This document is a Facility Planning Report for the Cascades Job Corps Center located in Sedro-Woolley, Washington. The report provides details on the current status of the campus, including the existing site layout, building and structure conditions, space utilization, environmental elements, and identified deficiencies.

The key details are:

  • The Cascades Job Corps Center has a planned on-board strength of 300 students, consisting of 180 residential male and 120 residential female students.
  • The center includes 24 buildings and 20 structures, with the majority constructed between 1922-1965. The buildings are in generally good condition, with some deficiencies noted in areas such as the roofing, HVAC systems, and electrical systems.
  • The campus has sufficient space for housing, education, food service, recreation, medical/dental, administration, and storage/support functions. However, some spaces do not fully meet recommended standards.
  • The site includes utility systems such as water, sewer, electrical, and HVAC, which are generally in good condition with some maintenance needs identified.
  • The report includes detailed surveys, assessments, and supporting documentation for the center's facilities.

View the file

Other files

File Type Posted
J.9 (Revised Facility Survey Volume 1).pdf PDF
Questions and Answers for Cascades (10-25-2024).xlsx XLSX spreadsheet
Lease Agreement.pdf PDF
Amendment 4.pdf PDF
J-1 (Further Revised Price Detail Template 10-17-2024).xlsx XLSX spreadsheet
Amendment 3.pdf PDF
Amendment 2.pdf PDF
J-1 (Revised Price Detail Template).xlsx XLSX spreadsheet
Amendment 1.pdf PDF
Solicitation for Cascades 09-27-2024.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CASCADES

Job Corps Center Sedro-Woolley, WA

Facility Planning Report (Public) Supporting Data

Volume II

Final February 2024

CASCADES JOB CORPS CENTER

PY2023 FACILITY SURVEY REPORT

VOLUME II – TABLE OF CONTENTS

1.0 EXECUTIVE SUMMARY

2.0 SITE LAYOUT AND PLANS

Location Map

Existing Site Plan

3.0 DESCRIPTIONS

Buildings and Structures

Space Utilization by function

Environmental Management Report

Radon Report

Site Description

Building Descriptions and Structures, Floor Plans

4.0 DEFICIENCIES

APPENDICES – CORRESPONDENCE AND REPORTS

APPENDIX A

APPENDIX B

Life Safety Deficiencies and List

APPENDIX C

O&M Deficiencies List i

Survey Brief

NSF by Building

Dorm Bed Capacity

Asbestos Report

Student Questionnaire

Page Intentionally Left Blank ii

1.0 EXECUTIVE SUMMARY

1.0 EXECUTIVE

SUMMARY

EXECUTIVE SUMMARY

The Program Year 2023 facility survey for Cascades Job Corps Center was completed the week of October 16, 2023. The information presented in Volume I, Supporting Data, represents the current status of the campus.

The information includes the following:

• Existing site layout

• Overall status of existing building and structures

• Space utilization by building and function compared to recommended standards

• Status of environmental elements of the Center’s operations

• Details on the site and buildings and structures based on architectural, electrical, and mechanical survey and supporting documentation

• Presentation of the status of historical deficiencies and compilation of deficiencies documented through this survey

• Supporting documentation, as presented in the appendices of the center review meeting; survey brief and student questionnaire; life safety IA/IIA transmittal; and active warranties

Section 1.0 of this volume addresses site layout and plans while Section 2.0 presents details on the buildings and structures. Section 3.0 presents deficiencies and their status as well as new ones identified in this survey. The appendices provide additional information as noted below:

• Appendix A. Survey Brief Questionnaire

• Appendix B. Life Safety Deficiencies and List

• Appendix C. O&M Deficiencies List

2.0 SITE LAYOUT

AND PLANS

Page Intentionally Left Blank

3.0 DESCRIPTIONS

3.0 DESCRIPTIONS

BUILDINGS AND STRUCTURES

01003 CASCADES 01/24/2024

Page: 1 of Date:

0010 - RECREATION/GYMNASIUM

0010A - SECURITY SHACK

0012 - MOUNT RAINIER DORMITORY

0013 - DINING HALL

0015 - ACADEMICS/EVERGREEN DORMITORY

0016 - CHALLENGER DORMITORY

0017 - WHITEWATER DORMITORY

0024 - REGISTRARS OFFICE

0025 -VOCATIONAL

0026 - MAINTENANCE STORAGE

0027E - WAREHOUSE/RECEIVING

0027W- MEDICAL ASSISTANT/MEDICAL OFFICE

SPECIALIST

0028 - CENTER MAINTENANCE SHOP

0029 - MAINTENANCE EQUIPMENT STORAGE

0030 - CULTURAL CENTER

0031 - VOCATIONS BUILDING

0032 - ADMINISTRATION/EDUCATION/MEDICAL-DENTAL

0033A - FORMER STORAGE (VACANT)

0033B - TEAP MEETING ROOM

0034 - SECURITY/SAFETY

0048 - LEARNING RESOURCE CENTER/LIBRARY

0050 - WAREHOUSE STORAGE A

0057 - ADMISSIONS AND PLACEMENT

0063 - TRACTOR SHED

0051 - WAREHOUSE STORAGE B (74FT X 25FT)

0053 - STORAGE (8FT X 15FT)

0054 - STORAGE (24FT X 64FT)

0056 - ELECTRICAL MOCK-UP (15FT X 25FT)

0057A - GAZEBO (15FT DIAMETER)

0057B - GAZEBO (15FT DIAMETER)

0057C - GAZEBO (15FT DIAMETER)

0057D - GAZEBO (15FT DIAMETER)

0057E - PAVILION (35FT DIAMETER)

0057F - PAVILION (35FT DIAMETER)

0058 - CARPORT (20FT X 30FT)

0059 - CEMENT MASONRY MOCK-UP (16FT X 30FT)

0061 - STORAGE (7FT X 8FT)

0062 - STORAGE (12FT X 20FT)

0064 - GREENHOUSE (25FT X 44FT)

0065 - TRANSFORMER BUILDING (8FT X 8FT)

0067 - ELECTRICAL MOCK-UP (20FT X 21FT)

0068 - CARPORT (10FT X 12FT)

0069 - GAS FILLING STATION

0070 - SHED (12FT X 20FT)

Name GSF

15,740

17,560 26,880 17,560 18,220 29,800 2,100 2,100 7,500

12,750 13,230

3,600 1,590

11,040 13,980 31,240 1,140

1,010 1,850 1,800 1,580 1,200 1,850

1,560

1,050 1,050

1,100

Active Active Active Active Active Active Active Active Active Active Active Active

Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active Active

StatusType

Building Building Building Building Building Building Building Building Building Building Building Building

Building Building Building Building Building Building Building Building Building Building Building Building Structure Structure Structure Structure Structure Structure Structure Structure Structure Structure Structure Structure Structure Structure Structure Structure Structure Structure Structure Structure

Use Group Built Flrs Const

Assembly Business Residential Assembly Residential Residential Residential Business Business Storage Storage Business

Business Storage Assembly Business Business Business Business Business Business Business Business Storage Storage Storage Storage Business Assembly Assembly Assembly Assembly Assembly Assembly Storage Business Storage Storage Utility/Misc.

Utility/Misc.

Business Storage Utility/Misc.

Storage

Fair Good Good Good Good Good Good Good Good Fair

Good Good

Good Fair

Good Good Good Fair Fair

Good Good Fair

Good Fair Fair Fair

Good Good Good Good Good Good Good Good Poor Good Fair Fair Fair

Good Good Good Good Good

Condition

24 234,130

20 10,020

44 244,150

Buildings

Structures

Total

GSF

GSF

GSF

Summary

01/24/2024

Space Utilization By Function 01003 Cascades Page: 1 of 2

HOUSING

EDUCATION

FOOD SERVICE

RECREATION

SUGGESTED

NSF/

ENROLLEE

SUGGESTED

TOTAL

NSF

ACTUAL

TOTAL

NSF

TYPE OF SPACE

SUB TOTAL

SUB TOTAL

SUB TOTAL

SUB TOTAL

Resident Men Resident Women Total Residents

Date:

Residents Non Residents Total Students

(300)

(300)

(300)

(300)

DIFFERENCE

32,400

16,850

7,800

15,000

43,265

38,020

13,508

15,491

Lounge Other Shower/Toilet Sleeping excl. SPD(121 rooms; 316 beds) Storage

Academic (300) Non-Academic

30 -- ACT (Off-Ctr) 15 -- Advanced A + Administrator 50 -- Cert. Nursing Asst.

