International Boundary and Water Commission United States and Mexico United States Section
Front Cover
Technical Specifications Rio Grande Canalization Project Thurman I and II Arroyos Channel Maintenance Doña Ana County, New Mexico
Solicitation 191BWC18B0004
July 5, 2018
United States and Mexico United States Section Engineering Services Division El Paso, Texas
These Technical Specifications may be reprinted after Contract award using the awarded Contract number instead of the Solicitation number currently shown. The reprint shall have all changes indicated incorporated.
Reissuance of the awarded Technical Specifications with the Contract number will proceed without an amendment or modification.
Reissuance with the Contract number will NOT result in a new date being displayed on the Technical
Specifications.
State of New Mexico
PLEASE NOTE - Technical Specifications should be printed double sided.
Printing this document single sided will take 216 additional pages of paper and 34 of those pages will be blank to facilitate double sided printing.
USIBWC Rio Grande Canalization Project
July 5, 2018 Division 00
USIBWC Solicitation 191BWC18B0004 Procurement and Contracting Requirements-Page 1
US International Boundary & Water Commission
International Boundary and Water Commission United States Section
TECHNICAL SPECIFICATIONS
DIVISION 00
PROCUREMENT AND CONTRACTING
REQUIREMENTS
Thurman I and II Arroyos Channel Maintenance US International Boundary & Water Commission Rio Grande Canalization Project Procurement and
Contracting
Requirements
Division 00
Division 00-Procurement and Contracting Requirements
Division 00 July 5, 2018
Procurement and Contracting Requirements-Page 2 USIBWC Solicitation 191BWC18B0004
This page intentionally left blank for double sided printing.
July 5, 2018 Table of Contents Governing
USIBWC Solicitation 191BWC18B0004 00.01.10-Page 1
SECTION 00.01.10
TABLE OF CONTENTS GOVERNING
00.01.10 Table of Contents Governing 00.01.10-Table of Contents Governing
Table of Contents
DIVISIONS AND SECTIONS
Division 00-Procurement and Contracting Requirements 00.01.10-Table of Contents Governing 00.01.15-List of Contract Drawings 00.21.13-Instructions to Bidders 00.31.19-Existing Condition Information 00.31.21-Survey Information 00.31.24-Environmental Information 00.31.26-Existing Hazardous Material Information 00.31.32-Geotechnical Data 00.31.43-Permit Application 00.60.00-USIBWC Forms and Standard Documents 00.70.00-Delivery of Data to USIBWC 00.73.63-Security Requirements
Division 01-General Requirements 01.11.00-Summary of Work 01.22.00-Measurement and Payment 01.29.00-Payment Procedures 01.29.15-Certified Payroll 01.31.00-Project Coordination 01.32.16-Construction Progress Schedule 01.32.33-Photographic Documentation 01.33.00-Submittal Procedures 01.35.23-Safety 01.42.00-References 01.43.26-Testing and Inspection Agencies 01.45.00-Quality Control 01.51.00-Temporary Utilities 01.52.13-Field Offices and Sheds 01.55.00-Vehicular Access and Parking 01.57.00-Temporary Controls for Work Areas 01.57.13-Temporary Environmental Controls 01.61.00-Common Product Requirements 01.61.16-Use of Recovered Materials and Biobased Products 01.74.19-Construction Waste Management and Disposal 01.77.19-Closeout Requirements 01.78.36-Warranties 01.78.39-Project Record Documents 01.78.99-Project Data
Division 02-Existing Conditions 02.02.00-Existing Conditions & Facilities
Table of Contents Governing July 5, 2018
00.01.10-Page 2 USIBWC Solicitation 191BWC18B0004
02.21.00-Surveys 02.21.13-Cultural Resources Surveys
Division 03-Concrete 03.11.00-Concrete Forming 03.15.00-Concrete Accessories 03.15.13-Waterstops 03.15.16-Concrete Joints 03.21.00-Reinforcing Steel 03.30.00-Cast-in-Place Concrete 03.35.00-Concrete Finishing 03.39.00-Concrete Curing
Division 05-Metal 05.05.23-Welding 05.58.63-Sediment Depth Gauges
Division 09-Finishes 09.97.13-Galvanizing
Division 31-Earthwork 31.05.19-Geotextile for Earthwork 31.11.00-Preparing Right of Way 31.14.00-Remove / Stockpile Existing Materials 31.23.00-Excavation 31.23.13-Subgrade Preparation 31.23.19-Dewatering and Control of Surface Water 31.23.23.23-Flowable Backfill 31.63.29-Drilled Pier Foundations 31.81.00-Proof Rolling
Division 32-Exterior Improvements 32.15.00-Aggregate Road Surfacing 32.32.13-Sediment Basin Inlet Flumes 32.32.16-Sediment Basin Concrete End Walls 32.92.00-Vegetation for Erosion Control
Division 35-Waterway Construction 35.42.00-Riprap
Technical Specification Tables
Table 1 - Index of Drawings Table 2 - Quality Control Testing Table 3 - Federally Listed Species in the RGCP Table 4 - Required Minimum Biobased Content Table 5 - Required Minimum Recovered Content Table 6 - Warranty Priority Code A Table 7 - Warranty Priority Code B
July 5, 2018 Table of Contents Governing
USIBWC Solicitation 191BWC18B0004 00.01.10-Page 3
