Amendment 0002 1605AE-24-R-00005 Potomac Bldg 54 Renovations.pdf

PDF 407 KB Posted

Attached to
Renovate the Male Dormitory Building 54, Potomac Job Corps Center in Washington, DC
Solicitation number
1605AE-24-R-00005
Issued by

About this file

This document is an amendment to a solicitation for a design-build renovation and remediation of the Male Dormitory Building 54 at the Potomac Job Corps Center in Washington, DC. The work includes interior renovations of the 1st and 2nd floors, including wall, ceiling, and flooring repairs/replacements, painting, door repairs, elevator repair and certification, plumbing and electrical system repairs/replacements, new fire alarm and sprinkler systems, HVAC system replacement, and attic insulation replacement. The solicitation is a competitive 8(a) set-aside, with an anticipated base award for Phase 1 work and an option for Phase 2 work on the remainder of the 1st floor. Proposal due date has been extended to 11/29/24, and the amendment provides additional responses to questions. The pricing terms include a base CLIN for the Phase 1 work, a separate CLIN for performance and payment bonds, and an option CLIN for the Phase 2 work along with associated bond costs.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

1605AE-24-R-00005

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Washington DC 20210

JCAS

N-4643 200 Constitution Ave, NW Job Corps Acquisition Services US Department of Labor

417910/30/20240002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

09/16/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Project 4179 Potomac Job Corps Center Building 54 Renovation

The purpose of this amendment is to:

1. Provide additional responses to timely submitted questions.

2. Extend the proposal due date to 11/29/24 @ 2pm EST.

Please see Attachments -

Attachment #1 Solicitation Section B.2 CONTRACT PRICE - CONTRACT LINE-ITEM NUMBERS

Attachment #2 Additional Responses to Solicitation Questions

(Please Note: Responses to questions received timely and not provided in Amendments #1 and

#2 will be addressed in Amendment #3.)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Martrelle A. Pyatt Harvin

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

TEL: EMAIL: 202-693-0149 pyattharvin.martrelle@dol.gov

Part I - The Schedule

SECTION B – PRICING

1605AE-24-R-00005

Potomac Job Corps Center – Male Dormitory Building 54 Renovation

B.2 CONTRACT PRICE - CONTRACT LINE-ITEM NUMBERS (CLIN)

PROJECT TITLE: DESIGN-BUILD –

RENOVATION & REMEDIATION OF BUILDING 54 at POTOMAC JCC

CONTRACTOR COMPLETES CONTRACT LINE-ITEM NUMBERS (CLIN):

CLIN 0001 Design Build – Phase 1-Renovation & Remediation of Building 54 at Potomac JCC:

The contractor shall complete all work outlined in the Statement of Work for the interior renovations and mold remediation the Male Dormitory, Building 54, at the Potomac Job Corps Center (JCC). Design and construction of second floor & attic, and first floor core area outlined in the statement of work.

The work includes, but is not limited to, interior renovations of the 1st and 2nd floors including wall, ceiling and flooring replacements and repairs; painting; door repairs; elevator repair, certification and permitting; plumbing and electrical system repairs and replacements inclusive of new fire alarm and sprinkler systems, mechanical system replacements; and attic insulation replacements.

Construction Services 1 JOB $____________________

CLIN 0002 Bonds (Performance and Payment Bonds):

These items are cost reimbursable items and will be reimbursed on a dollar per dollar basis (actual expenses) upon receipt of bonds and proof of payment to the surety.

Bonds Reimbursement 1 Lump Sum $____________________

CLIN 0003 Option 1 (Phase 2-Construction on Remainder of 1st Floor) Work shall be submitted as a Bid Option and will include the construction and execution for renovation of the remainder of the First Floor (approximately 10,000 SF) outlined in the statement of work under Phase 2.

Construction Services 1 Job $____________________

Option CLINs will be evaluated with FAR 52.217-4 or FAR 52.217-5. The Government reserves the right to unilaterally exercise the Option CLIN 0003 within 30 days of contract award. The completion date shall coincide with the completion date of CLIN 0001.

Part I - The Schedule

SECTION B – PRICING

1605AE-24-R-00005

Potomac Job Corps Center – Male Dormitory Building 54 Renovation

CLIN 0004 Option 1 (Bonds-Performance and Payment Bonds):

This CLIN will be utilized upon exercising CLIN 0003. These items are cost reimbursable items and will be reimbursed on a dollar per dollar basis (actual expenses) upon receipt of bonds and proof of payment to the surety.

Bonds Reimbursement 1 Lump Sum $____________________

QUESTION Drawing/Reference Responses

Per SOW 1.A.3, Page 1 of 104, it states “roof structure is wood with asphalt shingles roofing system and exterior gutters/downspouts which was replaced in 2019”. Please clarify if just the downspouts and gutters were replaced or the roof and gutters/downspouts were replaced.

Roof, downspouts, and gutters were replaced in 2018/2019.

Please clarify if Building 54 is a Registered Historic Building or not. There is a conflict in the SOW. Per SOW 1.A.2 on Page 1 of 104, it states that "the Department of Labor must initiate consultation with the State Historic Preservation Office (SHPO) to seek a determination of no adverse effect or, if an adverse effect found, to mitigate said adverse effect this project may cause to any "candidate" building or property." Meanwhile Page 4 of 104, Paragraph A.1.b Historic Preservation states "N/A".

