2. Schedule of Items.docx
DOCX document 22 KB Posted
- Attached to
- Canyon Fire Recovery Road Maintenance
- Solicitation number
- 127EAW25R0053
- Issued by
-
Department of Agriculture Forest Service
About this file
The Schedule of Items document details a federal contract for Canyon Fire Recovery Road Maintenance in the Cleveland National Forest's Trabuco Ranger District. The solicitation (No. 127EAW25R0053) involves road maintenance and recovery work with three primary project components: a base project, Option 1 (Annual Road Maintenance 2025), and Option 2 (Airport BAER, Trabuco Canyon Road Clearing and Bridge Clearing).
Key scope items include mobilization, road blading, drainage function restoration, corrugated metal spillway installation, material removal and end haul, and drainage structure maintenance. The contract requires contractors to submit pricing for all items, with estimated quantities that must be field verified. A pre-proposal site visit is scheduled for 13 August 2025, and all Requests for Information must be submitted to Tanya Torres via email by 15 August 2025 at 1100 AM PDT. The contract will be awarded by the Department of Agriculture Forest Service, with one award planned from this solicitation.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE OF ITEMS
CANYON FIRE RECOVERY ROAD MAINTENANCE
CLEVELAND NATIONAL FOREST
TRABUCO RANGER DISTRICT
| ITEM |
| CONSTRUCTION ITEMS |
| UOI |
| QTY. |
| UNIT PRICE |
| TOTAL PRICE |
| 805 |
| MOBILIZATON |
| EACH |
| 1.00 |
| 811 |
| ROAD BLADING |
| MILES |
| 8.40 |
| 839 |
| RESTORE DRAINAGE FUNCTION |
| MILES |
| 8.40 |
| 840 |
| CORRUGATED METAL SPILLWAY |
| EACH |
| 49.00 |
| 832 |
| REMOVE AND END HAUL MATERIALS |
| EACH |
| 17.00 |
SUB-TOTAL
PROJECT: CNF ANNUAL ROAD MAINTENANCE 2025 (OPTION 1)
| ITEM |
| CONSTRUCTION ITEMS |
| UOI |
| QTY. |
| UNIT PRICE |
| TOTAL PRICE |
TRABUCO RANGER DISTRICT
| 805 |
| MOBILIZATON |
| EACH |
| 2.00 |
| 811 |
| ROAD BLADING |
| MILES |
| 15.88 |
| 839 |
| RESTORE DRAINAGE FUNCTION |
| MILES |
| 15.88 |
SUB-TOTAL OPTION 1:
PROJECT: AIRPORT BAER, TRABUCO CANYON ROAD CLEARING AND BRIDGE CLEARING (OPTION 2)
| ITEM |
| CONSTRUCTION ITEMS |
| UOI |
| QTY. |
| UNIT PRICE |
| TOTAL PRICE |
| 805 |
| MOBILIZATON |
| EACH |
| 4.00 |
| 832 |
| REMOVE AND END HAUL MATERIAL |
| CY |
| 12,000 |
| 811 |
| ROAD BLADING |
| MILES |
| 3.30 |
| 839 |
| RESTORE DRAINAGE FUNCTION |
| MILES |
| 3.30 |
| 834 |
| DRAINAGE STRUCTURE MAINTENANCE (INLET AND CULVERT CLEANING) |
| EACH |
| 1.00 |
SUB-TOTAL OPTION 2:
PROJECT TOTAL
BASE, PLUS OPTION 1, AND 2 :
SCHEDULE NOTES
* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE MAPS, STATEMENT OF WORK, AND SPECIFICATIONS.
* One award will be made from this solicitation. Contractors are required to submit pricing for all items.
* Items labeled as optional are not required to be exercised by the government. If exercised, the contractor will be required to perform the optional work in accordance with the terms and conditions of this contract.
NOTE: In accordance with FAR Clause 52.228-16, Performance and Payment Bonds - Other than Construction (NOV 2006), payment for bond premiums shall be included within the contract price and shall not be considered an additional cost.
The contractor shall complete the table below and include the information with their proposal.
| Company Name: |
| POC & Title: |
| Email: |
| Phone Number: |
| UEI Number: |
| Tax ID: |
File details come from the government source that posted it. Updated .