Table 8 - Warranty Priority Code C Table 9 - Warranty Priority Code D Table 10 - Permitted Surface Irregularities Table 11 - Epoxy / Adhesive Requirements Table 12 - ASTM C881 Minimum Requirements Table 13 - Nonshrink Grout Requirements Table 14 - Expandable Waterstop Requirements Table 15 - PVC Waterstop Requirements Table 16 - TPE-R Waterstop Requirements Table 17 - Minimum Concrete Cover Variation Table 18 - Minimum Concrete Strength Table 19 - Maximum Water-Cement Ratio Table 20 - Deviations and Tolerances from Specified Lines, Grades, and Dimensions Table 21 - Acceptance Criteria for Questionable Water Supplies Table 22 - Chemical Limits for Mix Water Table 23 - Coarse Aggregate Gradation Chart Table 24 - Fine Aggregate Gradation Chart Table 25 - Standard Deviation Modification Factor Table 26 - Overdesign to Meet Compressive Strength Requirements (1) Table 27 - Overdesign to Meet Compressive Strength Requirements (2) Table 28 - Air Entrainment Table 29 - Slump Requirements Table 30 - Duration of Curing Table 31 - Galvanizing Standards Table 32 - Geotextile Requirements Table 33 - Aggregate Surfacing Gradation Requirements Table 34 - Drain Gravel Gradation Table 35 - Plant Varieties and Seeding Rates Table 36 - Riprap Gradation Requirements
Technical Specification Figures
Figure 1-Fillable Form (not printed) Figure 2-Printed Fillable Form Figure 3-Fabrication Tolerances for Bars Figure 4-Miscellaneous Qualification: Fillet Weld Break Specimen Figure 5-Miscellaneous Qualification: Method of Rupturing Specimen
--End of Section--file://///192.168.45.75/ESD-PROJECTS/URG%20Construction%20Files/191BWC18B0004%20Thurman%20I%20&%20II%20Arroyos/20-Design%20Data/Specs/191BWC18B0004%20Thurman%20Specs%2020180705.docm%23_Toc518548937 file://///192.168.45.75/ESD-PROJECTS/URG%20Construction%20Files/191BWC18B0004%20Thurman%20I%20&%20II%20Arroyos/20-Design%20Data/Specs/191BWC18B0004%20Thurman%20Specs%2020180705.docm%23_Toc518548938 file://///192.168.45.75/ESD-PROJECTS/URG%20Construction%20Files/191BWC18B0004%20Thurman%20I%20&%20II%20Arroyos/20-Design%20Data/Specs/191BWC18B0004%20Thurman%20Specs%2020180705.docm%23_Toc518548939
Table of Contents Governing July 5, 2018
00.01.10-Page 4 USIBWC Solicitation 191BWC18B0004
July 5, 2018 List of Contract Drawings
USIBWC Solicitation 191BWC18B0004 00.01.15-Page 1
SECTION 00.01.15
LIST OF CONTRACT DRAWINGS
00.01.15 List of Contract Drawings 00.01.15-List of Contract Drawings
PART 1 - GENERAL
1.1 SECTION INCLUDES
Part 1 - General
1.1 Section Includes
1.2 Measurement and Payment
1.3 Drawing Titles
1.4 Drawing Index
Part 2 - Products (Not Used)
2.1 Additional Or Revised Drawings
Part 3 - Execution (Not Used) --End of Section--
1.2 MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly, but shall be included in the various Bid Items under this Contract.
1.3 DRAWING TITLES
A. The Contract Drawings applicable to this Contract are entitled:
Thurman I and II Arroyos Channel Maintenance
Doña Ana County, New Mexico
1.4 DRAWING INDEX
A. The Contract Drawings include the following:
Table 1 - Index of Drawings
SHEET NO. SHEET TITLE
1 Cover Sheet
2 Drawing Index and Summary of Quantities
3 Legend and Abbreviations
4 General Notes
5 Existing Boring Plan
6 Existing Boring Logs
7 Overall Site Plan Sheet 1 of 2
8 Overall Site Plan Sheet 2 of 2
9 Thurman I Arroyo Existing Site Plan
10 Thurman I Arroyo Plan and Profile
List of Contract Drawings July 5, 2018
00.01.15-Page 2 USIBWC Solicitation 191BWC18B0004
SHEET NO. SHEET TITLE
11 Thurman I Arroyo Sediment Basin Cross-Sections
12 Thurman II Arroyo Existing Site Plan
13 Thurman II Arroyo Plan and Profile
14 Thurman II Arroyo Sediment Basin Cross-Sections
15 Typical Sections
16 Thurman I and II Arroyo Access Road Plans
17 Thurman I Arroyo End Wall Plan and Profile
18 Thurman II Arroyo End Wall Plan and Profile
19 Thurman I Arroyo Inlet Flume Plan and Profile
20 Thurman I Arroyo Inlet Flume Cross-Sections
21 Thurman II Arroyo Inlet Flume Plan and Profile
22 Thurman II Arroyo Inlet Flume Cross-Sections
23 Inlet Flume Details
24 Structural General Notes
25 End Wall Foundation Details
26 End Wall Sections and Details Sheet 1 of 2
27 End Wall Sections and Details Sheet 2 of 2
28 Sediment Removal Plan & Profile Sta 4555+00 To Sta 4546+00
29 Sediment Removal Plan & Profile Sta 4546+00 To Sta 4537+00
30 Sediment Removal Plan & Profile Sta 4537+00 To Sta 4528+00
31 Sediment Removal Plan & Profile Sta 4528+00 To Sta 4519+00
32 Sediment Removal Plan & Profile Sta 4519+00 To Sta 4510+00
33 Sediment Removal Plan & Profile Sta 4510+00 To Sta 4501+00
34 Sediment Removal Plan & Profile Sta 4501+00 To Sta 4492+00
35 Sediment Removal Plan & Profile Sta 4492+00 To Sta 4483+00
36 Sediment Removal Plan & Profile Sta 4483+00 To Sta 4474+00
37 Sediment Removal Plan & Profile Sta 4474+00 To Sta 4465+00
38 Sediment Removal Plan & Profile Sta 4465+00 To Sta 4456+00
39 Sediment Removal Cross-Sections Sta 4554+50 To Sta 4548+00
40 Sediment Removal Cross-Sections Sta 4547+00 To Sta 4540+00
41 Sediment Removal Cross-Sections Sta 4539+00 To Sta 4532+00
42 Sediment Removal Cross-Sections Sta 4531+00 To Sta 4524+00
July 5, 2018 List of Contract Drawings
USIBWC Solicitation 191BWC18B0004 00.01.15-Page 3
SHEET NO. SHEET TITLE
43 Sediment Removal Cross-Sections Sta 4523+00 To Sta 4516+00
44 Sediment Removal Cross-Sections Sta 4515+00 To Sta 4508+00
45 Sediment Removal Cross-Sections Sta 4507+00 To Sta 4500+00
46 Sediment Removal Cross-Sections Sta 4499+00 To Sta 4492+00
47 Sediment Removal Cross-Sections Sta 4491+00 To Sta 4484+00
48 Sediment Removal Cross-Sections Sta 4483+00 To Sta 4476+00
49 Sediment Removal Cross-Sections Sta 4475+00 To Sta 4468+00
50 Sediment Removal Cross-Sections Sta 4467+00 To Sta 4460+00
51 Sediment Removal Cross-Sections Sta 4459+00
PART 2 - PRODUCTS
(Not Used)
2.1 ADDITIONAL OR REVISED DRAWINGS
A. Except as provided in these specifications for drawings to be furnished by Contractor, Contract
Drawings will be supplemented by additional or revised general and detail drawings as necessary or desirable as work progresses.
