This is a Price Quotation Breakdown template for a roof replacement project at the Deputy Chief of Mission Residence (DCMR) in Cairo, Egypt under Request for Quotations solicitation 19GE5026Q0115, issued by the Department of State Office of Acquisition Management.
The quotation template requires contractors to provide a Firm Fixed Price breakdown across three distinct roof areas with different construction methods. The DCMR & CAC Plaza Deck section (3,300 square feet) includes demolition, substrate repairs, two-ply modified bitumen membrane installation, stone tile application, flashings, drains, and painting. The DCMR & CAC Clay Tile section (1,800 square feet) encompasses demolition, salvage and reinstallation of existing tiles, new wood deck and underlayment, wood battens, new clay tiles, metal flashings, and painting. The Generator Building section (200 square feet) requires elastomeric coating with demolition, base coat with fabric, and finish coats. Contractors must itemize material costs and labor/equipment costs separately for each line item, then calculate subtotals. The template includes separate sections for indirect costs including shipping, Davis-Bacon Act compliance, taxes and insurance percentages, labor overhead percentages, and profit percentages, with a final total estimated project cost. Quoters are responsible for adjusting this breakdown to correspond with their Firm Fixed Price as specified in Section B.5 of the solicitation.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Solicitation 19GE5026Q0115 - DCMR Roof Replacement, Cairo, Egypt
The quoter shall adjust this breakdown as desired to correspond with the Firm Fixed Price required for this project. See Section B.5. of solicitation.
| COST QUOTATION BREAKDOWN | |||||||
| ITEM OF WORK | QUANTITY | UNITS | MATERIAL COST | LABOR & EQUIPMENT COST | TOTAL | ||
| PER UNIT | SUBTOTAL | PER UNIT | SUBTOTAL | ||||
| DCMR & CAC PLAZA DECK (ROOF AREAS 1 ,2, 3, 11) | |||||||
| Mobilization / Demobilization | 1 | Lump Sum | $ - 0 | ||||
| Demolition / Disposal | 3,300 | Square Feet | $ - 0 | ||||
| Minor Repairs to Existing Substrate | 3,300 | Square Feet | $ - 0 | ||||
| Two-Ply Modified Bitumen Membrane | 3,300 | Square Feet | $ - 0 | ||||
| Mortar Setting Bed | 3,300 | Square Feet | $ - 0 | ||||
| Stone Tile | 3,300 | Square Feet | $ - 0 | ||||
| Base Flashings | 500 | Linear Feet | $ - 0 | ||||
| Metal Counterflashing | 500 | Linear Feet | $ - 0 | ||||
| Equipment / Curb Flashing | 500 | Linear Feet | $ - 0 | ||||
| Penetration Flashing | 25 | Each | $ - 0 | ||||
| Roof Drains | 5 | Each | $ - 0 | ||||
| Overflow Scuppers | 5 | Each | $ - 0 | ||||
| Sealant | 500 | Linear Feet | $ - 0 | ||||
| Painting | 1 | Lump Sum | $ - 0 | ||||
| Subtotal - Materials and Labor | $ - 0 | $ - 0 | $ - 0 | ||||
| DCMR & CAC CLAY TILE (ROOF AREAS 4, 5, 6, 12) | |||||||
| Demolition / Disposal | 1,800 | Square Feet | $ - 0 | ||||
| Salvage of Existing Tiles for Re-Install | 1,000 | Square Feet | $ - 0 | ||||
| New T&G Wood Deck | 1,800 | Square Feet | $ - 0 | ||||
| New Underlayment | 1,800 | Square Feet | $ - 0 | ||||
| New 2-Way Wood Battens | 1,800 | Square Feet | $ - 0 | ||||
| New Clay Tiles | 1,000 | Square Feet | $ - 0 | ||||
| Metal Flashings | 1,000 | Linear Feet | $ - 0 | ||||
| Penetration Flashing | 10 | Each | $ - 0 | ||||
| Wood Fascia, Soffit Repair/Replace | 1 | Lump Sum | $ - 0 | ||||
| Painting | 1 | Lump Sum | $ - 0 | ||||
| Subtotal - Materials and Labor | $ - 0 | ||||||
| GENERATOR BUILDING (ROOF AREA 10) - Elastomeric Coating | |||||||
| Demolition / Disposal | 200 | Square Feet | $ - 0 | ||||
| Minor Repairs To Concrete Deck | 200 | Square Feet | $ - 0 | ||||
| Base Coat w/ Fabric | 200 | Square Feet | $ - 0 | ||||
| Finish Coats | 200 | Square Feet | $ - 0 | ||||
| Subtotal - Materials and Labor | $ - 0 | $ - 0 | $ - 0 |
SUBTOTAL - ALL ROOF AREAS (M&L) $ - 0 $ - 0 $ - 0
| INDIRECT COSTS | ||
| Shipping | 1 | Lump Sum |
| DBA | 1 | Lump Sum |
| Taxes & Insurance | ____% | Labor |
| Overhead | _____% | Subtotal - M&L |
| Profit | ______% | All |
| Subtotal - Indirect Costs |
TOTAL - ESTIMATED PROJECT COST (M&L + IND.Costs) $ - 0