The document is a technical specification section (Section 01 1100) for the Abington Township American Rescue Plan Act (ARPA) Park Improvements project in Montgomery County, Pennsylvania. The project involves the resurfacing and construction of various park improvements, including an underdrain for an existing basketball court, construction of a raingarden and level spreader adjacent to a tennis court, and other related work. The specifications outline the general requirements, referenced standards, and quality assurance measures for the project, which involves multiple parks within the township.

The project is funded through the American Rescue Plan Act (ARPA) and will require compliance with various federal, state, and local regulations, including Pennsylvania Department of Labor & Industry, OSHA, ASTM, PennDOT, and DEP standards. The technical specifications cover details such as material requirements, workmanship standards, submittal procedures, and execution requirements. The contractor will be responsible for providing all necessary labor, equipment, and materials to complete the project, with specific attention to erosion control, accessibility requirements, and maintaining the existing landscape. The document emphasizes the need for high-quality materials, proper installation techniques, and adherence to all applicable codes and regulations.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 1100-1 (10/25) 25-1034_400 01 1100.docx

SECTION 01 1100

SUMMARY OF WORK

PART 1 - GENERAL

1.01 DESCRIPTION OF WORK

A. The work to be done under this Contract consists of all labor, equipment and materials and other facilities necessary and proper to complete the following: The project consists of the resurfacing and construction of an underdrain for an existing basketball court and the construction of a raingarden and level spreader adjacent to an existing tennis court.

B. The Drawings and Specifications are intended to cover a complete project, and it shall be thoroughly understood that failure to mention specifically any work which would naturally be required to complete the project shall not relieve CONTRACTOR of his responsibility to perform such work.

1.02 REFERENCED STANDARDS AND SPECIFICATIONS

A. All work shall comply with the current issues of the following codes, regulations, and requirements

(this list may not be inclusive; failure to mention any specific code, regulation or requirement does not relieve the CONTRACTOR from complying with such):

1. Pennsylvania Department of Labor & Industry, Regulations for Trenches, and Excavations.

2. Federal and State Air Pollution Regulations.

3. OSHA - Occupational Safety and Health Administration.

4. ASTM - American Society of Testing and Materials.

5. PennDOT - Pennsylvania Department of Transportation Publications 72, 213, 408 and TC-8600.

6. DEP - Pennsylvania Department of Environmental Protection - Erosion and Sedimentation

Control, and Sewerage Manual

7. AASHTO - American Association of State Highway and Transportation Officials.

8. Architectural Barriers Act of 1968

9. Rehabilitation Act of 1973 (Section 504)

10. PA Act 235 of 1965, as amended

11. Universal Accessibility Act

12. Americans with Disabilities Act of 1990, as amended

13. All codes and regulations of Abington Township

1.03 EQUAL OR APPROVED EQUAL

A. Unless otherwise specifically provided for in the Detail Specifications, all workmanship, equipment, materials, and other items incorporated in the Work shall be new and the best grade of the respective kinds for their purpose. Where equipment, materials, other items, or workmanship are referred to in the Detail Specifications as "Equal To" any particular standard, the Engineer in its sole discretion

01 1100-2 shall decide the question of equality. The Contractor shall furnish to the ENGINEER for approval the manufacturer's detailed specifications for all machinery, mechanical and other special equipment, which the Contractor contemplates installing, together with full information as to type, performance characteristics, and all other pertinent information as may be required, and shall likewise submit for approval as required full information concerning all other materials or articles which the Contractor proposes to incorporate in the Work. Machinery, mechanical and other equipment, materials, and/or any other items installed or used without such prior written approval shall be at the risk of subsequent rejections, in which case they shall be replaced by the Contractor at its sole cost and expense. Materials specified by reference to the number or symbol of a specific standard, such as an A.S.T.M. Specification, a Federal Specification or other similar standard, shall comply with requirements in the latest revision thereof, and any amendment or supplement thereto, in effect on the date of the Invitation for Bids, except as limited to type, class or grade, or modified in such reference. The standards referred to, except as modified in the Detail Specifications, shall have full force and effect as though set forth therein. The Owner may require the Contractor to dismiss from the Work such employee or employees as the Owner or the Engineer may deem incompetent, careless, or insubordinate.

B. If, subsequent to the award of the Contract, and in normally rare occurrences, it becomes necessary

(because of delays in delivery, strikes, discontinuance of the manufacture of items specified or the equal thereof, or any other similar reasons) for the CONTRACTOR to request the use of any item of equipment or product which is of a different type than the equipment or product specified, or the approved equal thereof, the ENGINEER at his discretion, may authorize the use of such different type equipment or product of the same, greater or less cost than that specified.

C. In such cases as described in Paragraphs B above, the CONTRACTOR shall submit to the

ENGINEER in writing (1) his request for permission to make a substitution, (2) a complete description of the proposed item, including dimensions, operational characteristics, changes (if any) that will be required to other related parts of the work, etc., and (3) full information as to the costs of the item specified, the cost of the different type item being proposed, as well as costs (additional or credits) or changes (if any) to any related parts of the work. Such information shall be in such form and detail as to permit the ENGINEER to check, to his satisfaction, the reason and costs involved. Upon acceptance of the substitution, in writing, the proper credits to be allowed the OWNER or the proper additional payments to be made to the CONTRACTOR represent the difference between the net cost to the CONTRACTOR of the substituted item or material, and the price at which he could have obtained the lowest priced item or materials specified.