Building 54 is not one of the Candidate buildings to be registered on the National Register of Historic Places.

With respect to the Design, please confirm the Design for the entire 1st floor shall be included and completed in Phase 1 and costs included in CLIN0001.

See Scope of Work page 20 section 9.a.1 Confirmed. See SOW Section IV.B.9.a.

For Section B Pricing, CLIN0002 is for Bond Costs to cover CLIN0001. Should we include bond costs for Option Item CLIN 0003 in CLIN0003 or will you be updating this to add a 4th

CLIN.

Fourth (4th) CLIN added to include bond costs if option- CLIN 3 is exercised. Please see attachment.

Has all mold / mildew been removed from the building or will the contractor be required to conduct a Haz-Mat study as part of the D-B SOW?

SOW, I-A.4., page 6/110 Mold/Mildew will be addressed in Amendment #3. A HAZMAT study is not required .

Have the bottom of the walls removed by the previous mold remediation been replaced or are these quantities included in quantities listed in Sections C & E? I-A.4. / Section C, pages 6 / 110 & 28/110 & 73/110 All quantities are included in Part IV, Sections C and E of the Scope of Work.

Are we correct to assume that the Sustainable Design and Building Requirements only pertain to those items being repaired/replaced within the project SOW and not the entire Building Envelope?

SOW, II - Section C-2, page 11/110 Yes. Sustainable Design and Building Requirements only pertain to those items being repaired/replaced within the project SOW and not the entire Building Envelope.

It is our understanding that D-B shall conduct a Seismic Design Review IAW JCH 814. Will repairs be made by the contractor with costs compensation via a contract modification issued by the KO?

SOW, II - Section C-2 & IV - C-14, pages 10/110 & 41/110

Structural repair costs will be compensated via modification if deemed necessary.

Reference to JCH-814 additional design requirements take precedence over the requirements of the contract. Can the Government advise how this statement impacts the project SOW and requirements on this project?

SOW, B. Job Corps Guidelines 1.b, page 10/110 JCH-814 requirements do not take precedence over the requirements of the contract. Where conflicts occur the contractor shall request clarification from the CO, Additional Responses to Questions Solicitation No. 1605AE-24-R-0005 Amendment 2

Project 4179, Building 54 Renovation at Potomac Job Corps Center

Please clarify the Government's intention with regard to the following Note;-Item 14. Note:

"All quantiles and assumptions provided within this scope are intended to be used as a basis for bidding purposes only." Are contractors to use only the quantities as enumerated in Sections C & D Phase 1 and Section E Phase 2?

SOW, Section IV-C, page 28/110 Yes. Contractors to use only the quantities as enumerated in Sections C & D Phase 1 and Section E Phase 2.

Please confirm that Incidental Cutting and Patching quantiles are not included in the Quantities as indicated In Item 14. Note: "All quantiles and assumptions provided within this scope are intended to be used as a basis for bidding purposes only." SOW, Sections IV-C & V- B, pages 28/110 & 99/110

Cutting and patching quantities are not included in the Quantities indicated in Item 14.

Contractor to include costs for cutting and patching as required.

CPM Schedule is limited to 2 pages. Would the government consider the elimination of the 2 page limit as this is too restrictive to present the information as required in section L and as stated in attachment J.3. We would recommend the page limit be deleted and the use of 11x17 sheets be permitted for the ease review by the government and to afford a complete presentation of the information required. Please advise.

Solicitation, L.12.2.2.1.2.1, page 95/98 L.12.2.2.1.2.1 SUBFACTOR 1: CPM Schedule page limit has been revised to 3 pages. The use of 11x17 sheet size is acceptable for the CPM Schedule only.

Will this building be one of the candidate buildings one of the eleven buildings listed on the National Register of Historic Places?

Duplicate - Please see question #2.

What is the maximum amount of time for Gov’t to award Phase 2 Bid Option? Page 20 “10. If the Department determines that Phase 1 and Phase 2 of the work will be awarded at the same time, all design and construction from both phases will be completed concurrently.” 2nd RFI, should we include the Option in our schedule showing the 557 days?) L.12.2.2.1.2.1 only mentions the base contract work of 467 days.

The Government reserves the right to unilaterally exercise the Option CLIN 0003 within 30 days of contract award. Please show the schedule as shown in the solicitation for the base period of 467 days. If the option is exercised, the a revised schedule will be required.

The RFP SOW mentions Lifecycle cost analysis in the Guiding Principles. Based on the prescriptive nature of the HVAC listed in the SOW, is this necessary as it will add additional costs.

Yes.

Please confirm that the winning contractor does not have any SHPO requirements relating to the renovation of Building 54.

Duplicate - Please see question #2.

Is there currently an ESC (Engineering Support Contractor) Coordinator involved in the project? If so, please provide POC.

This information will be provided once the project is awarded.

18 Is there an anticipated award date for use in preparing the schedule? An anticipated award date is not available at this time.

As this is a federal facility, please clarify the permitting requirements for this project? Will DCRA permits be required?

See SOW, page 5/104, 3.a-d.

