This is an Erosion and Sedimentation Control Plan (E&S Plan) for the demolition of a single-family residence located at 4237 Thoms Run Road in Collier Township, Allegheny County, Pennsylvania. The plan was prepared by LSSE Civil Engineers and Surveyors and finalized in February 2026. The project involves the complete demolition of an existing structure on approximately 0.41 acres, with the work consisting of utility termination, asbestos removal if applicable, off-site disposal of all building materials and debris, and site restoration. Construction activities will proceed in nine sequential phases, beginning with field marking the limits of disturbance and installation of erosion control measures including a FODS trackout control system, compost filter socks, and a temporary road crossing (GP-8-1) over Thoms Run in accordance with Pennsylvania General Permit No. 8. The temporary road crossing may remain in place for up to one year from the Department of Environmental Protection's acknowledgement unless extended in writing. All earth disturbance activities must be preceded by a mandatory preconstruction meeting at least seven days prior to work initiation, with notification to the Pennsylvania One Call System required at least three days before excavation begins. All disturbed areas must be stabilized with seed, mulch, and erosion control blankets upon reaching final grade, with a target of achieving 70% uniform perennial vegetative cover.

The project requires strict compliance with Pennsylvania Department of Environmental Protection regulations regarding erosion and sedimentation control, clean fill requirements, and environmental due diligence. All excess materials must be immediately loaded and transported to a PaDEP-approved disposal facility, with material disposal documented and tracked throughout the project. Weekly inspections of all erosion control best management practices (BMPs) are mandated, with maintenance performed within 24 hours of any identified deficiencies. The site contains three soil types (Gilpin, Weikert, and Culleoka) with varying slopes and depth to bedrock, requiring specific conservation practices and soil amendments to support vegetation establishment. No riparian forest buffers are present on site, and the site is not located within a High Quality or Exceptional Value watershed. The project will result in a net decrease in impervious surface from 0.03 acres to zero acres. Upon completion of all demolition activities and achievement of permanent stabilization, the owner/operator must contact the local conservation district for final inspection prior to removal or conversion of temporary erosion control measures. The project is part of a broader demolition initiative coordinated by Char-West Council of Governments, with sealed bids due by 11:00 am on July 31, 2026.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

T H

O M

S R

U N

R O

A D

STEEN HOLLOW ROAD

EXISTING STRUCTURE

TO BE DEMOLISHED

GsF

Ne

GsF

DoC

CuD

GsF

GuC

LIMIT OF DISTURBANCE

0.40 ACRES

FODS TRACKOUT

CONTROL SYSTEM

TEMPORARY ROAD

CROSSING GP-8-1

18" COMPOST FILTER

SOCK AREA No. 2 (See Detail)

12" COMPOST FILTER

SOCK AREA No. 1 (See detail)

CONTRACTOR TO IMMEDIATELY

LOAD ALL EXCESS MATERIAL

ONTO A TRUCK AND HAUL TO A

PaDEP APPROVED DISPOSAL

FACILITY.

LSSE

Civil Engineers and Surveyors

Fike LSI LSSE Rabell Senate ES1 of ES3394-081-ES1

1"=40'

February, 2026

Erosion And Sedimentation Control Plan4237 Thoms Run Demolition

Situate In Collier Township, Allegheny County, Pennsylvania

Collier Township 2418 Hilltop Road Presto, PA 15142

EXISTING LEGEND

CALL 811

CALL BEFORE YOU DIG!

Dial 8-1-1 or 1-800-242-1776 not less than 3 business days nor more than 10 business days prior to the start of excavation.

Coordinate your project via Coordinate PA at www.paonecall.org.

PRELIMINARY DESIGN SERIAL

No.

FINAL DESIGN SERIAL

No.

20253383173, (12/3/2025)

Location MapLocation Map

GlD

SITE LOCATION

PROPOSED LEGEND

LSSE

Civil Engineers and Surveyors

Fike LSI LSSE Rabell Senate ES2 of ES3394-081-ES2

As Shown

February, 2026

Erosion and Sedimentation Control Details4237 Thoms Run Demolition

Situate In Collier Township, Allegheny County, Pennsylvania

Collier Township 2418 Hilltop Road Presto, PA 15142

NOTES:

1. ALL EARTH DISTURBANCES, INCLUDING CLEARING AND GRUBBING AS WELL AS CUTS

AND FILLS SHALL BE DONE IN ACCORDANCE WITH THE APPROVED E&S PLAN. A COPY

OF THE APPROVED DRAWINGS (STAMPED, SIGNED AND DATED BY THE REVIEWING

AGENCY) MUST BE AVAILABLE AT THE PROJECT SITE AT ALL TIMES. THE REVIEWING

AGENCY SHALL BE NOTIFIED OF ANY CHANGES TO THE APPROVED PLAN PRIOR TO

IMPLEMENTATION OF THOSE CHANGES. THE REVIEWING AGENCY MAY REQUIRE A

WRITTEN SUBMITTAL OF THOSE CHANGES FOR REVIEW AND APPROVAL AT ITS

DISCRETION.

2. AT LEAST 7 DAYS PRIOR TO STARTING ANY EARTH DISTURBANCE ACTIVITIES,

INCLUDING CLEARING AND GRUBBING, THE OWNER AND/OR OPERATOR SHALL INVITE

ALL CONTRACTORS, THE LANDOWNER, APPROPRIATE MUNICIPAL OFFICIALS, THE E&S

PLAN PREPARER, THE PCSM PLAN PREPARER, THE LICENSED PROFESSIONAL

RESPONSIBLE FOR OVERSIGHT OF CRITICAL STAGES OF IMPLEMENTATION OF THE

PCSM PLAN, AND A REPRESENTATIVE FROM THE LOCAL CONSERVATION DISTRICT TO

AN ON-SITE PRECONSTRUCTION MEETING.

3. AT LEAST 3 DAYS PRIOR TO STARTING ANY EARTH DISTURBANCE ACTIVITIES, OR

EXPANDING INTO AN AREA PREVIOUSLY UNMARKED, THE PENNSYLVANIA ONE CALL

SYSTEM INC. SHALL BE NOTIFIED AT 811 FOR THE LOCATION OF EXISTING

UNDERGROUND UTILITIES.

4. ALL EARTH DISTURBANCE ACTIVITIES SHALL PROCEED IN ACCORDANCE WITH THE

SEQUENCE PROVIDED ON THE PLAN DRAWINGS. DEVIATION FROM THAT SEQUENCE

MUST BE APPROVED IN WRITING FROM THE LOCAL CONSERVATION DISTRICT OR BY

THE DEPARTMENT PRIOR TO IMPLEMENTATION.

5. AREAS TO BE FILLED ARE TO BE CLEARED, GRUBBED, AND STRIPPED OF TOPSOIL TO

REMOVE TREES, VEGETATION, ROOTS AND OTHER OBJECTIONABLE MATERIAL.