30 -- Computer Tech. Network + 150 -- IT Pathway 50 -- Medical Assistant 50 -- Medical Office Specialist

Dining (1 Serving) Food Preparation Food Storage

Arts & Crafts Gymnasium Pool Hall Recreation Office Recreation Room Student Store T.V. Room Weight Room

4,171 4,073 5,892

24,659 4,470

7,430 7,412

1,952 3,812

10,938 2,695 3,781

5,772 5,573 2,163

1,463 7,770 1,970 1,417

1,395

3,000 2,400 3,600

21,600 1,800

3,000 3,000

2,000

4,500 1,500 1,500

4,800 1,800 1,200

1,171 1,673 2,292 3,059 2,670

4,430 4,412

1,502 1,812

6,438 1,195 2,281

3,773

Vocations

RESIDENT

NON-RESIDENT

(300)

(0) 15

50 15,000

10,865

21,170

5,708

01/24/2024

Space Utilization By Function 01003 Cascades Page: 2 of Date:

MEDICAL/DENTAL

ADMINISTRATION

STORAGE/SUPPORT

SECURITY

VACANT

SUGGESTED

NSF/

ENROLLEE

SUGGESTED

TOTAL

NSF

ACTUAL

TOTAL

NSF

TYPE OF SPACE

SUB TOTAL

SUB TOTAL

SUB TOTAL

SUB TOTAL

SUB TOTAL

TOTAL 310.07 93,020 162,227

(300)

(300)

(300)

(300)

(0)

DIFFERENCE

234,130

0.69

TOTAL GSF

NET TO GROSS RATIO

2,070

12,000

6,000

4,682

11,655

29,292

5,594

Medical/Dental

Administration Outreach

Operations & Maintenance Warehouse

SECURITY

Vacant

6.9

4,682

5,898 5,757

2,570 26,722

5,594

2,070

6,000 6,000

2,400 3,600

2,612

-102 -243

23,122

-180

2,612

-345

23,292

-180

5,594

69,207

Net Square Footage By Building Page: 1 of 4

Date: 01/24/2024Center: CASCADES (01003)

HOUSING

Sleeping excl. SPD

Lounge

Storage

Shower/Toilet

Other

Function Suggested

NSF

3,296 7,366 5,948 8,049

1,439 1,438

3,150

1,400 1,468 2,363

1,534 1,139 1,070

0015 - ACADEMICS/EVERGREEN DORMITORY

0016 - CHALLENGER DORMITORY

0012 - MOUNT RAINIER DORMITORY

0017 - WHITEWATER DORMITORY

0012 - MOUNT RAINIER DORMITORY

0015 - ACADEMICS/EVERGREEN DORMITORY

0017 - WHITEWATER DORMITORY

0016 - CHALLENGER DORMITORY

0016 - CHALLENGER DORMITORY

0015 - ACADEMICS/EVERGREEN DORMITORY

0012 - MOUNT RAINIER DORMITORY

0017 - WHITEWATER DORMITORY

0017 - WHITEWATER DORMITORY

0016 - CHALLENGER DORMITORY

0012 - MOUNT RAINIER DORMITORY

0015 - ACADEMICS/EVERGREEN DORMITORY

0017 - WHITEWATER DORMITORY

0012 - MOUNT RAINIER DORMITORY

0016 - CHALLENGER DORMITORY

0015 - ACADEMICS/EVERGREEN DORMITORY

Bldg Name Actual NSF Difference

24,659

4,171

4,470

5,892

4,073

Sub Total: 43,265

21,600

3,000

1,800

3,600

2,400

32,400

3,059

1,171

2,670

2,292

1,673

( 300

10,865

13 rooms; 43 beds 40 rooms; 104 beds 29 rooms; 84 beds 39 rooms; 85 beds

Net Square Footage By Building Date: 01/24/2024 Page: 2

Center: CASCADES (01003) of 4

EDUCATION

FOOD SERVICE

Academic

Medical Assistant

Non-Academic

Advanced A + Administrator

Medical Office Specialist

Cert. Nursing Asst.

IT Pathway

Food Preparation

Food Storage

Dining (1 Serving)

Function Suggested

NSF

2,398

2,238 1,607

2,042

1,160

4,202

1,952

2,427 1,354

3,812

10,938

5,573

2,163

5,772

0015 - ACADEMICS/EVERGREEN DORMITORY

0032 - ADMINISTRATION/EDUCATION/MEDICAL-DENTAL

0032 - ADMINISTRATION/EDUCATION/MEDICAL-DENTAL

0032 - ADMINISTRATION/EDUCATION/MEDICAL-DENTAL

0032 - ADMINISTRATION/EDUCATION/MEDICAL-DENTAL

0031 - VOCATIONS BUILDING

0027W- MEDICAL ASSISTANT/MEDICAL OFFICE SPECIALIST

0017 - WHITEWATER DORMITORY

0048 - LEARNING RESOURCE CENTER/LIBRARY

0015 - ACADEMICS/EVERGREEN DORMITORY

0048 - LEARNING RESOURCE CENTER/LIBRARY

0032 - ADMINISTRATION/EDUCATION/MEDICAL-DENTAL

0027W- MEDICAL ASSISTANT/MEDICAL OFFICE SPECIALIST

0027W- MEDICAL ASSISTANT/MEDICAL OFFICE SPECIALIST

0031 - VOCATIONS BUILDING

0027W- MEDICAL ASSISTANT/MEDICAL OFFICE SPECIALIST

0031 - VOCATIONS BUILDING

0013 - DINING HALL

0013 - DINING HALL

0013 - DINING HALL

Bldg Name Actual NSF Difference

7,430

2,695

7,412

1,952

3,781

3,812

10,938

5,573

2,163

5,772

Sub Total:

Sub Total:

38,020

13,508

3,000

1,500

3,000

1,500

2,000

4,500

1,800

1,200

4,800

15,950

7,800

4,430

1,195

4,412

1,502

2,281

1,812

6,438

3,773

22,070

5,708

Page: 3

Center: CASCADES (01003) of 4

RECREATION

MEDICAL/DENTAL

ADMINISTRATION

Arts & Crafts

Gymnasium

Weight Room

Student Store

Pool Hall

Recreation Room

T.V. Room

Recreation Office

Medical/Dental

Administration

Outreach

Function Suggested

NSF

1,463

7,770

1,395

1,970

4,192

5,438

3,951

1,466

0010 - RECREATION/GYMNASIUM

0010 - RECREATION/GYMNASIUM

0010 - RECREATION/GYMNASIUM

0030 - CULTURAL CENTER

0030 - CULTURAL CENTER

0030 - CULTURAL CENTER

0030 - CULTURAL CENTER

0010 - RECREATION/GYMNASIUM

0030 - CULTURAL CENTER

0032 - ADMINISTRATION/EDUCATION/MEDICAL-DENTAL

0033B - TEAP MEETING ROOM

0032 - ADMINISTRATION/EDUCATION/MEDICAL-DENTAL

0027E - WAREHOUSE/RECEIVING

0032 - ADMINISTRATION/EDUCATION/MEDICAL-DENTAL

0031 - VOCATIONS BUILDING

0057 - ADMISSIONS AND PLACEMENT

Bldg Name Actual NSF Difference

1,463

7,770

1,395

1,970

1,417

4,682

5,898

5,757

Sub Total:

Sub Total:

Sub Total:

