This is a Statement of Work (SOW) for repair of the sanitary sewer system at Building 650, Travis Air Force Base, California, dated 25 July 2025 (Base Project Number: XDAT 24-1008).
The contractor shall provide all supplies, materials, tools, equipment, and qualified labor to repair defective sanitary sewer piping under Building 650, a retail shopping facility that has experienced sewer backups and flow interruptions. Work scope includes performing video (boroscope) inspection to verify existing pipe material, condition, size, and length; clearing all blockages; and repairing approximately 696 linear feet of 4-inch pipe and 144 linear feet of 2-inch pipe (approximately 840 linear feet total) plus approximately 50 wye/tee fittings using trenchless methods such as cured-in-place pipe lining. Piping serving the kitchen must be rated for 200°F water. If trenchless repair proves infeasible for any section, open trench construction may be negotiated through contract modification. Post-repair CCTV inspection is required, with videos provided to the Contracting Officer. The contractor must also deliver as-built documents in CAD/DWG and PDF formats showing new effective pipe sizes and drainage capacities. The facility must remain operational; disruptive activities are limited to after-hours (1700–0500). The contractor is responsible for maintaining safe jobsites, cleaning daily, protecting existing utilities and survey monuments, obtaining dig permits, providing traffic control plans, repairing any damaged finishes, disposing of excess soil, and providing a 12-month service warranty with 24-month telephone consultation. Work must comply with California State Marshal regulations, California Building Code (Titles 8 and 19–24), and applicable industry standards including the International Building Code, UFC standards, and NFPA codes.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Repair Wastewater Pipes, B650
TRAVIS AFB CALIFORNIA
Base Project Number: XDAT 24-1008
DATE: 25 July 2025
1.0 DESCRIPTION OF WORK: The contractor is to provide all supplies, materials, tools, equipment, and qualified labor necessary to repair sanitary sewer system as described herein.
1.1 BACKGROUND: Building 650 is a retail shopping facility. Sanitary sewer piping defects under bldg. 650’s footprint has caused unanticipated interruptions of flow and sanitary sewer backups/overflows.
1.2 Project Description:
a. See Tabs 2, 3 and 4 for floor plans and plumbing drawings. Perform a video (i.e boroscope) inspection to field verify the existing pipe material/condition, size/length of pipe and fittings.
The scope of inspection and repairs includes the sewer piping highlighted in green in Tab 3 and should extend approximately 5 ft beyond the building’s footprint. Note: a 2018 pharmacy renovation project included new sewer piping under the pharmacy footprint and is not part of this work scope.
b. Clear all blockages/obstructions in sanitary sewer piping.
c. Repair all sanitary sewer piping identified in Tab 3 using trenchless method (e.g. cured in place pipe lining). An estimated 696LF of 4-in pipe and 144LF of 2-in pipe (approx. 840LF total) need to be repaired. Approximately 50 wye/tee fittings also require repair. The repair method for sewer piping serving the kitchen will need to be rated for high temperature (i.e.
200F) water. Piping repairs for kitchen/food prep areas will need to be rated for high temperature.
d. If video inspection deems trenchless repair not feasible for section(s) of piping and open trench construction for point or line repair(s) is necessary, a contract modification may be negotiated.
e. Perform post-repair video inspection (CCTV) of all repaired piping. Provide videos to Contracting Officer (CO). Repaired piping will be free of debris and flow verified prior to placing in service.
f. Draft and provide as-built documents in both CAD/DWG and PDF formats showing the new effective pipe sizes and drainage capacities after repairs.
g. The facility must remain open for normal operation. Any activities that may disturb occupants shall be performed after hours (1700-0500).
h. Each job site shall be maintained in a safe and professional manner. All trash shall be cleaned up at the end of the day. Spoils and equipment shall be neatly stored at the end of the work day. Work with the CE Project Manager and/or Project Inspector for location of equipment staging at each work site.
i. The contractor shall repair/replace any exterior or interior finishes (e.g. concrete, asphalt, drywall, paint, flooring, etc.) damaged during its work. The contractor is responsible for all disposal costs.
j. Open trench work (i.e exterior excavation) includes locating existing utilities, obtaining dig permit(s), saw cutting asphalt and concrete, excavating, installing and connecting piping/fittings, valves, thrust blocks, bedding/backfilling, compacting soil, soil disposal, and patching (replacing) asphalt and concrete.
k. A construction schedule is required before work may begin. The schedule shall be approved by the contracting officer (CO) prior to construction and demonstrate efforts to minimize disruptions to facility operations.
l. Hazardous materials: If asbestos cement pipes (ACP) are encountered, stop work that will disturb the asbestos line and notify the CO for direction.