6. CLEARING, GRUBBING, AND TOPSOIL STRIPPING SHALL BE LIMITED TO THOSE AREAS

DESCRIBED IN EACH STAGE OF THE CONSTRUCTION SEQUENCE. GENERAL SITE

CLEARING, GRUBBING AND TOPSOIL STRIPPING MAY NOT COMMENCE IN ANY STAGE

OR PHASE OF THE PROJECT UNTIL THE E&S BMPS SPECIFIED BY THE BMP SEQUENCE

FOR THAT STAGE OR PHASE HAVE BEEN INSTALLED AND ARE FUNCTIONING AS

DESCRIBED IN THIS E&S PLAN.

7. AT NO TIME SHALL CONSTRUCTION VEHICLES BE ALLOWED TO ENTER AREAS

OUTSIDE THE LIMIT OF DISTURBANCE BOUNDARIES SHOWN ON THE PLAN MAPS. THESE

AREAS MUST BE CLEARLY MARKED AND FENCED OFF BEFORE CLEARING AND

GRUBBING OPERATIONS BEGIN.

8. TOPSOIL REQUIRED FOR THE ESTABLISHMENT OF VEGETATION SHALL BE STOCKPILED

AT THE LOCATION(S) SHOWN ON THE PLAN MAPS(S) IN THE AMOUNT NECESSARY TO

COMPLETE THE FINISH GRADING OF ALL EXPOSED AREAS THAT ARE TO BE STABILIZED

BY VEGETATION. EACH STOCKPILE SHALL BE PROTECTED IN THE MANNER SHOWN ON

THE PLAN DRAWINGS. STOCKPILE HEIGHTS SHALL NOT EXCEED 35 FEET. STOCKPILE

SLOPES SHALL BE 2H:1V OR FLATTER. STOCKPILE LOCATIONS MUST BE AT LEAST 50'

FROM ANY SURFACE WATER. TOPSOIL SHALL BE SEGREGATED FROM TRENCHING AND

SITE GRADING WHERE APPLICABLE. TOPSOIL SHALL BE REUSED FOR SITE

RESTORATION.

9. IMMEDIATELY UPON DISCOVERING UNFORESEEN CIRCUMSTANCES POSING THE

POTENTIAL FOR ACCELERATED EROSION AND/OR SEDIMENT POLLUTION, THE

OPERATOR SHALL IMPLEMENT APPROPRIATE BEST MANAGEMENT PRACTICES TO

MINIMIZE THE POTENTIAL FOR EROSION AND SEDIMENT POLLUTION AND NOTIFY THE

LOCAL CONSERVATION DISTRICT AND/OR THE REGIONAL OFFICE OF THE DEPARTMENT.

10. ALL BUILDING MATERIALS AND WASTES SHALL BE REMOVED FROM THE SITE AND

RECYCLED OR DISPOSED OF IN ACCORDANCE WITH THE DEPARTMENT'S SOLID WASTE

MANAGEMENT REGULATIONS AT 25 PA. CODE 260.1 ET SEQ., 271.1, AND 287.1 ET. SEQ.

NO BUILDING MATERIALS OR WASTES OR UNUSED BUILDING MATERIALS SHALL BE

BURNED, BURIED, DUMPED, OR DISCHARGED AT THE SITE.

11. ALL OFF-SITE WASTE AND BORROW AREAS MUST HAVE AN E&S PLAN APPROVED BY

THE LOCAL CONSERVATION DISTRICT OR THE DEPARTMENT FULLY IMPLEMENTED

PRIOR TO BEING ACTIVATED.

12. THE CONTRACTOR IS RESPONSIBLE FOR ENSURING THAT ANY MATERIAL BROUGHT

ON SITE IS CLEAN FILL. FORM FP-001 MUST BE RETAINED BY THE PROPERTY OWNER

FOR ANY FILL MATERIAL AFFECTED BY A SPILL OR RELEASE OF A REGULATED

SUBSTANCE BUT QUALIFYING AS CLEAN FILL DUE TO ANALYTICAL TESTING.

13. ALL PUMPING OF WATER FROM ANY WORK AREA SHALL BE DONE ACCORDING TO

THE PROCEDURE DESCRIBED IN THIS PLAN, OVER UNDISTURBED VEGETATED AREAS.

14. UNTIL THE SITE IS STABILIZED, ALL EROSION AND SEDIMENT BMPS SHALL BE

MAINTAINED PROPERLY. MAINTENANCE SHALL INCLUDE INSPECTIONS OF ALL

EROSION AND SEDIMENT BMPS AFTER EACH RUNOFF EVENT AND ON A WEEKLY BASIS.

ALL PREVENTATIVE AND REMEDIAL MAINTENANCE WORK, INCLUDING CLEAN OUT,

REPAIR, REPLACEMENT, REGRADING, RESEEDING, RE-MULCHING AND RE-NETTING

MUST BE PERFORMED IMMEDIATELY. IF THE E&S BMPS FAIL TO PERFORM AS

EXPECTED, REPLACEMENT BMPS, OR MODIFICATIONS OF THOSE INSTALLED WILL BE

REQUIRED.

15. SEDIMENT TRACKED ONTO ANY PUBLIC ROADWAY OR SIDEWALK SHALL BE

RETURNED TO THE CONSTRUCTION SITE BY THE END OF EACH WORK DAY AND

DISPOSED IN THE MANNER DESCRIBED IN THIS PLAN. IN NO CASE SHALL THE SEDIMENT

BE WASHED, SHOVELED, OR SWEPT INTO ANY ROADSIDE DITCH, STORM SEWER, OR

SURFACE WATER.

17. ALL SEDIMENT REMOVED FROM BMPS SHALL BE DISPOSED OF IN THE MANNER

DESCRIBED ON THE PLAN DRAWINGS.

18. AREAS WHICH ARE TO BE STRIPPED OF TOPSOIL SHALL BE SCARIFIED TO A MINIMUM

DEPTH OF 3 TO 5 INCHES -- 6 TO 12 INCHES ON COMPACTED SOILS -- PRIOR TO

PLACEMENT OF TOPSOIL. AREAS TO BE VEGETATED SHALL HAVE A MINIMUM 4 INCHES

OF TOPSOIL IN PLACE PRIOR TO SEEDING AND MULCHING. FILL OUT SLOPES SHALL

HAVE A MINIMUM OF 2 INCHES OF TOPSOIL.

19. SEEPS OR SPRINGS ENCOUNTERED DURING CONSTRUCTION SHALL BE HANDLED IN

ACCORDANCE WITH THE STANDARD AND SPECIFICATION FOR SUBSURFACE DRAIN OR

OTHER APPROVED METHOD.