15,491

4,682

11,655

2,070

6,000

6,000

15,000

2,070

12,000

2,612

-102

-243

2,612

-345

Page: 4

Center: CASCADES (01003) of 4

STORAGE/SUPPORT

SECURITY

VACANT

Warehouse

Operations & Maintenance

SECURITY

Vacant

Function Suggested

NSF

8,634

11,899 1,627 3,742

1,545 1,025

1,600 2,002

1,211

0026 - MAINTENANCE STORAGE

0027W- MEDICAL ASSISTANT/MEDICAL OFFICE SPECIALIST

0027E - WAREHOUSE/RECEIVING

0050 - WAREHOUSE STORAGE A

0028 - CENTER MAINTENANCE SHOP

0029 - MAINTENANCE EQUIPMENT STORAGE

0063 - TRACTOR SHED

0034 - SECURITY/SAFETY

0010A - SECURITY SHACK

0025 -VOCATIONAL

0024 - REGISTRARS OFFICE

0033A - FORMER STORAGE (VACANT)

0013 - DINING HALL

Bldg Name Actual NSF Difference

26,722

2,570

5,594

Sub Total:

Sub Total:

Sub Total:

29,292

5,594

3,600

2,400

6,000

23,122

-180

5,594

23,292

-180

5,594

Center CASCADES (01003)

Dorm Bed Capacity Date: 01/24/2024

Page: 1 of 6

Female

Resident Student

Non Resident Student Total 150

Male

Contract Strength 300 as of 01/03/2020 On Board Strength 150 as of 10/10/2023

Resident Student

Non Resident Student Total

Female Male

Total

Total

0012 - MOUNT RAINIER DORMITORY

0015 - ACADEMICS/EVERGREEN DORMITORY

0012 - MOUNT RAINIER DORMITORY

1st Floor - East Wing

1st Floor - Main Hallway

1st Floor - West Wing

2nd Floor - East Wing

2nd Floor - Main Hallway

2nd Floor - West Wing

0015 - First Floor

2nd Floor - East Wing

2nd Floor - Main Hall

2nd Floor - West Wing

Physical Capacity

#Rooms #Beds

Male

Male

Male

Male

Male

Male

Male

Male

Gender

Gender

Gender

Current Occupancy of Rooms

#Students Vacant Beds (Need Repairs)

Vacant Beds (Due to OBS)

Vacant Beds (due to no Furn)

Reason For Less than Full Occupancy

Building Name Wing Name Gender

CASCADES (01003)Center

Date: 01/24/2024

Page: 2 of 6

Building Name Wing Name bed beds beds beds beds beds beds beds beds beds beds beds beds beds beds

SP

beds Total beds

150Resident Student Female

Non Resident Student 0 Total 150

Male

Contract Strength 300 as of 01/03/2020 On Board Strength 150 as of 10/10/2023

Resident Student

Non Resident Student Total

Female Male

Total

Total

0016 - CHALLENGER DORMITORY

0016 - CHALLENGER DORMITORY

1st Floor - East Wing

1st Floor - Main Hall

1st Floor - West Wing

2nd Floor - East Wing

2nd Floor - West Wing

2nd Floor Main Hall

Physical Capacity

#Rooms #Beds

Male

Male

Male

Male

Male

Male

Male

Current Occupancy of Rooms

#Students Vacant Beds (Need Repairs)

Vacant Beds (Due to OBS)

Vacant Beds (due to no Furn)

Reason For Less than Full Occupancy

40 104 69

35 0 0

Building Name Wing Name

Gender

Date: 01/24/2024

Page: 3 of 6

Building Name Wing Name bed beds beds beds beds beds beds beds beds beds beds beds beds beds beds

SP

beds Total beds

150Resident Student Female

Non Resident Student 0 Total 150

Male

Contract Strength 300 as of 01/03/2020 On Board Strength 150 as of 10/10/2023

Resident Student

Non Resident Student Total

Female Male

Total

Total

0017 - WHITEWATER DORMITORY

0017 - WHITEWATER DORMITORY

1st Floor - East Wing

1st Floor - West Wing

2nd Floor - East Wing

2nd Floor - Main Hall

2nd Floor - West Wing

3rd Floor - East Wing

3rd Floor - Main Hall

3rd Floor - West Wing

Physical Capacity

#Rooms #Beds

Female

Female

Gender

Gender

Gender

Female

Female

Female

Current Occupancy of Rooms

#Students Vacant Beds (Need Repairs)

Vacant Beds (Due to OBS)

Vacant Beds (due to no Furn)

Reason For Less than Full Occupancy

39 85 68

17 0 0

121Grand Total 316 199 74 8 0

Building Name Wing Name

Gender

Date: 01/24/2024

Page: 4 of 6

0012 - MOUNT RAINIER

DORMITORY

0012 - MOUNT RAINIER

DORMITORY

0012 - MOUNT RAINIER

DORMITORY

0012 - MOUNT RAINIER

DORMITORY

0012 - MOUNT RAINIER

DORMITORY

0012 - MOUNT RAINIER

DORMITORY

0012 - MOUNT RAINIER

DORMITORY

0015 -

ACADEMICS/EVERGREEN

DORMITORY

0015 -

ACADEMICS/EVERGREEN

DORMITORY

0015 -

ACADEMICS/EVERGREEN

DORMITORY

0012 - MOUNT

RAINIER DORMITORY

1st Floor - East Wing

1st Floor - Main Hallway

1st Floor - West Wing

2nd Floor - East Wing

2nd Floor - Main Hallway

2nd Floor - West Wing

0015 - First Floor

2nd Floor - East Wing

2nd Floor - Main Hall

3 1

Building Name Wing Name bed beds beds beds beds beds beds beds beds beds beds beds beds beds beds

SP

beds

Total beds

Summary

150Resident Student Female

Non Resident Student 0 Total 150

Male

Contract Strength 300 as of 01/03/2020 On Board Strength 150 as of 10/10/2023

Resident Student

Non Resident Student Total

Female Male

Total

Total

Gender

Male

Male

Male

Male

Male

Male

Male

Male

Gender N

Gender N

Date: 01/24/2024

Page: 5 of 6

0015 -

ACADEMICS/EVERGREEN

DORMITORY

0016 - CHALLENGER

DORMITORY

0016 - CHALLENGER

DORMITORY

0016 - CHALLENGER

DORMITORY

0016 - CHALLENGER

DORMITORY

0016 - CHALLENGER

DORMITORY

0016 - CHALLENGER

DORMITORY

0016 - CHALLENGER

DORMITORY

0017 - WHITEWATER

DORMITORY

2nd Floor - West Wing

0016 - CHALLENGER

DORMITORY

1st Floor - East Wing

1st Floor - Main Hall

1st Floor - West Wing

2nd Floor - East Wing

2nd Floor - West Wing

2nd Floor Main Hall

0017 - WHITEWATER

DORMITORY

Building Name Wing Name bed beds beds beds beds beds beds beds beds beds beds beds beds beds beds

SP

beds

Total beds

Summary

150Resident Student Female

Non Resident Student 0 Total 150

Male

Contract Strength 300 as of 01/03/2020 On Board Strength 150 as of 10/10/2023

Resident Student

Non Resident Student Total

Female Male

Total

Total

Gender

Gender N

Male

Male

Male

Male

Male

Male

Male

Date: 01/24/2024

Page: 6 of 6

0017 - WHITEWATER

DORMITORY

0017 - WHITEWATER

DORMITORY

0017 - WHITEWATER

DORMITORY

0017 - WHITEWATER

DORMITORY

0017 - WHITEWATER

DORMITORY

0017 - WHITEWATER

DORMITORY

0017 - WHITEWATER

DORMITORY

0017 - WHITEWATER

DORMITORY

1st Floor - East Wing

1st Floor - West Wing

2nd Floor - East Wing

2nd Floor - Main Hall

2nd Floor - West Wing

3rd Floor - East Wing

3rd Floor - Main Hall

3rd Floor - West Wing

Building Name Wing Name bed beds beds beds beds beds beds beds beds beds beds beds beds beds beds

SP

beds

Total beds

19 74 117 100 6Total Beds:

Summary

150Resident Student Female

Non Resident Student 0 Total 150

Male

Contract Strength 300 as of 01/03/2020 On Board Strength 150 as of 10/10/2023

Resident Student

Non Resident Student Total

Female Male

Total

Total

Gender

Female

Female

Gender N

Gender N

Gender N

Female

Female

Female

Environmental Management Report

Center: CASCADES (01003) Page: 1 Date: 01/24/2024 of 1

SOLID & HAZARDOUS WASTE MANAGEMENT (RCRA)