B. Additional or revised general and detail drawings will show dimensions and details necessary for construction purposes more completely than are shown on these Contract Drawings for features of work.
C. Perform work in accordance with additional general and detail drawings or revisions at applicable prices bid in schedule for such work.
PART 3 - EXECUTION
List of Contract Drawings July 5, 2018
00.01.15-Page 4 USIBWC Solicitation 191BWC18B0004
July 5, 2018 Instructions to Bidders
USIBWC Solicitation 191BWC18B0004 00.21.13-Page 1
SECTION 00.21.13
INSTRUCTIONS TO BIDDERS
00.21.13 Instructions to Bidders 00.21.13-Instructions to Bidders
PART 1 - GENERAL
1.1 SECTION INCLUDES
Part 1 - General
1.1 Section Includes
1.2 Reference Standards
1.3 Measurement and Payment
1.4 Definitions
1.5 Duty to Inquire
1.6 Bid Submission
Part 2 - Products (Not Used) Part 3 - Execution
3.1 Requests for Interpretation
--End of Section--
1.2 REFERENCE STANDARDS
A. Federal Acquisition Regulation (FAR)
1. FAR 52.236-3, Site Investigation and Conditions Affecting the Work
1.3 MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly, but shall be included in the various Bid Items under this Contract.
1.4 DEFINITIONS
A. Within this section, the following terms are used interchangeably.
1. Bid - Offer - Proposal
2. Solicitation - Request for Proposal - RFP
3. Bidder - Offeror - Contractor
1.5 DUTY TO INQUIRE
A. Contractors shall review the full Solicitation including Technical Specifications, Contract Drawings, attachments, etc. to determine the full scope of work required.
B. The Contractor shall take no advantage of any item of which they have a duty to inquire.
C. If during review of these items, the Contractor finds discrepancies, omissions, conflicts, defects, errors, or ambiguities, they have a duty to inquire. The Contractor shall also inquire about items that are unclear or open to interpretation.
1.6 BID SUBMISSION
A. Submission of a bid shall be conclusive evidence that the Bidder has reviewed, investigated, and acknowledged all items detailed in FAR 52.236-3.
Instructions to Bidders July 5, 2018
00.21.13-Page 2 USIBWC Solicitation 191BWC18B0004
B. Submission of a bid shall be conclusive evidence that the Bidder has investigated and is satisfied as to the conditions to be encountered, the character, quality and scope of work to be performed, the quantities of materials to be furnished.
C. Submission of a bid constitutes agreement that Bidders has provided written notice of all conflicts, errors, ambiguities, and discrepancies discovered in the Contract Documents, that responses to these written notices are acceptable to Bidder, and that Contract Documents are sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing required work.
D. Bidder has the sole responsibility to make such independent instigation and examination as they deem necessary in order to satisfy themselves as to the conditions to be encountered in the performance of work and the quantities required to complete the work in a accordance with the
Contract Documents.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
3.1 REQUESTS FOR INTERPRETATION
A. Contractors shall submit requests for interpretation, questions, and other concerns about the
Solicitation, Technical Specifications, Contract Drawings, attachments, etc. to the Contracting
Officer identified on SF-1442.
B. Such requests shall be made even if the question and answer period identified in the Solicitation has passed.
C. Failure to request interpretation prior to providing a bid shall result in the Contractor being fully responsible for any cost or time impacts involved to perform the work required.
July 5, 2018 Existing Condition Information
USIBWC Solicitation 191BWC18B0004 00.31.19-Page 1
SECTION 00.31.19
EXISTING CONDITION INFORMATION
00.31.19 Existing Condition Information 00.31.19-Existing Condition Information
PART 1 - GENERAL
1.1 SECTION INCLUDES
Part 1 - General
1.1 Section Includes
1.2 Related Requirements
1.3 Measurement and Payment
1.4 General
Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--
1.2 RELATED REQUIREMENTS
A. Section 00.31.32-Geotechnical Data
1.3 MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly, but shall be included in the various Bid Items under this Contract.
1.4 GENERAL
A. Field assessment of existing conditions within the project limits was performed by Tetra Tech. The findings are available in a report titled "Channel Maintenance Alternatives and Sediment-Transport
Studies for the Rio Grande Canalization Project: Final Report," dated October 20, 2015.
B. A design report was written by URS entitled "Design for the Construction of Channel Maintenance
Alternatives within the Rio Grande Canalization Project Doña Ana County, New Mexico," dated
June 14, 2018.
C. Geotechnical investigations were performed as noted in Section 00.31.32.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
Existing Condition Information July 5, 2018
00.31.19-Page 2 USIBWC Solicitation 191BWC18B0004
July 5, 2018 Survey Information
USIBWC Solicitation 191BWC18B0004 00.31.21-Page 1
SECTION 00.31.21
SURVEY INFORMATION
00.31.21 Survey Information 00.31.21-Survey Information
PART 1 - GENERAL
1.1 SECTION INCLUDES
Part 1 - General
1.1 Section Includes
1.2 Related Requirements
1.3 Measurement and Payment
1.4 Survey Control
1.5 Right of Way (ROW)
1.6 Existing Utility Survey
Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--
1.2 RELATED REQUIREMENTS
A. Section 02.02.00-Existing Conditions & Facilities
1.3 MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly, but shall be included in the various Bid Items under this Contract.
