About this file
This document is a cost spreadsheet format sample for the APD Crime Lab LED Lighting and Controls Upgrade Energy Efficiency Project. The spreadsheet provides a detailed template for breaking down project costs into three primary groups: Group A (Fixtures), Group B (Miscellaneous Material, Labor, Bond, Permit, NMGRT), and Group C (Subcontract Material, Labor, NMGRT - Parking Sign Alternate). The template includes columns for Lot Count, Lot Cost, Extended Cost, Markup per Contract, and Direct Cost, allowing for comprehensive financial documentation of the proposed lighting upgrade project.
The total project cost is set at $00000, with the spreadsheet designed to capture granular cost details across different project components. The template includes line items for Design & Engineering, Miscellaneous Materials, Labor, Permits, Bonds, Pre-Commissioning and Post-Commissioning activities, and an alternate parking sign component. While the specific dollar amounts are not filled in, the spreadsheet provides a structured approach to cost accounting, enabling precise tracking of expenses across various project elements and facilitating transparent financial reporting for the energy efficiency upgrade at the APD Crime Lab.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 4-Exhibit F - FIXTURE FORENSIC DELIVERABLE.xlsx | XLSX spreadsheet | |
| 11-Exhibit H.pdf | ||
| 9-Addendum 3.pdf | ||
| 3-Metro Forensics Mechanical.pdf | ||
| 13-Addendum 6.pdf | ||
| 6-RFB Crime Lab Lighting FINAL 04.09.2025.pdf | ||
| 7-Addendum 1.pdf | ||
| 5-Exhibit G - Lighting Specs.pdf | ||
| 8-Addendum 2.pdf | ||
| 10-Addendum 4.pdf | ||
| 14-Addendum 7.pdf | ||
| 12-Addendum 5.pdf | ||
| 1-Exhibit D SUBCONTRACTOR LISTING.docx | DOCX document |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exhibit E: Cost Spreadsheet Format Sample
RFB Title: APD Crime Lab LED Lighting and Controls Upgrade Energy Efficiency Project
Lot
Count Lot
Cost Extended
Cost
Markup per
Contract Direct Cost
Group A – Fixtures Totals
Design & Engineering
Total Group A
$ 0000 0000 $00 $00 $00 $00
Group B - Mic. Material, Labor , Bond, Permit, NMGRT, Mic. Material:
Labor:
Permit:
Bond:
Pre-Commissioning & Post Commissioning
Total Group B
$0000 Group B Subtotals 0000 $00 $00 $00 $00 Group C- Sub Contract . Material, Labor , NMGRT, (Parking Sign) ALTERNATE
Material:
Labor:
NMGRT: (Labor Only) Pre-Commissioning & Post Commissioning
Total Group C
$0000 Group C Subtotals 0000 $00 $00 $00 $00
Group A + B + C Totals
TOTAL PROJECT COST $00000