Please clarify the order of precedence for the bid documents, specifically all the prototype guidelines and other checklists included in the solicitation as hyperlinks.

There is no specific order of precedence for bid documents.

Can the government estimate the historical amount of domestic hot water generated in the fully occupied building for use in the Solar DHW analysis?

No, the designer of record is responsible for estimating the amount of domestic hot water.

22 Is there an installation wide fire alarm contractor? If so, please provide a POC. No.

23 Is there an installation wide mechanical controls contractor? If so, please provide a POC. No.

24 Is there an installation wide security controls contractor? If so, please provide a POC. No.

The SOW states that the Center will remain in operation throughout the construction phase and that the Contractor will coordinate with the Department’s ESC to minimize disruption of the Center operations during construction. Please confirm the building will be unoccupied during construction.

The building is currently unoccupied, and will remain unoccupied during the construction project.

Due to the age of the building, is there any reason to conduct an Lead Based Paint or Asbestos survey prior to demolition?

There is no reason to conduct a lead-based paint or asbestos survey prior to demolition.

27 Was the stated HVAC SOW developed for bid leveling purposes only? Yes, the stated HVAC SOW developed for bid leveling purposes only.

Will the government provide CADD files for developing the base sheets for the design of the project? If no CADD files are provided, this will add a big cost on the design fee.

CADD files are not available.

REF IV Extent of Work. B. 9.a.1 states to Design entire first, second and attic levels. The same section item 13. Provides a table indicating that the design of the remainder of the 1st floor is in phase 2 of the project. Please confirm the entire design cost and level of effort for the project is to be provided in Phase 1.

Yes, the complete design costs for both Phase 1 and Phase 2 should be included in the Phase 1 costs.

The SOW for the ceilings indicates very small areas for removal and repair. This portion of the scope does not seem to consider the HVAC demolition required. Please confirm that larger portions of the ceiling must be removed and repaired to complete the HVAC Scope.

Yes, more substantial portions of the ceiling will need to be removed and repaired to complete the HVAC scope. Contractor to include costs in bid.

31 Can the flue for the domestic water heater be re-used? Remove and replace per SOW Page 52 item 16.

REF MECH DEMO: Item 7 states to remove and dispose offsite VAV Dampers; Item 12 states to dismantle, retain, clean, service and reinstall. Please clarify.

VAV Dampers shall be removed and disposed. Dismantle and retain all HVAC registers, diffusers, grilles, and volume dampers for cleaning, servicing, and reinstallation.

33 Does the EF in the 1st floor mech. Rm. get removed and replaced? Yes.

ASHRAE 90.1 requires interrupting power to specific duplex outlets outside of normal operating hours; because this is a low-rise residential building is it exempt from this requirement?

Low rise residential buildings, three stories or fewer above grade, shall conform to the International Energy Conservation Code IECC 2012. Page 13 item C.

The SOW states that the roof is still under warranty. Please provide the name of the installing contractor, the roof system manufacturer, a description of the existing system and copy of the warranty.

AIM Green Construction Services LLC is the General Contractor.

The plumbing demolition portion of the SOW discusses removing the sanitary/waste lines for the laundry rooms on 1 and 2. Does this include the floor drains and service sink sanitary lines?

Prior to demolition, provide and install protection for all items to remain, including, but not limited to, plumbing fixtures, sanitary and domestic piping. Page 20 item 8.

Can Pro-press or similar fitting/pipe joining technology be used in the building or is brazing the preferred method?

Pipe fittings/joining method to be determined by the project designer of record.

Please confirm that the washers and dryers are to included in the Contractor's scope of work.

New washers and dryers are not included in this contract.

If washers and dryers are included in the Contractor's scope, please clarify the quantity and type to be installed.

New washers and dryers are not included in this contract.

The plumbing SOW does not discuss the removal or replacement of the electric water coolers on the 1st or 2nd floors. Are these fixtures existing to remain?

Yes.

Please clarify the intent of Plumbing scope item qq. Double handle wall mounted faucet with vacuum breaker and 5.2 GPM flow rate.

They are usually installed in the janitors' room to prevent domestic water contaminations. Page 55 item pp and qq.

Are tubs removed in 204 and 206 to be replaced after refinishing and wall repairs or are new tubs to be installed that meeting

Refer to SOW page 31/104 item 9.c.

Please clarify is any existing firestopping material is to be removed under the demolition scope for the project.

Refer to SOW pages 57 and 58 for fire-stopping requirements.

Please clarify the exterior lighting scope. There are currently two poles mounted fixtures at the approach to the building. Are these fixtures to be replaced with LED? Is an exterior photometric study required as part of the base bid design?

Exterior pole mounted lighting is not included in the SOW. Exterior photometric study is required for all exterior building lighting required by the scope.

There are two aluminum storefront doors (as-built # 14 and 15) at the vestibule and two metal gate doors (as-built #19) at the 1st floor exterior stair wells. Are these doors to be replaced? If so, will they be considered part of the core area of the 1st floor or Phase 2 Option?

The first-floor exterior stairwells and aluminum storefront doors are not included in the SOW.

From a electrical, fire alarm and access control perspective, should the stairwells at each end of the building be considered part of the core area or Phase 2 for pricing purposes?

Phase 2.