20. ALL GRADED AREAS SHALL BE PERMANENTLY STABILIZED IMMEDIATELY UPON

REACHING FINISHED GRADE. CUT SLOPES IN COMPETENT BEDROCK AND ROCK FILLS

NEED NOT BE VEGETATED. SEEDED AREAS WITHIN 50 FEET OF A SURFACE WATER (100

FEET OF SPECIAL PROTECTION WATERSHEDS), OR AS OTHERWISE SHOWN ON THE PLAN

DRAWINGS, SHALL BE BLANKETED ACCORDING TO THE STANDARDS OF THIS PLAN.

21. IMMEDIATELY AFTER EARTH DISTURBANCE ACTIVITIES CEASE IN ANY AREA OR

SUBAREA OF THE PROJECT, THE OPERATOR SHALL STABILIZE ALL DISTURBED AREAS.

DURING NON-GERMINATING MONTHS, MULCH OR PROTECTIVE BLANKETING SHALL BE

APPLIED AS DESCRIBED IN THE PLAN. AREAS NOT AT FINISHED GRADE, WHICH WILL BE

REACTIVATED WITHIN 1 YEAR, MAY BE STABILIZED IN ACCORDANCE WITH THE

TEMPORARY STABILIZATION SPECIFICATIONS. THOSE AREAS WHICH WILL NOT BE

REACTIVATED WITHIN 1 YEAR SHALL BE STABILIZED IN ACCORDANCE WITH THE

PERMANENT STABILIZATION SPECIFICATIONS.

22. PERMANENT STABILIZATION IS DEFINED AS A MINIMUM UNIFORM, PERENNIAL 70%

VEGETATIVE COVER OR OTHER PERMANENT NON-VEGETATIVE COVER WITH A

DENSITY SUFFICIENT TO RESIST ACCELERATED EROSION. CUT AND FILL SLOPES SHALL

BE CAPABLE OF RESISTING FAILURE DUE TO SLUMPING, SLIDING, OR OTHER

MOVEMENTS.

23. E&S BMPS SHALL REMAIN FUNCTIONAL AS SUCH UNTIL ALL AREAS TRIBUTARY TO

THEM ARE PERMANENTLY STABILIZED OR UNTIL THEY ARE REPLACED BY ANOTHER

BMP APPROVED BY THE LOCAL CONSERVATION DISTRICT OR THE DEPARTMENT.

24. UPON COMPLETION OF ALL EARTH DISTURBANCE ACTIVITIES AND PERMANENT

STABILIZATION OF ALL DISTURBED AREAS, THE OWNER AND/OR OPERATOR SHALL

CONTACT THE LOCAL CONSERVATION DISTRICT FOR AN INSPECTION PRIOR TO

REMOVAL/CONVERSION OF THE E&S BMPS.

25. AFTER FINAL SITE STABILIZATION HAS BEEN ACHIEVED, TEMPORARY EROSION AND

SEDIMENT BMPS MUST BE REMOVED OR CONVERTED TO PERMANENT POST

CONSTRUCTION STORMWATER MANAGEMENT BMPS. AREAS DISTURBED DURING

REMOVAL OR CONVERSION OF THE BMPS SHALL BE STABILIZED IMMEDIATELY. IN

ORDER TO ENSURE RAPID REVEGETATION OF DISTURBED AREAS, SUCH

REMOVAL/CONVERSIONS ARE TO BE DONE ONLY DURING THE GERMINATING SEASON.

26. UPON COMPLETION OF ALL EARTH DISTURBANCE ACTIVITIES AND PERMANENT

STABILIZATION OF ALL DISTURBED AREAS, THE OWNER AND/OR OPERATOR SHALL

CONTACT THE LOCAL CONSERVATION DISTRICT TO SCHEDULE A FINAL INSPECTION.

27. FAILURE TO CORRECTLY INSTALL E&S BMPS, FAILURE TO PREVENT SEDIMENT-LADEN

RUNOFF FROM LEAVING THE CONSTRUCTION SITE, OR FAILURE TO TAKE IMMEDIATE

CORRECTIVE ACTION TO RESOLVE FAILURE OF E&S BMPS MAY RESULT IN

ADMINISTRATIVE, CIVIL, AND/OR CRIMINAL PENALTIES BEING INSTITUTED BY THE

DEPARTMENT AS DEFINED IN SECTION 602 OF THE PENNSYLVANIA CLEAN STREAMS

LAW. THE CLEAN STREAMS LAW PROVIDES FOR UP TO $10,000 PER DAY IN CIVIL

PENALTIES, UP TO $10,000 IN SUMMARY CRIMINAL PENALTIES, AND UP TO $25,000 IN

MISDEMEANOR CRIMINAL PENALTIES FOR EACH VIOLATION.

28. COMPOST FILTER SOCKS IN AREAS THAT CANNOT BE STAKED (I.E. PAVED AREAS)

SHALL BE BACKED WITH CONCRETE BLOCKS PER THE MANUFACTURER'S

RECOMMENDATIONS.

29. EROSION CONTROL BLANKET SHALL BE INSTALLED ON ALL DISTURBED SLOPES 3H:1V

OR STEEPER, AND ON ALL DISTURBED AREAS WITHIN 50 FEET OF A SURFACE WATER

(100 FEET OF SPECIAL PROTECTION WATERSHEDS) AND ON ALL OTHER DISTURBED

AREAS SPECIFIED ON THE PLAN MAPS AND/OR DETAIL SHEETS.

30. ALL AREAS DISTURBED BY BMP MAINTENANCE ACTIVITIES SHALL BE IMMEDIATELY

STABILIZED WITH SEED AND MULCH.

31. CROSSINGS MAY REMAIN INSTALLED FOR A PERIOD OF TIME NOT NOT EXCEED ONE (1)

YEAR FROM THE DATE OF THE DEPARTMENTS' ACKNOWLEDGEMENT UNLESS

EXTENDED IN WRITING BY THE DEPARTMENT.

32. OWNERS SHALL INVESTIGATE FOR DRINKING WATER INTAKES OR RESERVOIRS FOR

PUBLIC WATER SUPPLIES WITHIN FIVE (5) MILES DOWNSTREAM OF THE SITE OF THE

TEMPORARY ROAD CROSSING. WRITTEN NOTICE SHALL BE GIVEN TO OPERATORS OF

ANY SUCH INTAKES OR RESERVOIRS AT LEAST TEN (10) DAYS PRIOR TO CONSTRICTION

OF THE TEMPORARY ROAD CROSSING. OWNERS MUST NOTIFY PUBLIC WATER SUPPL

OPERATORS IMMEDIATELY AND NO LONER THAN ONE (1) HOUR AFTER AND

OCCURRENCE AT THE CROSSING SITE WHICH RESULTS IN THE RELEASED OF

SUSPENDED SOLIDS AND TURBIDITY TO THE STREAM.

PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION (PADEP) REGULATIONS

STATE THAT THE APPLICANT IS RESPONSIBLE TO PROVIDE CLEAN FILL AND PERFORM

ENVIRONMENTAL DUE DILIGENCE. THE PADEP DEFINITION OF CLEAN FILL AND

ENVIRONMENTAL DUE DILIGENCE ARE LISTED BELOW.

