penetration firestop system manufacturer based on testing and field experience.

Section 078413 - Page 4

C. Accessories: Provide components for each through-penetration firestop system that are needed to install fill materials and to comply with Part 1 "Performance Requirements" Article. Use only components specified by through-penetration firestop system manufacturer and approved by qualified testing and inspecting agency for firestop systems indicated. Accessories include, but are not limited to, the following items:

1. Permanent forming/damming/backing materials, including the following:

a. Slag-/rock-wool-fiber insulation.

b. Sealants used in combination with other forming/damming/backing materials to prevent leakage of fill materials in liquid state.

c. Fire-rated form board.

d. Fillers for sealants.

2. Temporary forming materials.

3. Substrate primers.

4. Collars.

5. Steel sleeves.

2.3 FILL MATERIALS

A. General: Provide through-penetration firestop systems containing the types of fill materials required by the manufacturer of the through-penetration firestop system.

2.4 MIXING

A. For those products requiring mixing before application, comply with through-penetration firestop system manufacturer's written instructions for accurate proportioning of materials, water (if required), type of mixing equipment, selection of mixer speeds, mixing containers, mixing time, and other items or procedures needed to produce products of uniform quality with optimum performance characteristics for application indicated.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates and conditions, with Installer present, for compliance with requirements for opening configurations, penetrating items, substrates, and other conditions affecting performance of work.

1. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Surface Cleaning: Clean out openings immediately before installing through-penetration firestop systems to comply with firestop system manufacturer's written instructions and with the following requirements:

Section 078413 - Page 5

1. Remove from surfaces of opening substrates and from penetrating items foreign materials that could interfere with adhesion of through-penetration firestop systems.

2. Clean opening substrates and penetrating items to produce clean, sound surfaces capable of developing optimum bond with through-penetration firestop systems. Remove loose particles remaining from cleaning operation.

3. Remove laitance and form-release agents from concrete.

B. Priming: Prime substrates where recommended in writing by through-penetration firestop system manufacturer using that manufacturer's recommended products and methods. Confine primers to areas of bond; do not allow spillage and migration onto exposed surfaces.

C. Masking Tape: Use masking tape to prevent through-penetration firestop systems from contacting adjoining surfaces that will remain exposed on completion of Work and that would otherwise be permanently stained or damaged by such contact or by cleaning methods used to remove smears from firestop system materials. Remove tape as soon as possible without disturbing firestop system's seal with substrates.

3.3 THROUGH-PENETRATION FIRESTOP SYSTEM INSTALLATION

A. General: Install through-penetration firestop systems to comply with Part 1 "Performance Requirements" Article and with firestop system manufacturer's written installation instructions and published drawings for products and applications indicated.

B. Install forming/damming/backing materials and other accessories of types required to support fill materials during their application and in the position needed to produce cross-sectional shapes and depths required to achieve fire ratings indicated.

1. After installing fill materials and allowing them to fully cure, remove combustible forming materials and other accessories not indicated as permanent components of firestop systems.

C. Install fill materials for firestop systems by proven techniques to produce the following results:

1. Fill voids and cavities formed by openings, forming materials, accessories, and penetrating items as required to achieve fire-resistance ratings indicated.

2. Apply materials so they contact and adhere to substrates formed by openings and penetrating items.

3. For fill materials that will remain exposed after completing Work, finish to produce smooth, uniform surfaces that are flush with adjoining finishes.

3.4 CLEANING AND PROTECTING

A. Clean off excess fill materials adjacent to openings as Work progresses by methods and with cleaning materials that are approved in writing by through-penetration firestop system manufacturers and that do not damage materials in which openings occur.

B. Provide final protection and maintain conditions during and after installation that ensure that through-penetration firestop systems are without damage or deterioration at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, cut out and remove damaged or deteriorated through-penetration firestop systems immediately and install new materials to produce systems complying with specified requirements.

END OF SECTION 078413

B140 RADIO ROOM HVAC JOINT SEALANTS

SECTION 079200 - JOINT SEALANTS

PART 1 - GENERAL

A. Drawings and general provisions of the Contract, including Division 1 Specification Sections, apply to this Section.

A. This Section includes joint sealants for the following applications:

1. Exterior joints in vertical surfaces and nontraffic horizontal surfaces.

2. Interior joints in the following vertical surfaces and horizontal nontraffic surfaces:

a. Perimeter joints of exterior openings where indicated.

b. Perimeter joints between interior wall surfaces and frames of interior doors, windows and elevator entrances.

c. Joints between plumbing fixtures and adjoining walls, floors, and counters.

d. Other joints as indicated.

B. Related Sections include the following:

1. Division 7 Section "Metal Siding" for joint sealant used with metal siding and trim.

2. Division 7 Section "Through-Penetration Firestop Systems" for fire-resistant building joint-sealant systems.

1.3 PERFORMANCE REQUIREMENTS

A. Provide elastomeric joint sealants that establish and maintain watertight and airtight continuous joint seals without staining or deteriorating joint substrates.