1.4 SURVEY CONTROL
A. Horizontal and vertical controls are based on New Mexico State Plane Coordinate Grid System
(NMSPCGS) NM Central Zone North American Datum of 1983 (NAD 83) in US survey feet, using
GEOID 03, and North American Vertical Datum of 1988 (NAVD 88) in US survey feet, respectively.
B. The survey was based on LiDAR data of the area collected in 2011. Data were provided by
USIBWC.
1.5 RIGHT OF WAY (ROW)
The existing ROW was provided by USIBWC as a GIS shapefile.
1.6 EXISTING UTILITY SURVEY
A. The surveyor performed a utility survey of the project areas to determine if any above-ground structures, utilities, or markers were present. In addition, the surveyor contacted New Mexico's 811
(www.nm811.org) to obtain any available utility information for the project areas.
1. NOTE: It is the Contractor’s responsibility to verify locations of all existing utilities (shown and not shown) prior to construction.
2. Additionally, attention is called to Sections 02.02.00 for additional requirements and guidelines for existing utility survey.
http://www.nm811.org/
Survey Information July 5, 2018
00.31.21-Page 2 USIBWC Solicitation 191BWC18B0004
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
July 5, 2018 Environmental Information
USIBWC Solicitation 191BWC18B0004 00.31.24-Page 1
SECTION 00.31.24
ENVIRONMENTAL INFORMATION
00.31.24 Environmental Information 00.31.24-Environmental Information
PART 1 - GENERAL
1.1 SECTION INCLUDES
Part 1 - General
1.1 Section Includes
1.2 Related Requirements
1.3 Reference Standards
1.4 Measurement and Payment
1.5 General
1.6 Preservation of Cultural and Natural Resources and the Environment
1.7 Other Considerations
1.8 NEPA Documentation
1.9 Use of Geologic Materials on a Federally Funded Project
Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--
1.2 RELATED REQUIREMENTS
A. Section 01.57.00-Temporary Controls for Work Areas
B. Section 01.57.13-Temporary Environmental Controls
C. Section 02.21.13-Cultural Resources Surveys
1.3 REFERENCE STANDARDS
A. United States Code (USC)
1. Clean Air Act, 42 USC 7401 et seq.
2. Clean Water Act (CWA), 33 USC 1251 et seq.
3. Endangered Species Act (ESA), 16 USC 1531 et seq.
4. Migratory Bird Treaty Act (MBTA), 16 USC 703 - 712
5. National Environmental Policy Act (NEPA), 42 USC 4321-4347
6. National Historic Preservation Act (NHPA), 54 USC 300101 et seq.
7. National Wildlife Refuge System Improvement Act of 1997, 16 USC 668dd
8. Native American Graves Protection and Repatriation Act (NAGPRA), 25 USC 3001 et. seq.
9. Refuge Recreation Act, 16 USC 460k - 460k-4
1.4 MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly, but shall be included in the various Bid Items under this Contract.
Environmental Information July 5, 2018
00.31.24-Page 2 USIBWC Solicitation 191BWC18B0004
1.5 GENERAL
A. The project’s Environmental Assessment (EA), entitled "Final Environmental Assessment and
Finding of No Signification Impact: Channel Maintenance Alternatives at Thurman I and II Arroyos in Hatch, NM, Rio Grande Canalization Project," dated December 6, 2017. The Contractor shall review and comply with the requirements provided in the EA document.
B. The project’s Biological Opinion (BO), entitled "Final Biological Opinion for US International
Boundary and Water Commission Long-Term River Management of the Rio Grande Canalization
Project, New Mexico," dated August 16, 2017. The Contractor shall review and comply with the requirements provided in the BO document.
C. Also see the "Final Biological Assessment: Integrated Land Management for Long‐Term River
Management of the Rio Grande Canalization Project," dated October 2011 by SWCA
Environmental Consultants and "Record of Decision: River Management Alternative for the Rio
Grande Canalization Project," dated June 9, 2009.
D. These documents lists environmentally and culturally sensitive areas that need to be protected from any disturbances of construction activities. The environmentally and culturally sensitive areas that were identified on the document are identified below.
1. Biological Resources
Work should be scheduled to occur outside of the bird breeding season whenever possible.
Migratory birds may be present within the project area; birds, nests, and eggs are to be protected and avoided during construction. The breeding and nesting season is identified in
Section 01.57.13. If work continues into the bird breeding/nesting season the areas proposed for disturbance shall be surveyed in order to avoid the inadvertent destruction of nests and eggs.
2. Natural Resources
Equipment cannot be parked, staged, or used under large, mature trees. Keeping equipment away from the large, mature trees will prevent incidental damage to the tree and prevent compression of the root ball.
E. Further details of environmental requirements are in Sections 01.57.00 and 01.57.13.
1.6 PRESERVATION OF CULTURAL AND NATURAL RESOURCES AND THE
ENVIRONMENT
A. If the Contractor initiates changes to the Contract and USIBWC approves the changes, the
Contractor is responsible for obtaining clearances and coordinating with the appropriate regulatory agencies.
B. Culturally Sensitive Areas
If a site, building, or location of historical, archaeological, educational, or scientific interest is discovered within the right of way, cease all work immediately, secure the site from further disturbance and possible vandalism, and notify USIBWC. The site, building, or location will be investigated and evaluated by USIBWC.
1.7 OTHER CONSIDERATIONS
The Contractor is required to ensure that all Environmental Permits, Issues, and Comments (EPIC), which are included within the Contract Documents are followed and implemented to ensure potential impacts are avoided.
July 5, 2018 Environmental Information
USIBWC Solicitation 191BWC18B0004 00.31.24-Page 3
1.8 NEPA DOCUMENTATION
The USIBWC shall complete appropriate NEPA documentation prior to the construction of the project.
The USIBWC will be responsible for compliance with National Environmental Policy Act (NEPA).
1.9 USE OF GEOLOGIC MATERIALS ON A FEDERALLY FUNDED PROJECT
A. To ensure preservation of historical and archaeological data, prior to use of any soil, rock, or gravel, the source must first be compliance confirmed by the COR to ensure compliance with Section 106 of the National Historic Preservation Act (NHPA).