D. The decision of the ENGINEER, from time to time, as to the proper credits to be allowed by the

OWNER or proper payments to be made by the CONTRACTOR, shall be final and conclusive upon the CONTRACTOR.

1.04 PRIORITY OF AND DISCREPANCIES IN CONTRACT DOCUMENTS

A. If the Bidder or CONTRACTOR finds an error in or a discrepancy between any of the Contract

Documents, such error or discrepancy shall be immediately reported to the ENGINEER for correction. If found during the bidding period, the correction will be issued by Addendum, and if during the Contract period, by field order or change order, as appropriate. No work shall proceed which is affected by the discrepancy prior to the ENGINEER's resolution of the problem.

01 1100-3

B. In general, the plans and specifications are complementary; what is called for by one is as binding as if required by all. All items necessary or incidental to completely construct or erect the work denoted shall be furnished as required to provide a complete operating facility whether specifically detailed by the plans and/or specifications or not.

C. Where dimensions or locations of existing facilities are of importance to the successful performance of any part of the work of this Contract, the CONTRACTOR shall verify the correctness of such dimension or location in the field before any other procedure, whether of manufacture of related equipment or construction of related structure, shall begin. Failure of the CONTRACTOR to follow the required verification procedure here specified shall cause him to waive all right to claim for additional cost by reason on the later discovery of inaccurate dimensions or locations of existing facilities as depicted in the Contract Documents.

D. Should discrepancy be found to exist between the various Contract Documents, the following order of priority shall be followed in resolving the intent of the effected documents. In decreasing order of importance, the documents are: the Specifications; Drawings; Supplementary Conditions.

Further, it shall be understood that, in all cases, calculated dimensions shall prevail over scaled dimensions, and larger scale drawings shall take precedence over small scale drawings.

1.05 PRECONSTRUCTION MEETING

A. A pre-construction meeting will be held after award of the contract but prior to CONTRACTOR's

Notice to Proceed. A tentative meeting is scheduled for January 13, 2026 at Abington Township, 1176 Old York Road, Abington, PA 19001.

B. CONTRACTOR will be notified of any changes to the date and time of this meeting and will be expected to attend with the designated Project Superintendent.

C. CONTRACTOR is required to submit a construction schedule showing the order in which the

CONTRACTOR proposes to carry on the work, the dates on which he will start several of the more salient features and the contemplated dates for completing the same. The schedule shall be in the form of a progress chart of suitable scale as to approximately indicate the percentage of work completed at any time.

1.06 PROGRESS MEETINGS

A. During the construction period, progress meetings shall be held with the ENGINEER at the job site to discuss recent developments and future work plans as they relate to the schedule specified hereinafter.

B. Progress meetings will be held monthly in general, but the interval between meetings may be increased or decreased by the ENGINEER to suit the then current circumstances.

C. The Construction Manager, CONTRACTOR and major Subcontractors shall be represented at every meeting by a responsible member of their respective organizations.

D. All decisions and interpretations given by the ENGINEER at project meetings, shall be on behalf of the OWNER and shall be conclusive on each CONTRACTOR or Subcontractor affected.

01 1100-4

E. The proceedings of these meetings will be recorded by the Construction Manager, and each required representative at meetings will be furnished one copy.

F. The ENGINEER's act of conducting meetings, recording, and distributing meeting minutes on behalf of the OWNER, shall not be construed as coordinating or scheduling CONTRACTOR's work.

G. If a change of meeting date/time is required due to causes beyond control of the OWNER or

ENGINEER, the ENGINEER will advise each concerned party in advance of such change.

PART 2 - PRODUCTS

2.01 MATERIALS AND EQUIPMENT

All materials and equipment supplied for use on this project shall be new and purchased specifically for incorporation into the work included in the Contract Documents.

2.02 PRODUCT DELIVERY, STORAGE AND HANDLING

A. Proper and suitable tools, equipment, and appliances for the safe and convenient handling and placing of all materials and equipment shall be used.

B. During loading, unloading, and placing, care shall be taken in handling the equipment and materials so that no equipment of materials are damaged.

C. Any precautions necessary to protect items of equipment and materials from damage while stored on the construction site shall be exercised.

D. The CONTRACTOR shall follow all written instructions and recommendations of the equipment manufacturer and all requirements of the ENGINEER regarding the oiling, exercising, maintenance and protection of the equipment during storage. It shall be the CONTRACTOR's complete responsibility to satisfactorily store and care for equipment and materials.

E. Equipment may be initially delivered to a warehouse, conveniently located in the vicinity of the site, with the approval of and under such conditions as may be further imposed by the ENGINEER.

2.03 SUPPLIERS/MANUFACTURERS

CONTRACTOR shall provide the names of the suppliers and manufacturers from whom major equipment items will be purchased. The suppliers and manufacturers shall not be altered from those listed without written approval of the ENGINEER. Only one supplier and manufacturer shall be shown for each equipment item. In the event that the ENGINEER determines that the equipment to be furnished is not equal to the equipment specified, the CONTRACTOR will absorb all costs incidental to changing the equipment to that which is determined to be equal. In no event will there be an adjustment of the bid amount. If the CONTRACTOR is required to change the equipment furnished from that listed on the Bid Form attachment.

01 1100-5

PART 3 - EXECUTION

3.01 INSPECTION

CONTRACTOR is required to carefully examine the site of the work, Drawings, Specifications, applicable State, County and local codes, and other Contract Documents for the work contemplated, and it will be assumed that he has familiarized and satisfied himself as to the conditions and obstacles to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of these Specifications, Drawings and other Contract Documents. He must also be prepared to execute a finished job in every particular, without any extra charge whatever, except as may be specifically provided for elsewhere in these Contract Documents.