2.0 Process: Contractor is to use the “Project Phase Listing,” below as a general guideline for project sequence.
Project Phase Listing **Phase elements and components listed are for description purposes and are performed as contracted** Phase I: Pre-project
Engineer – Site inspection, validation, pre-engineered certified design submitted for approval
Project Safety – Validation of utility service isolation (natural gas, electricity, and water) Administration – Authorization to proceed and list of required submittals Project Manager – Coordination of end-user/vendor schedule, site access, and project milestone plans Project Manager – Submit all required pre-project submittals as instructed Operations Lead – Element material acquisition and start necessary fabrication Phase 2: Build
Inspection – Building site for necessary access, materials Layout – Site layout (marking), grading and excavation Subsurface – Build infrastructure Infrastructure – Install pre-engineered storage facility, electric, natural gas, and water systems Surface – Install concrete as designed curbs and pavements Connect – Connect all elements, components, devices, assets into a comprehensive system Test – Complete validation, inspection and certification Phase 3: Post-Project
Inspection – Formal walkthrough with project manager/end-user for verification and acceptance
Warrantee – Provide service warranty (12-months w/ additional 24-month telephone consultation)
Real Property – Process DD 1354 Survey – Perform customer satisfaction survey
2.1 Description: The “Project Phase Listing” offers a methodical approach to project performance and logical sequence of events allowing for greater organization, evaluation and performance.
2.1.1 Project Phase Listing: Listing categorizes performance into four (4) phases:
(1) (Phase 1) Pre-Project – Period between contract award, used for materials, supplies acquisition, project validation, utility services installation/isolation, permit submittals/acquisition and installation Civil Engineer Squadron (CES) representative (POC) coordination.
(2) (Phase 2) Construction – General period between construction preparation and project completion (Building services are complete and pre-inspection review of project elements meet or exceed project requirements).
(3) (Phase 3) Post-Construction Inspection, Certification and End-User Training – Period used to validate project meets or exceeds project, applicable inspection standards requirements and end-users are provided informational tours, site control and training.
2.1.2 Contractor is to provide a Vendor Point of Contact (VPOC) tentative schedule of project performance and estimated timelines associated with progress in each phase.
2.1.3 Contractor has the discretion to perform project phases concurrently as coordinated with the Governments Point of Contact (GPOC).
2.2 Phase 1 (Pre-Project): Contractor has the autonomy to perform each pre-project requirements as desired in accordance with applicable installation, operation, local, state and federal laws and industry standards as required by contract.
2.2.1 Contractor shall, as the Subject Matter Expert (SME), coordinate the Professional Engineer (PE) approved design, planning and details of project with installation Civil Engineer project managers as orchestrated by the GPOC and provide approved as-builts to the government as required by contract.
2.2.2 Contractor shall coordinate, with GPOC, required project permits, authorizations and site utility service points (electric, natural gas and water utility service shut-down at nearest junction point) at GPOC’s discretion as required by contract.
2.2.3 Contractor shall isolate utility services to the GPOC designated utility source points, disconnecting the services from site infrastructure network of pipes, lines, and wires as required by contract.
2.2.4 All work shall comply with the current regulations of the California State Marshal, California Building Code, Titles 8 and 19 through 24, serving utility rules and all other applicable State ordinances.
2.2.5 Contractor shall perform pre-project site inspection and continued as-build updates to validate characteristics for any revised or value engineering in plans and engineering as required by contract.
2.2.6 Contractor shall produce revised project design and plans as required and certified by the project and fire engineer during and at conclusion of construction.
2.3. Phase 2 (Build): Contractor is to use approved designs, components, elements (parts) materials, assets, devices, construction procedures and processes that meet or exceed requirements as specified below.
2.3.1 Contractor’s methods of removal and debris disposal is at contractor’s discretion, but shall comply with all installation, local, state and federal standards and requirements.
2.3.2 All results of project demolition shall be organized and disposed of as coordinated with the GPOC. Contractor shall comply with all installation, local, state and federal standards.
2.3.3 Contractor shall only use material, methods and processes recognized by the International Building Code (IBC), NFPA, AFOSH, OSHA and industry specific safety and application standards as required by contract.
2.3.4 Contractor shall perform a facility site inspection to validate and certify all systems operate safely as designed and required IAW this Statement of Work.
2.4. Phase 3 (Post-Construction Inspection, Certification and End-User Training):
Contractor shall coordinate with POC to perform Post-Construction acceptance, project records, completed inspection report and End-User Training.
2.4.1 Contractor shall validate all post-project deliverables with GPOC prior to scheduling project acceptance as required by contract.
2.4.2 Contractor shall provide training to base shop technicians to safely operate facility utility systems.
3.0 Project Requirements and Specifications: The Contractor shall adhere to the following requirements:
3.1 The Contractor is responsible for determining the exact location of all existing utilities and for the protection of and repair of damage to them. Contact underground service alert at 811, 48 hours before work is to begin. Coordinate dig permit through 60CES Customer Service (707-424-2575). Base dig permit process takes approximately two months.