B. Take no action to use or alter the proposed location until written approval for site use is received from the COR.
C. If the quarry or borrow site already provides materials for NMDOT, USACE, or other governmental agency, a copy of the environmental approvals from said agencies may be provided to the COR.
D. Include permission for Government access to any geological source locations.
E. Full details of requirements for geological materials are in Section 02.21.13.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
Environmental Information July 5, 2018
00.31.24-Page 4 USIBWC Solicitation 191BWC18B0004
July 5, 2018 Existing Hazardous Material Information
USIBWC Solicitation 191BWC18B0004 00.31.26-Page 1
SECTION 00.31.26
EXISTING HAZARDOUS MATERIAL INFORMATION
00.31.26 Existing Hazardous Material Information 00.31.26-Existing Hazardous Material Information
PART 1 - GENERAL
1.1 SECTION INCLUDES
Part 1 - General
1.1 Section Includes
1.2 Related Requirements
1.3 Measurement and Payment
1.4 General
Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--
1.2 RELATED REQUIREMENTS
A. Section 00.31.24-Environmental Information
1.3 MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly, but shall be included in the various Bid Items under this Contract.
1.4 GENERAL
Based on the environmental report(s) identified in Section 00.31.24, there are no hazardous material or waste storage, disposal sites, or spill sites, identified within the immediate Project area.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
Existing Hazardous Material Information July 5, 2018
00.31.26-Page 2 USIBWC Solicitation 191BWC18B0004
July 5, 2018 Geotechnical Data
USIBWC Solicitation 191BWC18B0004 00.31.32-Page 1
SECTION 00.31.32
GEOTECHNICAL DATA
00.31.32 Geotechnical Data 00.31.32-Geotechnical Data
PART 1 - GENERAL
1.1 SECTION INCLUDES
Part 1 - General
1.1 Section Includes
1.2 Measurement and Payment
1.3 Geotechnical Reports
Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--
1.2 MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly, but shall be included in the various Bid Items under this Contract.
1.3 GEOTECHNICAL REPORTS
A. Geotechnical analysis for this project was performed by S&B Infrastructure, Ltd. and summarized in their report entitled, "Final Technical Memorandum Volume I for Geotechnical Explorations of
Levee System with the Rio Grande Canalization Project, hatch-Tonuco Levee Segment," and "Final
Technical Memorandum Volume II for Geotechnical Explorations of Levee System with the Rio
Grande Canalization Project, hatch-Tonuco Levee Segment," both dated August 4, 2008.
B. The data and report are not intended as a representation or warranty of continuity of conditions between soil borings nor of groundwater levels at dates and times other than date and time when measured. Additional test borings and other exploratory operations may be made by Contractor subsequent to award of the Contract.
C. Due to the site location adjacent to the Rio Grande, groundwater levels may fluctuate, sometimes to extreme levels, based upon time of year and amount of water in the river. Higher groundwater levels than those shown in the bore logs may occur causing changes in soil saturation and strength.
D. The worksite is adjacent to the Rio Grande and is located in an area where the river flowed in the past. Fluvial deposits can change rapidly in type (sand, slit, clay, loam, gravel, rocks, etc.) both horizontally and vertically due to depositional characteristics and channel shifting. Rocks may be present even if not visible on the ground surface. Rocks larger than the borehole would not have been captured in any logging data.
E. The Contractor is charged with the duty to read and understand the geotechnical data provided, including any data referenced within. The Contractor shall consider all geotechnical information including geotechnical reports, bore logs, and site visits as a whole. The Contractor shall consider the limitations of any geotechnical tests performed including the auger size, borehole spacing and location, consistency of borehole data, as well as the frequency of testing, results of testing, and groundwater level at time.
Geotechnical Data July 5, 2018
00.31.32-Page 2 USIBWC Solicitation 191BWC18B0004
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
July 5, 2018 Permit Application
USIBWC Solicitation 191BWC18B0004 00.31.43-Page 1
SECTION 00.31.43
PERMIT APPLICATION
00.31.43 Permit Application 00.31.43-Permit Application
PART 1 - GENERAL
1.1 SECTION INCLUDES
Part 1 - General
1.1 Section Includes
1.2 Reference Standards
1.3 Measurement and Payment
1.4 General
1.5 Work in Waters of the United States
1.6 Responsibilities
Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--
1.2 REFERENCE STANDARDS
A. Doña Ana County, NM
1. Doña Ana County Code Chapter 157, Design and Construction Standards
2. Doña Ana County Stormwater Management Ordinance
B. Environmental Protection Agency (EPA)
1. General Construction Permit 2017
2. National Pollutant Discharge Elimination System (NPDES) Permit Program
C. State of New Mexico
1. New Mexico Environmental Department application of Clean Water Act §401
D. US Army Corps of Engineers (USACE)
1. Section 404 of Clean Water Act, 33 USC §1251 et seq.
1.3 MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly, but shall be included in the various Bid Items under this Contract.
1.4 GENERAL
Prior to the beginning of construction, the Contractor shall be responsible for researching, coordinating, obtaining, and paying all applicable fees for all permits required by Federal, state, and local entities, including, but not limited to, a specific or general stormwater permit prepared in accordance with the requirements of Stormwater Pollution Prevention Plan (SWPPP).
1.5 WORK IN WATERS OF THE UNITED STATES
A. For work in the right of way, USIBWC has obtained a Section 404 permit from the US Army Corps of Engineers as well as the associated New Mexico Section 401 permit. Adhere to all agreements, mitigation plans, and standard best management practices required by the permits.
Permit Application July 5, 2018
00.31.43-Page 2 USIBWC Solicitation 191BWC18B0004
B. If Contractor initiated changes in the construction method result in impacts to waters of the US, the
Contractor shall have sole responsibility to obtain all required new or revised Section 404 permit and shall adhere to all agreements, mitigation plans, and standard best management practices required by these permits.
1.6 RESPONSIBILITIES
A. The Contractor shall be responsible for providing the proposed location of the project staging areas for compliance confirmation of the COR prior to installation of stormwater pollution prevention
(SWPP) measures.
B. The Federal Government is not subject to local jurisdictions' building codes, nor is it required to obtain building permits from local jurisdictions for construction on real estate owned or controlled by the USIBWC. However, borrow pits and other offsite locations are subject to local regulations.