3.02 CONDUCT OF WORK

A. All work shall be subject to the control of the ENGINEER and the OWNER. In the performance of the work, the CONTRACTOR shall abide by all orders, directions and requirements of the ENGINEER and the OWNER and shall perform all work in such manner and sequence as the OWNER may require. The ENGINEER and OWNER shall determine the amount, quality, acceptability, and fitness of all parts of the work; shall interpret the Plans, Specifications and Contract Documents; shall issue any extra work orders; and shall decide all other questions in connection with the work. The CONTRACTOR shall employ no plant, equipment, materials, or methods to which the ENGINEER or OWNER objects and shall remove no plant, materials, equipment, or other facilities from the site of the work without the ENGINEER's or OWNER's permission. Upon request, the ENGINEER or OWNER shall confirm in writing, any oral order, direction, requirement or determination. If any person employed on the work by the CONTRACTOR shall appear to the ENGINEER or OWNER to be incompetent or to act in a disorderly or improper manner, such person shall be removed immediately upon request by the

ENGINEER.

B. CONTRACTOR agrees to use, at all times, on the work, only such labor as will in no way disturb or affect labor employed by the OWNER and/or other CONTRACTORs on the project. The CONTRACTOR and each and every subcontractor performing work at the site of the project shall comply with all "Labor Laws" of the Government, and of the State, County, Township, and Municipality in which the project is located.

3.03 SUBSURFACE INFORMATION

OWNER has not obtained any data concerning subsurface materials or conditions. Bidders shall, therefore, make their own investigation of existing subsurface conditions and if they do not do so, the OWNER will not be responsible in any way for the consequences.

3.04 EXISTING UTILITIES - ACT 172 (187 As Amended)

CONTRACTOR shall check the location of existing utilities, either overhead or underground, and take all necessary precautions to prevent injury or damage the performance of the contract and shall be responsible for any and all damage thereto. CONTRACTOR's attention is directed to the provisions of Act 172 enacted by the General Assembly of the Commonwealth of Pennsylvania.

01 1100-6

3.05 AS-CONSTRUCTED DRAWINGS

No As-Constructed Drawings need be provided for this Contract.

3.06 CLEANING UP

A. Continuously keep the work, the site, and adjacent properties free from accumulations of waste materials, excess excavation, rubbish, and windblown debris resulting from construction operations.

Periodically remove waste materials, excess excavation, debris, and rubbish from the site and dispose of at legal disposal areas away from the project site.

B. Remove grease, mastics, adhesives, dust, dirt, stains, finger prints, labels, and other foreign materials from site-exposed interior and exterior surfaces of structures. Broom clean exterior paved surfaces;

rake clean other surfaces of the grounds. Restore areas disturbed by construction. Provide continuous dust control during construction.

C. At the completion of the work, or each major portion thereof, CONTRACTOR shall remove surplus materials, tools, construction equipment, and machinery, and leave the site clean and ready for occupancy by the OWNER.

END OF SECTION

01 2300-1 (9/25) 25-1034_400 01 2300.docx

SECTION 01 2300

ALTERNATES

1.01 SUMMARY

A. Section Includes:

1. Submission Procedures

2. Documentation of changes to Contract Sum/Price and Contract Time

1.02 RELATED SECTIONS

A. Agreement Form: Incorporating monetary value of accepted Alternates.

B. Bid Form: Requirements for Alternates.

1.03 REQUIREMENTS

A. Submit alternates with full description of the proposed Alternate and the effect on adjacent or related components.

B. Alternate quotes on Bid Forms will be reviewed and accepted or rejected at OWNER’s option.

Accepted Alternates will be identified in the OWNER-CONTRACTOR Agreement.

C. Coordinate related work and modify surrounding work to integrate the Work of each Alternate.

1.04 SELECTION AND AWARD OF ALTERNATES

A. Indicate variation of Bid Price for Alternates described below and list in Bid Form Document or any supplement to it, which requests a “difference” in Bid Price by adding to or deducting from the base bid price.

B. Bid may be evaluated on base bid price.

1.05 ALTERNATE #1 – EXISTING SPORT FIELD EQUIPMENT DEMOLITION &

REMOVAL PER PARK

A. Demolition, removal from site, and disposal of existing sport field equipment including player benches, fencing, backstops, and bleachers on a per park basis.

01 2300-2

B. Alternate Bid Item

1. Provide demolition, removal from site, and disposal of existing sport field equipment on a per park basis. Backstop dimensions have been provided on sheet C-501 for reference and shall be verified by the contractor. All concrete bases shall be entirely removed and shall be considered incidental to this line item. Additional fill shall be provided to bring excavation to grade and shall be considered incidental to this line item. The total number of parks has been tabulated under the Alternate #1 category on the bid form.

1.06 ALTERNATE #2 – EQUIPMENT STORAGE BOX INSTALLATION

A. Demolition, removal from site, and disposal of existing equipment storage boxes. Furnish and install new equipment storage boxes at park locations indicated on applicable plan sheets.

B. Alternate Bid Item

1. Provide demolition, removal from site and disposal of existing equipment storage boxes on a per field basis. Furnish and install new equipment storage boxes at park locations indicated on applicable plan sheets. The total number of equipment boxes to be removed and replaced has been tabulated under the Alternate #2 category on the bid form.