CLEAN FILL IS DEFINED AS: UNCONTAMINATED, NON-WATER SOLUBLE,

NON-DECOMPOSABLE, INERT, SOLID MATERIAL. THE TERM INCLUDES SOIL, ROCK, STONE,

DREDGED MATERIAL, USED ASPHALT, AND BRICK, BLOCK OR CONCRETE FROM

CONSTRUCTION AND DEMOLITION ACTIVITIES THAT IS SEPARATE FROM OTHER WASTE

AND IS RECOGNIZABLE AS SUCH. THE TERM DOES NOT INCLUDE MATERIALS PLACED IN OR

ON THE WATERS OF THE COMMONWEALTH UNLESS OTHERWISE AUTHORIZED. (THE TERM

"USED ASPHALT" DOES NOT INCLUDE MILLED ASPHALT OR ASPHALT THAT HAS BEEN

PROCESSED FOR RE-USE.)

ENVIRONMENTAL DUE DILIGENCE IS DEFINED AS: INVESTIGATIVE TECHNIQUES,

INCLUDING, BUT NOT LIMITED TO, VISUAL PROPERTY INSPECTIONS, ELECTRONIC DATA

BASE SEARCHES, REVIEW OF PROPERTY OWNERSHIP, REVIEW OF PROPERTY USE HISTORY,

SANBORN MAPS, ENVIRONMENTAL QUESTIONNAIRES, TRANSACTION SCREENS,

ANALYTICAL TESTING, ENVIRONMENTAL ASSESSMENTS OR AUDITS. ANALYTICAL TESTING

IS NOT A REQUIRED PART OF DUE DILIGENCE UNLESS VISUAL INSPECTION AND/OR REVIEW

OF THE PAST LAND USE OF THE PROPERTY INDICATES THAT THE FILL MAY HAVE BEEN

SUBJECTED TO A SPILL OR RELEASE OF REGULATED SUBSTANCE. IF THE FILL MAY HAVE

BEEN AFFECTED BY A SPILL OR RELEASE OF A REGULATED SUBSTANCE, IT MUST BE TESTED

TO DETERMINE IF IT QUALIFIES AS CLEAN FILL. TESTING SHOULD BE PERFORMED IN

ACCORDANCE WITH APPENDIX A OF THE DEPARTMENT'S POLICY "MANAGEMENT OF FILL".

NOTES:

1. THE EXISTING SITE CONSISTS OF THOMS RUN, SECONDARY GROWTH FOREST, AND A

SINGLE FAMILY HOME TO BE DEMOLISHED.

2. THE DEVELOPMENT HAS BEEN DESIGNED TO MINIMIZE LAND CLEARING, GRADING,

IMPERVIOUS AREAS, SOIL COMPACTION, AND HAS BEEN DESIGNED TO MAXIMIZE

PROTECTION OF EXISTING DRAINAGE FEATURES AND VEGETATION TO THE EXTENT

POSSIBLE.

3. THE SITE IS NOT LOCATED WITHIN A HQ OR EV WATERSHED.

4. THE DEVELOPMENT IS LOCATED ON 0.41 ACRES WITH APPROXIMATELY 0.03 ACRES OF

EXISTING IMPERVIOUS SURFACE. THE PROPOSED DEVELOPMENT WILL RESULT IN 0.0

ACRES OF IMPERVIOUS SURFACE RESULTING IN A DECREASE TO THE EXISTING

IMPERVIOUS SURFACE.

5. NO KNOWN NATURALLY OCCURRING GEOLOGICAL FEATURES OR SOIL CONDITIONS

WITH THE POTENTIAL TO CAUSE POLLUTION ARE EVIDENT ONSITE.

6. RUNOFF FROM IMPERVIOUS AREAS WILL BE DIRECTED TO A EROSION AND

SEDIMENTATION CONTROL FACILITIES WHERE IT WILL BE ALLOWED TO COOL BEFORE

ENTERING WATERS OF THE COMMONWEALTH.

102.4(B)(5)(VII) SEQUENCE OF BMP INSTALLATION AND REMOVAL

CRITICAL STAGE BEST MANAGEMENT PRACTICES (PCSM SCMS)

DISTURBED AREAS WILL BE RETURNED TO APPROXIMATE ORIGINAL CONTOURS AND

PRE-CONSTRUCTION COVER CONDITIONS; THEREFORE, CRITICAL STAGE SCMS ARE NOT

REQUIRED.

DETAILED EROSION CONTROL PLAN AND PHASING

REFER TO THE SITE GRADING PLAN AND THE SOIL EROSION AND SEDIMENTATION CONTROL

PLANS WHICH ARE REFERENCED IN THE FOLLOWING NARRATIVE:

CONSTRUCTION PHASING

THE WORK CONSISTS OF APPROXIMATELY 0.41 ACRES OF DISTURBED AREA WHICH

CONSISTS OF THE DEMOLITION OF AN EXISTING SINGLE-FAMILY HOME, EROSION CONTROL

FACILITIES, AND ALL OTHER APPURTENANCE NECESSARY. ALL DISTURBED SLOPES 3:1 H:V

OR GREATER SHALL BE STABILIZED WITH SEED, MULCH AND EROSION CONTROL

BLANKETS. ANY BUILDING MATERIALS ENCOUNTERED DURING EXCAVATION MUST

IMMEDIATELY BE TAKEN TO A PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL

PROTECTION (PADEP) APPROVED OR PERMITTED LANDFILL. MATERIAL DISPOSED OF

OFFSITE MUST BE TAKEN TO A SITE WITH AN APPROVED EROSION AND SEDIMENTATION

CONTROL PLAN OR A PADEP APPROVED SITE. ALL EROSION AND SEDIMENTATION

CONTROL BMPS THAT ARE INSTALLED MUST BE COMPLETE AND FUNCTIONING BEFORE

THEIR TRIBUTARY AREAS ARE DISTURBED. ALL AREAS DISTURBED BY BMP MAINTENANCE

ACTIVITIES SHALL BE IMMEDIATELY STABILIZED WITH SEED AND MULCH. NO MORE THAN

15,000 SQUARE FEET OF DISTURBED AREA SHALL REACH FINAL GRADE BEFORE INITIATING

SEEDING AND MULCHING OPERATIONS. CESSATION OF ACTIVITY FOR AT LEAST 4 DAYS

REQUIRES TEMPORARY STABILIZATION. IT IS PROPOSED TO PROCEED WITH THE PROJECT IN

THE FOLLOWING SEQUENCE:

1. FIELD-MARK THE LIMIT OF DISTURBANCE AND ANY ENVIRONMENTALLY SENSITIVE

AREAS (INCLUDING STEEP SLOPES, WETLANDS, AND FLOODWAYS) IN ACCORDANCE

WITH THE PLAN.