The Contractor is responsible for researching and obtaining all necessary permits for offsite work.
C. The Contractor shall be responsible for obtaining all necessary permits and rights of entry for all work required under this Contract.
D. The Contractor will also be required to research the need for any other required permits, based on the information available from the Contract Drawings and Technical Specifications prior to the beginning of construction. For the work under this Contract, the Contractor shall be responsible for coordinating and obtaining all permits required by Federal, state, and local entities, unless otherwise specified within the Contract Provisions and these Technical Specifications.
E. The Contractor shall apply and pay for all required permits. The Government is not responsible for any existing or newly introduced permits required before, during and/or after construction.
F. The Contractor shall be responsible for and shall give and maintain any and all notices required by applicable regulations, laws, or permitting authorities pertaining to construction of this project.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
July 5, 2018 USIBWC Forms and Standard Documents
USIBWC Solicitation 191BWC18B0004 00.60.00-Page 1
SECTION 00.60.00
USIBWC FORMS AND STANDARD DOCUMENTS
00.60.00 USIBWC Forms and Standard Documents 00.60.00-USIBWC Forms and Standard Documents
PART 1 - GENERAL
1.1 SECTION INCLUDES
Part 1 - General
1.1 Section Includes
1.2 Measurement and Payment
1.3 General
1.4 Location of Items
Part 2 - Products (Not Used) Part 3 - Execution
3.1 Providing Fillable Forms to USIBWC
3.2 Printing
--End of Section--
1.2 MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly, but shall be included in the various Bid Items under this Contract.
1.3 GENERAL
A. The USIBWC ftp site is available at:
Address: 63.96.218.8
User Name: ESD_User
Password: 2erAsatu
B. USIBWC's ftp site must be accessed using ftp software. Internet browsers (e.g., Internet Explorer, Chrome, Firefox, etc.) will not work.
C. Ftp software is available as freeware or as commercial software. Examples of available ftp software include FileZilla, WinSCP, SmartFTP, and Ipswitch.
D. Contractor shall use the most current version of each form.
E. Form filenames contain a date. This date is the revision date of the form. Keeping the date in the filename can cause confusion when submitting files. Prior to submitting the forms, rename the file as suggested in these Technical Specifications or as agreed to with the COR.
1.4 LOCATION OF ITEMS
A. All forms are under the directory entitled 'Construction\Forms.'
B. Posters are under the directory entitled 'Construction\Posters.'
USIBWC Forms and Standard Documents July 5, 2018
00.60.00-Page 2 USIBWC Solicitation 191BWC18B0004
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
3.1 PROVIDING FILLABLE FORMS TO USIBWC
A. Fillable forms shall be "printed" prior to sending to USIBWC. Printing a fillable form to pdf fixes the form data permanently so it cannot be changed. It also allows the merging of multiple pdf files without compromising form data.
1. Printing resolution shall not be less than 400 dpi. 1200 dpi is preferred and easily handled by
Adobe Acrobat.
Figure 1-Fillable Form (not printed)
Figure 2-Printed Fillable Form
3.2 PRINTING
The Contractor is responsible for printing copies of items provided in electronic format for their own use.
July 5, 2018 Delivery of Data to USIBWC
USIBWC Solicitation 191BWC18B0004 00.70.00-Page 1
SECTION 00.70.00
DELIVERY OF DATA TO USIBWC
00.70.00 Delivery of Data to USIBWC 00.70.00-Delivery of Data to USIBWC
PART 1 - GENERAL
1.1 SECTION INCLUDES
Part 1 - General
1.1 Section Includes
1.2 Measurement and Payment
1.3 General
1.4 Adobe PDF Files
Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--
1.2 MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly, but shall be included in the various Bid Items under this Contract.
1.3 GENERAL
A. USIBWC will perform most document transfer communications via email.
B. The Design-Builder shall send all files electronically via email whenever possible. USIBWC's email system can accept files up to 50 MB. Very large files shall be transferred via ftp sites or via
CD/DVD.
1. The US Army Aviation and Missile Research Development and Engineering Center
(AMRDEC) provides a free, safe ftp system which can be used to deliver items up to 2 GB.
This is available at: safe.amrdec.army.mil/safe/.
C. Direct delivery via drop off, US Postal Service, FedEx, UPS, etc. is acceptable.
1. No delivered boxes shall exceed forty (40) pounds.
D. Placing documents on a cloud server, online drop box, "web hub," or online management system
(e.g. Owner Insite) is unacceptable as a delivery method.
E. Electronic files shall be provided in their native format (MSWord, Excel, Primavera, etc.) as well as
Adobe pdf.
1. The entire filename shall not exceed thirty (30) characters, excluding extension.
F. Hard copies shall not be provided in 3-ring binders (except for O&M manuals, if required). Large, lengthy hard copies shall be grouped in expandable folders. Folders shall not exceed 3.5 inches in width.
1.4 ADOBE PDF FILES
A. Pdfs shall be produced directly via software whenever possible and shall include valid electronic signatures or they shall be scans of the original documents.
https://safe.amrdec.army.mil/safe/
Delivery of Data to USIBWC July 5, 2018
00.70.00-Page 2 USIBWC Solicitation 191BWC18B0004
B. The minimum scanning resolution shall be:
1. Color-400 dpi
2. Grayscale-400 dpi
3. Black and White-600-dpi
C. Color documents shall be scanned in color. NCR pages that are other than white (e.g. all yellow or all pink) are not considered color documents and may be scanned in grayscale or black and white.
D. The Contractor shall ensure that the electronic copy is legible.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
July 5, 2018 Security Requirements
USIBWC Solicitation 191BWC18B0004 00.73.63-Page 1
SECTION 00.73.63
SECURITY REQUIREMENTS
00.73.63 Security Requirements 00.73.63-Security Requirements
PART 1 - GENERAL
1.1 SECTION INCLUDES
Part 1 - General
1.1 Section Includes
1.2 Measurement and Payment
1.3 General
1.4 Security
1.5 Insurance
1.6 Department of Homeland Security
Part 2 - Products (Not Used) Part 3 - Execution (Not Used) --End of Section--
1.2 MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly, but shall be included in the various Bid Items under this Contract.