1.07 ALTERNATE #3 – FOUL POLE INSTALLATION PER EACH FIELD

A. Furnish and install foul pole bases and foul poles pairs on a per field basis in accordance with application specification sections.

1. Complete any required excavation to install the foul pole bases and foul poles on a per field basis. The total number of foul pole pairs has been tabulated under the Alternate #3 category on the bid form.

1.08 ALTERNATE #4 – BASEBALL BASE SET (1ST, 2ND, 3RD, AND HOME PLATE)

INSTALLATION, INFIELD MIX TOP DRESSING & BASEBALL FIELD STRIPING

APPLICATION PER FIELD

A. Furnish and install a complete baseball base set including first, second, third, and home plate

Infield mix top dressing shall consist of the application of infield mix to all existing fields.

Baseball field striping shall consist of the application of white lines in accordance with the plans.

1. Furnish and install a complete baseball base set including first, second, third, and home plate. Infield mix top dressing will consist of the application of a one-half inch section of infield mix to all existing fields, any removal of existing infield mix shall be considered incidental. Baseball field striping shall consist of the application of four (4) inch white lines in accordance with the plans. The total quantity of fields has been tabulated under the Alternate #4 category on the bid form.

01 2300-3

1.09 ALTERNATE #5 – HALLOWELL FIELD #2 - BASEBALL FIELD RELOCATION &

EXISTING FIELD RESTORATION

A. Construct a baseball field in the location specified on the sheet C-123A and in accordance with the details on sheet C-503. The existing field on sheet C-121 shall be restored to lawn.

Improvements for Hallowell Field #2 on sheet C-123A shall supersede those on sheet C-123 should this alternate be selected.

1. Complete any required excavation to install four (4) inches of infield mix. Contractor shall furnish and install backstop, bleachers, player benches, baseball base sets, four (4) and inch white foul lines. The existing field shall be restored to lawn in accordance with the sod specification of this contract. Proposed backstops, bleachers, and player benches associated with the field relocation are included under the base items and not part of this alternate.

1.10 ALTERNATE #6 – HALLOWELL FIELD #3 - BASEBALL FIELD RELOCATION &

EXISTING FIELD RESTORATION

A. Construct a baseball field in the location specified on the sheet C-123A and in accordance with the details on sheet C-503. The existing field on sheet C-121 shall be restored to lawn.

Improvements for Hallowell Field #3 on sheet C-123A shall supersede those on sheet C-123 should this alternate be selected.

1. Complete any required excavation to install four (4) inches of infield mix. Contractor shall furnish and install backstop, bleachers, player benches, baseball base sets, four (4) and inch white foul lines. The existing field shall be restored to lawn in accordance with the sod specification of this contract. Proposed backstops, bleachers, and player benches associated with the field relocation are included under the base items and not part of this alternate.

1.11 ALTERNATE #7 – ROSLYN PARK FIELD #1 & FIELD #3 - INFIELD MIX

RESTORATION

A. Furnish and install infield mix per applicable specification sections for the identified fields on the plans within Roslyn Park.

1. Furnish and install a four (4) inch section of infield mix per applicable specification sections for the identified fields on the plans within Roslyn Park. Removal and disposal of a four (4) inch section of infield mix from existing fields shall be considered incidental.

The quantity of infield mix has been tabulated under Alternate #7 category on the bid form.

01 2300-4

1.12 ALTERNATE #8 – PENBRYN PARK FIELD #1 & FIELD #3 - INFIELD MIX

RESTORATION

A. Furnish and install infield mix per applicable specification sections for the identified fields on the plans within Penbryn Park.

1. Furnish and install a four (4) inch section of infield mix per applicable specification sections for the identified fields on the plans within Penbryn Park. Removal and disposal of a four (4) inch section of infield mix from existing fields shall be considered incidental.

The quantity of infield mix has been tabulated under Alternate #8 category on the bid form.

This part not used.

01 2900-1 (10/25) 25-1034_400 01 2900.docx

SECTION 01 2900

CONTRACT CONSIDERATIONS

PART 1 – GENERAL

A. Section Includes:

1. Schedule of Values

2. Application for Payment

B. Related Sections:

1. Section 01 3300 - Submittal Procedures

1.02 SCHEDULE OF VALUES

A. Submit typed schedule on forms EJCDC 1910-8-E or AIA G703. CONTRACTOR’s standard form or electronic media printout will be considered.

B. Format: Utilize the bid form. Identify each line item with number and title indicated on the bid form.

C. Revise schedule to list approved Change Orders, with each Application for Payment.

1.03 APPLICATIONS FOR PAYMENT

The procedure for submittal, review, and payment of monthly applications for progress payments shall be established at the preconstruction conference. Submit one (1) executed original and four

(4) copies of each application for payment to the ENGINEER in a format similar to AIA Document G702 and Continuation Sheets G703. Complete every entry on the form, including notarization and execution by person authorized to sign legal documents on behalf of the CONTRACTOR. Incomplete applications will be returned without action. Entries shall match data on the Schedule of Values and Construction Schedule. Use updated schedules if revisions have been made. Include amounts of Change Orders issued prior to the last day of the construction period covered by the application.

PART 2 – PRODUCTS

PART 3 – EXECUTION

01 2900-2 (10/25) 25-1034_400 01 2900.docx

APPLICATION FOR PAYMENT NO.

To: Abington Township (OWNER) From: (CONTRACTOR) Contract: American Rescue Plan Act (ARPA) Park Improvements OWNER’s Contract No. ENGINEER’s Project No. 25-1034.00 For Work accomplished through the date of: .