Does the removal of wood shelves in the dorm rooms include both the open shelves and shelves in the closets?

Remove and replace open shelves only.

Do walls at 1st floor mech and laundry rooms need to be upgraded for fire rating, similar to 2nd floor?

No.

Estimate for Progress Payments - Based upon an approved D-B contractor schedule of values, please confirm the D-B team will be permitted to invoice on a monthly basis for project design ? Will invoicing during design be permitted for additional services such as building studies, existing MEP system testing, and other items normally considered construction elements of work?

Solicitation, G.7. page 27 Project design invoices will be accepted as listed in the solicitation. Any additional invoices will be considered as needed upon receipt.

Currently the solicitation provides no photos, surveys, or assessment reports, on the current conditions of building systems or other elements potentially impacted by water leakage, mold remediation, demolition, or system maintenance outages making the site visit very important. In light of this fact, would the gov't consider extending the period for asking RFIs to 7 days instead of 2 (currently Oct 4th), and extending further for the govt to reply with additional information, and then 14 days from receiving answers so offerors can finalize their design, schedule and cost proposal, ~ 4 weeks extension in total?

Solicitation, L.8, pg 89 Period for RFI's/Submission of Questions will not be extended. Proposal due date extended until 11/12/24, per Amendment #2.

Please confirm that the design, installation and testing of the Building Fire Alarm System for the entire building will be included in CLIN 0001. No others CLIN's include Fire Alarm design or construction of any kind.

Solicitation/SOW, B.2 & Section IV C,D, &E, pages- 10/98 & 37/110

Confirmed.

The following statement is included in the last paragraph of B.2 " The Government reserves the right to unilaterally exercise the Option CLIN 0003 within 30 days of the contract award. The completion date shall coincide with the completion date of CLIN 0001." This contradicts Section VII Project Schedule of the project SOW that provides for 467 days for CLIN 0001 and 557 days for CLIN 0003. Please clairfy which is correct.

Solicitation / SOW, B.2 / Section VII, pages-10/98 & 109/110

The project provides for Base only (CLIN 0001) - 467 calendar days after NTP; Base + Option, concurrently- 557 calendar days after NTP

Please confirm DOL will be responsible for all efforts regarding SHPO submissions and review on this project. In the course of the design and construction schedule, when does DOL anticipate this being completed? Should this be listed as a separate owner activity on the project schedule?

SOW, I-A.2.,page 6 / 110 Duplicate - Please see question #2.

Does the Gov't's scope and budget anticipate an upgrade to the existing electrical service to the building or is it anticipated electrical service requirements will remain the same or less based on new Mech equipment.

SOW, Section 1-A.10, page 7/110 No, the Government's scope and budget do not anticipate an upgrade to the existing electrical service to the building .

The sections of the SOW regarding the electrical service for the building appear to be contradictory and unclear as to the Government's intentions. The documents appear to indicate that the existing electrical panels are to be reused as stated in item c.1). However item a. states that the Contractor shall comply with JCH 814 and provide load calculations for compliance with the National Electrical Codes. If the load calculations determine that the existing electrical service is inadequate and require modifications or replacement will the Government issue a Contract Modification to the D-B for the additional costs to be incurred for Design and Construction?

SOW, Section 1-A.10 & Section 15. Electrical, pages 7/110 & 42/110

The SOW indicates that the distribution panel and down stream panels are to remain. However, load calculations must verify the new and existing loads are not exceeding the rating of the panel.

How will the DOL-Initiated / DOL - Provided service for compliance with Section 106 of the Historic Preservation Act impact the project scope of work and schedule through out the project design and construction phases of the project?

SOW, Section 1-A.2, page 6/110 Duplicate - Please see question #2

Re: "The roof structure is wood with asphalt shingles roofing system and exterior gutters/downspouts which was replaced in 2019 and is under the manufacturer’s warranty" Please confirm all of the following were replaced in their entirety: Roofing;

Gutters; Downspouts; and that all are functioning properly now. DOL noted that the damage was severe; were wood components of the roof system also replaced during repairs? If so are there any scope/ contract documents available regarding the work performed by others?

SOW, Section 1-A.3, page 6/110 The roof and all affected components were addressed in the 2019 roof project.

Please confirm that ongoing leaking into the envelop of the building has been resolved.

SOW, Section 1-A.4, page 6/110 Confirmed. Leaking into the envelop of the building has been resolved.

When was the elevator last inspected? Can records of the prior inspections be provided?

SOW, Section 1-A.4, page 6/110 Last date of inspection is unknown. No records are available.

Was the original elevator machine room constructed to code? Is achieving a fire rating included in the project RFP "repair work" or something else not done in the original construction?

SOW, Section 1-A.5, page 6/110 Any work associated with the elevator machine room is not required by the scope.

Can DOL provide the make, model, & rating of the elevator and associated equipment?

SOW, Section 1-A.5, page 6/110 No.

The existing HVAC is a DX system. Please confirm we are replacing generally "in like-in-kind" to avoid extensive alterations to associated pipe, ductwork, and other equipment.

Please confirm its the Governments expectation to provide a contemporary, controllable, energy efficient system in keeping with current LEED / Sustainable Construction Standards as maybe available, but without extensive modification to the existing building systems?