1.3 GENERAL
The project site may be exposed to vandalism and theft. The Contractor shall be responsible for providing adequate security of the project site in order to prevent vandalism and theft.
1.4 SECURITY
A. The Contractor is responsible for securing the worksite, equipment, and materials from vandalism and theft.
B. The Contractor shall implement a security program that:
1. Protects the work, the existing premises, and the Government’s operations from theft, vandalism, and unauthorized entry.
2. Initiates a security program in coordination with Government’s existing security system at mobilization.
3. Maintains the security program throughout construction duration until Contract Closeout.
C. The Contractor shall implement entry control to the work area that notifies people of the construction area, of PPE required, and of the dangers of entry.
D. The Government shall not be responsible for the security of any items within the work area and associated PSLs.
1.5 INSURANCE
A. When not required by the Contract clauses, the Contractor has the right to purchase coverage for property insurance, builder's risk insurance (including perils of wind, collapse, vandalism/malicious
Security Requirements July 5, 2018
00.73.63-Page 2 USIBWC Solicitation 191BWC18B0004 mischief, and theft, including theft of materials whether or not attached to any structure), and/or flood insurance or to be self-insured for these exposures.
B. The Contractor shall be held liable for all costs associated with losses, deductibles, and self-insurance for coverages not required by the Contract clauses.
1. Losses shall include architects' and engineers' fees that may be necessary to provide drawings and specifications for the repair and/or replacement of damaged property.
2. Losses shall include appropriate supervision and quality control of all work for the repair and/or replacement of damaged property.
C. Any insurance policies purchased for work or property related to this Contract for coverages not required by the Contract clauses shall list the International Boundary and Water Commission, United States Section, as an additional insured.
1.6 DEPARTMENT OF HOMELAND SECURITY
In any event the staff of the US Department of Homeland Security (also known as US Customs and
Border Protection (CBP)) alerts and directs any field crews to stop work in for any security reasons in the area, the Contractor shall consider this as top priority and fully cooperate with the directions of DHS at all times until the security alert is cleared by the DHS. In addition the Contractor shall contact and coordinate with the COR for any additional steps to be taken during and after the security alert from the DHS is cleared.
PART 2 - PRODUCTS
(Not Used)
PART 3 - EXECUTION
July 5, 2018 Division 01
USIBWC Solicitation 191BWC18B0004 General Requirements-Page 1
United States Section
TECHNICAL SPECIFICATIONS
DIVISION 01
GENERAL REQUIREMENTS
General Requirements Division 01 Division 01-General Requirements
Division 01 July 5, 2018
General Requirements-Page 2 USIBWC Solicitation 191BWC18B0004
July 5, 2018 Summary of Work
USIBWC Solicitation 191BWC18B0004 01.11.00-Page 1
SECTION 01.11.00
SUMMARY OF WORK
01.11.00 Summary of Work 01.11.00-Summary of Work
PART 1 - GENERAL
1.1 SECTION INCLUDES
Part 1 - General
1.1 Section Includes
1.2 Related Requirements
1.3 Reference Standards
1.4 Measurement and Payment
1.5 Work Covered by the Contract Documents
1.6 Sequence of Work/Time for Completion of Work
1.7 Work Under Other Contracts
1.8 Labor and Staffing
1.9 Project Location
1.10 Investigation of Site Conditions
1.11 Other Contractual Requirements
Part 2 - Products
2.1 Government Furnished Materials
2.2 Products to be Furnished by the Contractor
Part 3 - Execution
3.1 Submittals Required Prior to Mobilization
3.2 Use of Right-of-Way
3.3 Occupancy of Right-of-Way
3.4 Work Restrictions
--End of Section--
1.2 RELATED REQUIREMENTS
A. Section 01.32.16-Construction Progress Schedule
B. Section 01.32.33-Photographic Documentation
C. Section 01.33.00-Submittal Procedures
D. Section 01.35.23-Safety
E. Section 01.45.00-Quality Control
F. Section 01.51.00-Temporary Utilities
G. Section 01.52.13-Field Offices and Sheds
H. Section 01.55.00-Vehicular Access and Parking
I. Section 01.57.13-Temporary Environmental Controls
J. Section 01.57.00-Temporary Controls for Work Areas
K. Section 01.74.19-Construction Waste Management and Disposal
L. Section 02.02.00-Existing Conditions & Facilities
Summary of Work July 5, 2018
01.11.00-Page 2 USIBWC Solicitation 191BWC18B0004
M. Section 02.21.00-Surveys
1.3 REFERENCE STANDARDS
A. United States Code (USC)
1. Davis Bacon Act (DBA), 40 USC §3141-3148
1.4 MEASUREMENT AND PAYMENT
The work performed by the Contractor under this Section shall not be paid for directly, but shall be included in the various Bid Items under this Contract.
1.5 WORK COVERED BY THE CONTRACT DOCUMENTS
A. The work for this project generally consists of the construction of two sediment basins, and the removal of river sediment from within the Rio Grande.
B. The major construction efforts include, but are not limited to, the construction of the two sediment basins – one each at Thurman I Arroyo and Thurman II Arroyo – will include the following major construction tasks:
1. Excavation and offsite disposal of existing rocks, sediment, and soil from Thurman I and II
Arroyos within the limits of USIBWC's right of way to construct sediment basins;
2. Construction of reinforced concrete drilled shaft piers.
3. Construction of reinforced concrete sediment basin end walls.
4. Installation of rock riprap erosion protection.
5. Installation of flexible base maintenance roads.
6. Site grading and associated drainage improvements.
7. Removal of river sediment from with the Rio Grande main channel and disposed of in an manner meeting Section 01.74.19.
C. The final product shall be two earthen sedimentation basins with concrete end walls. The basins shall have maintenance roads to allow workers to access and clean the basins of sediment.
1.6 SEQUENCE OF WORK/TIME FOR COMPLETION OF WORK
A. The Contractor shall comply with all submittal requirements as covered under these specifications and obtain Government review of each submission.
1. No construction shall be started, until the Government reviews the required submittals and determines they are satisfactory for purposes of beginning construction.