1. Original Contract Price: $

2. Net change by Change Orders and Written Amendments (+ or -): $

3. Current Contract Price (1 plus 2): $

4. Total completed and stored to date: $

5. Retainage (per Agreement):

% of Completed Work: $

% of Stored Material: $

Total Retainage: $

6. Total Completed and stored to date less retainage (4 minus 5) $

7. Less previous Application for Payments: $

8. DUE THIS APPLICATION (6 MINUS 7): $

Accompanying Documentation:

CONTRACTOR’s Certification:

The undersigned CONTRACTOR certifies that (1) all previous progress payments received from OWNER on account of Work done under the Contract referred to above have been applied on account to discharge CONTRACTOR’s legitimate obligations incurred in connection with Work covered by prior Applications for Payment numbered 1 through inclusive; (2) title of all Work, materials and equipment incorporated in said Work or otherwise listed in or covered by this Application for Payment will pass to OWNER at time of payment free and clear of all Liens, security interests and encumbrances (except such as are covered by a Bond acceptable to OWNER indemnifying OWNER against any such lien, security interest or encumbrance); and (3) all Work covered by this Application for Payment is in accordance with the Contract Documents and not defective.

Date

CONTRACTOR

By:

State of County of Subscribed and sworn to before me this ______ Day of

Notary Public My Commission expires:

Payment of the above AMOUNT DUE THIS APPLICATION is recommended.

Dated CARROLL ENGINEERING CORPORATION

ENGINEER

By:

EJCDC No. 1910-8-E (1996 Edition) Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America and the Construction Specification Institute.

01 2973-1 (10/25) 25-1034_400 01 2973.docx

SECTION 01 2973

MEASUREMENT AND PAYMENT

1.01 DESCRIPTION

This Section includes the description of the various pay items found in the Bid Form and the method of measurement for payment of each pay item.

1.02 QUALITY ASSURANCE

A. Work completed under the Contract shall be measured by the ENGINEER according to the standards of weights and measures recognized by the U.S. Bureau of Standards.

B. The method of measurement and computations to be used in determination of quantities of material furnished and of work performed under the Contract will be those methods generally recognized as conforming to good engineering practice.

C. Measurement for area computations will be made on the surface. Pay measurements for area computations will not exceed the neat dimensions indicated on the Drawings, unless otherwise ordered in writing by the ENGINEER.

D. Structures will be measured according to neat lines indicated on the Drawings or as altered to fit field conditions. No payment will be made for length, width, or depth, in excess of that indicated on the Drawings or specified for any construction, unless otherwise approved by the ENGINEER in writing.

E. Items that are measured by the linear foot, such as pipe and concrete curb will be measured parallel to the base or foundation upon which such items are placed and from outside edge/surface to outside edge/surface of the same.

F. In computing volumes of excavation, the average end area method, based on horizontal measurements, or other acceptable methods, will be used.

G. The term "each", when used as an item of payment, will mean complete payment for the work described in the Contract Documents.

H. The term "lump sum", when used as an item of payment, will mean complete payment for the work described in the Contract Documents, including all incidentals of which includes necessary fittings, accessories, and restoration.

I. The term "incidental" when used will mean items, equipment, materials, labor, etc., incidental, and necessary to obtain a final product satisfactory to the ENGINEER. No additional payment will be made for incidentals.

01 2973-2 (10/25) 25-1034_400 01 2973.docx

PART 3 – EXECUTION

3.01 WORK TO BE COMPLETED WITH EACH CONTRACT ITEM

Bonds, Insurance, and Mobilization - Lump Sum (LS) - Includes cost for required bonds, insurance, mobilization, or any other miscellaneous costs incidental to the completion of the project as a whole but not expressly required for completion of Contract Bid Form item(s). Cost for this item should not be included in any other Contract Bid Form Item and it shall be assumed unit price(s) bid do not include such costs. No extra payment will be permitted with this item.

01 3100-1 (10/25) 25-1034_400 01 3100.docx

SECTION 01 3100

PROJECT MANAGEMENT AND COORDINATION

1.01 PROJECT COORDINATION

A. CONTRACTOR is responsible for coordinating CONTRACTOR’s work and the work of any subcontractors in order to produce the finished product as intended by the Contract Documents.

Claims for extra work resulting from failure to properly coordinate the work of all trades will not be honored.

B. CONTRACTOR shall coordinate scheduling, submittals, and work of the various sections of

Specifications to assure efficient and orderly sequence of installation of construction elements, with provisions for accommodating items to be installed later.

1.02 COORDINATION MEETINGS

CONTRACTOR shall schedule and hold coordination meetings and preinstallation conferences with OWNER, ENGINEER, and any subcontractors to assure coordination of the work.

1.03 COORDINATION OF SUBMITTALS

A. Schedule and coordinate submittals as specified in Section 01 3300.

B. Coordinate requests for substitutions to assure compatibility of space, of operating elements, and effect on work of other sections.

1.04 COORDINATION WITH OWNER

A. Notify OWNER five (5) days in advance of beginning work in a work area.

B. CONTRACTOR shall provide OWNER with a schedule indicating anticipated dates of disruption to sanitary sewer service with corresponding address. CONTRACTOR shall submit a weekly update of this schedule.

C. Operate existing equipment and valves only with permission of OWNER and in presence of

OWNER's designated representative.