3.2 The Contractor shall be responsible for and furnish, install, and maintain temporary signs, bridges, barricades, flagmen, and other facilities to adequately safeguard the general public and work. The contractor shall provide to the Travis AFB Traffic Engineer for review, a plan showing traffic control measures and or detours for vehicles affected by the construction work. The approved plan shall be delivered to the Project Manager prior to the implementation of the traffic control measures.
3.3 The Contractor shall be responsible for the protection of all existing survey monuments or markers during construction.
3.4 Trenches shall be backfilled and pavement shall be replaced per standard construction practices. All striping and pavement markings shall be restored.
3.5 Aggregate sub-base shall conform to specifications. Any grading operations outside of scope of work area shall be coordinated with 60 CES PM prior to commencement.
3.6 All grading, erosion and sediment control shall be in conformance with all applicable building codes and UFCs.
3.7 All open ends of utilities, conduit, sewer pipe, etc. shall be fabric protected until reinstallation of the connection.
3.8 All excess soil must be deposited offsite and at the Contractor’s expense.
3.9 City Lights and Power is the system owner of electrical distribution system while CALWater is the system owner of water distribution system here at Travis AFB.
3.10 Conduit installed underground shall be schedule 40 PVC. Conduit installed above ground shall be galvanized rigid steel.
4.1. Notification of Environmental Spills: If the contractor spills or releases any hazardous substance into the environment, the contractor shall immediately report the incident to the QA, base fire department, and base civil engineering. The contractor shall be liable for containment and environmental clean-up of the spill or release of such substance.
5. SAFETY: Personnel shall practice proper grounding procedures in accordance with the National Electrical Code (NEC). Personnel working with or near high voltage equipment should be familiar with modern methods of resuscitation. Personnel shall wear appropriate protective clothing and be aware of emergency procedures to perform emergency shutdown and start-up.
6. GOVERNMENT FURNISHED PROPERTY AND SERVICES: None.
7. GENERAL INFORMATION: Any as built adjustments or deviations to the original SOW will be submitted as proposals to the contracting officer.
7.1. QUALITY CONTROL. The contractor shall develop and implement warranty procedures to identify and prevent defective services from hindering usage.
7.2. QUALITY ASSURANCE. The Facility Manager and/or Project Inspector will periodically evaluate the contractor’s performance during the installation.
8. GOVERNING CODES
1. FC 1-300-09N Navy and Marine Corps Design Procedures
2. UFC 3-201-01 Civil Engineering
3. UFC 3-240-01 Wastewater Collection
4. UFC 3-240-02 Domestic Wastewater Treatment
5. Water Environment Federation Manual of Practice No. FD-6/American Society of Civil
Engineers Manuals and Reports on Engineering Practice No. 62, “Existing Sewer Evaluation and Rehabilitation”, 2009
6. International Building Code, 2015 Edition
7. Unified Facilities Criteria
a. UFC 1-200-01 – DoD Building Code (General Building Requirements)
b. UFC 1-300-02, Unified Facilities Guide Specifications (UFGS) format standard
c. UFC 1-300-08, Criteria for Transfer and Acceptance of DoD Real Property w/ C2
d. UFC 3-101-01, Architecture with C3 e.UFC 3-250-01, Pavement Design for Roads and Parking Areas
f. UFC 3-250-04, Standard Practice for concrete pavement with C2
g. UFC 3-301-01, Structural Engineering with C3
h. UFC 3-301-04, Seismic Design for Buildings with C1
i. UFC 3-320-06A, Concrete Floor Slabs on Grade Subjected to Heavy Loads
j. UFC 3-501-01, Electrical Engineering k.UFC 3-560-01, Electrical Safety, O&M with C5
l. UFC 3-600-01, Fire Protection Engineering m.UFC 4-010-01, DoD Minimum Antiterrorism Standards for buildings with C1
8. NFPS including:
NFPA 1, Fire Code
NFPA 10, Standard for Portable Fire Extinguishers
NFPA 13, Standard for the installation of Sprinkler Systems
NFPA 70, National Electrical Code
NFPA 70E, Standard for Electrical Safety in the Workplace
NFPA 72, National Fire Alarm signaling Code
NFPA 101, Life Safety Code
9. Accessibility Requirements:
ABA Accessibility Standard for Department of Defense Facilities
Attachments
Tab 1 – B650 overhead photo
Tab 2 – B650 floor plan
Tab 3 – B650 plumbing
Tab 4 – B650 pharmacy plumbing
| STATEMENT OF WORK |
| 1.2 Project Description: |
| 6. GOVERNMENT FURNISHED PROPERTY AND SERVICES: None. |
| 8. GOVERNING CODES |