2. The Government will not grant any time extension for any resubmittal required when, in the opinion of the CO, the initial submission failed to meet the minimum quality requirements as set forth in the Contract.
3. If the Government allows the Contractor to proceed with limited construction based on pending minor revisions to the reviewed submittals, no payment will be made for any in-place construction related to the pending revisions until they are completed, resubmitted and are satisfactory to the Government.
4. No payment will be made for any in-place construction until all submittals required for that portion of the work and/or required prior to the start of construction have been made, reviewed, and are satisfactory to the Government.
USIBWC Solicitation 191BWC18B0004 01.11.00-Page 3
B. The work under this Contract shall be completed within the timeframe specified in the Contract
Provisions.
1.7 WORK UNDER OTHER CONTRACTS
No construction work is anticipated to be performed at the project site under separate Contract with other
Contractors during the Contractor’s performance period.
1.8 LABOR AND STAFFING
A. Contractors are responsible for determining the appropriate staffing necessary to perform the
Contract work. Contractors are also responsible for complying with the minimum wage and benefits requirements for each labor classification performing work on the Contract.
B. If a classification considered necessary by the Contractor for performance of the work is not listed on the applicable wage determination, the Contractor must initiate a request for approval of an additional classification along with the proposed wage and benefit rates for that classification.
C. The Contracting Officer will attach the appropriate Davis-Bacon wage determination to this
Contract. The Contractor is responsible for all requirements of the Davis-Bacon Act.
1.9 PROJECT LOCATION
The work is within the United States Section of the International Boundary and Water Commission
(USIBWC) Rio Grande Canalization Project, in Doña Ana County, New Mexico.
1.10 INVESTIGATION OF SITE CONDITIONS
A. The Contractor, as well as their subcontractors, is urged to visit the jobsite and to become fully aware as to the existing conditions affecting the work to be performed under the Contract documents.
B. The Contractor shall be responsible for ensuring that all of its suppliers, manufactures, and subcontractors have reviewed all applicable Contract documents relative to their work. The
Contractor shall provide all labor, material, equipment, and services not provided by the
Contractor’s suppliers, manufacturers, fabricators, and/or subcontractors but required for complete and operable facilities as described in the Contract documents.
1.11 OTHER CONTRACTUAL REQUIREMENTS
A. Items mentioned in the Technical Specifications and not shown on the Drawings, or shown on the
Drawings and not mentioned in the Technical Specifications, shall be of like effect as if shown or mentioned in both.
B. In any case where these Technical Specifications conflict with the Federal Acquisition Regulations
(FAR), use the following rules of precedence.
1. In any case where FAR requirements are stricter or impose a higher standard than these
Technical Specifications, FAR requirements will take precedence.
2. In any case where Technical Specification requirements are stricter or impose a higher standard than the FAR, Technical Specification requirements will take precedence.
01.11.00-Page 4 USIBWC Solicitation 191BWC18B0004
PART 2 - PRODUCTS
2.1 GOVERNMENT FURNISHED MATERIALS
The Government will not provide any materials for this project.
2.2 PRODUCTS TO BE FURNISHED BY THE CONTRACTOR
A. The Contractor shall provide all labor, all equipment, and all other products required to execute the project.
B. All materials provided by the Contractor for the project shall be new or recycled, high grade, free from defects, meeting the specifications herein. The minimum quality of the work shall be in accordance with the specifications herein. The Contractor's Quality Control System Manager will ensure compliance confirmation and the Contractor's testing company will ensure that materials, equipment, and work quality strictly adhere to the requirements of the Contract documents.
C. Materials, equipment, and work quality not conforming to the requirements of these specifications shall be considered defective and will be subject to rejection. Defective work material, whether in place or not, or equipment shall be removed immediately from the site by the Contractor, at its expense, when so directed by the COR.
D. If the Contractor fails to replace any defective or damaged work, materials, or equipment after receiving notice, the COR may cause such work or materials to be replaced by other forces. The replacement expense shall be deducted from the amount to be paid to the Contractor. Defective equipment will not be allowed in the performance of any work.
E. Water for All Construction Activities
1. The water required for all construction activities including, but not limited to, dust control
(Section 01.57.13), shall be considered as incidental and shall be provided from a metered source that is compliance confirmed by the USIBWC.
a. See Section 01.51.00 for requirements of weekly meter reading reports.
2. Water from the Rio Grande shall not be used by the Contractor at any time.
3. Water use must be in accordance with New Mexico water law.
PART 3 - EXECUTION
3.1 SUBMITTALS REQUIRED PRIOR TO MOBILIZATION
A. Specific sections detail submittal requirements. The list below are the submittals required prior to full mobilization, and prior to starting construction activities.
1. Progress Schedule (Section 01.32.16)
2. Scheduler Qualifications (Section 01.32.16)
3. Video and Photographs of Existing Conditions (Section 01.32.33)
4. Submittal Register (Section 01.33.00)
5. Accident Prevention Plan and applicable AHAs (Section 01.35.23)
6. Site Safety and Health Officer Qualifications (Section 01.35.23)
7. Employee First-Aid and CPR Training Records (Section 01.35.23)
8. Quality Control Plan (Section 01.45.00)
USIBWC Solicitation 191BWC18B0004 01.11.00-Page 5
9. Contractor Quality Control System Manager Qualifications (Section 01.45.00)
10. Staging Area/Haul Routes/Trailer Location/Storage (Section 01.52.13 and 01.57.00)
11. SWPP Plan (Section 01.57.13)
12. Resource Conservation Construction Plan (Section 01.74.19)
13. Flood Protection Plan (Section 02.02.00)
14. Preconstruction Survey (Section 02.21.00)
B. Once these required submittals have been compliance confirmed by the COR, the Contractor will be allowed to mobilize and begin work within USIBWC's right-of-way.
3.2 USE OF RIGHT-OF-WAY
A. Construction operations shall be confined to the USIBWC right-of-way. Portions of the site beyond areas on which the work is to be performed are not to be disturbed.
B. Roads serving the right-of-way, identified as such or not, owned by the USIBWC or CBP shall be clear and available to these agencies.
C. It is the Contractor’s responsibility to locate…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.