D. Cooperate with OWNER to keep existing facilities in service during construction.

1.05 COORDINATION OF PROJECT CLOSEOUT

A. Coordinate completion and cleanup of portions of work designated for partial usage by the OWNER in preparation for Substantial Completion.

01 3100-2 (10/25) 25-1034_400 01 3100.docx

B. After OWNER's occupation of premises, coordinate access to site for correction of defective work and work not in accordance with Contract Documents, to minimize disruption of OWNER's activities.

C. Assemble and coordinate closeout submittals specified in Section 01 7700.

1.06 COORDINATION OF UTILITIES AND OTHER OWNERS

A. Prior to beginning construction, inform all public service companies, individuals, and others owning or controlling any facilities or structures within the project, which may be affected by the work, that it will commence on a certain date.

B. Where the proposed facilities cross telephone, telegraph or electric cables, gas, oil or water lines, sewers, or other facilities and structures on, under or over the proposed facilities, it shall be the responsibility of CONTRACTOR to give the owner of the facility due notice of the proposed crossing to permit the owner of the affected facility time to send a field representative to the site to mark, guard, or protect the facility if the owner of the affected facility so desires. CONTRACTOR shall cooperate with facility owners by arranging and performing work in and around such facilities, without additional compensation, to facilitate their relocation, preservation or reconstruction, as may be required. In addition, CONTRACTOR shall obtain names of persons to contact if damage should occur during construction operations. The ENGINEER will cooperate in working out construction problems involved with existing utilities and other facilities, but without relieving CONTRACTOR of CONTRACTOR’s responsibility.

C. CONTRACTOR's attention is directed to the Provisions of Pennsylvania General Assembly Act

No. 287 as they apply to the work under this Contract.

01 3119-1 (10/25) 25-1034_400 01 3119.docx

SECTION 01 3119

PROJECT MEETINGS

1.01 PRECONSTRUCTION CONFERENCE

A. A preconstruction conference will be held prior to the start of work in accordance with the General

Conditions.

B. The CONTRACTOR will be notified as to the location, date and time of this conference and will be expected to attend with the designated Project Superintendent.

C. A proposed construction schedule shall be prepared by the CONTRACTOR and shall be submitted to the ENGINEER at or before the preconstruction conference.

1.02 PROGRESS MEETINGS

A. During the construction period, progress meetings shall be held with the ENGINEER at the job site to discuss recent developments and future work plans as they relate to the schedule.

B. Progress meetings will be held bi-weekly, in general, but the interval between meetings may be increased or decreased by the ENGINEER to suit the then current circumstances.

C. CONTRACTOR and major subcontractors shall be represented at every meeting by a responsible member of their respective organizations.

D. All decisions and interpretations given by the ENGINEER at project meetings shall be on behalf of the OWNER and shall be conclusive on each CONTRACTOR or subcontractor affected.

E. The proceedings of these meetings will be recorded by the ENGINEER and each required representative at meetings will be furnished one copy.

F. The ENGINEER's act of conducting meetings and recording and distributing meeting minutes on behalf of the OWNER, shall not be construed as coordinating or scheduling CONTRACTOR's work.

G. If a change of meeting date/time is required due to causes beyond control of the OWNER or

ENGINEER, the ENGINEER will advise each concerned party in advance of such change.

PART 2 - PRODUCTS

This part not used.

PART 3 - EXECUTION

01 3233-1 (10/25) 25-1034_400 01 3233.docx

SECTION 01 3233

AUDIO-VIDEO DOCUMENTATION

CONTRACTOR shall engage the services of a professional electrographer actively engaged in color audio-DVD or CD recordings for various municipalities and construction projects similar to the work included under this Contract.

A. OWNER may make such investigation as OWNER deems necessary to determine the ability of the electrographer to perform the work, and the CONTRACTOR shall furnish to the OWNER all such information and data for this purpose as the OWNER may request. OWNER reserves the right to reject any electrographer if the investigation of such electrographer fails to satisfy the OWNER that such electrographer is properly qualified to carry out the work specified herein. Upon rejection of an electrographer, the CONTRACTOR shall engage the services of another electrographer, which shall undergo the review and approval process specified hereinbefore.

B. No construction shall begin prior to the review and approval of the DVD’s or CD’s covering the construction area. Any recorded coverage not acceptable to the ENGINEER shall be refilmed at no additional charge. All DVD’s or CD’s and written records shall become the property of the

OWNER.

1.03 SUBMITTALS

Two (2) complete copies of project coverage CD’s or DVD’s shall be submitted to the ENGINEER for approval.

1.04 JOB CONDITIONS

All recording shall be done during times of good visibility. No recording shall be done during periods of visible precipitation or when more than 10% of the ground area is covered with snow, unless otherwise authorized by the ENGINEER.

2.01 EQUIPMENT

A. Mobile Unit:

When conventional wheeled vehicles are used, the distance from the camera lens to the ground shall not be less than 12 feet to insure proper perspective.

01 3233-2

In some instances, recorded coverage will be required in areas not accessible by conventional wheeled vehicles. Such coverage shall be obtained by walking or special conveyance approved by the ENGINEER.

B. Audio-Video Recording Medium:

The CONTRACTOR shall furnish professional grade DVD or CD recording equipment and provide a sufficient quantity of DVDs or CDs to record the work. DVDs or CDs shall become the property of the OWNER at the completion of the project.

C. Camera:

Video output from camera(s) used must be capable of producing NTSC-525 lines/60 field/s.

