SF-30 - Amendment 1 - SOW - Change of requirements 1.pdf
PDF 838 KB Posted
- Solicitation number
- 19P05026Q0006
- Issued by
-
Department of State US Embassy Lisbon
About this file
This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by the American Embassy Lisbon on June 2, 2026, for RFQ 19P05026Q0006 concerning CMR Master Bath Refurbishment. The amendment, identified as A0001, is addressed to prospective offerors and requires acknowledgment prior to offer submission. The contracting officer is Jonathan Nwosu, and the purchase requisition number is PR16027913.
The amendment provides additional information regarding changes to initial requirements in the Statement of Work. The primary modifications include: correction of the title on the main page, updates to Section #2 (Technical Requirements) and Section #3 (Deliverables), and introduction of three distinct bathroom design proposals for offerors to consider. These proposals are Proposal No. 1 – Balanced Bath and Shower Concept, Proposal No. 2 – Vanity and Storage Priority Concept, and Proposal No. 3 – Alternative Vanity and Storage Priority Concept. A revised SOW reflecting these changes is attached. Offerors are instructed to adjust their offers accordingly to reflect the changed requirements. All other terms and conditions of the original solicitation remain unchanged and in full force and effect.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO.
A0001
3. EFFECTIVE DATE
06/02/2026
4. REQUISITION/PURCHASE REQ. NO.
PR16027913
5. PROJECT NO. (If applicable)
6. ISSUED BY CODE
7. ADMINISTERED BY (If other than Item 6)
CODE
AMERICAN EMBASSY LISBON
AV. DAS FORCAS ARMADAS, ATTN: GSO/PROCUREMENT
LISBOA 1649-044
PORTUGAL
8. NAME AND ADDRESS OF CONTRACTOR (NO., street,city,county,State,and ZIP Code)
9a. AMENDMENT OF SOLICITATION NO.
19P05026Q0006
Prospective Offerors
9b. DATED (SEE ITEM 11) 6/01/2026
10a. MODIFICATION OF CONTRACT/ORDER NO.
10b. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
[] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [ ] is extended, [ ] is not extended Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning ____1___ copies of the amendment;(b) By acknowledging receipt of this amendment on each copy of the offer submitted; or(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers.
FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b)
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
X
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor [ ] is not, [X ] is required to sign this document and return __1_ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to provide additional information regarding the changes in initial requirements (below) by the Requesting Office.
Offers should be adjusted accordingly to reflect the changes in the requirements - SOW
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME OF CONTRACTING OFFICER
Jonathan Nwosu
15B. NAME OF CONTRACTOR/OFFEROR
BY
(Signature of person authorized to sign)
15C.DATE
SIGNED
16B. UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C.DATE SIGNED
NSN 7540-01-152-8070 Standard Form 30 (revised 10/83)
06/02/2026 12:40 GMT
Nwosu, Jonathan (NwosuJ@state.gov)
Previous edition unusable Prescribed by GSA FAR (48 CFR) 53.243
RFQ 19P05026Q0006
CMR Master Bath Refurbishment
The changes were made in the main page “Title is corrected”
#2- TECHNICAL REQUIREMENTS
#3- DELIVERABLES
The changings were made to introduce the three distinct proposals/ or layouts for the bathroom.
Proposal No. 1 – Balanced Bath and Shower Concept.
Proposal No. 2 – Vanity and Storage Priority Concept.
Proposal No. 3 – Alternative Vanity and Storage Priority Concept.
Attached: Revised SOW to reflect the changes.
File details come from the government source that posted it. Updated .