SOW, Section 1-A.6 &7, page 7/110

Confirmed. The system will be replaced "in like-in-kind" to avoid extensive alterations to associated pipe, ductwork, and other equipment. It is the Government's expectation to provide a contemporary, controllable, energy efficient system in keeping with current LEED / Sustainable Construction Standards as maybe available, but without extensive modification to the existing building systems.

Is the sprinkler system currently operational? When was the last sprinkler test performed and can system records be provided?

SOW, Section 1-A.9, page 7/110 Contractor to assume existing sprinkler system is currently operational. No sprinkler test data is available.

With regard to Project Scope Intent, how long has the building been out of service? Have utilities and building HVAC Systems been maintained since 2019 or has the building been subject to long term non-occupancy without regard to maintaining the systems and environment within the building? Has the Owner/government performed a Facility Condition Assessment or other evaluation of the building and the MEP Systems operational functional conditions to determine the SOW for this project? If so can these documents be provided?

SOW, Section 1-B, page 7/110 The building has been out of service since 2019. Contractor to assume all utilities and systems are functional.

Due to the protracted 180 Day Award Period, please confirm that the application of all codes, rules, standards, & regulations will be as of the date of the proposal submission to the Government as oppsed to the contract award date.

SOW, Section II, page 8/110 The application of all codes, rules, standards, and regulations will be as of the date of the proposal submission to the Government.

Re: "If lead paint is discovered during the work the Contractor shall immediately contact the Contracting Officer" Based on the age of the building it is unlikely that any hazardous material such as lead, asbestos.. etc. will be encountered, please confirm that any work associated with surveying, testing, abatement or remediation work of hazardous material is outside of the current scope and will be a change order.

SOW, Section II - A.1.a.2, page 7/110 Unknown and/or unforseen site conditions will be addressed as discovered during the work in accordance with Section H.28 NOTIFICATION OF DIFFERING SITE CONDITIONS of the Solicitation.

Re: Permits and Licenses, will the Gov't please provide a list of permits and approving authorities/ jurisdiction's related to the original building designed in 1997.

SOW, Section II - A.3 A list of Permits and Licenses of the building built in 1997 is not available.

Reference Drawing Photo copies have been provided. Are electronic / AutoCAD or equal versions available? If not, please confirm that the Government's schedule and budget anticipates the considerable A/E efforts of as-built verification and development of AutoCAD documents required prior to the 15% Design Submission.

SOW, Section II - D.13., page 22/110 Electronic/AutoCADD or equal reference drawings are not available.The Government Schedule and Budget anticipates the level of effort required to verify reference drawings and develop Auto-CAD documents.

Will the Government permit submitting and acquisition of Architectural Elements including items for wall construction, doors, hardware, and selected surface finishes SOW, Section II - D.3.b.2)c., page 16/110

Submitting and acquisition of Architectural Elements is permitted upon Government acceptance of the Design Submissions identified in Section II.D.3 of the Solicitation Scope of Work.

Due to the stringent requirements of JCH - 814 should the SOW take precedence over the JCH 814 versus what is stated in the referenced guideline paragraph B?

SOW, Section II -B.1.b., page 10/110 The Scope of Work takes precedence over the JCH-814.

Will Commissioning & Recommissioning Services be performed by a third party retained by the Government or by the D-B Contractor? Please confirm its the gov't intent to only commission those NEW system elements proposed for the building and not the existing systems to repaired, patch or simply remain.

SOW, Section II -C.5., page 14/110 Commissioning and re-commissioning is to be performed by Design/Build Contractor. Reference page 9 item 5 and page 51 item 37. It is the Government's intent to commissioning and re-commissioning both the new system elements and existing systems to be repaired.

Firestopping - Is the D-B team expected to inspect the entire building and provide firestopping as required at each rated wall/floor penetration or only in new penetrations created during the project? If firestopping of the entire facility is required does the existing building firestop application log exist? If so can the Government provide a copy?

SOW, Section IV - 18, Page 62/110

Firestopping is required only for new penetrations created during the project.

Does the government have any O&M Manuals and/or maintenance records for the building? If so can copies be provide to the D-B Contractors?

SOW, Section IV - C & E, page 28/110 No O&M Manuals or maintenance records are available.

If permitted by building codes is the use of MC Cable for branch circuits permitted in lieu of EMT or RG Conduit?

SOW, Section IV - C.15.c., page 42/110 If permitted by Building Codes, the use of MC Cable is acceptable.

Please clarify the SOW does not mention HVAC Humidity Control as a requirement for the project. In the JCH 814 humidity control is a design requirement, is this being waived by the Government for this project?

SOW, Section IV - C.15.c., page 52/110 Humidity control is required.

Are all existing panelboards and feeders considered part of the 1200A service, or will only the main MDP remain? Will short circuit/arc flash/coordination studies be required if all subsequent panels are being replaced? SOW, Section IV - C.15.c.1), page 42/110

Yes. All existing panelboards and feeders are considered part of the 1200A service. Arc flash and coordination studies are not required.

Please confirm new site lighting will be required. Is site lighting confined to building mounted lighting? If pole mounted site lighting is required will the Government provide the limits of the site to be serviced by the new site lighting?