Resolution in the Y channel, minimum 500 TV lines at center, utilizing a bias lit beam split prism, in combination with a Professional and/or Industrial charge-coupled device (CCD) camera, for optimum color imagery and minimum lag through 3.1 meter (10 foot) candles, with Geometric Distortion not to exceed 1.5% of Picture Height at any point in picture area.

D. Lighting:

The CONTRACTOR shall provide, if required, all lighting and power therefore, to fill in all shadow areas caused by trees, signs, and other objects.

2.02 RECORDED INFORMATION

A. Audio:

Each DVD or CD shall begin with the current date, project name and municipality and be followed by the general location, i.e., name of the street or location of "cross-country" line, viewing side and direction of progress.

B. Video:

Periodic transparent alpha numeric information consisting of the name of the project, name of the area covered, direction of travel, viewing side, etc., shall appear on the screen. To preclude the possibility of tampering or editing in any manner, all video recordings shall, by electronic means, display continuously and simultaneously generated transparent digital information to include the date and time of recording. The date information shall contain the month, day, and year (for example 10/5/04) and shall be placed directly below the time information. The time information shall consist of hours, minutes, and seconds, separated by colons (for example 10:35:18). This transparent information shall appear on the extreme upper left-hand third of the screen or as approved by the OWNER’s Representative.

01 3233-3

C. Audio-Video Tracks:

The DVD or CD shall consist of both visual and audio information, recorded simultaneously.

Tracks shall consist of original live recordings and thus shall not be copies of other audio or video recordings. Audio track shall contain the narrative commentary of the electrographer, recorded simultaneously with his fixed elevation visual record of the zone of influence of construction.

Provide a microphone and mixing equipment for the narrative commentary and evaluations of the ground level remote technician whose function shall be to provide a complete circumspection of any features not adequately visible to the electrographer and to describe in detail the extent of any damage encountered. The ENGINEER shall have the option of recording comments on the audio track.

3.01 DVD or CD COVERAGE

A. The entire project site shall be recorded. Zone of influence shall extend to 50 feet from each side of the proposed pipeline.

B. Recorded coverage shall include all surface features located within the above mentioned area supported by appropriate audio description. Audio description shall be made simultaneously with video coverage. Such coverage shall include, but not be limited to, all existing driveways, road surface, sidewalks, curbs, ditches, roadways, landscaping, trees, culverts, headwalls, and retaining walls or buildings located within the above described area.

C. Houses and buildings shall be identified visually by house number, when visible, in such a manner that structures of the proposed system, i.e., manholes, can be located by reference.

D. The rate of speed in the general direction of travel of the conveyance used during recording shall not exceed 48 feet per minute. Panning rates and zoom-in, zoom-out rates shall be controlled sufficiently such that during playback will produce clarity of the object viewed.

3.02 IDENTIFICATION

A. All DVD’s or CD’s (on the disk and on storage case) shall be properly identified by number, location and project name and municipality in a manner acceptable to the ENGINEER.

B. A record of the contents of each DVD or CD shall be supplied by a sheet identifying each segment in the disk by location, i.e., roll number, street or road viewing, tape counter number, viewing side, point starting from, traveling direction, and ending destination point.

01 3300-1 (10/25) 25-1034_400 01 3300.docx

SECTION 01 3300

SUBMITTAL PROCEDURES

1.01 CONSTRUCTION SCHEDULE

Within fifteen (15) calendar days after the Contract commences, submit a construction schedule.

A. Construction Schedule shall be horizontal bar-chart type with a separation time bar for each significant construction activity. No activity on the schedule shall have a duration longer than fifteen

(15) calendar days, with the exception of fabrication, procurement, and punch list activities. Activity duration shall be the total number of actual days required to perform that activity including consideration of weather impact on completion of that activity. Note: The Township reserves the right to designate the sequence in which the park improvements are to be commenced, in accordance with its internal priority list and the needs of organizations utilizing the fields.

The Contractor shall adjust the project schedule as directed by the Township to reflect these priorities.

B. Prepare the schedule on a sheet, or series of sheets, of reproducible media and sufficient width to show data for the entire construction period. Provide a continuous vertical line to identify the first working day of each week. Within each time bar, indicate estimated completion percentage in 10 percent increments. As work progresses, place a contrasting mark in each bar to indicate actual completion.

C. Secure time commitments for performing critical elements of the work from all parties involved.

Coordinate each element on the schedule with other construction activities. Show each activity in proper sequence. Graphically indicate the sequences necessary for completion of related portions of the work.

D. Coordinate the Construction Schedule with the Schedule of Values, list of subcontractors, list of suppliers, and anticipated submittal schedule for shop drawings, product data, and samples.

E. Indicate completion in advance of the date established for Substantial Completion. Indicate

Substantial Completion on the schedule to allow time for the ENGINEER's procedures necessary to issue a Certificate of Substantial Completion.

F. Following favorable response to the submittal by the ENGINEER, print and distribute copies to each subcontractor and other parties required to comply with scheduled dates. Post copies in the temporary field office(s). When revisions are made, distribute to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the work and are no longer involved in construction activities.

G. In general, update the schedule every month. All Change Orders to the Contracts or other activity, where revisions have been recognized or made, must be incorporated into the schedule.

