20190PR260000141_SOW Self Help Replace Front Gate.pdf
PDF 213 KB Posted
- Solicitation number
- 70Z03326Q201900012
About this file
This is a Scope of Work (SOW) for a front gate replacement and refurbishment project at U.S. Coast Guard Air Station Port Angeles. The contractor must provide all personnel, equipment, tools, materials, freight, and services necessary to complete the work within 30 calendar days from the scheduled start date. Primary deliverables include furnishing and installing one 6x23 Cantilever Gate and one 6x18 VTrack Gate, replacing main gate operators with customer-supplied units, replacing rollers and guides (Cantilever Rollers, Hysec Drive Rails, Gate Guide Roller Sets, and VTRACK wheels), repairing the flightline gate operator (Drive Arm FLG and Motor Assembly), relocating one reclaimed operator to an inoperable gate, and performing all electrical terminations, commissioning, and testing. The contractor must also provide heavy equipment rental (such as telehandler delivery), remove and dispose of existing gates and hardware in compliance with local, state, and federal environmental regulations, and ensure OSHA Safety and Health Standards compliance per 29 CFR Part 1926.
The contractor must designate a Project Manager as a single point of contact who cannot be replaced without prior Contracting Officer approval. All contractor personnel must present a professional appearance, comply with government regulations and security procedures, and cannot include current U.S. Government employees or Coast Guard members without approval. The Government reserves the right to remove any employee for misconduct or security reasons. Technical points of contact are LT Alec MacLeod (Primary: 206-831-4302) and LT Jacob Sily (Alternate: 206-831-0396). Invoicing must be submitted through the Invoice Processing Platform (IPP) at https://www.ipp.gov/. The SOW references an attached quote but does not specify pricing terms or contract award details.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
U.S. COAST GUARD
AIRSTATION PORT ANGELES
REPLACE FRONT GATE
SECTION 1 – GENERAL INFORMATION
1.1 BACKGROUND
A front gate replacement and refurbishment is needed for USCG AIRSTA Port Angeles.
1.2 SCOPE
The contractor must provide all personnel, equipment, tools, materials, freight, and other items and services necessary to furnish and replace the main gates, replace main gate operators with customer-supplied units, replace rollers and guides, repair the flightline gate operator, move one reclaimed operator to an inoperable gate, and fully commission and test the systems. Per attached quote.
1.2.1 Primary Point of Contact/Technical Representative:
Name: LT Alec MacLeod Work: (206) 831-4302 E-mail: alexander.j.macleod@uscg.mil
1.2.2 Alternate Point of Contact
Name: LT Jacob Sily Phone: 206-831-0396 E-mail: Jacob.K.Sily@uscg.mil
SECTION 2 – SPECIFIC REQUIREMENTS/TASKS
2.1 GENERAL
The contractor must provide all personnel, equipment, tools, materials, freight, and other items and services necessary to furnish and replace the main gates, replace main gate operators with customer-supplied units, replace rollers and guides, repair the flightline gate operator, move one reclaimed operator to an inoperable gate, and fully commission and test the systems. Per attached quote.
2.2 TASKS
Contractor shall provide all personnel, equipment, transportation, tools, materials, and other items and services necessary to complete the gate replacement and refurbishment, which includes:
• Furnish and install one (1) 6x23 Cantilever Gate.
• Furnish and install one (1) 6x18 VTrack Gate.
• Replace main gate operators using customer-supplied units.
• Replace rollers and guides, including supplying and installing Cantilever Rollers (2SQ), Hysec
Drive Rails, Gate Guide Roller Sets, and VTRACK wheels.
• Repair the flightline gate operator (including Drive Arm FLG and Motor Assy -10").
• Move one (1) reclaimed operator to a gate that is currently inoperable.
• Perform all necessary electrical terminations, commissioning, and testing of the installed and repaired systems.
• Provide necessary heavy equipment (e.g., telehandler delivery and rental) to accomplish the work.
• Removal, freight, and proper disposal of existing replaced gates, hardware, and associated waste.
2.3 CONTROL AND DISPOSAL OF WASTES
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all wastes and demolished materials become the contractor’s property and shall be removed from the job site daily in accordance with all local, state, and federal environmental regulations.
2.4 SAFETY
During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 – Safety and Health Regulations for Construction.
SECTION 3 – CONTRACTOR PERSONNEL
3.1 QUALIFIED PRESONNEL
3.1.1 Contract Manager
The Contractor shall provide a Project Manager who shall be responsible for all Contractor work performed under this SOW. The Project Manager shall be a single point of contact for the Contracting Officer and the Technical representative. The name of the Project Manager, and the name(s) of any alternate(s) who shall act for the Contractor in the absence of the Project Manager, shall be provided to the Government as part of the Contractor's proposal. The Project Manager is further designated as Key by the Government. During any absence of the Project Manager, only one alternate shall have full authority to act for the Contractor on all matters relating to work performed under this contract. The Project Manager and all designated alternates shall be able to read, write, speak and understand English.
Additionally, the Contractor shall not replace the Project Manager without prior approval from the Contracting Officer.
3.1.2 Contractor Employees
The contractor must not employ persons for work on this contract if such employee is considered by the Contracting Officer to be a potential threat to the health, safety, and security, general well –being, or operational mission of the installation and its population. Contractor personnel must present a neat appearance and be easily recognized as contractor employees. The contractor must not employ any person who is an employee of the U.S. Government if employing that person would create a conflict of interest. Additionally, the contractor must not employ any person who is an employee of the U.S. Coast Guard unless such person seeks and receives approval according to U.S. Coast Guard regulations.
3.2 CONTINUITY OF SUPPORT
The Contractor shall ensure that the contractually required level of support for this requirement is maintained at all times. The Contractor shall ensure that all contract support personnel are present for all hours of the workday. If for any reason the Contractor staffing levels are not maintained due to vacation, leave, appointments, etc., and replacement personnel will not be provided, the Contractor shall provide e-mail notification to the Contracting Officer’s Representative (COR) prior to employee absence. Otherwise, the Contractor shall provide a fully qualified replacement.
3.3 EMPLOYEE CONDUCT
Contractor’s employees shall comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, wearing of parts of DHS uniforms, and possession of weapons) when visiting or working at Government facilities. The Contractor shall ensure Contractor employees present a professional appearance at all times and that their conduct shall not reflect discredit on the United States or the Department of Homeland Security. The Project Manager shall ensure Contractor employees understand and abide by Department of Homeland Security established rules, regulations and policies concerning safety and security.
3.4 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS
The Government may, at its sole discretion (via the Technical representative), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons. Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.
SECTION 4 – OTHER APPLICABLE CONDITIONS
4.1 PERIOD OF PERFORMANCE
The period of performance for this contract shall not exceed 30 calendar days from the scheduled start date of award.
4.2 APPLICABLE PUBLICATIONS
Publications and forms that apply to the SOW are listed below. The publications have been designated as mandatory. The contractor must be guided by those publications to the extent necessary to accomplish requirements in this SOW.
4.2.1 Mandatory Publications
OSHA Safety and Health Standards, 29 CFR Part 1926 – Safety and Health Regulations for Construction
4.3 INVOICING
Invoices will be submitted through the Invoice Processing Platform (IPP) at https://www.ipp.gov/. IPP is a secure web-based electronic invoicing system provided by the U.S. Department of the Treasury’s Bureau of the Fiscal Service in partnership with the Federal Reserve Bank of St. Louis (FRSTL). IPP is available at no cost to any commercial vendor or independent contractor doing business with a participating government agency. Action to take instructions will be provided upon award.