2. INSTALL THE FODS TRACKOUT CONTROL SYSTEM AS SHOWN ON THE PLANS AND

DETAILS. THIS IS THE ONLY ENTRANCE TO BE USED BY CONSTRUCTION VEHICLES.

CONTRACTOR TO VACUUM/STREET SWEEP PAVED AREAS AT THE END OF EACH WORK

DAY AND AFTER EACH RAIN EVENT, AS WELL AS MANUALLY CLEAN TIRES PRIOR TO

SITE EGRESS.

3. INSTALL 12” COMPOST FILTER SOCK AREA NO. 1 AS SHOWN ON THE PLANS AND

DETAILS.

4. INSTALL THE GP-8-1 TEMPORARY ROAD CROSSING OVER THOMS RUN AS SHOWN ON

THE PLANS AND DETAILS AND PER THE CONDITIONS AND REGULATIONS OF THE

APPROVED GENERAL PERMIT NO. 8. CROSSINGS MAY REMAIN INSTALLED FOR A PERIOD

OF TIME NOT TO EXCEED ONE (1) YEAR FROM THE DATE OF THE DEPARTMENT'S

ACKNOWLEDGES UNLESS EXTENDED IN WRITING BY THE DEPARTMENT.

5. INSTALL 18" COMPOST FILTER SOCK AREA NO. 2 AS SHOWN ON THE PLANS AND

DETAILS

6. BEGIN WORK TO DEMOLISH THE EXISTING HOUSE ON-SITE. EXCESS MATERIAL IS TO BE

IMMEDIATELY LOADED ONTO A TRUCK AND DISPOSED OF AS STATED IN THE

RECYCLING AND DISPOSAL OF MATERIALS SECTION OF THIS REPORT. ANY

ACCUMULATED WATER SHALL BE REMOVED BY PUMPING THROUGH A PUMPED WATER

FILTER BAG SURROUNDED BY COMPOST FILTER SOCK. SEED AND MULCH DISTURBED

AREA.

7. UPON COMPLETION OF THE DEMOLITION AND REMOVAL OF THE HOUSE, REMOVE

COMPOST FILTER SOCK AREA NO. 2, THEN REMOVE THE GP-8-1 TEMPORARY ROAD

CROSSING OVER THOMS RUN. SEED AND MULCH DISTURBED AREA. DISPOSE OF ANY

REMOVED MATERIALS AS STATED IN THE RECYCLING AND DISPOSAL OF MATERIALS

SECTION OF THIS REPORT.

8. REMOVE FODS TRACKOUT CONTROL SYSTEM. SEED AND MULCH ALL REMAINING

DISTURBED AREAS.

9. ONCE THE SITE HAS ACHIEVED A UNIFORM 70% PERENNIAL VEGETATIVE COVER AND

SITE IS STABILIZED WITH STONE OR PAVEMENT, REMOVE COMPOST FILTER SOCK AREA

NO. 1. DISPOSE OF ANY REMAINING SILT AND COMPOST FILTER SOCKS AS STATED IN

THE RECYCLING AND DISPOSAL OF MATERIALS SECTION OF THIS REPORT. SEED AND

MULCH ALL REMAINING DISTURBED AREAS.

102.4(B)(5)(X) MAINTENANCE OF CONTROL FACILITIES

MAINTENANCE OF CONTROL FACILITIES

INSPECTION AND MAINTENANCE PROGRAMS WILL BE IMPLEMENTED DURING AND AFTER

CONSTRUCTION TO ASSURE THAT EROSION AND SEDIMENTATION MEASURES ARE

MAINTAINED. ALL EROSION AND SEDIMENTATION CONTROL FACILITIES WILL BE

INSPECTED WEEKLY AND AFTER EVERY RUNOFF EVENT. INSPECTIONS AND MAINTENANCE

ARE TO BE DOCUMENTED ON THE PADEP VISUAL INSPECTION FORM 3800-FM-BCW0271D IN

ACCORDANCE WITH THE PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION

AND THE ALLEGHENY COUNTY CONSERVATION DISTRICT GUIDELINES. REPAIRS AND

MAINTENANCE WILL BE PERFORMED BY THE CONTRACTOR AS REQUIRED TO MAINTAIN

THE INTEGRITY OF THE MEASURES AND FACILITIES. ANY DEFICIENCIES MUST BE

CORRECTED BY THE CONTRACTOR WITHIN 24 HOURS UPON IDENTIFICATION OF THE

DEFICIENCY. ALL AREAS DISTURBED BY BMP MAINTENANCE ACTIVITIES SHALL BE

IMMEDIATELY STABILIZED WITH SEED AND MULCH. SPECIFIC MAINTENANCE PROGRAMS

FOR EROSION CONTROL BMPS ARE DESCRIBED BELOW. ALL MAINTENANCE MEASURES ARE

THE RESPONSIBILITY OF THE CONTRACTOR AND OF THE INDIVIDUAL PERMIT HOLDER.

FODS TRACKOUT CONTROL SYSTEM

VEHICLES SHOULD TRAVEL DOWN THE LENGTH OF THE FODS TRACKOUT CONTROL SYSTEM

AND NOT CUT ACROSS THE MATS. DRIVERS SHOULD TURN THE WHEEL OF THEIR VEHICLES

SUCH THAT THE VEHICLE WILL TAKE A SERPENTINE ROUTE DOWN THE LENGTH OF THE

SYSTEM. MATS SHOULD BE CLEANED ONCE THE VOIDS BETWEEN THE PYRAMIDS BECOME

FULL OF SEDIMENT. TYPICALLY, THIS TASK WILL NEED TO BE PERFORMED WITHIN TWO

WEEKS AFTER A STORM EVENT. BRUSHING IS THE PREFERRED METHOD OF CLEANING,

EITHER MANUALLY OR MECHANICALLY. THE USE OF ICE MELT, ROCK SALT, SNOW MELT,

DEICER, ETC. SHOULD BE UTILIZED AS NECESSARY DURING THE WINTER MONTHS AND

AFTER A SNOW EVENT. ANY REPAIRS WILL BE MADE WITHIN 24 HOURS.

COMPOST FILTER SOCKS

COMPOST FILTER SOCKS WILL BE INSPECTED WEEKLY AND AFTER EVERY RUNOFF EVENT

AND ANY REQUIRED REPAIRS, SUCH AS REPLACING OR RE-STAKING, WILL BE MADE WITHIN

24 HOURS. SEDIMENT DEPOSITS WILL BE REMOVED WHEN IT REACHES 1/2 OF THE HEIGHT

OF THE FILTER SOCK.