01 3300-2

1.02 APPLICATIONS FOR PAYMENT

The procedure for submittal, review, and payment of monthly applications for progress payments shall be established at the preconstruction conference. Submit one (1) executed original and four

(4) copies of each application for payment to the ENGINEER on form EJCDC 1910-8E with attachments referenced to the original Schedule of Values, which identified quantity of work completed, quantity of material stored, and the total amount completed and stored for each individual pay item. Complete every entry on the form, including notarization and execution by person authorized to sign legal documents on behalf of the CONTRACTOR. Incomplete applications will be returned without action. Entries shall match data on the Schedule of Values and Construction Schedule. Use updated schedules if revisions have been made. Include amounts of Change Orders issued prior to the last day of the construction period covered by the application.

1.03 SHOP DRAWINGS, PRODUCT DATA, SAMPLES AND CERTIFICATIONS

A. Fabricated materials or equipment to be incorporated in the work shall be subject to review by the

ENGINEER. CONTRACTOR shall obtain and check prints of manufacturers certified shop drawings and other pertinent data. When the CONTRACTOR has reviewed the shop drawings and is satisfied they are correct, they shall number each submittal (shop drawing, certificate, and manual) and submit them to the ENGINEER for review. Submittal numbering system shall be the section number referenced by these Specifications followed by the submittal number (i.e., 32 1200-1, 33 1216-1 and 33 1216-2).

B. Shop drawings are intended to mean fabrication and installation drawings. These drawings and pertinent data shall be complete and in such detail as the ENGINEER may require for providing information regarding the design, installation, testing, and operation for products and/or equipment.

C. All costs necessary for compliance with the requirements of this section of the Specifications shall be included in the bid. ENGINEER shall review individual submittals a total of two times.

CONTRACTOR shall be responsible for OWNER’s and ENGINEER’s costs for the third and all subsequent review of any submittal.

D. Detailed shop drawings, data, and literature for fabricated materials or equipment to be incorporated in the work shall be submitted to the ENGINEER for review at least two weeks before fabrication.

CONTRACTOR shall obtain and check manufacturer's shop drawings, certified prints, and other pertinent data for conformance with all requirements of the Drawings and Specifications in ample time to permit satisfactory progress of the work.

E. After completion of such checking and verification by the CONTRACTOR, the CONTRACTOR shall include a full completed copy of Attachment 1 as a cover sheet for the shop drawing. In addition, the submittal number shall be written or typed in the lower right-hand corner of all copies of each shop drawing. The submittal numbering system should be the specification section number followed by the submittal number (i.e., 33 3113-1 Ductile Iron Pipe, 33 3113-2 PVC Pipe). Failure to include a cover sheet or not numbering submittals shall be grounds for rejection of the submittal by the ENGINEER. (See Attachment 1 at the end of this section).

01 3300-3

F. All data, drawings, and correspondence from subcontractors, material men, or suppliers shall be routed through the CONTRACTOR. This procedure is required so that the CONTRACTOR's superintendent can familiarize himself with all information which the CONTRACTOR sends to the ENGINEER and also to prevent the ENGINEER from taking action upon something other than that which is desired by the CONTRACTOR. The ENGINEER shall consider for review only such data and details as are verified and transmitted to him directly by the CONTRACTOR.

G. All correspondence between the ENGINEER and the CONTRACTOR, all shop drawings, and all data for review of drawings or materials will be handled by the ENGINEER. All such data shall be delivered directly to him at the ENGINEER's office. The replies pertaining to these matters will be delivered to the CONTRACTOR or the CONTRACTOR's representative at the job site.

H. A sufficient number of shop drawings and review data shall be submitted to the ENGINEER, who will retain four (4) copies of each submittal. All additional copies, up to a maximum of four (4), received by ENGINEER will be returned to the CONTRACTOR or CONTRACTOR’s representative at the job site. The ENGINEER's notations of the action which the ENGINEER has taken will be noted on all the returned copies. Sufficient time for the review of all shop drawing submittals shall be allowed in the CONTRACTOR's schedule. A minimum of two weeks shall be allotted for each shop drawing review.

Electronic submissions may also be acceptable at the discretion of the ENGINEER and must conform to the following requirements:

1. Submit shop drawings in PDF format via email to the designated Carroll Engineering staff member.

2. Electronic submissions are limited to no more than 15 pages including Attachment 1.

Submissions of greater than 15 pages must be mailed with the required number of copies (4 minimum).

3. Shop drawings “Approved” or “Furnish as Corrected,” will be emailed to the

CONTRACTOR and OWNER.

4. Shop drawings “Revise and Resubmit” or “Submit Specific Item” will be emailed to the

CONTRACTOR for revisions.

I. Drawings of minor or incidental fabricated materials and/or equipment may not be required by the

ENGINEER. The CONTRACTOR shall furnish the ENGINEER with tabulated lists of such fabrications, showing the names of the manufacturers and catalog numbers, together with samples of general data as may be required to permit intelligent determination as to their acceptability for incorporation in the work.

J. Upon successful review by the ENGINEER of the shop drawings, data sheets, samples, other data, the fabrications furnished shall be in conformity with the same. The acceptance of the shop drawings, data sheets, samples, or other data shall in no way release the CONTRACTOR from CONTRACTOR’s responsibility for the proper fulfillment, by any fabrication, of the requirements of the Agreement.

01 3300-4

K. All reviews of shop drawings, data sheets or literature are subject to the products fulfilling the specific requirements of the Drawings and Specifications. Review of items that do not conform in detail to the specified product shall place upon the CONTRACTOR the responsibility for successful operation of the proposed product. Should the item subsequently prove to be defective or otherwise unsatisfactory for the service for which it was intended, the CONTRACTOR shall, without cost to the OWNER and without obligation on the part of the ENGINEER, replace the item with the material originally specified.