SOW, Section IV - C.15.d.3), page 49/110 Site lighting is only limited to the exterior wall mounted fixtures required by the scope and do not include pole lights.

Scope notes conduit system for branch circuits. Will MC cable be accepted, where allowable by code?

Power requirements, pg 37, c-2 Repeat question. Please reference the response to question #74.

79 Which rooms are designated as ADA? Life safety/fire alarm Rooms 204 and 206, 104 and 106.

Please confirm that Authority having jurisdiction for the Building Permits on the project is the District of Columbia, Department of Buildings.

SOW, Section II,B.3. Permits & Licenses, 5/110 Confirmed. The Authority having jurisdiction for the Building Permits on the project is the District of Columbia, Department of Buildings.

During the site visit we observed various pieces of loose and wall mounted FF&E throughout the building. Will these items be removed by the Government prior to commencement of the project design & construction? If not will it be the responsibility of the D-B Contractor to remove, store and reinstall these items?

Site visit 10-2-24 FF&E in the areas of work will be removed and replaced by the Government.

Please confirm that design professions affixing their seal and signatures to the IFC documents are required to be Licensed in the District of Columbia.

SOW, Section II.D.4.c page 17/110 Confirmed. The design professionals affixing their seal and signature to the IFC documents are required to be Licensed in the District of Columbia.

Will the Government permit early submission and acquisition of identified long-lead time Architectural Elements including items for wall construction, doors, hardware, and selected surface finishes after approval of the 60% design submission similar to the select MEP equipment?

SOW, Section II-D.3.b.2)c., page 16/110

No. The Government will not allow early submission and acquisition of identified long-lead time Architectural Elements including items for wall construction, doors, hardware, and selected surface finishes after approval of the 60% design submission similar to the select MEP equipment.

RFP page 98 M.6 lists “Joint Venture/Signed Statement of JV Intent and Description of Partnership” as an evaluation factor for award. Please confirm that M.6.1 can be met by the submission of a JV agreement within Factor 3: Management and Organization.

Solicitation, Section M.6, page 98/98 Yes, submission of a JV agreement within Factor 3: Management and Organization is acceptable

Please confirm that the evaluation of M.6.2 will be conducted through a review of all sections of the submitted proposal and is not an additional narrative be added to Factor 3:

Management and Organization by JV offerors.

Solicitation, Section M.6, page 98/98 Yes, all sections of the proposals will be evaluated for JV consideration.

Please confirm that any required response to M.6 will be exempted from the page count so as not hamper JV offerors’ ability to be as responsive as non-JV offerors.

Solicitation, Section M.6, page 98/98 Additional pages, within reason, will be allowed to address JV offeror's requirements.

87 Please clarify what we are going to do with operable windows? Refer to SOW page 30 item 7.

88 Can we use a base coat with primer in it instead of two coats of paint? Paint with 1 base coat of low VOC primer and 2 coats of low VOC paint as required by the scope.

89 Page 19 Item J fire rated dry wall is to be what size? Refer to SOW Section IV for all drywall thickness requirements.

90 Page 19 Item K what fire rating are they looking for? Fire rating as per code.

91 Pg. 27 Item B please clarify intent?

Remove and reinstall all existing ceiling light fixtures, registers and grills, fire alarm devices and all other devices connected to the ceiling system unless otherwise specified elsewhere in the

SOW.

Pg. 30 Item G we take issue with the contractor having to provide notification of any HAZMAT in the building. This should be requirement of the owner.

Contractor to follow requirements of the SOW.

93 Pg. 30 Item 8(a): please clarify what we should do with damaged vinyl base? The damaged vinyl base should be replaced with new 4" vinyl base.

94 Pg. 31 Item D In reference to 4x4 glazed tile are we to match as close as possible? Confirmed.

Pg. 31 Item E “Provide and install only damaged pieces to match existing tiles” … please clarify?

Replace only damaged pieces to match existing tiles with grout color and texture to match the existing grout; assume 50 SF.

Pg. 32 Item 10(a): … “match existing colors of the existing doors”. What doors are we matching colors to?

The colors should match the green color of the existing frames.

97 Pg. 65 Item 7: what type of rubber flooring and where is it located?

The rubber flooring should match the existing rubber flooring found on the stair treads and landing.

98 Pg. 65 Item K: Please define where room 138 is located? The room 138 is open communicating stairs.

Stairs # 2 shows the handrail and metal door at the bottom of landing; Is this to remain? If so, what is the finish?

The handrail and metal door at the bottom of the landing are not in the SOW.

100 Is stair # 2 considered to be emergency exit? Yes. Stair #2 is considered an emergency exit.

101 Regarding the window on 1st floor; are these considered to be emergency exits? No. Windows on the first floor are not considered emergency exits.

102 Confirm whether SHPO and/or NCPC review will be required for this project. Duplicate - Please see question #2.

Confirm whether any Site Work (i.e. Storm Sewer, Domestic Water, Electrical Service, etc.)

is included in this project. Site work is not included.

104 Confirm whether any exterior work other than securing the operable windows is required. Confirmed.

105 Confirm whether any Structural Work is required for this project. No, there is no structural work required for this project.

106 Confirm incoming fire service line is sufficient for the fire sprinkler system modification. Refer to SOW item 17 on pages 55 through 57 for fire service line work.

