This is a Statement of Work (SOW) for the Federal Emergency Management Agency (FEMA) Transportable Temporary Housing Unit (TTHU) Bath & Shower program. FEMA requires contractors to furnish and deliver bathroom and shower fixtures and accessories to support the agency's Individual Assistance Direct Housing Program for displaced individuals with disabilities. The contractor must supply seven line items: a roll-in shower (Model 5LBS6030E75B or equivalent), a T-shaped water stopper kit, safety/grab bars in four sizes (12", 18", 24", and 48"), and a padded shower seat with legs. All items must be new, unused, delivered in original manufacturer packaging, and comply with American National Standard A117.1, Uniform Federal Accessibility Standards (UFAS), Americans with Disabilities Act (ADA), and 16 CFR Chapter II Subpart Consumer Product Safety Act standards.
Deliveries must be made to the FEMA Manufactured Housing Storage Site (MHSS) Cumberland facility in Cumberland, Maryland within 30 calendar days of order placement (potentially 32 days if ordered on a weekend). The contractor bears all shipping costs, which are to be included in unit pricing, and may use dedicated loads, less-than-load (LTL), or package carriers. Contractors must provide shipping notifications via email to the Contracting Officer, Contracting Officer's Representative, and delivery point of contact with bill of lading copies, tracking numbers, and estimated delivery dates. Upon delivery, items must be accompanied by itemized bills of lading and delivered on pallets. The contractor has 72 hours from notification to repair or replace damaged items at its own expense. The ordering period extends for five years from contract award. Government inspection and acceptance will occur at the delivery location, with the technical point of contact conducting inspections and the Contracting Officer's Representative issuing final acceptance.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FEDERAL EMERGENCY MANAGEMENT AGENCY (FEMA) TRANSPORTABLE
TEMPORARY HOUSING UNIT (TTHU) BATH & SHOWER STATEMENT OF WORK (SOW)
1. BACKGROUND
The Federal Emergency Management Agency (FEMA, or the Agency) is authorized under Section 408 of the Robert T. Stafford Disaster Relief and Emergency Assistance Act (42 U.S.C. 5174), as amended, to provide Direct Assistance to eligible disaster survivors. As part of its emergency response mission, FEMA provides standard household Bath & Shower items which are required in each Transportable Temporary Housing Units (TTHUs) to support displaced individuals with disabilities. These resources ensure the Logistics Operations Division can maintain a Ready for Deployment stock of Manufacture Housing Units (MHUs) in support of Individual's Assistance Direct Housing Program.
2. SCOPE
The Contractor shall furnish all materials, supplies, equipment, and related resources necessary to provide Bath & Shower items in accordance with the specifications and guidelines outlined in this Statement of Work (SOW).
3. REQUIREMENTS
The Contractor shall adhere to the following:
A. Requirements
• Select Bath & Shower items that meet the requirements specified in the (CLIN) Table.
• All Bath & Shower items shall comply with applicable fire and safety standards.
• Deliver Bath & Shower items to the destination specified in the call order.
B. Regulations:
• American National Standard A117.1
• Uniform Federal Accessibility Standards (UFAS) and Americans with
Disabilities Act (ADA)
• 16 Code of Federal Regulations (CFR) Chapter II Subpart Consumer Product Safety Act
3.1 TTHU Bath & Shower
The Contractor shall deliver only those Bath & Shower items specified and accepted by FEMA as part of the Request for Call Order Proposal (RFCOP). If an accepted product becomes unavailable, the Contractor shall propose a substitute product that meets the specifications outlined in this Statement of Work (SOW). Prior to shipment, the Contractor must submit a written justification to the Contracting Officer’s Representative (COR) detailing how the proposed substitute meets the required specifications.
All items shall be delivered in their original manufacturer/factory packaging. All items shall be new and unused.
3.2 Bath & Shower List
Bath & Shower CLIN # Item Unit
0001 Roll In Shower - Model Number 5LBS6030E75B (Brand name or equal)
EA
0002 T-shaped Water Stopper Kit EA 0003 Safety/Grab bar 12" EA 0004 Safety/Grab bar 18" EA 0005 Safety/Grab bar 24" EA 0006 Safety/Grab bar 48" EA 0007 Padded Shower Seat with Legs EA
4. PACKINING, LABELING AND DELIVERY
4.1 Packaging Instructions
All individual items shall remain packaged and sealed in the original factory packaging.
4.2 Tracking and Delivery
The Contractor may use any of the following methods to ship items: Dedicated Load; Less Than Load (LTL); or Package Carrier (e.g., FedEx, UPS, DHL, USPS, etc.)
The shipping cost is accounted for within the Unit Price for each item.
4.2.1 Tracking
The Contractor shall provide notice of shipping. The notice shall be provided by email to the Contracting Officer (CO), the Contracting Officer’s Representative (COR) and the delivery point of contact (POC).
Shipping shall include a copy of the Contractor’s bill of lading (BOL) and an estimated date of delivery.
The Contractor shall require that the delivery carrier’s driver notify the delivery POC 24 hours prior to delivery unless the delivery is using a carrier such as FedEx, UPS, DHL, USPS, etc. for package delivery.
Items that are shipped as package delivery shall have the tracking number provided to the COR and Delivery POC within 24 hours of the items being shipped.
Upon invoicing, the Contractor shall provide an electronic spreadsheet showing details of commodity shipped from place of origin to destination. At a minimum, the electronic spreadsheet must provide these details: Load number, Bill of Lading number, nomenclature and units shipped, personal identifier for each unit, carrier, truck number, trailer number, place of origin, and destination.
4.2.2 Delivery Locations
The delivery location is Contiguous United States (CONUS) and identified below:
FEMA Manufactured Housing Storage Site (MHSS) Cumberland located at:
Cumberland MHSS-FEMA 11601 PPG Road Cumberland, MD 21502
Delivery POC:
Keith Albright
(202) 957-3930 Keith.Albright@fema.dhs.gov
5. ORDERING PERIOD
The ordering period shall be for five (5) years from award.
6. DELIVERY
The Contractor shall call the specified POC at the delivery location identified in each Call Order to arrange a delivery window (day and time) and to understand any limitations at the site which would impact a delivery (ex. clearance levels into garage, building hours, etc.).
All items shall be delivered on (a) pallet(s). Itemized BOL shall accompany all deliveries. Any discrepancies will be reported back to the Contractor within 1 day of completed delivery and inventory inspection. The Contractor shall provide a spreadsheet to the COR indicating totals for each item after each delivery and grand totals for all deliveries within 72 hours of delivery.
The Contractor shall be able to deliver the items identified as Bath & Shower to the specified FEMA destination within 30 calendar days from the date of the order. Delivery may take place up to two additional days after this requirement if the order is placed on a weekend day and if the destination facility is not open.
7. GOVERNMENT INSPECTION AND ACCEPTANCE
Government inspection and acceptance will be in accordance with FAR 52.212-4(b). The technical point of contact at the delivery location will inspect the Bath & Shower items and orders will be accepted by the COR.
8. DAMAGED ITEMS
The Contractor shall repair/replace damaged items at FEMA’s discretion. The Contractor shall have 72 hours from time of notification to repair a damaged item or replace the item and deliver it on the time schedule agreed to in the Call Order. Replacement items shall be shipped to FEMA at the Contractor’s expense and damaged items shall be returned to the Contractor at the Contractor’s expense.