HAZARDOUS MATERIALS STORAGE (EPCRA)

PETROLEUM UNDERGROUND STORAGE TANKS (RCRA)

N/A0

PETROLEUM ABOVEGROUND STORAGE TANKS (CWA)

ASBESTOS AND PCB MANAGEMENT (TSCA)

AIR POLLUTION CONTROL (CAA)

N/A None

Attainment

Solid Waste Disposal :

Hazardous Waste Generator :

Hazardous Waste ID :

Generator Classification :

Hazardous Materials Storage :

Hazardous Materials ID :

HazMat Storage Area :

Number of Regulated USTs :

Number of Un-regulated USTs :

HazMat Spill Response Plan :

Local Hazardous Use Permit :

LEPC Notification :

EPA Generator ID Number :

Hazardous Waste Disposal :

RCRA Compliance :

Capacity LocationID Fuel Type

Asbestos Survey Date :

Asbestos Type :

PCB Transformer Testing :

PCB Transformers :

PCB-Contaminated Transformers :

Transformers Labelled :

Regional Air Quality :

Permitted Air Pollution Source :

Source Description :

Commercial Waste Service Rural Skagit Sanitation Yes Organic solvent (< 25 gals/month)

Conditionally Exempt Small Quantity Generator N/A Commercial Hazardous Waste Disposal Service Various licensed contractors

Yes Oil-based paint (200 gals), organic solvent (100 gals), propane (250 gals)

Building 29 Yes No No

Prevention/Detection Overfill Leak Corrosion

SPCC Plan Required : SPCC Plan Completed :

Number of ASTs : 1

No N/A

01/17/1991 Friable/Non-Friable

Yes

Yes

ID Fuel Type Capacity Location Overfill

Prevention Secondary Containment

1 Petroleum - Gasoline 500 Near Building 26 Yes Yes

Tank Status Active

Tank Status

Asbestos-Containing Materials Inventory Page: 1 of 2 Date: 01/24/2024Center : Cascades (01003)

Bldg System Floor Finishes Floor Finishes Roof Repair/Replacement

Bldg System Floor Finishes Floor Finishes Floor Finishes Floor Finishes

Bldg System Roof Repair/Replacement

Bldg System Floor Finishes Floor Finishes

Bldg System Roof Repair/Replacement Wall Finishes Floor Finishes

Bldg System Floor Finishes

Category Description 12x12 floor tile, brown/tan 9x9 floor tile, brown/white Roof flashing

Category Description 9x9 floor tile, gray 9x9 floor tile, tan/black 12x12 floor tile, brown/white 9x9 floor tile, tan

Category Description Roofing felt

Category Description 12x12 flr. tile, tan (covered) 12x12 floor tile, tan

Category Description Roof flashing Asbestos cement board 12x12 floor tile, tan

Category Description 12x12 floor tile, tan

Sq. Ft.

Sq. Ft.

Sq. Ft.

Sq. Ft.

Sq. Ft.

Sq. Ft.

Sq. Ft.

Sq. Ft.

Sq. Ft.

Sq. Ft.

Sq. Ft.

Sq. Ft.

Sq. Ft.

Sq. Ft.

Unit

Unit

Unit

Unit

Unit

Unit

Quantity

Quantity

Quantity

Quantity

Quantity

Quantity

Location Weight room office Hallway, arts/crafts Around vent stacks

Location Lobby storage room 1st fl. jan. closet Stairwell landings 1st fl. closet, SW

Location Culinary arts roof

Location Dorm rooms, hallways 1st fl. jan. closet

Location Around vent stacks Plaster vocation Bathroom, office

Location Bathroom, paint shop

12000

10000

Building :

Building :

Building :

Building :

Building :

Building :

0010 - RECREATION/GYMNASIUM

0012 - MOUNT RAINIER DORMITORY

0013 - DINING HALL

0016 - CHALLENGER DORMITORY

0027W- MEDICAL ASSISTANT/MEDICAL OFFICE SPECIALIS

0031 - VOCATIONS BUILDING

Asbestos-Containing Materials Inventory

Date: 01/24/2024Center : Cascades (01003) Page: 2 of 2

Floor Finishes Floor Finishes Heating Floor Finishes Roof Repair/Replacement Floor Finishes Floor Finishes

Floor Finishes

Bldg System

Bldg System

12x12 floor tile, tan 12x12 floor tile, gray Pipe fitting insulation 9x9 floor tile, green Roof flashing 9x9 floor tile, green/white 9x9 floor tile, tan/gray

9x9 floor tile, tan/red

Category Description

Category Description

Sq. Ft.

Sq. Ft.

Ea.

Sq. Ft.

Lin. Ft.

Sq. Ft.

Sq. Ft.

Sq. Ft.

Location

Location

Unit

Unit

Quantity

Quantity

Vocational office Storage/Support Storage/Support Medical hallway Rooftop HVAC units East wing Southwest wing

Detention/isolation

14000 12500

Building :

Building :

0032 - ADMINISTRATION/EDUCATION/MEDICAL-DENTAL

0034 - SECURITY/SAFETY

Radon

Page: 1 of 2

0010 - RECREATION/GYMNASIUM

0010A - SECURITY SHACK

0012 - MOUNT RAINIER DORMITORY

0013 - DINING HALL

0015 - ACADEMICS/EVERGREEN DORMITORY

0016 - CHALLENGER DORMITORY

0017 - WHITEWATER DORMITORY

0024 - REGISTRARS OFFICE

0025 -VOCATIONAL

0026 - MAINTENANCE STORAGE

0027E - WAREHOUSE/RECEIVING

0027W- MEDICAL ASSISTANT/MEDICAL OFFICE SPE

0028 - CENTER MAINTENANCE SHOP

0029 - MAINTENANCE EQUIPMENT STORAGE

0030 - CULTURAL CENTER

0031 - VOCATIONS BUILDING

0032 - ADMINISTRATION/EDUCATION/MEDICAL-DENT

0033A - FORMER STORAGE (VACANT)

0033B - TEAP MEETING ROOM

0034 - SECURITY/SAFETY

0048 - LEARNING RESOURCE CENTER/LIBRARY

0050 - WAREHOUSE STORAGE A

0057 - ADMISSIONS AND PLACEMENT

0063 - TRACTOR SHED

Bldg Name

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

05/23/1990

11/02/2004

Test Date

Yes

No

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

No

Yes

No

N/A

Radon Testing

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

< 4 pCi

Test Result

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Mitigation Mitigation Date

Radon

Page: 2 of 2

RADON EXPLANATORY NOTES

The US Environmental Protection Agency (EPA) has established a radon action level of 4.0 picoCuries per liter (pCi/L). Occupied buildings with radon concentrations less than 4.0 pCi/L do not require radon mitigation; un-occupied buildings, or those buildings which are occupied only infrequently for brief periods of time, also do not require radon mitigation. Occupied buildings with radon concentrations greater than

4.0 pCi/L require radon mitigation and verification of radon reductions as soon as possible, with priority given to dormitories and student recreation buildings. Occupied buildings with radon concentrations greater than 20.0 pCi/L should be considered significant radon exposure hazards, and priority for mitigation should be given to buildings with these highly elevated radon concentrations.

Radon mitigation techniques include: (1) adjustment of the building HVAC system to create a positive pressure within the building; (2) sealing of foundation wall cracks, penetrations, or other openings;

(3) sealing crawlspace openings and sump pits; (4) installing an active subslab depressurization (ASD) system.

Site Description

Aerial view of Cascades JCC

Page: 1 Date: 02/14/2024 of 4

Comments:

Paving Type for Roads & Parking

A gravel road loops around Building 33A. Parking areas located between Administration/Education/Medical-Dental Building 32 and Vocations Building 31 and near Dining Hall Building 13 and Dormitory Buildings 15, 16 and 17 are concrete. Visitor parking at west side of Security/Safety Building 34 is compacted dirt road.