107 Confirm whether a fire hydrant flow test be required by the FPE. Confirmed. A fire hydrant flow test will be required by the FPE.

Confirm whether a Qualified Fire Protection Engineer is required to be part of the Design Team. Confirmed. A Qualified Fire Protection Engineer is required to be part of the Design Team.

Confirm whether the roof leak issue has been resolved or whether it is part of the SOW for this project.

Confirmed.The roof leak issue has been resolved, and it is not included in the Solicitation Scope of Work.

Confirm whether the Contractor is required to perform another HAZMAT study as part of the SOW for this project. No HAZMAT study is required for this project.

111 Confirm whether any Lead Based Paint (LBP) is present on the project. Confirmeds no lead-based paint (LBP) present.

112 Confirm whether the existing floor tile has asbestos. Confirmed no asbetos present.

113 Confirm whether the Design Team will work with a Government appointed CxAgent for the Commissioning or whether the Contractor needs to include a CxA as part of the work.

Contractor required to provide commissioning agent per SOW page 9 of 104.

114 Confirm whether a LCCA is required. Confirmed. A LCCA is required.

115 Confirm whether any FF&E is included with this project. FF&E is not included with this project.

116 Confirm that building security will be necessary during off hours. Building security will not be necessary during off hours.

Confirm process for access to the site. Will badges be issued for the entire project or will daily check in at Visit Center be required.

Daily check-in will be required.

118 Please provide HAZMAT Reports, if available. Repeated

119 Please confirm that existing furniture and items left in room will be moved to storage containers by others.

Confirmed. The existing furniture and items left in room will be moved to storage containers by others.

120 Is 11” x 17” acceptable for the schedule? 11" x17" sheets will be allowed for the schedule, but not required.

121 Is there a maximum contract value acceptable for Subfactor 1 – Experience? No. There is not a maximum contract value acceptable for Subfactor 1 – Experience 122 Is Times New Roman font acceptable for the proposal? No. Please reference L.11.1.4.1

Does the facility utilize an existing access control vendor? If so, can their contact information be shared?

No. The facility does not utilize an existing access control vendor.

124 Is the Contractor responsible for obtaining the building permit? Yes. See SOW page 5/104 item 3.

125 Where and how many employees will be allowed to park their personal vehicles? General Contractor parking will be located at the front parking lot and a few by the work site.

Please confirm personnel will be able to utilize the facilities utilities (water/electrical) and restroom facilities during work activities.

General Personnel will not be able to utilize the facilities utilities (water/electrical) and restroom facilities during work activities.

Please confirm the work areas may be cordoned off from public access during work activities. Please identify any requirements for temporary protection.

General Work areas may be cordoned off from public access during work activities by the contractor.

Contractor to provide temporary protection as required to prevent damage to building spaces.

128 Please identify a location for a laydown area. General See SOW section III.B.1 129 What is the expected timeframe for receipt of badging for onsite personnel? General No badging is required. Daily check-in is required.

Please confirm all existing furniture, artwork, or any other personal items will be removed by others prior to the commencement of work. If not, please provide quantities, storage locations and any other requirements.

Furnishings Confirmed. All existing furniture, artwork, or any other personal items will be removed by others prior to the commencement of work.

Please confirm no furniture, furnishings, or appliances are included in this contract. If not, please advise.

Furnishings Confirmed. No furniture, furnishings, or appliances are included in this contract.

Please confirm the existing storage containers adjacent to the building vestibule entrance will be removed by others prior to the commencement of work.

Site storage Existing storage containers adjacent to the building vestibule entrance will not be removed by others prior to the commencement of work.

What notification requirements and/or lead times are there for any utility shut off requests?

Utilities One week lead time is required by the Center.

Please confirm the renovations will utilize the same building layout and systems that are currently present within the facility. If modifications to meet code/ADA compliance, or any other requirement, please advise.

Design intent The design intent is to maintain the same building layout and systems. Refer to Section IV SOW for Extent of Work.

Please identify any security, badging, and/or citizenship requirements for access to the facility.

Personnel Access A valid ID is required to access center facility.

Please confirm this contract will require a minimum of 15% of the work (not including the cost of materials) to be self-performed per FAR Clause 19.809-2 Limitations on subcontracting and nonmanufacturer rule - Section (a)(3).

Self-Performance Correct. FAR 19.809-2(a)(3) does apply.

Please identify any required permits for performance of this work. Who is responsible for acquiring and paying for said permits?

Permits Refer to SOW page 5/104, item 3.

Please confirm all existing ductwork is to remain in place and is to be cleaned and tied into the new HVAC systems and re-terminated in the same locations. If modifications to the building layout or system needs is anticipated, please provide requirements.

SOW Section I.B.1.i: HVAC Refer to Section IV of the SOW for ductwork requirements.

The SOW indicates that the design shall use sustainable design methods "within budget constraints". However, the evaluation of offers does not consider sustainable design in the review of offers, and the award is based on the "Lowest-Priced-Technically Acceptable Source. Please advise.

SOW Section II.C.2.b: Sustainable design All information and documentation provided in and with the proposal will be evaluated and considered as noted in Section M.5 Basis of Award this procurement will be awarded using a Lowest Priced-Technically Acceptable Source Selection approach as defined in FAR 15.101-2.