FILTER BAG

THE PURPOSE OF A FILTER BAG IS TO REMOVE SEDIMENT FROM RUNOFF OR

GROUNDWATER WHICH IS PUMPED FROM THE WORK AREA. THE BAG MUST BE LOCATED IN

AN AREA THAT IS WELL-VEGETATED AND HAS A LAND SLOPE OF LESS THAN FIVE PERCENT

(5%) OR ON A BED OF AASHTO NO. 57 STONE. THE FILTER BAG SHALL BE CONSTRUCTED OF

NON-WOVEN GEOTEXTILE. THE BAG MUST TRAP PARTICLES LARGER THAN 150 MICRONS.

THE PUMPING RATE SHOULD NOT EXCEED 1/2 OF THE MAXIMUM RECOMMENDED BY THE

BAG MANUFACTURER. FILTER BAGS MUST DISCHARGE INTO STABLE, EROSION RESISTANT

AREAS. THE FILTER BAG SHOULD BE INSPECTED DAILY AND AFTER EACH PRECIPITATION

EVENT. ANY REQUIRED REPAIRS, SUCH AS REPLACING OF THE FILTER BAG, WILL BE MADE

WITHIN 24 HOURS OF RECOGNITION OF THE FAILURE. THE FILTER BAG AND TRAPPED

SEDIMENT SHALL BE DISPOSED OF OFF-SITE WHEN THE BAG IS 1/2 FULL AT A DUMP SITE

APPROVED BY THE ALLEGHENY COUNTY CONSERVATION DISTRICT.

VEGETATION

INSPECT ALL SEEDED AREAS WEEKLY AND AFTER EVERY RUNOFF EVENT. RESEED ALL

AREAS THAT VEGETATION HAS FAILED TO ESTABLISH. REPAIR ALL ERODED SLOPES, SEED

AND MULCH AS NECESSARY.

DISTURBED AREAS

AS SOON AS SLOPES, CHANNELS, DITCHES AND OTHER DISTURBED AREAS REACH FINAL

GRADE THEY MUST BE PERMANENTLY STABILIZED WITH A UNIFORM 70% PERENNIAL

VEGETATIVE COVER, STONE, OR PAVEMENT. TEMPORARY STABILIZATION SHALL BE

ESTABLISHED IN ANY AREAS WHERE CONSTRUCTION ACTIVITIES HAVE CEASED FOR FOUR

(4) DAYS OR MORE AND WHERE CONSTRUCTION ACTIVITIES WILL NOT RESUME WITHIN

FOUR (4) DAYS. A PERMANENT COVER SHALL BE INSTALLED IN ANY AREA WHERE

CONSTRUCTION IS TO BE HALTED FOR MORE THAN ONE YEAR. NO MORE THAN 15,000

SQUARE FEET OF DISTURBED AREA SHALL REACH FINAL GRADE BEFORE INITIATING

STABILIZATION OPERATIONS. ALL DISTURBED SLOPES 3:1 H:V OR GREATER SHALL BE

STABILIZED WITH SEED, MULCH, AND EROSION CONTROL BLANKET.

SEDIMENT DISPOSAL

ALL SEDIMENT TAKEN FROM THE EROSION CONTROL FACILITIES WILL BE SPREAD AND

DRIED FOR USE IN ONSITE GRADING OR DISPOSAL OFF SITE. UNSUITABLE MATERIAL SHALL

BE HAULED FROM THE SITE FOR PROPER DISPOSAL. AS CONSTRUCTION IS COMPLETED,

VEGETATION ESTABLISHED AND STABILIZATION MEASURES FINISHED, TEMPORARY

EROSION CONTROL FACILITIES WILL BE REMOVED.

PERMANENT CONTROL MEASURES WILL INCLUDE, BUT ARE NOT LIMITED TO: PERMANENT

SEEDING AND LANDSCAPING. THESE FACILITIES WILL BE IMPLEMENTED AND MAINTAINED

AS CONSTRUCTION IS COMPLETED. THE TOWNSHIP OF COLLIER WILL MAINTAIN THE

PERMANENT FACILITIES.

TOPSOIL APPLICATION

BEFORE THE SEEDING BEGINS, TOPSOIL SHOULD BE APPLIED AND ANY REQUIRED SOIL

AMENDMENTS WORKED INTO THE SOIL TO A DEPTH OF 4 TO 6 INCHES. IF COMPOST IS TO BE

ADDED TO THE TOPSOIL, IT SHOULD BE WORKED INTO THE SOIL WITH OTHER SOIL

AMENDMENTS UNLESS IT IS BEING APPLIED AS AN EROSION CONTROL BMP.

GRADED AREAS SHOULD BE SCARIFIED OR OTHERWISE LOOSENED TO A DEPTH OF 3 TO 5

INCHES TO PERMIT BONDING OF THE TOPSOIL TO THE SURFACE AREAS AND TO PROVIDE A

ROUGHENED SURFACE TO PREVENT TOPSOIL FROM SLIDING DOWN SLOPE.

TOPSOIL SHOULD BE UNIFORMLY DISTRIBUTED ACROSS THE DISTURBED AREA TO A DEPTH

OF 4 TO 8 INCHES MINIMUM -- 2 INCHES ON FILL OUTSLOPES. SPREADING SHOULD BE DONE

IN SUCH A MANNER THAT SODDING OR SEEDING CAN PROCEED WITH A MINIMUM OF

ADDITIONAL PREPARATION OR TILLAGE. IRREGULARITIES IN THE SURFACE RESULTING

FROM TOPSOIL PLACEMENT SHOULD BE CORRECTED IN ORDER TO PREVENT FORMATION OF

DEPRESSIONS UNLESS SUCH DEPRESSIONS ARE PART OF THE PCSM PLAN.

TOPSOIL SHOULD NOT BE PLACED WHILE THE TOPSOIL OR SUBSOIL IS IN A FROZEN OR

MUDDY CONDITION, WHEN THE SUBSOIL IS EXCESSIVELY WET, OR IN A CONDITION THAT

MAY OTHERWISE BE DETRIMENTAL TO PROPER GRADING AND SEEDBED PREPARATION.

COMPACTED SOILS SHOULD BE SCARIFIED 6 TO 12 INCHES ALONG CONTOUR WHEREVER

POSSIBLE PRIOR TO SEEDING.

SEEDING AND MULCHING MATERIALS

a) TEMPORARY VEGETATIVE COVER. FROM MARCH 15 TO JUNE 1, APPLY ANNUAL OATS

AT THE RATE OF 30.0 POUNDS PER ACRE (6 POUND PER 1,000 SQUARE YARDS) BY

BROADCASTING, DRILLING, OR HYDRAULIC APPLICATION. FROM AUGUST 1 TO

OCTOBER 15, APPLY ANNUAL CEREAL RYE AT THE RATE OF 30.0 POUNDS PER ACRE (6

POUND PER 1,000 SQUARE YARDS) BY BROADCASTING, DRILLING, OR HYDRAULIC

APPLICATION. ANY OTHER TIME, USE ANNUAL RYEGRASS PLUS A STRAW MULCH

ANCHORED TO PREVENT LOSS.