Paving Type for Sidewalks

Asphalt Concrete

Comments:

Topography Buildings and Structures

Center is not fully enclosed by fencing. A chain link fence with lockable gates secures the area of vocational buildings at the north-east side of campus. The site has an abundance of mature trees and well maintained green space and other plantings.

ROADS, PARKING & SIDEWALKS

Water Source Water Authority Service Meter On-Site Treatment Plant

1. Water System

Treatment Type Storage Type Storage Capacity(Gallons)

NoIndividualSkagit County Public Utility District No. 1.Public Water Authority

None 0None

Water is metered at 8 locations for Job Corps buildings. Buildings 10, 12, 13, and 57 are individually metered, and all other buildings are zoned metered.

Comments:

Comments:

Fire Hydrants On-Site Water Supply Storage Capacity

(Gallons) Pressure Source FD Response Time

(Minutes)

Yes 0 4None Municipal

The Center is supported by the Sedro Woolley Fire Department, located at 325 Metcalf Street, Sedro Woolley, which is approximately 2.6 mile away and has an estimated response time of four minutes.

Number of Deficiencies = 4

Number of Deficiencies = 1

SITE FEATURES

UTILITIES

2. Fire Protection System

Buildings Structures24 20Flat

Surrounding

Outdoor Recreation

Forest

Basketball, Football, Soccer, Soft/Baseball, Volleyball Retention Pond, Two Bioswales, Underground Utility Tunnel System

Vocations Chain Link

Location Type

Maintenance Responsibility System Capacity Adequate System Condition

Lessor Lessor Yes Good

Separate Loop

No

Ownership Maintenance Responsibility System Capacity Adequate System Condition

Lessor Lessor Yes Good

Ownership

Roads & Parking Adequate Roads & Parking Condition Sidewalks Adequate Sidewalk Condition No Fair No Good

Number of Deficiencies = 1

Fencing

Other Features

Page: 2 Date: 02/14/2024 of 4

Comments:

Sewage Treatment Flow

The underground sewer from the Center flows into the publicly owned wastewater treatment plant by means of gravity and a lift station west of Administration Building 32.

Utility

Publicly Owned Treatment Works

Lessor

Gravity

Maintenance ResponsibilityOwnership

Comments: Propane is provided by Amerigas. A 500-gallon above-ground propane tank located in the northwest corner of Admission and Placement Building 57 provides natural propane gas to the building for heating.

Cascade Natural Gas Corporation

Comments: Steam is provided to the Center buildings from the on-site Lessor-operated power plant (Building 19). At most Center buildings, the steam is converted to hot water and used for space heating.

3. Sanitary Sewer System/ Sewage Treatment Plant

5. Fuel Distribution System

6. Central Plant

System Capacity Adequate System Condition

Yes Good

4. Storm Water System Number of Deficiencies = 4

Drain Type On-Site Storm Water Management

Underground Retention Pond

Ownership Maintenance Responsibility System Capacity Adequate System Condition

Lessor Yes GoodLessor

Gas Company Metering

Master

Ownership Maintenance Responsibility System Capacity Adequate System Condition

Lessor Lessor Yes Good

Type Energy Source

Steam Natural Gas Most Cascades JCC buildings.

Bldgs Served

Ownership Maintenance Responsibility Plant Capacity Adequate Plant Condition

Lessor Lessor Yes Good

Page: 3 Date: 02/14/2024 of 4

Comments:

Electric Company PCB Trans.

Transformer Mounting Transformer Ownership

Systems Ownership Maintenance Responsibility

Puget Sound Energy (PSE)

Service is brought to the center from the main switchgear located in the lessor's powerhouse. The 4.16/2.4 kV lines are routed through a loop of transformer vaults which are either above ground or underground in the tunnel.

From these vaults the secondary 120/208V, 3-phase, 4 wire system is distributed to DOL leased buildings via their respective service disconnects and/or main distribution panels. Some buildings have their own meter while others are zone metered. Dining Hall Building 13 and Dormitory Buildings 12, 15, 16 and 17 have backup power from an emergency generator in the powerhouse for critical loads such as condensate pumps and cooking equipment. The emergency backup power is metered separately.

Vault Utility

Lessor Lessor

No

Comments:

Telephone Company

On-site Line Owner

Six T-1 lines are brought to the main telephone/server room located in Building 32. Local telephone service is provided by Frontier Communication with a T-1 line connected to the router. Long distance calls are provided via Voice over Internet Protocol (VoIP) on the Job Corps Data Center network. The data and VoIP communication networks are routed via underground fiber optic cabling. A central fire alarm control/annunciator panel in Security Building 34 monitors fire alarm panels in Dining Hall Building 13, Warehouse/Receiving Building 27E, Medical Assistant/Medical Office Specialist Building 27W, and Dormitory Buildings 12, 15, 16, and 17. Other fire alarm panels at the center are monitored by lessor's central fire alarm control/annunciator panel in the powerhouse.

Comcast provides cable TV in all dormitory lounges and other recreational spaces at the center. The security system is limited to dormitories only with door alarms for unauthorized ingress/egress detection.

Frontier Communication

Maint. Responsibility

Center Center, Lessor

Door Alarms

4.16/2.4 kV, 3-Phase, 4 Wire

120/208V, 3-Phase, 4 WireUnderground

UndergroundPrimary Service

Secondary Service

Distribution Characteristics

Number of Deficiencies = 2

9. Electrical (Communication/Alarm/Security)

7. Electrical (Service)

Yes

Central

VOIP

System Capacity Adequate System Condition

GoodYes

Transformer Maint Resp

Utility

System Capacity Adequate System Condition

Yes Good

Generator

Diesel

8. Electrical (Site Lighting)

Roadways Parking Walkways Building Outdoor Sports

Mounting

Control

Pole Pole Pole Building Sport Light

Photocell, Time Clock Photocell, Time Clock Photocell Photocell Switch

System Ownership Maintenance Responsibility System Capacity Adequate System Condition

Center, Lessor Center, Lessor Yes Good

Comments: The site lighting system, consisting of building-mounted exterior and pole-mounted fixtures, is owned and maintained by the lessor. The site lighting system is controlled by photocells and time clocks.

ATS MTS

Yes No

Number of Deficiencies = 2

Number of Deficiencies = 3

Fire Alarm Security

Metering Individual and Groups

Page: 4 Date: 02/14/2024 of 4

ACCESSIBILITY

Yes

Comments:

UnknownYesYes

The site and nine buildings were listed on the National Historical Preservation Registry in December, 2010. The nine buildings are Mount Rainier Dormitory Building 12, Dining Hall Building 13, Academic/Evergreen Dormitory Building 15, Challenger Dormitory Building 16, Whitewater Dormitory Building 17, Registrars Office Building 24, Warehouse/Receiving Building 27E, Cultural Center Building 30 and Vocations Building 31.

Yes

Nationally Registered Site

Site Eligible for National Register

Located in Historic District

Archaeological Significance

04/01/1999

04/01/1999

Center

Center

Active

Active

Aboveground

Aboveground

Near Building 26

Near Building 57

Yes

Yes

Petroleum - Gasoline

Propane

STORAGE TANKS

TypeStatus Location Owner Fuel Type Capacity (Gallons) Install Date

Earthquake Risk

High Low LowMedium LowIBC Low

LightningEarthquake Def. Authority Flooding Tornado Hurricane Forest

Fire

ID

Reg.

Number of Deficiencies = 4

Number of Deficiencies = 1

Accessible Parking: Accessible Slope:

No

Curb Cuts:

Yes

Ramps:

YesYes

Site Accessible Route:

GENERAL SITE CONDITION

Rating X Good Fair Poor

The site is well maintained and in good condition.

HISTORIC PRESERVATION

NATURAL HAZARDS

The site condition is not impacting the functional use of the facilities.

The site condition IS impacting the functional use of the facilities.

The site condition IS SIGNIFICANTLY impacting the functional use of the facilities.