The SOW indicates that the design shall use "energy and water consuming products which are in the upper 25% of energy and water efficiently whenever practicable and cost effective". However, the evaluation of offers does not consider this requirement in the review of offers, and the award is based on the "Lowest-Priced-Technically Acceptable Source. Please advise.

SOW Section II.C.3.d: energy and water consuming products

The SOW indicates that the design shall provide preference to utilize solar heating for a minimum of 30% of domestic hot water, and options for the use of energy/water conservative appliances. However, the evaluation of offers does not consider this requirement in the review of offers, and the award is based on the "Lowest-Priced- Technically Acceptable Source. Please advise.

SOW Section II.C.3.J.1)&2): Solar Water Heating & Water Conservation

The SOW indicates that the A/E team should include one site visit per week for the entire construction duration (240 calendar days) for a anticipated total of 34 visits. This is not standard and will incur a significant cost impact to the contract. Please advise.

SOW Section II.D.12.a: site visits Comply with SOW.

Please confirm the requirement to repair any damage to the construction area as well as adjacent landscaping and paving only refers to damage incurred by the contractor during the course of the work. If existing damage is to be repaired, please provide requirements.

SOW Section IV.A.1: Site Repairs Confirmed. The requirement to repair any damage to the construction area as well as adjacent landscaping and paving only refers to damage incurred by the contractor during the course of the work.

The SOW indicates installation of matching wall tile in the 2nd floor areas. An exact match is not possible and patches will have a minor color difference that will be somewhat noticeable. Please confirm this is acceptable.

SOW Section IV.C.8.d: Matching tile Confirmed.

a typo was identified on SOW section IV.C.17.L. Please confirm thirty-two (32) sprinkler heads are to be replaced.

SOW Section IV.C.17.L: Sprinkler heads Confirmed. Thirty-two (32) sprinkler heads are to be replaced.

The SOW indicates a requirement to use R410A refrigerant. Due the federal regulations R410A is no longer permitted to be manufactured for new systems. Please confirm use of R32 or R454B refrigerants will be acceptable.

HVAC Refrigerant Refrigerant shall be as per current EPA requirements.

Please identify any LEED or other sustainablility criteria and/or standards required for this project.

LEED Standards See SOW pages 6 and 7, item 2. Sustainable Design and Building Requirements

To allow for generation of RFIs generated by the site visit and pre-bid meeting, will the government consider extending the RFI deadline to 10/09/2024?

RFI Extension Refer to Amendment #1_1605AE-24-R-00005_Potomac Bldg54 Renovations

Can we confirm that damage to the drywall was prior to the 2019 roof repair? If not has the roof been reevaluated for new leaks? Are there any new areas of drywall damage not already captured in SOW?

Yes, all drywall damage occurred before the 2019 roof repair. The roof has been repaired, and there are no new leaks. There are no additional areas of drywall damage, and all issues are included in the scope of work (SOW).

Please clarify if there any new areas of drywall damage not already captured in SOW. There are no additional areas of drywall damage, and all issues are included in the scope of work

(SOW).

SOW - Page 35 - (11. Architectural Woodwork b.) Please locate the new shelves in the plans.

Only the two shelves above each desk to be removed and replaced.

With regard to security / low voltage network cabling, AV requirements, alarm systems, access control, video, public address systems, gates, barriers and all door and door hardware - our organization is unique in that we cover all of these solutions with in-house personnel including locksmith, door repair and replacement experts, ADA door system installations, and ongoing support for all platforms. We also support most fire alarm platforms and monitoring of all systems. Please let us know if more information is required.

This is not a question. No response required.

Per the site visit, we noticed that most, if not all, of the existing cameras in other buildings and access control equipment all appear to be in EMT protected conduit. Question - is EMT conduit required for all security related points where the cabling is in an exposed or accessible area?

Yes, EMT conduit required for all security related points where the cabling is in an exposed or accessible area.

There is mention of additional credit for utilizing 8a contractors - please note the preference of the 8a contractor utilization as part of the vendor selection process.

This requirement has been set-aside for an 8(a) contractor.

Is there any preference for a DC resident company over others, such as Maryland or Virginia based organizations?

No. There are no preferences for a DC resident company over others, such as Maryland or Virginia based organizations

Will the Government confirm if the superintendent can also carry the duties of site safety manager and quality control manager for the subject project?

The Superintendent can carry the duties of safety manager if properly qualified. Quality control manager will remain a separate person.

If we are submitting as a JV, should we submit our JV agreement? If so, where/which proposal should we submit it with?

Yes, if using a joint venture, submit the JV agreement within one of the sections in Volume Two of the proposal.

158 The kind of refrigerant shall be by latest EPA requirements.

IV.B.15.c.11 (pg 49 of SOW) requires new refrigerant systems use R-410a. R-410a is currently being phased out with most manufacturers using R32 or R454B after January 2025. Will equipment with R32 or R454B be acceptable?

Government requests that the entire electrical, mechanical, roofing and HVAC controls be completed at the 60% design submission. Is this required or can this be modified for only long lead items?

Follow SOW, page 11/104, item 2.b.

161 Will government be providing cutsheets for anticipated dryers?