IN THE ABSENCE OF A SOIL TEST, LIME SHOULD BE APPLIED AT THE RATE OF 1 TON PER

ACRE, AND FERTILIZER SHOULD BE APPLIED AT THE RATE OF 50 POUNDS OF NITROGEN,

50 POUNDS OF P2O5 AND 10 POUNDS OF K2O PER ACRE (E.G. 500 POUNDS OF 10-10-10 PER

ACRE).

b) PERMANENT VEGETATIVE COVER. SMOOTH AND FIRM SEEDBED WITH CULTIPACKER

OR OTHER SIMILAR EQUIPMENT PRIOR TO SEEDING. APPLY ERNMX-178 AS SHOWN ON

THE DETAILS AT A RATE OF 20 LB PER ACRE WITH A COVER CROP AT 30 LB PER ACRE

(DRY SITES - GRAIN OATS, JANUARY 1 TO AUGUST 1; OR GRAIN RYE, AUGUST 1 TO

JANUARY 1; MOIST SITES - GRAIN RYE YEAR-ROUND).

SEED AND SOIL SUPPLEMENTS (EXCEPT LIME AND SEED MIX) SHALL CONFORM TO THE

REQUIREMENTS OF SECTION 804 OF THE PENNSYLVANIA DEPARTMENT OF

TRANSPORTATION FORM 408 (APPENDED). LIMING SHALL CONFORM TO THE

REQUIREMENTS LISTED ON PAGE 540 OF THE EROSION AND SEDIMENTATION

POLLUTION CONTROL PROGRAM MANUAL (APPENDED). ALL AREAS ARE TO BE

TEMPORARILY SEEDED WITH FORMULA E SEED MIX.

MULCH SHALL CONFORM TO THE REQUIREMENTS OF SECTION 805 OF THE

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION FORM 408.

IN THE ABSENCE OF A SOIL TEST, LIME SHOULD BE APPLIED AT THE RATE OF 6 TONS

PER ACRE, AND FERTILIZER SHOULD BE APPLIED AT THE RATE OF 100 POUNDS OF

NITROGEN, 200 POUNDS OF P2O5 AND 200 POUNDS OF K2O PER ACRE (E.G. 1,000 POUNDS

OF 10-20-20 PER ACRE).

102.4(B)(5)(XI) RECYCLING AND DISPOSAL OF MATERIALS

INDIVIDUALS RESPONSIBLE FOR EARTH DISTURBANCE ACTIVITIES MUST ENSURE THAT PROPER

MECHANISMS ARE IN PLACE TO CONTROL WASTE MATERIALS. CONSTRUCTION WASTES

INCLUDE, BUT ARE NOT LIMITED TO, EXCESS SOIL MATERIALS, BUILDING MATERIALS, EROSION

AND SEDIMENTATION CONTROL BMPS, CONCRETE WASH WATER, SANITARY WASTES, ETC.

THAT COULD ADVERSELY IMPACT WATER QUALITY. MEASURES SHOULD BE PLANNED AND

IMPLEMENTED FOR HOUSEKEEPING, MATERIALS MANAGEMENT, AND LITTER CONTROL.

WHEREVER POSSIBLE, RECYCLING OF EXCESS MATERIALS IS PREFERRED, RATHER THAN

DISPOSAL AT AN APPROVED PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION

WASTE SITE.

EXCAVATED EXCESS SOIL MATERIAL DISPOSED OF OFFSITE MUST BE DISPOSED OF AT A SITE

WITH AN APPROVED EROSION AND SEDIMENTATION CONTROL PLAN OR A PADEP APPROVED

SITE. IMPORTED FILL MATERIAL MUST BE OBTAINED FROM A SITE WITH AN APPROVED

EROSION AND SEDIMENTATION CONTROL PLAN OR A PADEP APPROVED BORROW SITE. THE

CONTRACTOR SHALL PROVIDE DOCUMENTATION OF THE STATUS OF ALL BORROW AND

DISPOSAL SITES PRIOR TO PROCEEDING WITH THE IMPORT OR EXPORT OF SOIL MATERIAL ON

SITE.

102.4(B)(5)(XII) IDENTIFICATION OF NATURALLY OCCURRING GEOLOGICAL FORMATIONS OR

SOIL CONDITIONS

NO KNOWN NATURALLY OCCURRING GEOLOGICAL FORMATIONS OR SOIL CONDITIONS WITH

THE POTENTIAL TO CAUSE POLLUTION ARE EVIDENT ONSITE.

102.4(B)(5)(XIII) IDENTIFICATION OF POTENTIAL THERMAL IMPACTS

ALL DISTURBED AREAS WILL BE RETURNED TO APPROXIMATE ORIGINAL CONTOURS AND

PRE-CONSTRUCTION COVER CONDITIONS, THEREFORE NO INCREASE IN THERMAL IMPACTS IS

EXPECTED.

102.4(B)(5)(XIV) EROSION CONTROL PLAN MUST BE CONSISTENT WITH THE POST CONSTRUCTION

STORMWATER MANAGEMENT PLAN

ALL DISTURBED AREAS WILL BE RETURNED TO APPROXIMATE ORIGINAL CONTOURS AND

PRE-CONSTRUCTION COVER CONDITIONS; THEREFORE, A POST CONSTRUCTION STORMWATER

MANAGEMENT PLAN IS NOT REQUIRED.

102.4(B)(5)(XV) IDENTIFICATION OF EXISTING AND PROPOSED RIPARIAN FOREST BUFFERS

NO EXISTING OR PROPOSED RIPARIAN FOREST BUFFERS ARE PRESENT ONSITE.

CONCLUSION

THE EROSION AND SEDIMENTATION CONTROL PLAN HAS BEEN DEVELOPED TO MINIMIZE THE

EXTENT AND DURATION OF EARTH DISTURBANCE; MAXIMIZE PROTECTION OF EXISTING

DRAINAGE FEATURES AND VEGETATION TO THE EXTENT PRACTICAL; MINIMIZE SOIL

COMPACTION TO EXTENT PRACTICAL AND IMPLEMENT BMPS TO PREVENT OR MINIMIZE THE

GENERATION OF INCREASED STORMWATER RUNOFF.

SOIL TYPE USE LIMITATIONS AND RESOLUTIONS

GSF GILPIN - 25 TO 80% SLOPES - SOIL HAS A MEDIUM TO HIGH RUNOFF. DEPTH TO

BEDROCK IS 1 ½ TO 3 ½ FEET. SEASONAL HIGH WATER TABLE IS GREATER THAN 6 FEET.

CONSERVATION PRACTICES ARE NEEDED TO HELP CONTROL EROSION. SLOPE,

MODERATE DEPTH TO BEDROCK, CAVING, CORROSION TO CONCRETE, DROUGHTY,

EROSION, HYDRIC INCLUSIONS, LANDSLIDES, SLOW PERCOLATION, PIPING, POOR

TOPSOIL AND FROST ACTION ARE LIMITATIONS WITH THIS SOIL. WATER

ENCOUNTERED IN THE TRENCH SHALL BE PUMPED FROM THE AREA BY USE OF A

FILTERBAG. THE PROPOSED SUBSURFACE CONCRETE WILL BE SEALED TO RESIST

CORROSION. TRENCHES ARE TO BE SHORED TO PREVENT CAVING. EROSION CONTROL

BMPS WILL BE UTILIZED TO CONTROL ERODED MATERIAL. A WETLAND DELINEATION

WAS PERFORMED FOR THIS SITE. TRENCHES WILL BE BACKFILLED WITH COMPACTED

STONE AND COMPACTED SUITABLE MATERIAL REMOVED FROM THE TRENCH. TRENCH

PLUGS SHALL BE INSTALLED PER THE DETAILS TO PREVENT PIPING OF WATER

THROUGH THE TRENCH. SOIL AMENDMENTS WILL BE USED WHERE NEEDED TO

SUPPORT THE GROWTH OF VEGETATION.

WEIKERT - 25 TO 80% SLOPES - SOIL HAS A HIGH RUNOFF. DEPTH TO BEDROCK IS 1 TO 1

½ FEET. SEASONAL HIGH WATER TABLE IS GREATER THAN 6 FEET. CONSERVATION

PRACTICES ARE NEEDED TO HELP CONTROL EROSION. SLOPE, MODERATE DEPTH TO

BEDROCK, CAVING, CORROSION TO CONCRETE AND STEEL, DROUGHTY, HYDRIC

INCLUSIONS, LANDSLIDES, SLOW PERCOLATION, PIPING, POOR TOPSOIL AND FROST

ACTION ARE LIMITATIONS WITH THIS SOIL. WATER ENCOUNTERED IN THE TRENCH

SHALL BE PUMPED FROM THE AREA BY USE OF A FILTERBAG. THE PROPOSED

SUBSURFACE CONCRETE AND STEEL WILL BE SEALED TO RESIST CORROSION.

TRENCHES ARE TO BE SHORED TO PREVENT CAVING. EROSION CONTROL BMPS WILL

BE UTILIZED TO CONTROL ERODED MATERIAL. A WETLAND DELINEATION WAS

PERFORMED FOR THIS SITE. TRENCHES WILL BE BACKFILLED WITH COMPACTED STONE

AND COMPACTED SUITABLE MATERIAL REMOVED FROM THE TRENCH. TRENCH PLUGS

SHALL BE INSTALLED PER THE DETAILS TO PREVENT PIPING OF WATER THROUGH THE

TRENCH. SOIL AMENDMENTS WILL BE USED WHERE NEEDED TO SUPPORT THE

GROWTH OF VEGETATION.

CULLEOKA - 20 TO 35% SLOPES - SOIL HAS A VERY LOW TO HIGH RUNOFF. DEPTH TO

BEDROCK IS 1 ½ TO 3 ½ FEET. SEASONAL HIGH WATER TABLE IS GREATER THAN 6 FEET.

CONSERVATION PRACTICES ARE NEEDED TO HELP CONTROL EROSION. SLOPE,

MODERATE DEPTH TO BEDROCK, CAVING, CORROSION TO CONCRETE, EROSION,

LANDSLIDES, SLOW PERCOLATION, PIPING, POOR TOPSOIL AND FROST ACTION ARE

LIMITATIONS WITH THIS SOIL. WATER ENCOUNTERED IN THE TRENCH SHALL BE

PUMPED FROM THE AREA BY USE OF A FILTERBAG. THE PROPOSED SUBSURFACE

CONCRETE WILL BE SEALED TO RESIST CORROSION. TRENCHES ARE TO BE SHORED TO

PREVENT CAVING. EROSION CONTROL BMPS WILL BE UTILIZED TO CONTROL ERODED

MATERIAL. A WETLAND DELINEATION WAS PERFORMED FOR THIS SITE. TRENCHES

WILL BE BACKFILLED WITH COMPACTED STONE AND COMPACTED SUITABLE

MATERIAL REMOVED FROM THE TRENCH. TRENCH PLUGS SHALL BE INSTALLED PER

THE DETAILS TO PREVENT PIPING OF WATER THROUGH THE TRENCH. SOIL

AMENDMENTS WILL BE USED WHERE NEEDED TO SUPPORT THE GROWTH OF

VEGETATION.

NE NEWARK SILT LOAM - SEASONAL HIGH WATER TABLE IS 0 TO 1 FEET. DEPTH TO

BEDROCK IS GREATER THAN 6 ½ FEET. CONSERVATION PRACTICES ARE NEEDED TO

HELP CONTROL EROSION. SLOPE, MODERATE DEPTH TO BEDROCK, CAVING,

CORROSION TO STEEL, EROSION, FLOODING, DEPTH TO SATURATED ZONE/SEASONAL

HIGH WATER TABLE, HYDRIC INCLUSIONS, LANDSLIDES, SLOW PERCOLATION, PIPING,

POOR TOPSOIL, FROST ACTION AND POTENTIAL FOR SINKHOLES ARE LIMITATIONS

WITH THIS SOIL. WATER ENCOUNTERED IN THE TRENCH SHALL BE PUMPED FROM THE

AREA BY USE OF A FILTERBAG. THE PROPOSED SUBSURFACE STEEL WILL BE SEALED

TO RESIST CORROSION. TRENCHES ARE TO BE SHORED TO PREVENT CAVING. EROSION

CONTROL BMPS WILL BE UTILIZED TO CONTROL ERODED MATERIAL. [A WETLAND

DELINEATION WAS PERFORMED FOR THIS SITE (OR) THE DISTURBED AREAS CONSIST OF

BITUMINOUS PARKING AREAS AND MAINTAINED/LANDSCAPED AREAS, THEREFORE

WETLANDS DO NOT EXIST.] TRENCHES WILL BE BACKFILLED WITH COMPACTED

STONE AND COMPACTED SUITABLE MATERIAL REMOVED FROM THE TRENCH. TRENCH

PLUGS SHALL BE INSTALLED PER THE DETAILS TO PREVENT PIPING OF WATER

THROUGH THE TRENCH. SOIL AMENDMENTS WILL BE USED WHERE NEEDED TO

SUPPORT THE GROWTH OF VEGETATION.

LSSE

Civil Engineers and Surveyors

Fike LSI LSSE Rabell Senate ES3 of ES3394-081-ES3

AS SHOWN

February, 2026

Erosion and Sedimentation Control Details4237 Thoms Run Demolition

Situate In Collier Township, Allegheny County, Pennsylvania

Collier Township 2418 Hilltop Road Presto, PA 15142

COMPOST FILTER SOCK

TYPICAL WOOD MAT CROSSING

FODS TRACKOUT CONTROL SYSTEM

PUMPED WATER FILTER BAG WITH COMPOST FILTER SOCK

Collier Township Collier Township Allegheny County