Equip/Veh Fueling

Heating

Purpose

Active Energy Use Reduction Program

Active Water Use Reduction Program

Approximate or Measured Waste Recycled

Use of Brightly or CMMS for Preventative Maintenance

Green Purchasing Policy Practiced

Site Stormwater Absorption Measures in Place

Center has Onsite Renewable Energy (PV or Wind)

Center has a Chartered Green Committee & Roster

Center Uses Green Cleaning Practices

SUSTAINABILITY

Comments: The Center currently uses the Brightly a Computerized Maintenance Management System (CMMS) for preventive maintenance.

Yes

Yes

NO

NO

Yes

Yes

Yes

Yes

50 %

Building Descriptions and Structures

BUILDING 10 - RECREATION/GYMNASIUM

WEIGHT ROOM ARTS &

CRAFTS

KILN ROOM

ARTS & CRAFTS

LOBBY

EXERCISE

ROOM/STORAGE

GYMNASIUM

MEN'S LOCKER

ROOM

WOMEN'S

LOCKER ROOM

W M

MECH. RM

SHOWERS

SHOWERS

MECH.

TV ROOM

OFFICES

JAN

STORAGE

LAUNDRY

STORAGE

BLEACHERS

TOILET

TOILET

ELEC.

ART SUPPLY

RECREATION/GYMNASIUM

BUILDING 10

0 10' 30' 60'

CASCADES JOB CORPS CENTER

SEDRO-WOOLLEY, WASHINGTON

RECREATION

Building Descriptions Date: 02/14/2024Center : Cascades (01003) Page: 1 of 117

Building: 0010 - RECREATION/GYMNASIUM

BUILDING ENVELOPE

Foundation RoofBuilding

Concrete Loadbearing Masonry Steel

CMU Masonry

Comments: There is stucco finish on the exterior walls.

Wall Roof None Batt

Metal Units - Metal Frame

AccessibilityFeature

GSF NSF Year Built Use Group Historic Ownership #Floors

Assembly 15,740 11,157 1 Leased 1963 Not Evaluated

REAL ESTATE

Access to Building Ramps Entrance 2nd Egress Visual Alarm Corridor/Aisle Rooms Stairs Elevator Restrooms Drinking Fountain Telephone

Yes N/A Yes Yes Yes Yes Yes N/A N/A Yes No N/A

ACCESSIBILITY

Structural Systems1.

Exterior Walls2. Number of Deficiencies = 3

Insulation4.

Exterior Doors5.

Material

Asbestos: Yes

The roof is old, and damaged. Roof life is estimated based on observation during the October 2023 Facility Survey.

Drainage Year Life

Type Area Served

Single Ply Interior Roof Drains, Scuppers 1996 0 Flat Entire Building

Number of Deficiencies = 2

Comments:

3. Roof

Entire Building

Area Served

Page: 2 of 117

Building: 0010 - RECREATION/GYMNASIUM

INTERIOR FINISH

Carpet Concrete Rubber Terrazzo Vinyl Tile Wood

Ceramic Tile Drywall Plaster

Metal Units - Metal Frame Metal Units - Wood Frame

Wood Units - Wood Frame

VERTICAL CIRCULATION

Metal Ladder Comments: There is a steel ladder to the roof hatch.

Casement - Wood Frame; Single Glazing; Fixed - Aluminum Frame; Double Glazing;

Sliding - Aluminum Frame; Double Glazing;

Acoustical Tile Exposed Structure Gypsum Board Plaster

Windows6.

Floors1. Asbestos: Yes Number of Deficiencies = 1

Interior Walls2.

3.

Interior Doors4.

Heat Source

Heat Distribution

Piping System

Control System

Fresh Air Intake

Energy Conservation

Measure

Area Served

Heating for the building is provided by seven vertical floor-mounted fan coil units, manufactured by McQuay with hot water heating coils.

There are two gas-fired water boilers, manufactured by Burnham (model P807NEI-E2, 396 MBH input, 316 MBH output, built in 10/2002) provide heating water circulated throughout the building by two in-line pumps located in the northwest mechanical room. Four wall-mounted heating and ventilating units with hot water heating coils serve the gymnasium.

Heating for the offices is provided by a ceiling mounted air handling unit with hot water heating coil.

Comments:

Comments:

Comments:

HVAC

Heat1.

Gas-Fired Hot Water Boiler

Gas-Fired Hot Water Boiler

Gas-Fired Hot Water Boiler

Radiator

Unit Ventilator

Single Duct

Two-Pipe

Two-Pipe

Two-Pipe

Electric

Electric

Electric

Natural

Mechanical

Natural

None

None

None

Recreation Area

Gymnasium

Recreation Area

Ceilings

Page: 3 of 117

Building: 0010 - RECREATION/GYMNASIUM

Mechanical

Mechanical

Mechanical

Mechanical

Toilet/Shower

Recreation

Kiln Area

Restroom

Comments:

Comments:

Comments:

Comments:

Roof-mounted exhaust fans ventilate the men’s and women’s toilet/showers rooms.

Roof-mounted exhaust fans ventilate the Arts and Crafts and Exercise Room/Storage.

Wall-mounted exhaust fan, manufactured by Nutone, (model 8170) ventilates the Kiln Room.

Roof-mounted exhaust fan ventilates the men’s and women’s restrooms.

Domestic hot water is provided by a gas-fired water heater, manufactured by A. O. Smith (model BTR 197 118, with an input heating capacity of 199 MBH, 100-gallon storage capacity, recovery rate of

192.96 GPH, built in 05/14/2002) located in the mechanical room.

Comments:

Cast-Iron None Cast-Iron

Electric Water Cooler Hose Bibb Lavatory Shower Sink Urinal Water Closet (Flush Valve)

Gas (Natural)

Ventilation Area Served

Copper Copper Gas-Fired None No

Hot Water Cold Water Water Heater Water Treatment HW Storage Tank

Grease InterceptorWaste / Vent Interior Storm

Packaged Direct

Expansion (Air Source)

Window Unit None Electric Natural None Recreation Area

PLUMBING

Exhaust Ventilation

Two window air conditioning units, manufactured by Whirlpool, model number ACM102XL0, provide DX-cooling to Arts and Craft.

Comments:

Ventilation2.

System Type

Number of Deficiencies = 1

Air Distribution

Piping System

Control System

Fresh Air Intake

Energy Conservation Area

Served

Water Distribution1.

Sanitary Distribution2.

Fixtures3.

Fuel Distribution4.

3. Number of Deficiencies = 1Air Conditioning

Page: 4 of 117

Building: 0010 - RECREATION/GYMNASIUM

None None ABC Type Fire Extinguisher

Comments: Service is brought from a 75 kVA pad-mounted transformer located outside the electrical room and terminates in a 225A main circuit breaker main distribution panel (MDP) located inside. A meter is installed next to the MDP. This transformer also serves Learning Resource Center/Library Building 48.

FIRE ALARM

Comments: The fire alarm control/annunciator panel is a Notifier SFP-1024 unit located in the main corridor. The building fire alarm system is monitored by the lessor's central fire alarm control/annunciator panel in the power house.

Service Entrance Electrical Characteristics Distribution Equipment Wiring Devices

Audible Alarm Control/Annunciator Panel Heat Detector Manual Pull Station Smoke Detector Visual Alarm

Comments: Recorded footcandle levels include natural light contribution.

High Intensity Discharge (HID) Comments: Exterior building-mounted and surrounding area pole-mounted light fixtures are controlled by time clock and photocells.

T8 - Fluorescent

T8 - Fluorescent

Compact Fluorescent

Compact Fluorescent

T8 - Fluorescent

T8 - Fluorescent

Compact Fluorescent

T8 - Fluorescent

T8 - Fluorescent

T8 - Fluorescent

Offices

Corridors & Stairs

Equipment Rooms (Elec/Mech)

Toilets

Storage Rooms

Classrooms

Shower

Gymnasium

Locker Room

Recreation

Area Recommended Recorded Light Type

Battery Backup Battery Backup

Main Distribution Panel 120/208V, 3-Phase, 4 Wire Panelboard Receptacles, GFCI, Switches

Sprinkler System Stand Pipe System Fire Suppression

Emergency Exit

Number of Deficiencies = 1

FIRE PROTECTION

ELECTRICAL SERVICES Number of Deficiencies = 1

Exterior Lighting1. Number of Deficiencies = 1

Interior Lighting2. Number of Deficiencies = 1

Emergency /Exit Lighting3. Number of Deficiencies = 2

LIGHTING

Page: 5 of 117

Building: 0010 - RECREATION/GYMNASIUM

Connected to Main System None Connected to Main System Local Cable Company

Telephone Security Public Address Television

GENERAL BUILDING CONDITION

Rating

Comments:

X Good Fair Poor

The single-ply membrane roof is at the end of its life expectancy.

COMMUNICATION

The facility condition is not impacting the functional use of the facility.

The facility condition IS impacting the functional use of the facility.

The facility condition IS SIGNIFICANTLY impacting the functional use of the facility.

Electric Water Gas Yes YesYes

BUILDING UTILITY METERING

Structure: Good Exterior: Fair Interior: Good Mechanical: Good Electrical: Good

Type Location N/A N/A

Not requared.

CARBON MONOXIDE DETECTION

Detection Required No

Number of Deficiencies = 0

IMPAIRMENT

Potentially Impaired

DOL Responded

DOL Determination

Potential Impaired Comments DOL Determination Discussion/Comments

BUILDING 10A - SECURITY SHACK

Page: 6 of 117

Building: 0010A - SECURITY SHACK

BUILDING ENVELOPE

Foundation RoofBuilding

Wall Roof

AccessibilityFeature

GSF NSF Year Built Use Group Historic Ownership #Floors

Business 80 1 Owned 2020 Not Evaluated

REAL ESTATE

Access to Building Ramps Entrance 2nd Egress Visual Alarm Corridor/Aisle Rooms Stairs Elevator Restrooms Drinking Fountain Telephone

N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A

ACCESSIBILITY

Structural Systems1.

Exterior Walls2.

Insulation4.

Exterior Doors5.

Windows6.

Material Drainage Year Life

Type Area Served

Asphalt Shingles 2020 27 Shed Entire Building

3. Roof

Page: 7 of 117

Building: 0010A - SECURITY SHACK

INTERIOR FINISH

Ventilation Area Served

No

Hot Water Cold Water Water Heater Water Treatment HW Storage Tank

Grease InterceptorWaste / Vent Interior Storm

VERTICAL CIRCULATION

PLUMBING

Exhaust Ventilation

Floors1.

Interior Walls2.

3.

Interior Doors4.

Heat Source

Heat Distribution

Piping System

Control System

Fresh Air Intake

Energy Conservation

Measure

Area Served

HVAC

Heat1.

Ventilation2.

System Type

Air Distribution

Piping System

Control System

Fresh Air Intake

Energy Conservation Area

Served

Water Distribution1.

Sanitary Distribution2.

Fixtures3.

Fuel Distribution4.

Ceilings

3. Air Conditioning

Page: 8 of 117

Building: 0010A - SECURITY SHACK

FIRE ALARM

Service Entrance Electrical Characteristics Distribution Equipment Wiring Devices

Telephone Security Public Address Television

Area Recommended Recorded Light Type

Sprinkler System Stand Pipe System Fire Suppression

Emergency Exit

GENERAL BUILDING CONDITION

Rating X Good

Fair Poor

FIRE PROTECTION

ELECTRICAL SERVICES

Exterior Lighting1.

Interior Lighting2.

Emergency /Exit Lighting3.

COMMUNICATION

The facility condition is not impacting the functional use of the facility.

The facility condition IS impacting the functional use of the facility.

The facility condition IS SIGNIFICANTLY impacting the functional use of the facility.

Electric Water Gas

UNKNOWN UNKNOWNUNKNOWN

BUILDING UTILITY METERING

Structure: Good Exterior: Good Interior: Good Mechanical: Good Electrical: Good

Type Location

CARBON MONOXIDE DETECTION

LIGHTING

Detection Required No

Number of Deficiencies = 0

Page: 9 of 117

Building: 0010A - SECURITY SHACK

IMPAIRMENT

Potentially Impaired

DOL Responded

DOL Determination

BUILDING 12 - MOUNT RAINIER DORMITORY

BASEMENT FLOOR

UP

UNEXCAVATED

UTILITY TUNNEL

UNEXCAVATED

UNEXCAVATED

STORAGE

STORAGE

(VACANT)

BUILDING 12

0 10' 20' 40'

CASCADES JOB CORPS CENTER

SEDRO-WOOLLEY, WASHINGTON

MOUNT RAINIER DORMITORY

VACANT

Page: 10 of 117

Building: 0012 - MOUNT RAINIER DORMITORY

BUILDING ENVELOPE

Foundation RoofBuilding

Concrete Concrete and Clay Tile Block

Wood w/Conc.Truss Frame

Stucco

Comments: The stucco finish is chipped.

Wall Roof None Batt

Metal Units - Metal Frame

AccessibilityFeature

GSF NSF Year Built Use Group Historic Ownership #Floors

Residential 17,560 10,605 2 Leased 1922 Listed

REAL ESTATE

Access to Building Ramps Entrance 2nd Egress Visual Alarm Corridor/Aisle Rooms Stairs Elevator Restrooms Drinking Fountain Telephone

Yes N/A Yes Yes Yes Yes Yes No N/A Yes Yes Yes

ACCESSIBILITY

Structural Systems1.

Exterior Walls2. Number of Deficiencies = 1

Insulation4.

Exterior Doors5.

Material Drainage Year Life

Type Area Served

Fiberglass Tile Gutters and Downspouts 2010 17 Hip Entire Building

3. Roof

Entire Building

Page: 11 of 117

Building: 0012 - MOUNT RAINIER DORMITORY

INTERIOR FINISH

Carpet Ceramic Tile Concrete Terrazzo Vinyl Tile

Ceramic Tile Drywall Plaster

Comments: Toilet partitions are metal.

Metal Units - Metal Frame Wood Units - Metal Frame

Wood Units - Wood Frame

VERTICAL CIRCULATION

Concrete Stairs Metal Stairs Wood Stairs Comments: Exterior steel stairs (at east and west side of building) provide fire escape from second floor. A wood stair leads to the attic HVAC area.

Double Hung - Aluminum Frame; Double Glazing; Fixed - Aluminum Frame; Double Glazing;

Single Hung - Aluminum Frame; Double Glazing;

Acoustical Tile Gypsum Board Plaster

Number of Deficiencies = 1

Windows6.

Floors1. Asbestos: Yes

Interior Walls2.

3.

Interior Doors4. Number of Deficiencies = 1

Heat Source

Heat Distribution

Piping System

Control System

Fresh Air Intake

Energy Conservation

Measure

Area Served

A central heating and ventilation air handler, manufactured by Brod and McClung with hot water heating coils, located in the utility tunnel. The space heating hot water is provided by a steam to water shell and tube heat exchanger, manufactured by Helitherm (model SW1A03, serial number H-78-733 and built in 1978) located in the utility tunnel. Steam is generated at the central power plant Building 19 operated by Lessor.

The restrooms and shower areas have supplemental heat provided by floor-mounted radiators with hot water heating coils.

Heating to the laundry rooms is provided by wall mounted electric heaters.

Comments:

Comments:

HVAC

Heat1.

Gas-Fired Steam Boiler

Gas-Fired Steam Boiler

Unit Ventilator

Radiator

Two-Pipe

Two-Pipe

Direct Digital Control (DDC)

Thermostatic Valves

Mechanical

Natural

None

None

Entire Building

Dorm Rooms

Page: 12 of 117

Building: 0012 - MOUNT RAINIER DORMITORY

Mechanical Toilet/Shower

Comments: Wall-mounted exhaust fans manufactured by Multifan (model 4E25 with override controller) ventilate the toilet/showers and laundry rooms. Four central exhaust fans ventilates the building and are located in the attic.

Domestic hot water is provided by a steam to water shell and tube heat exchanger, circulating pump, and an associated 200-gallon capacity hot water insulated steel storage tank, manufactured by A. O.

Smith, located in the utility tunnel.

Comments:

Cast-Iron None None

Electric Water Cooler Hose Bibb Lavatory Portable Bottled Water Cooler Shower Sink Urinal Water Closet (Flush Valve)

None

Wet None ABC Type Fire Extinguisher

Ventilation Area Served

Copper Copper Steam Heat Exchanger

None Yes

Hot Water Cold Water Water Heater Water Treatment HW Storage Tank

Grease InterceptorWaste / Vent Interior Storm

None None None None Natural None Entire Building

Sprinkler System Stand Pipe System Fire Suppression

PLUMBING

Exhaust Ventilation

Ventilation2.

System Type

Air Distribution

Piping System

Control System

Fresh Air Intake

Energy Conservation Area

Served

Water Distribution1.

Sanitary Distribution2.

Fixtures3.

Fuel Distribution4.

Number of Deficiencies = 2FIRE PROTECTION

Page: 13 of 117

Building: 0012 - MOUNT RAINIER DORMITORY

Comments: Service is brought from a 150 kVA transformer vault in the tunnel beneath the building. Equipment in the vault consists of a 150 kVA pad-mounted transformer, transformer disconnect switch, a current/transformer (C/T) cabinet, a meter and a 600A, 120/208V, 3-phase, 4 wire main distribution panel (MDP). This building also has a 60A emergency panel, which is sub-fed from emergency panel in Dining Hall Building 13.

FIRE ALARM

Comments: The fire alarm control/annunciator panel is a Notifier SFP-1024 unit located in the first floor janitor closet.

A Notifier remote annunciator panel is installed at the main entrance. The building fire alarm system is monitored by the Center control/annunciator panel in Security/Safety Building 34.

Service Entrance Electrical Characteristics Distribution Equipment Wiring Devices

Audible Alarm Control/Annunciator Panel Flow Switch Manual Pull Station Remote Annunciator Smoke Detector Visual Alarm

Comments: Recorded footcandle levels include natural light contribution.

High Intensity Discharge (HID) Comments: Exterior building-mounted and surrounding area pole-mounted light fixtures are controlled by time clock and photocells.

T8 - Fluorescent

T8 - Fluorescent

T8 - Fluorescent

T8 - Fluorescent

T8 - Fluorescent

T8 - Fluorescent

T8 - Fluorescent

T8 - Fluorescent

T8 - Fluorescent

Offices

Corridors & Stairs

Equipment Rooms (Elec/Mech)

Toilets

Storage Rooms

Laundry Room

Housing Lounge

Shower

Sleeping Rooms

Area Recommended Recorded Light Type

Battery Backup Battery Backup

Main Distribution Panel 120/208V, 3-Phase, 4 Wire Panelboard Receptacles, GFCI, Switches

Emergency Exit

ELECTRICAL SERVICES

Exterior Lighting1. Number of Deficiencies = 1

Interior Lighting2.

Emergency /Exit Lighting3. Number of Deficiencies = 4

Page: 14 of 117

Building: 0012 - MOUNT RAINIER DORMITORY

Connected to Main System Magnetic Door/Alarm None Local Cable Company

Telephone Security Public Address Television

GENERAL BUILDING CONDITION

Rating X Good

Fair Poor

COMMUNICATION

The facility condition is not impacting the functional use of the facility.

The facility condition IS impacting the functional use of the facility.

The facility condition IS SIGNIFICANTLY impacting the functional use of the facility.

Electric Water Gas Yes NoYes

BUILDING UTILITY METERING

Structure: Good Exterior: Good Interior: Good Mechanical: Good Electrical: Good

Type Location N/A N/A

There is no plausible means by which harmful levels of CO could enter sleeping rooms.

CARBON MONOXIDE DETECTION

Detection Required No

Number of Deficiencies = 0

IMPAIRMENT

Potentially Impaired

DOL Responded

DOL Determination

BUILDING 13 - DINING HALL

CULINARY

ARTS

DININIG

VACANT

ELECTRICAL

MECHANICAL/

TRANSFORMER

ROOM

DINING

AREA DINING

AREA

CONFERENCE

ROOM

KITCHEN

DISHWASH

POTWASH

FOOD PREP.

AREA

DRY FOOD

STORAGE

STOR.

REFRIGERATOR

FREEZER

REFRIGERATOR

FR

EE

ZE

R

T T

T

LOADING

DOCK

BASEMENT

FIRST FLOOR

JAN

OFFICE

KI

TC

H

EN

DISHWASHING

STAFF

BREAK

ROOM

FOOD

SERVICE

MANAGER

STR.

LOCKER

HAND

WASH

TO ATTIC

MECH. EQUIP.

T

T

T

STORAGE

STORAGE

DN

UP

STORAGESTAGING

AREA

RAMP UP

CLUB HOUSE

SERVING

DN

RAMP UP

VACANT

ST.

UP

RAMP UP

C

AN

O

PY

CHASE

LADDER TO

ATTIC MECH

EQUIPMENT

ST.

JAN

CRAWL SPACE

ACCESS DOOR

DINING HALL

BUILDING 13

0 10' 30' 60'

CASCADES JOB CORPS CENTER

SEDRO-WOOLLEY, WASHINGTON

FOOD SERVICE

VOCATION/THEORY

Page: 15 of 117

Building: 0013 - DINING HALL

BUILDING ENVELOPE

Foundation RoofBuilding

Concrete Concrete w/Clay Tile Block Wood

Stucco

Wall Roof None Batt

Metal Overhead - Metal Frame Metal Rollup - Metal Frame Metal Units - Metal Frame

AccessibilityFeature

GSF NSF Year Built Use Group Historic Ownership #Floors

Assembly 26,880 14,719 2 Leased 1922 Listed

REAL ESTATE

Access to Building Ramps Entrance 2nd Egress Visual Alarm Corridor/Aisle Rooms Stairs Elevator Restrooms Drinking Fountain Telephone

Yes N/A Yes Yes Yes Yes Yes Yes No Yes No N/A

ACCESSIBILITY

Structural Systems1.

Exterior Walls2.

Insulation4.

Exterior Doors5. Number of Deficiencies = 1

Material

Asbestos: Yes

Drainage Year Life

Type Area Served

Asphalt Shingles Gutters and Downspouts 2020 27 Hip Entire Building

3. Roof

Entire Building

Page: 16 of 117

Building: 0013 - DINING HALL

INTERIOR FINISH

Carpet Ceramic Tile Concrete Quarry Tile Terrazzo

Ceramic Tile Drywall Fiberglass Reinforced Panels Plaster Wallpaper Wood Paneling

Comments: Toilet partitions are metal.

Metal Units - Metal Frame Wood Units - Wood Frame

VERTICAL CIRCULATION

Concrete Stairs Metal Ladder Wood Stairs Comments: There is a metal ladder to the attic mechanical room that contains three sets of wood stairs to access mechanical equipment.

Awning Units - Steel Frame; Single Glazing; Fixed - Aluminum Frame; Double Glazing;

Sliding - Aluminum Frame; Double Glazing;

Acoustical Tile Exposed Structure Gypsum Board Perforated Fiberboard Tiles Plaster

Windows6.

Floors1.

Interior Walls2.

3.

Interior Doors4.

Page: 17 of 117

Building: 0013 - DINING HALL

Mechanical

Mechanical

Mechanical

Mechanical

Restroom

Dishwashing

Kitchen

Pizza Oven

Ventilation Area Served

Packaged Direct

Expansion (Air Source)

Packaged Heat Pump (Air

Source)

Window Unit

Single Duct

None

None

Electric

Electric

Natural

Mechanical

None

None

Offices

Classrooms

Exhaust Ventilation

Window air conditioning units provide DX-cooling to Conference Room and the adjacent room.

A wall-mounted high-efficiency heat pump, manufactured by Carrier, R-22 refrigerant, provides DX-cooling to Club House.

Comments:

Comments:

Number of Deficiencies = 1

Heat Source

Heat Distribution

Piping System

Control System

Fresh Air Intake

Energy Conservation

Measure

Area Served

A heating and ventilation air handler with heating water coils serves the dining area. The space heating hot water is provided by a steam to water shell and tube heat exchanger. Steam is generated at the central power plant Building 19 operated by Lessor.

A gas-fired package unit provides tempered make-up air to the culinary arts kitchen hood.

Ceiling-hung unit heaters with heating water coils provide…