B. Provide joint sealants for interior applications that establish and maintain airtight and water-resistant continuous joint seals without staining or deteriorating joint substrates.

1.4 QUALITY ASSURANCE

A. Installer Qualifications: An experienced installer who has specialized in installing joint sealants similar in material, design, and extent to those indicated for this Project and whose work has resulted in joint-sealant installations with a record of successful in-service performance.

B. Source Limitations: Obtain each type of joint sealant through one source from a single manufacturer.

Section 079200 - Page 2

1.5 DELIVERY, STORAGE, AND HANDLING

A. Deliver materials to Project site in original unopened containers or bundles with labels indicating manufacturer, product name and designation, color, expiration date, pot life, curing time, and mixing instruction for multi-component materials.

B. Store and handle materials in compliance with manufacturer’s written instructions to prevent their deterioration or damage due to moisture, high or low temperatures, contaminants, or other causes.

1.6 PROJECT CONDITIONS

A. Environmental Limitations: Do not proceed with installation of joint sealants under the following conditions:

1. When ambient and substrate temperature conditions are outside limits permitted by joint-sealant manufacturer.

2. When joint substrates are wet.

B. Joint-Width Conditions: Do not proceed with installation of joint sealants where joint widths are less or more than those allowed by joint sealant manufacturer for applications indicated.

C. Joint-Substrate Conditions: Do not proceed with installation of joint sealants until contaminants capable of interfering with adhesion are removed from joint substrates.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Reserved.

2.2

MATERIALS, GENERAL

A. Compatibility: Provide joint sealants, backings, and other related materials that are compatible with one another and with joint substrates under conditions of service and application, as demonstrated by sealant manufacturer, based on testing and field experience.

B. VOC Content of Interior Sealants: Provide interior sealants and sealant primers that comply with the following limits for VOC content when calculated according to 40 CFR 59, Subpart D (EPA Method 24):

1. Sealants: 250 g/L.

2. Sealant Primers for Nonporous Substrates: 250 g/L.

3. Sealant Primers for Porous Substrates: 775 g/L.

C. Colors of Exposed Joint Sealants: As selected by Architect from manufacturer's full range for this characteristic.

Section 079200 - Page 3

2.3 ELASTOMERIC JOINT SEALANTS

A. Elastomeric Sealant Standards: Comply with ASTM C 920 and other requirements indicated for

2.4 each liquid-applied chemically curing sealant for type, grade, class, and uses related to exposure and joint substrates.

LATEX JOINT SEALANTS

A. Latex Sealant Standard: Comply with ASTM C 834.

2.6 JOINT-SEALANT BACKING

A. General: Provide sealant backings of material and type that are nonstaining; are compatible with joint substrates, sealants, primers, and other joint fillers; and are approved for applications indicated by sealant manufacturer based on field experience and laboratory testing.

2.7 MISCELLANEOUS MATERIALS

A. Primer: Material recommended by joint-sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate tests and field tests.

B. Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and sealant backing materials, free of oily residues or other substances capable of staining or harming joint substrates and adjacent nonporous surfaces in any way, and formulated to promote optimum adhesion of sealants to joint substrates.

C. Masking Tape: Nonstaining, nonabsorbent material compatible with joint sealants and surfaces adjacent to joints.

Section 079200 - Page 4

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine joints indicated to receive joint sealants, with Installer present, for compliance with requirements for joint configuration, installation tolerances, and other conditions affecting joint-sealant performance.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with joint-sealant manufacturer's written instructions and the following requirements:

1. Remove all foreign material from joint substrates that could interfere with adhesion of joint sealant, including dust, paints (except for permanent, protective coatings tested and approved for sealant adhesion and compatibility by sealant manufacturer), old joint sealants, oil, grease, waterproofing, water repellents, water, surface dirt, and frost.

2. Clean porous joint substrate surfaces by brushing, grinding, blast cleaning, mechanical abrading, or a combination of these methods to produce a clean, sound substrate capable of developing optimum bond with joint sealants. Remove loose particles remaining after cleaning operations above by vacuuming or blowing out joints with oil-free compressed air.

3. Clean nonporous surfaces with chemical cleaners or other means that do not stain, harm substrates, or leave residues capable of interfering with adhesion of joint sealants.

B. Joint Priming: Prime joint substrates, where recommended in writing by joint-sealant manufacturer.

C. Masking Tape: Use masking tape where required to prevent contact of sealant with adjoining surfaces. Remove tape immediately after tooling without disturbing joint seal.

3.3 INSTALLATION OF JOINT SEALANTS

A. General: Comply with joint-sealant manufacturer's written installation instructions for products and applications indicated, unless more stringent requirements apply.

B. Sealant Installation Standard: Comply with recommendations in ASTM C 1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.

C. Acoustical Sealant Application Standard: Comply with recommendations in ASTM C 919 for use of joint sealants in acoustical applications as applicable to materials, applications, and conditions indicated.

D. Install sealant backings of type indicated to support sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.

Section 079200 - Page 5

1. Do not leave gaps between ends of sealant backings.

2. Do not stretch, twist, puncture, or tear sealant backings.

3. Remove…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .