1603949-QMI ROAD ACCESS_GuardRail-Replacement-Drawing.pdf
PDF 10 MB Posted
- Attached to
- QMI ARSR Guardrail Replacement Federal contract opportunity
- Solicitation number
- 697DCK-26-R-00352
About this file
This is a set of construction design drawings for the Federal Aviation Administration (FAA) project to replace guardrails along the QMI ARSR (Airport Surveillance Radar Station) access road at Mica Peak in Washington State. The project encompasses approximately 4.6 miles of mountainous terrain descending from elevation 5,178 feet to 2,875 feet, with multiple construction stations from 0.0 to 4.6 miles downhill of the facility gate.
The construction scope includes installation of new MGS and G4 W-beam guardrails totaling approximately 5,030 linear feet, replacement of approximately 380 linear feet of damaged existing guardrails, and demolition of obsolete guardrail sections. The project requires coordination with existing utilities including Washington Water & Power Company power lines, Telephone Utilities of Moses Lake, and U.S. West Communications lines. Contractor responsibilities include site preparation, utility location coordination with FAA and Washington One Call Service, excavation and backfill with 95% soil compaction, installation of guardrail posts with specified spacing (typically 6'3"), and site restoration to match existing grades. The design references FLH Standards 617-13, 617-18, 617-19, 617-20, 617-31, 617-32, 617-37, and 617-38 for guardrail installation specifications, post embedment in rock, terminal systems, and steel post details. All construction activities must maintain facility operations, protect communication and electrical equipment, utilize temporary power and sanitary facilities, and comply with OSHA requirements and local safety regulations.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFIs - 697DCK-26-R-00352- QMI ARSR Guardrail Replacement.docx | DOCX document | |
| RFI 1603949-QMI Road Access GuardRail Replacement Specification.pdf | ||
| RFI SE-RE-468 QMI ROAD ACCESS Survey Map.pdf | ||
| 697DCK-26-R-00352 AMENDMENT 0001.pdf | ||
| 697DCK-26-R-00352.pdf | ||
| QMI-Guardrail Replacement_Project-SOW.pdf | ||
| Wage Determination WA20260001 06-16-26.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV DESCRIPTION JCN REDLINE
DATE APVD
SUBMITTED BY APPROVED BY
JCN
DRAWN
CHECKED
REV
ISSUED BY
H
G
F
E
D
C
B
A
8 1234567
DATE
DRAWING NO
DESIGNED
REVIEWED BY
D
A T
E
T
IM
E
N A
M E
APPROVED
DATE
F
IL
E
S
8 234567
H
G
F
E
D
C
A
B
IS
SU
E D
F O
R
E D
M
MGR: ENGINEERING - SEATTLE
MICA PEAK
ARSR
REPLACE GUARDRAILS ALONG QMI ARSR ACCESS ROAD
COVER SHEET & VICINITY MAP
Q M
I-
-G
1.
dw g
ATO - TECHNICAL OPERATIONS WESTERN SERVICE AREA
C O
N S
T R
U C
T
IO
N
WA
DRAWING PRODUCED ON WSA MICROSTATION SYSTEM
PROJECT ENGINEER
1603949
FOR OFFICIAL USE ONLY
PUBLIC AVAILABILITY TO BE DETERMINED UNDER 5 USC 552
SITE DATA
OWNER: FEDERAL AVIATION ADMINISTRATION
MICA PEAK (QMI) ARSR FACILITY:(PROJECT START POINT AT TOP)
LOCATION: T. 24 N., R. 45 E., W.M., SEC. 14 STAT OF WASHINGTON
PLANE COORDINATE SYSTEM USC AND GS 1933 MARKER AT
231789.250 & 2925962.44
LATITUDE/ LONGITUDE: 47°34'27.7"N / 117°04'51.4"W
ELEVATION: 5178FT MSL AT FACILITY
FMP STATION AT DOWNHILL: (PROJECT END POINT)
LATITUDE/ LONGITUDE: 47°31'34.4"N / 117°04'11.3"W
ELEVATION: 2875FT MSL
POWER: WASHINGTON WATER & POWER CO.
TELEPHONE: TELEPHONE UTILITIES OF MOSES LAKE
U.S. WEST COMMUNICATIONS INC.
PROJECT SITE
START POINT:
47°34'27.7"N 117°04'51.4"W
END POINT:
47°31'34.4"N 117°04'11.3"W
VICINITY MAP
REV DESCRIPTION JCN REDLINE
DATE APVD
SUBMITTED BY APPROVED BY
JCN
DRAWN
CHECKED
REV
ISSUED BY
H
G
F
E
D
C
B
A
8 1234567
DATE
DRAWING NO
DESIGNED
REVIEWED BY
D
A T
E
T
IM
E
N A
M E
APPROVED
DATE
F
IL
E
S
8 234567
H
G
F
E
D
C
A
B
IS
SU
E D
F O
R
E D
M
MGR: ENGINEERING - SEATTLE
MICA PEAK
ARSR
REPLACE GUARDRAILS ALONG QMI ARSR ACCESS ROAD
GENERAL CONSTRUCTION NOTE
Q M
I-
-C
1.
dw g
ATO - TECHNICAL OPERATIONS WESTERN SERVICE AREA
C O
N S
T R
U C
T
IO
N
WA
PROJECT ENGINEER
1603949
THE CONTRACTOR CONSTRUCTION SAFETY MANUAL SHALL COMPLY WITH OSHA
29 CFR 1910 AND 29 CFR 1926.
LOCATIONS AND ELEVATIONS OF EXISTING FEATURES TO BE VERIFIED
BY FIELD MEASUREMENTS PRIOR TO CONSTRUCTION OF NEW WORK.
ALL DIMENSIONS ARE TO BE VERIFIED IN THE FIELD. ANY
DISCREPANCIES FOUND BETWEEN THE DRAWINGS AND SPECIFICATIONS
AND SITE CONDITION OR ANY INCONSISTENCIES OR AMBIGUITIES IN
THE DRAWINGS OR SPECIFICATIONS SHALL BE IMMEDIATELY REPORTED
TO THE RESIDENT ENGINEER (RE) IN WRITING, WHO SHALL CORRECT
SUCH INCONSISTENCIES OR AMBIGUITIES IN WRITING. THE CONTRACTOR
SHALL NOT PERFORM ANY WORK BEFORE VERIFICATION AND AFTER
DISCOVERY OF SUCH DISCREPANCIES, INCONSISTENCIES, OR AMBIGUITIES
WITHOUT WRITTEN RE AUTHORIZATION. ANY WORK PERFORMED BY THE
CONTRACTOR AFTER DISCOVERY OF SUCH DISCREPANCIES WITHOUT PRIOR
WRITTEN AUTHORIZATION BY RE WILL BE CONSIDERED TO BE DONE AT THE
CONTRACTOR'S RISK.
FINISHED GRADE SHALL BE SLOPED AT A UNIFORM SLOPE BETWEEN
SPOT ELEVATIONS.
ALL FILL MATERIAL SHALL MEET REQUIREMENTS AS OUTLINED IN THE
PROJECT SPECIFICATIONS.
THE CONTRACTOR SHALL BE RESPONSIBLE FOR ENSURING THAT ALL
SLOPES ARE BUILT IN ACCORDANCE WITH THESE PLANS. IF THERE IS
ANY QUESTION REGARDING THESE PLANS, THE CONTRACTOR SHALL
REQUEST AN INTERPRETATION BEFORE DOING ANY WORK. THE
CONTRACTOR SHALL ALSO TAKE NECESSARY STEPS TO PROTECT
THE PROJECT AND ADJACENT PROPERTY FROM ANY EROSION AND
SILTATION THAT RESULT FROM THEIR OPERATIONS BY APPROPRIATE
MEANS, (SAND BAGS, TEMPORARY DESILTING BASINS, DIKES, ETC.) UNTIL SUCH
TIME THAT THE PROJECT IS COMPLETED AND ACCEPTED BY FAA.
PRIOR TO ANY EXCAVATIONS UNDER THIS CONTRACT, THE
CONTRACTOR SHALL PERFORM GPRS UTILITY LOCATE TO IDENTIFY
ALL UTILITIES AT THE SITE. CONTRACTOR SHALL POTHOLE AND
HAND EXCAVATE NEAR KNOWN UTILITY LINES TO PREVENT EXCAVATION DAMAGE
TO UNDERGROUND UTILITIES.
THE CONTRACTOR SHALL TAKE PRECAUTIONARY MEASURES TO
PROTECT WITHIN THE SITE, ALL UTILITY LINES, EXISTING PERMANENT
STRUCTURES AND ANY OTHER EXISTING LINES THAT ARE NOT OF
RECORD OR SHOWN ON PLANS. ANY UTILITIES OR STRUCTURES
DAMAGED DURING THE COURSE OF CONSTRUCTION SHALL BE
IMMEDIATELY REPAIRED AND/OR REPLACED BY THE CONTRACTOR,
UNLESS APPROVED OTHERWISE BY THE RE, TO A CONDITION EQUAL
TO OR BETTER THAN THE EXISTING AND AS APPROVED BY THE RE.
THE CONTRACTOR SHALL BE RESPONSIBLE FOR RESTORING ANY
MONUMENTATION AND/OR BENCHMARKS THAT ARE DISTURBED OR
DESTROYED BY CONSTRUCTION. SUCH POINTS SHALL BE REFERENCED
AND REPLACED WITH APPROPRIATE MONUMENTATION BY A LICENSED
SURVEYOR AT THE CONTRACTOR'S SOLE EXPENSE.
THE CONTRACTOR SHALL SECURE ANY REQUIRED PERMITS FOR
CONSTRUCTION PRIOR TO THE START OF CONSTRUCTION.
THE CONTRACTOR IS HEREBY NOTIFIED THAT ESSENTIAL AND
PERTINENT INFORMATION REGARDING THE CONSTRUCTION AND
COMPLETION OF WORK FOR THIS PROJECT IS CONTAINED IN THE
CONTRACT DOCUMENTS AND SPECIFICATIONS. IT IS THE CONTRACTOR'S
RESPONSIBILITY TO READ AND REVIEW THIS INFORMATION TO THEIR
OWN SATISFACTION PRIOR TO PERFORMING ANY WORK. ANY DEFICIENT,
INCOMPLETE OR INCORRECT WORK SHALL BE REDONE TO MEET
REQUIREMENTS AT THE CONTRACTOR'S SOLE EXPENSE.
THE CONTRACTOR SHALL DESIGN, CONSTRUCT, AND MAINTAIN ALL
SAFETY DEVICES, AND SHALL BE SOLELY RESPONSIBLE FOR CONFORMING TO ALL
LOCAL, STATE, AND FEDERAL SAFETY AND HEALTH STANDARDS, LAWS AND
REGULATIONS.
THE CONTRACTOR AGREES TO ASSUME SOLE AND COMPLETE
RESPONSIBILITY FOR JOB SITE CONDITIONS DURING THE COURSE OF
CONSTRUCTION OF THIS PROJECT, INCLUDING SAFETY OF ALL PERSONS AND
PROPERTY. CONTRACTOR FURTHER AGREES THAT THIS REQUIREMENT SHALL
APPLY CONTINUOUSLY AND NOT BE LIMITED TO NORMAL WORKING HOURS AND
THAT THE CONTRACTOR SHALL DEFEND; INDEMNIFY AND HOLD THE FAA
HARMLESS FROM ANY AND ALL LIABILITY, REAL OR ALLEGED IN CONNECTION WITH
THE PERFORMANCE OF WORK ON THIS PROJECT.
EXISTING VEHICULAR ACCESS TO SITE SHALL BE KEPT IN SERVICE
DURING THE COURSE OF CONSTRUCTION. THE CONTRACTOR SHALL
PREPARE A PLAN SHOWING PROPOSED LOCATIONS OF STAGING, STORAGE OF
MATERIALS, AND VEHICLES ON SITE TO BE SUBMITTED TO THE RESIDENT
ENGINEER FOR REVIEW, COMMENT AND/OR APPROVAL PRIOR TO START OF
CONSTRUCTION. DUE TO LIMITED SPACE ON SITE, CONTRACTOR SHALL
COORDINATE WITH RE FOR ADDITIONAL AREAS REQUIRED FOR MATERIAL AND
EQUIPMENT STORAGE.
THE NORMAL ACTIVITIES WITHIN THE FACILITY WILL CONTINUE DURING
CONSTRUCTION. CONTRACTOR SHALL DEVISE A DETAILED WORK
SCHEDULE AND CLOSELY COORDINATE WITH THE RE FOR ALL
ACTIVITIES. THE CONTRACTOR SHALL USE GREAT CARE AND
CAUTION WHILE WORKING WITHIN THE EXISTING FACILITY
(SITE AND BUILDINGS) AS NOT TO DISRUPT THE FUNCTIONS OF
THIS FAA FACILITY.
IT IS ABSOLUTELY MANDATORY THAT THE CONTRACTOR PROTECT
ALL NEW AND EXISTING COMMUNICATION EQUIPMENT, ELECTRICAL AND
MECHANICAL EQUIPMENT, BOTH INSIDE AND OUTSIDE THE BUILDING
FROM DAMAGE.
STAGING AND STORAGE OF CONSTRUCTION MATERIAL AND EQUIPMENT
SHALL BE LIMITED TO THE CONSTRUCTION STAGING AREA.
CONTRACTOR'S PARKING AREA SHALL BE DETERMINED AT THE
PRE-CONSTRUCTION CONFERENCE. MATERIALS SHALL BE NEATLY
STORED AND PROTECTED AT ALL TIMES. UPON COMPLETION OF
WORK THE CONTRACTOR SHALL RESTORE THIS AREA BACK TO
ITS ORIGINAL PRE-CONSTRUCTION CONDITION.
ALL CONSTRUCTION MATERIAL SHALL BE REASSEMBLED TO AN
OPTIMUM SIZE AND WEIGHT TO MINIMIZE ACTIVITIES WITHIN THE
FACILITY. CONTRACTOR SHALL VERIFY ACCESS PATHWAYS WITH RE
BEFORE START OF CONSTRUCTION.
WELDING & CADWELDING REQUIRES A HOT WORK PERMIT. WELDING
AND HEAVY CONSTRUCTION SHALL BE DONE OUTSIDE IN TEMPORARY
CONSTRUCTION AREAS AS DETERMINED BY THE RE AND TO BE
CLEANED UP AT THE END OF THE DAY. CONTRACTOR SHALL PROVIDE
THEIR OWN POWER FOR THESE OPERATIONS. NO WELDING OR HEAVY
CONSTRUCTION IS PERMITTED INSIDE THE BUILDING AS IT MAY DAMAGE
OR INTERFERE WITH ELECTRONICS EQUIPMENT.
ENCLOSED DUMPSTERS FOR DISPOSAL OF CONSTRUCTION DEBRIS
SHALL BE PROVIDED BY THE CONTRACTOR WITHIN AREA
DESIGNATED BY RE AT THE PRE-CONSTRUCTION MEETING. THE AREA
AROUND THE DUMPSTERS SHALL BE KEPT CLEAN AND FREE OF
EXCESS DEBRIS AND DUST DURING CONSTRUCTION. ALL DEBRIS
SHALL BE REMOVED BY CONTRACTOR. ANY WASTE THAT CAN
ATTRACT WILDLIFE SHALL BE REMOVED FROM THE SITE DAILY.
FAA DUMPSTER SHALL NOT BE USED BY CONTRACTOR.
CONSTRUCTION DEBRIS MUST BE REMOVED DAILY.
CONTRACTOR SHALL PROVIDE TEMPORARY UTILITIES DURING
CONSTRUCTION. VERIFY TEMPORARY UTILITIES LOCATIONS AND
USE AS PERMITTED BY RE.
THE CONTRACTOR SHALL PROVIDE SANITARY TOILET FACILITIES
WITH WATER FOR THE WORKERS AND RE.
THE CONTRACTOR SHALL PROVIDE TEMPORARY POWER FOR ALL
CONSTRUCTION ACTIVITIES. CONSTRUCTION TOOLS SHALL BE
POWERED FROM THE TEMPORARY POWER SOURCE ONLY. ALL
POWER TOOLS SHALL BE PRE-APPROVED BY THE RE.
SHUTDOWN AND CUTOVERS OF ENVIRONMENTAL AND ELECTRICAL
SYSTEMS SHALL BE PERFORMED BY FAA PERSONNEL AND NOT
BY CONTRACTOR. ALL PREPARATORY WORK FOR SHUTDOWN
AND CUTOVER SHALL BE SCHEDULED AND COORDINATED WITH THE
RE A MINIMUM OF 10 WORKING DAYS IN ADVANCE.
WHERE NEW WORK IS TO BE CONNECTED TO EXISTING WORK,
EXERCISE CARE NOT TO DISTURB OR DAMAGE EXISTING WORK.
USE SACRIFICIAL LAYERS OF PROPER MATERIAL AT THE POINT OF
CONNECTIONS BETWEEN DISSIMILAR METALS WHERE IT APPLIES.
CONTRACTOR TO PROPERLY DISPOSE/REMOVE HAZARDOUS
MATERIALS IN ACCORDANCE WITH SPECIFICATION SECTION 02 82 00.
REPAIR DAMAGED GALVANIZATION PER SPECIFICATIONS SECTION 09 97
00, SPECIAL COATINGS.
ALL HOT-DIPPED GALVANIZED METALS SHALL BE PAINTED PER
SPECIFICATIONS SECTION 09 97 00, SPECIAL COATINGS.
GENERAL NOTES
1. 15.
26.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
27.
28.
29.
REV DESCRIPTION JCN REDLINE
DATE APVD
SUBMITTED BY APPROVED BY
JCN
DRAWN
CHECKED
REV
ISSUED BY
H
G
F
E
D
C
B
A
8 1234567
DATE
DRAWING NO
DESIGNED
REVIEWED BY
D
A T
E
T
IM
E
N A
M E
APPROVED
DATE
F
IL
E
S
8 234567
H
G
F
E
D
C
A
B
IS
SU
E D
F O
R
E D
M
MGR: ENGINEERING - SEATTLE
MICA PEAK
ARSR
REPLACE GUARDRAILS ALONG QMI ARSR ACCESS ROAD
EXISTING ROAD MAP & PROFILE
Q M
I-
-C
2.
dw g
ATO - TECHNICAL OPERATIONS WESTERN SERVICE AREA
C O
N S
T R
U C
T
IO
N
WA
PROJECT ENGINEER
1603949
NOT TO SCALE
ROAD MAP W/ EXISTING FEATURES
NOT TO SCALE
ROAD PROFILE
REV DESCRIPTION JCN REDLINE
DATE APVD
SUBMITTED BY APPROVED BY
JCN
DRAWN
CHECKED
REV
ISSUED BY
H
G
F
E
D
C
B
A
8 1234567
DATE
DRAWING NO
DESIGNED
REVIEWED BY
D
A T
E
T
IM
E
N A
M E
APPROVED
DATE
F
IL
E
S
8 234567
H
G
F
E
D
C
A
B
IS
SU
E D
F O
R
E D
M
MGR: ENGINEERING - SEATTLE
MICA PEAK
ARSR
REPLACE GUARDRAILS ALONG QMI ARSR ACCESS ROAD
STATION: 0.00 TO 1.05 MILE
Q M
I-
-C
3.
dw g
ATO - TECHNICAL OPERATIONS WESTERN SERVICE AREA
C O
N S
T R
U C
T
IO
N
WA
PROJECT ENGINEER
1603949 10' 0 10' 20'
SCALE: 1" = 10'
1 1100± LF NEW GUARDRAIL
180± LF NEW GUARDRAIL
150± LF REPLACED GUARDRAIL
DEMOLISH/ REPLACED
NEW GUARDRAIL
DEMOLITION / SITE CLEAN UP NOTES
PREPARE THE AREA FOR DEMOLITION OF EXISTING GUARDRAILS AS REQUIRED. PROTECT
ALL EXISTING UTILITIES. DEMOLISH EXISTING DAMAGED GUARDRAILS AS SHOWN. VERIFY
THE LOCATION WITH RE PRIOR TO DEMOLITION.
BACK FILL ALL HOLES CREATED BY CONSTRUCTION AND DEMOLITION. COMPACT THE SOIL
AND PATCH THE AFFECTED AREA TO MATCH EXISTING GRADE AND ADJACENT PAVING
MATERIAL.
DISCARD ALL OBSOLETE MATERIAL PROPERLY. COORDINATE WITH RE AND SSC.
COORDINATE WITH FAA AND WASHINGTON ONE CALL SERVICE AND PROCURE THIRD
PARTY UTILITY LOCATING SERVICE TO LOCATE ALL UNDERGROUND CABLES (INCLUDING
TELCO LINE, POWER LINE AND U/G UTILITIES) PRIOR TO ANY CONSTRUCTION ACTIVITY.
CONSTRUCTION AND INSTALLATION OF NEW GUARDRAILS INCLUDES THE NEW OR
REPLACEMENT OF THE EXISTING DAMAGED RAILS AT MICKA PEAK ACCESS ROAD AS
INDICATED IN C001~C008.
PREPARE THE SITE FOR CONSTRUCTION OF NEW GUARDRAIL AT LOCATIONS SHOWN.
COORDINATE WITH RE & SSC TO LOCATE AND SETUP THE STAGING AREA AND
TEMPORARY FACILITIES. CONTRACTOR TO COORDINATE WITH RE FOR ACCESS ROUTE
AS NEEDED.
THE LOCATION OF THE NEW REPLACEMENT GUARDRAILS IS TENTATIVE. CONTRACTOR
SHALL COORDINATE WITH SSC & RE FOR FINAL LOCATION. VERIFY SITE UTILITIES BEFORE
START OF EXCAVATION.
INSTALLATION OF NEW BARRIER INCLUDES BUT IS NOT LIMITED TO INSTALLING WBEAMS,
SUPPORTS, AND EARTHWORK INCLUDING EXCAVATION AND BACKFILL WITH THESE
CONSTRUCTION DRAWINGS AND STANDARDS ATTACHED TO.
CONTRACTOR SHALL HAND DIG TO LOCATE ALL UNDERGROUND CABLES WHEN
EXCAVATION AROUND EXISTING STRUCTURES.
BACK FILL ALL HOLES CREATED BY CONSTRUCTION. COMPACT THE SOIL (INSIDE THE
ROAD AREA) TO 95% DENSITY AND PATCH THE AFFECTED AREA TO MATCH EXISTING
GRADE AND ADJACENT PAVING MATERIAL.
CONSTRUCTION NOTES:
A
B
C
D
E
F
G
H
I
J
NOT TO SCALE
ROAD STA.0.00~1.05 MILE DOWNHILL OF GATE
180± LF NEW GUARDRAIL
APPROXIMATE START POINT:
0.65 MILE DOWNHILL OF QMI ARSR
FACILITY GATE
150± LF REPLACED GUARDRAIL
(SAME AMOUNT OF DAMAGED
GUARDRAIL TO BE DEMOLISHED
AND REMOVED)
APPROXIMATE START POINT:
0.3 MILE DOWNHILL OF QMI ARSR
FACILITY GATE
1100± LF NEW GUARDRAIL
APPROXIMATE START POINT:
420FT DOWNHILL OF QMI ARSR
FACILITY GATE
START POINT:
QMI ARSR FACILITY GATE
47°34'27.7"N 117°04'51.4"W
LAST ABOVE GROUND
POWER LINE POLE
G POWER POLE# 459568 /
U/G POWER LINE
THE EXACT LOCATION TO
BE FIELD VERIFIED
EXISTING U/G POWER LINE
REV DESCRIPTION JCN REDLINE
DATE APVD
SUBMITTED BY APPROVED BY
JCN
DRAWN
CHECKED
REV
ISSUED BY
H
G
F
E
D
C
B
A
8 1234567
DATE
DRAWING NO
DESIGNED
REVIEWED BY
D
A T
E
T
IM
E
N A
M E
APPROVED
DATE
F
IL
E
S
8 234567
H
G
F
E
D
C
A
B
IS
SU
E D
F O
R
E D
M
MGR: ENGINEERING - SEATTLE
MICA PEAK
ARSR
REPLACE GUARDRAILS ALONG QMI ARSR ACCESS ROAD
STATION: 1.05MILE TO 2.25MILE
Q M
I-
-C
4.
dw g
ATO - TECHNICAL OPERATIONS WESTERN SERVICE AREA
C O
N S
T R
U C
T
IO
N
WA
PROJECT ENGINEER
1603949
NOT TO SCALE
ROAD STA. 1.05 ~1.45 MILE DOWNHILL OF GATE
4 1600± LF NEW GUARDRAIL
350± LF NEW GUARDRAIL
NEW GUARDRAIL
NOT TO SCALE
ROAD STA. 1.45 ~1.85 MILE DOWNHILL OF GATE
NOT TO SCALE
ROAD STA. 1.85~2.25 MILE DOWNHILL OF GATE
DEMOLITION / SITE CLEAN UP NOTES
PREPARE THE AREA FOR DEMOLITION OF EXISTING GUARDRAILS AS REQUIRED. PROTECT
ALL EXISTING UTILITIES. DEMOLISH EXISTING DAMAGED GUARDRAILS AS SHOWN. VERIFY
THE LOCATION WITH RE PRIOR TO DEMOLITION.
BACK FILL ALL HOLES CREATED BY CONSTRUCTION AND DEMOLITION. COMPACT THE SOIL
AND PATCH THE AFFECTED AREA TO MATCH EXISTING GRADE AND ADJACENT PAVING
MATERIAL.
DISCARD ALL OBSOLETE MATERIAL PROPERLY. COORDINATE WITH RE AND SSC.
COORDINATE WITH FAA AND WASHINGTON ONE CALL SERVICE AND PROCURE THIRD
PARTY UTILITY LOCATING SERVICE TO LOCATE ALL UNDERGROUND CABLES (INCLUDING
TELCO LINE, POWER LINE AND U/G UTILITIES) PRIOR TO ANY CONSTRUCTION ACTIVITY.
CONSTRUCTION AND INSTALLATION OF NEW GUARDRAILS INCLUDES THE NEW OR
REPLACEMENT OF THE EXISTING DAMAGED RAILS AT MICKA PEAK ACCESS ROAD AS
INDICATED IN C001~C008.
PREPARE THE SITE FOR CONSTRUCTION OF NEW GUARDRAIL AT LOCATIONS SHOWN.
COORDINATE WITH RE & SSC TO LOCATE AND SETUP THE STAGING AREA AND
TEMPORARY FACILITIES. CONTRACTOR TO COORDINATE WITH RE FOR ACCESS ROUTE
AS NEEDED.
THE LOCATION OF THE NEW REPLACEMENT GUARDRAILS IS TENTATIVE. CONTRACTOR
SHALL COORDINATE WITH SSC & RE FOR FINAL LOCATION. VERIFY SITE UTILITIES BEFORE
START OF EXCAVATION.
INSTALLATION OF NEW BARRIER INCLUDES BUT IS NOT LIMITED TO INSTALLING WBEAMS,
SUPPORTS, AND EARTHWORK INCLUDING EXCAVATION AND BACKFILL WITH THESE
CONSTRUCTION DRAWINGS AND STANDARDS ATTACHED TO.
CONTRACTOR SHALL HAND DIG TO LOCATE ALL UNDERGROUND CABLES WHEN
EXCAVATION AROUND EXISTING STRUCTURES.
BACK FILL ALL HOLES CREATED BY CONSTRUCTION. COMPACT THE SOIL (INSIDE THE
ROAD AREA) TO 95% DENSITY AND PATCH THE AFFECTED AREA TO MATCH EXISTING
GRADE AND ADJACENT PAVING MATERIAL.
CONSTRUCTION NOTES:
A
B
C
D
E
F
G
H
I
J
1600± LF NEW GUARDRAIL
APPROXIMATE START POINT:
1.70 MILE DOWNHILL OF QMI ARSR
FACILITY GATE 350± LF NEW GUARDRAIL
APPROXIMATE START POINT:
2.1 MILE DOWNHILL OF QMI ARSR
FACILITY GATE
DEMOLITION / SITE CLEAN UP NOTES
PREPARE THE AREA FOR DEMOLITION OF EXISTING GUARDRAILS AS REQUIRED. PROTECT
ALL EXISTING UTILITIES. DEMOLISH EXISTING DAMAGED GUARDRAILS AS SHOWN. VERIFY
THE LOCATION WITH RE PRIOR TO DEMOLITION.
BACK FILL ALL HOLES CREATED BY CONSTRUCTION AND DEMOLITION. COMPACT THE SOIL
AND PATCH THE AFFECTED AREA TO MATCH EXISTING GRADE AND ADJACENT PAVING
MATERIAL.
DISCARD ALL OBSOLETE MATERIAL PROPERLY. COORDINATE WITH RE AND SSC.
COORDINATE WITH FAA AND WASHINGTON ONE CALL SERVICE AND PROCURE THIRD
PARTY UTILITY LOCATING SERVICE TO LOCATE ALL UNDERGROUND CABLES (INCLUDING
TELCO LINE, POWER LINE AND U/G UTILITIES) PRIOR TO ANY CONSTRUCTION ACTIVITY.
CONSTRUCTION AND INSTALLATION OF NEW GUARDRAILS INCLUDES THE NEW OR
REPLACEMENT OF THE EXISTING DAMAGED RAILS AT MICKA PEAK ACCESS ROAD AS
INDICATED IN C001~C008.
PREPARE THE SITE FOR CONSTRUCTION OF NEW GUARDRAIL AT LOCATIONS SHOWN.
COORDINATE WITH RE & SSC TO LOCATE AND SETUP THE STAGING AREA AND
TEMPORARY FACILITIES. CONTRACTOR TO COORDINATE WITH RE FOR ACCESS ROUTE
AS NEEDED.
THE LOCATION OF THE NEW REPLACEMENT GUARDRAILS IS TENTATIVE. CONTRACTOR
SHALL COORDINATE WITH SSC & RE FOR FINAL LOCATION. VERIFY SITE UTILITIES BEFORE
START OF EXCAVATION.
INSTALLATION OF NEW BARRIER INCLUDES BUT IS NOT LIMITED TO INSTALLING WBEAMS,
SUPPORTS, AND EARTHWORK INCLUDING EXCAVATION AND BACKFILL WITH THESE
CONSTRUCTION DRAWINGS AND STANDARDS ATTACHED TO.
CONTRACTOR SHALL HAND DIG TO LOCATE ALL UNDERGROUND CABLES WHEN
EXCAVATION AROUND EXISTING STRUCTURES.
BACK FILL ALL HOLES CREATED BY CONSTRUCTION. COMPACT THE SOIL (INSIDE THE
ROAD AREA) TO 95% DENSITY AND PATCH THE AFFECTED AREA TO MATCH EXISTING
GRADE AND ADJACENT PAVING MATERIAL.
CONSTRUCTION NOTES:
FEDERAL AVIATION ADMINISTRATION
DEPARTMENT OF TRANSPORTATION
REV DESCRIPTION JCN REDLINE
DATE APVD
SUBMITTED BY APPROVED BY
JCN
DRAWN
CHECKED
REV
ISSUED BY
H
G
F
E
D
C
B
A
8 1234567
DATE
DRAWING NO
DESIGNED
REVIEWED BY
D
A T
E
T
IM
E
N A
M E
APPROVED
DATE
F
IL
E
S
8 234567
H
G
F
E
D
C
A
B
IS
SU
E D
F O
R
E D
M
MGR: ENGINEERING - SEATTLE
MICA PEAK
ARSR
REPLACE GUARDRAILS ALONG QMI ARSR ACCESS ROAD
STATION: 2.25MILE TO 3.25MILE
Q M
I-
-C
5.
dw g
ATO - TECHNICAL OPERATIONS WESTERN SERVICE AREA
C O
N S
T R
U C
T
IO
N
WA
PROJECT ENGINEER
1603949
A
B
C
D
E
F
G
H
I
J
NOT TO SCALE
ROAD STA.2.25~2.75 MILE DOWNHILL OF GATE
NOT TO SCALE
ROAD STA. 2.75~3.25 MILE DOWNHILL OF GATE
8.1
6 450± LF NEW GUARDRAIL
250± LF NEW GUARDRAIL
350± LF NEW GUARD RAIL
8.2
DEMOLISH/ REPLACED
NEW GUARDRAIL
110± LF REPLACED GUARDRAIL
8.1
8.2
450± LF NEW GUARDRAIL
APPROXIMATE START POINT:
2.3 MILE DOWNHILL OF QMI ARSR
FACILITY GATE
250± LF NEW GUARDRAIL
APPROXIMATE START POINT:
2.62 MILE DOWNHILL OF QMI ARSR
FACILITY GATE
110± LF REPLACED GUARDRAIL
APPROXIMATE START POINT:
3.12 MILE DOWNHILL OF QMI ARSR
FACILITY GATE
350± LF NEW GUARDRAIL
APPROXIMATE START POINT:
3.15 MILE DOWNHILL OF QMI ARSR
REV DESCRIPTION JCN REDLINE
DATE APVD
SUBMITTED BY APPROVED BY
JCN
DRAWN
CHECKED
REV
ISSUED BY
H
G
F
E
D
C
B
A
8 1234567
DATE
DRAWING NO
DESIGNED
REVIEWED BY
D
A T
E
T
IM
E
N A
M E
APPROVED
DATE
F
IL
E
S
8 234567
H
G
F
E
D
C
A
B
IS
SU
E D
F O
R
E D
M
MGR: ENGINEERING - SEATTLE
MICA PEAK
ARSR
REPLACE GUARDRAILS ALONG QMI ARSR ACCESS ROAD
STATION: 3.25MILE TO 3.90MILE
Q M
I-
-C
6.
dw g
ATO - TECHNICAL OPERATIONS WESTERN SERVICE AREA
C O
N S
T R
U C
T
IO
N
WA
PROJECT ENGINEER
1603949NOT TO SCALE
ROAD STA. 3.25~3.90 MILE DOWNHILL OF GATE
COORDINATE WITH FAA AND WASHINGTON ONE CALL SERVICE AND PROCURE THIRD
PARTY UTILITY LOCATING SERVICE TO LOCATE ALL UNDERGROUND CABLES (INCLUDING
TELCO LINE, POWER LINE AND U/G UTILITIES) PRIOR TO ANY CONSTRUCTION ACTIVITY.
CONSTRUCTION AND INSTALLATION OF NEW GUARDRAILS INCLUDES THE NEW OR
REPLACEMENT OF THE EXISTING DAMAGED RAILS AT MICKA PEAK ACCESS ROAD AS
INDICATED IN C001~C008.
PREPARE THE SITE FOR CONSTRUCTION OF NEW GUARDRAIL AT LOCATIONS SHOWN.
COORDINATE WITH RE & SSC TO LOCATE AND SETUP THE STAGING AREA AND
TEMPORARY FACILITIES. CONTRACTOR TO COORDINATE WITH RE FOR ACCESS ROUTE
AS NEEDED.
THE LOCATION OF THE NEW REPLACEMENT GUARDRAILS IS TENTATIVE. CONTRACTOR
SHALL COORDINATE WITH SSC & RE FOR FINAL LOCATION. VERIFY SITE UTILITIES BEFORE
START OF EXCAVATION.
INSTALLATION OF NEW BARRIER INCLUDES BUT IS NOT LIMITED TO INSTALLING WBEAMS,
SUPPORTS, AND EARTHWORK INCLUDING EXCAVATION AND BACKFILL WITH THESE
CONSTRUCTION DRAWINGS AND STANDARDS ATTACHED TO.
CONTRACTOR SHALL HAND DIG TO LOCATE ALL UNDERGROUND CABLES WHEN
EXCAVATION AROUND EXISTING STRUCTURES.
BACK FILL ALL HOLES CREATED BY CONSTRUCTION. COMPACT THE SOIL (INSIDE THE
ROAD AREA) TO 95% DENSITY AND PATCH THE AFFECTED AREA TO MATCH EXISTING
GRADE AND ADJACENT PAVING MATERIAL.
CONSTRUCTION NOTES:
A
B
C
D
E
F
G
9 180± LF NEW GUARDRAIL
NEW GUARDRAIL180± LF NEW GUARDRAIL
APPROXIMATE START POINT:
3.6 MILE DOWNHILL OF QMI ARSR
REV DESCRIPTION JCN REDLINE
DATE APVD
SUBMITTED BY APPROVED BY
JCN
DRAWN
CHECKED
REV
ISSUED BY
H
G
F
E
D
C
B
A
8 1234567
DATE
DRAWING NO
DESIGNED
REVIEWED BY
D
A T
E
T
IM
E
N A
M E
APPROVED
DATE
F
IL
E
S
8 234567
H
G
F
E
D
C
A
B
IS
SU
E D
F O
R
E D
M
MGR: ENGINEERING - SEATTLE
MICA PEAK
ARSR
REPLACE GUARDRAILS ALONG QMI ARSR ACCESS ROAD
STATION: 3.90MILE TO 4.60MILE
Q M
I-
-C
7.
dw g
ATO - TECHNICAL OPERATIONS WESTERN SERVICE AREA
C O
N S
T R
U C
T
IO
N
WA
PROJECT ENGINEER
1603949
200± LF NEW GUARDRAIL
NEW GUARDRAIL
NOT TO SCALE
ROAD STA. 3.90~4.60MILE DOWNHILL OF GATE
20± LF REPLACED GUARDRAIL
DEMOLISH/ REPLACED
ENTRANCE (DOWNHILL) GATE:
47°31'34.4"N 117°04'11.2"W
DEMOLITION / SITE CLEAN UP NOTES
PREPARE THE AREA FOR DEMOLITION OF EXISTING GUARDRAILS AS REQUIRED. PROTECT
ALL EXISTING UTILITIES. DEMOLISH EXISTING DAMAGED GUARDRAILS AS SHOWN. VERIFY
THE LOCATION WITH RE PRIOR TO DEMOLITION.
BACK FILL ALL HOLES CREATED BY CONSTRUCTION AND DEMOLITION. COMPACT THE SOIL
AND PATCH THE AFFECTED AREA TO MATCH EXISTING GRADE AND ADJACENT PAVING
MATERIAL.
DISCARD ALL OBSOLETE MATERIAL PROPERLY. COORDINATE WITH RE AND SSC.
COORDINATE WITH FAA AND WASHINGTON ONE CALL SERVICE AND PROCURE THIRD
PARTY UTILITY LOCATING SERVICE TO LOCATE ALL UNDERGROUND CABLES (INCLUDING
TELCO LINE, POWER LINE AND U/G UTILITIES) PRIOR TO ANY CONSTRUCTION ACTIVITY.
CONSTRUCTION AND INSTALLATION OF NEW GUARDRAILS INCLUDES THE NEW OR
REPLACEMENT OF THE EXISTING DAMAGED RAILS AT MICKA PEAK ACCESS ROAD AS
INDICATED IN C001~C008.
PREPARE THE SITE FOR CONSTRUCTION OF NEW GUARDRAIL AT LOCATIONS SHOWN.
COORDINATE WITH RE & SSC TO LOCATE AND SETUP THE STAGING AREA AND
TEMPORARY FACILITIES. CONTRACTOR TO COORDINATE WITH RE FOR ACCESS ROUTE
AS NEEDED.
THE LOCATION OF THE NEW REPLACEMENT GUARDRAILS IS TENTATIVE. CONTRACTOR
SHALL COORDINATE WITH SSC & RE FOR FINAL LOCATION. VERIFY SITE UTILITIES BEFORE
START OF EXCAVATION.
INSTALLATION OF NEW BARRIER INCLUDES BUT IS NOT LIMITED TO INSTALLING WBEAMS,
SUPPORTS, AND EARTHWORK INCLUDING EXCAVATION AND BACKFILL WITH THESE
CONSTRUCTION DRAWINGS AND STANDARDS ATTACHED TO.
CONTRACTOR SHALL HAND DIG TO LOCATE ALL UNDERGROUND CABLES WHEN
EXCAVATION AROUND EXISTING STRUCTURES.
BACK FILL ALL HOLES CREATED BY CONSTRUCTION. COMPACT THE SOIL (INSIDE THE
ROAD AREA) TO 95% DENSITY AND PATCH THE AFFECTED AREA TO MATCH EXISTING
GRADE AND ADJACENT PAVING MATERIAL.
CONSTRUCTION NOTES:
A
B
C
D
E
F
G
H
I
J
10.1
10.2
10.2 10.1
200± LF NEW GUARDRAIL
APPROXIMATE START POINT:
4.4 MILE DOWNHILL OF QMI ARSR
FACILITY GATE
20± LF REPLACED GUARDRAIL
(SAME AMOUNT OF DAMAGED
GUARDRAIL TO BE DEMOLISHED
AND REMOVED)
APPROXIMATE START POINT:
4.4 MILE DOWNHILL OF QMI ARSR
5.
4.
3.
2.
1.
Case 1: Overlying material Case 2: Overlying material between drilled holes
Excavate area between drilled holes
Excavate area
Overlying material Overlying material
Rock material Rock material backfill or overlying material
Crushed coarse aggregate backfill or overlying material
Crushed coarse aggregate aggregate backfill
Crushed coarse aggregate backfill
Crushed coarse
Finished gradeFinished grade depth (A) is 18" or less depth (A) is greater than 18" the base metal with two coats of zinc-oxide paint.
Treat field cut galvanized steel post surfaces that expose requirements in Section 617.
Place crushed coarse aggregate according to the post
"Underdrain pipe with geotextile".
"Coarse aggregate for concrete" or granular backfill for
Use crushed coarse aggregate conforming to Section 703 oblong hole configuration for Case 1 conditions.
Unless otherwise specified, use either the circular or the
Use this standard when posts cannot be embedded to the
ELEVATION
PLAN VIEWPLAN VIEW
ELEVATION
Steel Post
Wood Post
Wood Post
Steel Post
POST EMBEDMENT DIMENSIONS
B A
E m b e d m e n t
D e p th
B A
E m b e d m e n t
D e p th
23"
23"
21"
21"
12"
8"
617-31 or 617-32.
minimum depth shown on Standard 617-10, 617-11, f o r
M G
S f o r G f o r
M G
S f o r G
21" or 23" 8" or 12"
DEPTH
EMBEDMENT
Case 1
Case 2
DEPTH (B)
DRILLING
MATERIAL (A)
OVERLYING
TYPE
HOLE
NOTE:
NO SCALE
42”
30" to 42”
24" to 42”
> 30”
> 18" to 30”
0 to 18”
42" - A
12”
24”
INSTALLATION IN ROCK
W-BEAM GUARDRAIL
MGS AND G4
617-13
FP-24, FP-14
1/2024
FLH STANDARD
:3
P
M
J u ly
S td
-1 c p w
-w o rk
\d \S td -1
.d g n
OFFICE OF FEDERAL LANDS HIGHWAY
U.S. DEPARTMENT OF TRANSPORTATION, FHWA
SPECIFICATION
APPROVED FOR USE
PROJECT
NUMBER
SHEET
Abbass Zakeri Rectangle
2.
1.
Steel post
Wood blockout Wood blockout
Wood blockout
Steel post Steel post
Steel post
V ditch (typ.)
Steel post Wood blockout bolt and nut guardrail steeper
1V:4H or
Rub rail (typ.)
See Standard 617-31 (wood posts) and 617-32 (steel
Typical post spacing is 6'-3" unless otherwise noted.
" span2
12 ga. W-beam, 9'-4
" x 5" Bolt8
" dia. hole in post4
Field drill "2
12 ga. W-beam, 9'-4
NOTE:
PLAN
ALONG RAIL
ELEVATION
SECTION A-A SECTION B-B
DETAIL A
SECTION C-C
SECTION D-D
BLOCKOUT DETAIL
STEEL POST ANDDETAIL B
ELEVATION
D
C
BA
B C
D
A
See Detail A
Field bend
See Detail B
Ditch bottom
Edge of shoulder
S e e T a b le
Mid-span splice (typ.)
Top of cut
See Note 1
Washer
Pipe sleeve spacer
Shoulder Shoulder VariesShoulder
VariesShoulder w h e n r u b r a il i s r e q u ir e d
Terminal system, Type MGS-BAT
Pay Limits
Guardrail system MGS
Pay limits
Length of Need posts) for other details.
M in im u m p o s t le n g th
" x 2"8
6'-3
"21
3'-1
"21
3'-1
8" W6 x 8.5
W6 x 9 or c o v e r m in
POST DISTANCE
FROM EDGE OF SHOULDER
POST OFFSETS
22 13 or st ee pe r1V:
3H or st ee pe r1V:
3H or steeper
1V:4H
4681012141618202224 or steeper
1V:4H or steeper
1V:4H
NO SCALE
"4
13'-11
10'-11"
"4
8'-10
5'-9"
75'-0"
25'-0"
12'-6
12'- 6"
Sheet 1 of 2
MGS-BATTYPE
BACK SLOPE ANCHOR TERMINAL
MGS W-BEAM GUARDRAIL
617-18
FP-24
2/2024
:3
J u ly
S td a p w w o r k
\d
\S td
.d g n
OFFICE OF FEDERAL LANDS HIGHWAY
U.S. DEPARTMENT OF TRANSPORTATION, FHWA
SPECIFICATION
APPROVED FOR USE
PROJECT
Posts 1 -3 and rub rail at Post 4.
Anchor plate and hardware are typical on top rail of
Use zinc rich paint to coat field drilled holes.
See Sheet 1 of 2 for terminal layout.
3.
2.
1.
Steel plate (see Detail)
Washer of post� slots (typ.)
hole (typ.)
" dia. (typ.)4
" dia. (typ.)4
" dia. (typ.)4
" dia. (typ.)4
" dia.16
" dia. (typ.)16 13 " dia. (typ.)16
1" dia.
W6 x 8.5 W6 x 9 or W6 x 8.5
W6 x 9 or W6 x 8.5 W6 x 9 or
" bolts8 7as needed for
Field drill 1" holes
" x 2" bolt (typ.)8
" Nut (typ.)8
1" dia. hole
1" dia.
AT POSTS 1, 2, AND 3
SPECIAL RAIL TO POST CONNECTION
GALVANIZED SQUARE WASHER
GALVANIZED STEEL PLATE
See Note 3
STEEL PLATE AND WASHER
POSTS 5-21POST 4POSTS 1-3
4"
" Thickness2 1 Thickness"16
14"
"2 12"2
12"4 12"4
31"2 12"2
"8 16"8
" 8
4" 4"
"4
"4
"4 12 "4
"8
"4 31" x 1
" dia.4
"4
"4
"8
NO SCALE
NOTE:
617-18
FP-24
2/2024
FLH STANDARD
:3
P
M J u ly
S td
-1 b p w
-w o rk
\d \S td -1
.d g n
OFFICE OF FEDERAL LANDS HIGHWAY
U.S. DEPARTMENT OF TRANSPORTATION, FHWA
SPECIFICATION
APPROVED FOR USE
Sheet 2 of 2
MGS-BATTYPE
BACK SLOPE ANCHOR TERMINAL
MGS W-BEAM GUARDRAIL
PROJECT
6.
4.
3.
2.
1.
guardrail terminal grading extents where practical.
Construct a 1V:4H or flatter slope outside of the terminal.
Install a reflectorized object marker on the end of the when indicated on the plans.
Pave widened shoulder on both ends of guardrail runs according to the manufacturer's recommendations.
grading as necessary to install the flared terminal need with the manufacturer of a specific product. Adjust begin as shown on the drawing. Verify the length of
For design purposes, the length of need is assumed to recommended by the manufacturer.
construct grading as shown on this sheet and as notes or model. If no staking notes or model is provided, Construct the terminal grading as shown in the staking manufacturer's drawings for other details.
to the manufacturer's recommendations. See
Install a flared W-beam guardrail terminal according shoulder widening
Edge of
See Note 6
Guardrail terminal grading o r f la tt e r
V
:1
H
W f la tt e r
V
:1
H o r
Hinge point line
PLAN
Back of post
Varies by manufacturer end of terminal not shown.
Terminal posts and
See Note 3
Length of Need (MGS)
Guardrail system
Pay limits
G4 or MGS post section
Standard L
See Note 3
Length of Need (G4) of the rail in the standard post section
Tangent line projected from the face
MGS AND G4 W-BEAM GUARDRAIL
STRAIGHT FLARED OPTION
shoulder widening
Edge of
W
See Note 6
Guardrail terminal grading o r f la tt e r
V
:1
H
Hinge point line f la tt e r
V
:1 H o r
PLAN
G4 W-BEAM GUARDRAIL
PARABOLIC FLARED OPTION
Back of post
Varies by manufacturer end of terminal not shown.
Terminal posts and
Guardrail system G4
Pay limits post section
Standard
L
See Note 3
Length of Need (G4) of the rail in the standard post section
Tangent line projected from the face
2' (min.)
2' (min.)
12'-6"
3'-0"
3'-0"
20'-0"16'-8"
20'-0"12'-6"
TEST LEVEL
L
TEST LEVEL
W
L W
NOTE:
NO SCALE
3 (> 45 mph)
2 (≤ 45 mph)
39.6 (for MGS)
37.5 (for G4)
25.0
3.0
2.5 - 4.0
1.67 - 2.67
3 (> 45 mph) 37.5 3.0 or 4.0
(FT) (FT)
(FT) (FT)
AND GRADING
TYPE FLARED TERMINAL
W-BEAM GUARDRAIL
MGS AND G4
617-19
:5
A
J u ly
S td
-1 p w
-w o rk
\d \S td -1
.d g n
OFFICE OF FEDERAL LANDS HIGHWAY
U.S. DEPARTMENT OF TRANSPORTATION, FHWA
SPECIFICATION
APPROVED FOR USE
PROJECT
6.
4.
3.
2.
1.
embankment
Edge of widened post section. See Note 4 face of the rail in the standard
Tangent line projected from the embankment
Edge of widened post section. See Note 4 face of the rail in the standard
Tangent line projected from the
Varies by manufacturer end of terminal not shown.
Terminal posts and
Varies by manufacturer end of terminal not shown.
Terminal posts and terminal grading extents where practical.
Construct a 1V:4H slope outside of the guardrail terminal.
Install a reflectorized object marker on the end of the according to the manufacturer's recommendations.
end farther from the edge of shoulder, or use a taper
Install terminal at a 1:25 taper or flatter to position the the manufacturer's recommendations.
necessary to install the tangent terminal according to manufacturer for a specific product. Adjust grading as begin at post 3. Verify the length of need with the
For design purposes, the length of need is assumed to of site limitations, use the alternative grading layout.
as practical within site constraints. If necessary because are provided, use the preferred grading layout as much staking notes or model. If no staking notes or model
Construct the terminal grading layout as shown in the other details.
recommendations. See manufacturer's drawings for
Install tangent terminal according to the manufacturer's
See Note 6
Guardrail terminal grading o r f la tt e r
V
:1 H
Front of rail face
PLAN
PREFERRED GRADING
Post section
See Note 6
Guardrail terminal grading o r f la tt e r
V
:1
H
Hinge point line
See Note 3
Length of Need
Guardrail system
Pay limits
Pay limits terminal system type tangent or type MGS tangent
Back of post
Back of post
Front of rail face
Hinge point line
PLAN
ALTERNATIVE GRADING
post section
Guardrail system
Pay limits
Pay limits terminal system type tangent or type MGS tangent
See Note 3
Length of Need
12'-6"
(min.)
10'-0" m in m in m in
12'-6" m in
TEST LEVEL
L
NOTE:
NO SCALE
50 (for MGS)
37.5 or 50 (for G4)
(FT)
3 (> 45 mph)
2 (≤ 45 mph)
AND GRADING
TYPE TANGENT TERMINAL
W-BEAM GUARDRAIL
MGS AND G4
617-20
:4
J u ly
S td
-2 p w
-w o rk
\d \S td -2
.d g n
OFFICE OF FEDERAL LANDS HIGHWAY
U.S. DEPARTMENT OF TRANSPORTATION, FHWA
SPECIFICATION
APPROVED FOR USE
PROJECT
guardrail post bolt
3" x 4" (min.)
Post spacing 6'-3""2
3'-1 fill slope
Variable
TOP
symmetry of�
FRONTSIDE SIDE
TOP
PLAN VIEW
BLOCKOUT
steeper than fill slope Variable slope but not
W beam rail
(See Note 2) Blockout on terminal systems All posts except those
DETAIL
POST AND BLOCKOUT
4.
3.
2.
1.
SHAPE POST
STRUCTURAL
Note 4 See terminal systems approach and departure Widening required for Subgrade shoulder.
TYPICAL GUARDRAIL ELEVATION
OMITTED POST DETAIL
See Note 1
POST FACE
terminal systems approach and departure Widening required for Subgrade shoulder.
Hinge point Hinge point
1V:2H or flatter slope shown on Typical Section Aggregate base or as groundline at face of rail Edge of pavement or
1V:10H or flatter slope blockout (typ.)
Post and rail as applicable ground line at face of Edge of pavement or splice Mid-span
Lap in direction of traffic
See Note 2
See Note 2
TYPICAL GUARDRAIL CROSS SECTION TYPICAL GUARDRAIL CROSS SECTION
o s t le n g th
P o s t le n g th
GUARDRAIL MOUNT
FLEXIBLE DELINEATOR
1V:10H or flatter slope groundline at face of rail Edge of pavement or shown on Typical Section Aggregate base or as terminal systems approach and departure Widening required for Subgrade shoulder.
1V:2H or flatter slope
Hinge point shown on Typical Section Aggregate base or as
1V:10H or flatter slope
TYPICAL GUARDRAIL CROSS SECTION
manufacturer's recommendations.
an adhesive or mechanical means according to the Fasten delineator to the web of the steel post using either Install a flexible hinged delineator every fourth post.
manufacturing practices.
part, including its appearance, and accepted to be those consistent with the proper functioning of the Dimensional tolerances not shown or implied are intended consistent material throughout the length of guardrail run.
may be wood, plastic, or composite material. Use Size of blockout shown elsewhere in the plans. Blockout guardrail post and the hinge point. For all other locations, be omitted in locations where the typical guardrail cross When encountering impenetrable material, one post may
Traffic
(one omitted post) Unsupported span
(max.)
Note 2 See
N o te
S e e sheeting Retroreflective
Note 2
See bolts and nuts (8 per splice)
" x 10" or 14" guardrail bolt8
(ty p.)
6"
8" or 12"
(t y p
" dia. (typ.)4
" plain round washer.4
" recess nut8
6"
"4
" dia.4
W6 x 9 or W6 x 8.5
8" or 12"
"4 o r
6"
"4
5" (max.)
see Section 617 and Standard 617-13 or 617-37.
section includes 2-feet (min.) between the back of the
8" or 12" blockout
6' Post 8' Post
8" blockout
8' POST ON SLOPE, 8" BLOCKOUT6' POST CENTERED ON HINGE, 8" OR 12" BLOCKOUT
56'-3" (min.) Distance between omitted posts
43'-9" (min.)
12'-6"
6' Post
6' POST, 8" OR 12" BLOCKOUT
(typ.)
2'-0"
8" or 12" blockout
(t y p
" x 10" or 14"8
" guardrail splice4 1" x 18
NOTE:
NO SCALE STEEL POSTS
MGS W-BEAM GUARDRAIL
617-32
2/2024
:4
J u ly
S td
-3 p w
-w o rk
\d \S td -3
.d g n
OFFICE OF FEDERAL LANDS HIGHWAY
U.S. DEPARTMENT OF TRANSPORTATION, FHWA
SPECIFICATION
APPROVED FOR USE
PROJECT
Line
Abbass Zakeri Line
Abbass Zakeri Line
Abbass Zakeri Line
Abbass Zakeri Line
SPAN WITH HEADWALL DETAIL
WOOD POST DETAIL STEEL POST DETAIL CRT POST DETAIL
PLAN
ELEVATION
Finished grade
PLAN VIEW
See Note 1
POST AND
BURIED OBSTRUCTION
BURIED OBSTRUCTION
See Note 3 See Note 3
Hinge point line
Rail splice (typ.)
(no nesting required)
Single W-beam rail element
Slope varies
Slope varies
Slope varies the face of the headwall flush (zero offset) with
Back of post may be See Note 4
Headwall the face of the headwall flush (zero offset) with
Back of post may be
Hinge point line
CRT WOOD POST
FRONT SIDE
TOP
the maximum height of the culvert headwall above the the finished grade to act as a vertical roadway curb, In locations where the culvert headwall extends above upstream and downstream of posts 2 and 7 is
The minimum length of guardrail, including the end terminals, Use wood posts for CRT posts.
Posts 1 and 8 may be wood or steel.
5.
4.
3.
2.
1.
See Note 1
POST AND
See Note 2
POST THRU
12" (min.)12" (min.)
8"
24"
6"
24"
12"
8"
24" hole (typ.)
" dia.2
8"
" dia.4
6"
6"
See Standard 617-31 or 617-32 for other assembly details.
finished grade is 2 inches.
62.5 feet.
1 2 3 4 5 6 7 8
1 2 3 4 5 6 7 8
2 3 4 5 6 7 8
8 1 8 2 7
NO SCALE
NOTE:or 25'-0" (3 omitted posts)
18'-9" (2 omitted posts)
6'-3"
LONG-SPAN SYSTEM
MGS W-BEAM GUARDRAIL
617-37
:2
J u ly
S td p w w o r k
\d
\S td
.d g n
OFFICE OF FEDERAL LANDS HIGHWAY
U.S. DEPARTMENT OF TRANSPORTATION, FHWA
SPECIFICATION
APPROVED FOR USE
PROJECT
3.
2.
1.
Mid-span splice
MGS guardrail
Box culvert slab
Finished grade
TYPICAL ELEVATION VIEW
PLAN
alternative may be used.
Wood blockouts are shown. Blockouts of an approved zinc coating.
bonded anchors. Use carbon steel rods with a minimum
See Note 2
TOP
SIDEPOST FACE
BLOCKOUT
4 required (see Note 1)
Threaded rod
Compacted soil
Finish grade
Base plate
Box culvert slab
Base plate
STEEL POST
BOX CULVERT MGS GUARDRAIL
BOX CULVERT POST
ELEVATION
base plate
"2
19""2
12"
W6 x 9 steel post
W6 x 8.5 or
1" Ø Hole (typ.)
"2
3'-16'-3"6'-3"6'-3""2
3'-1
"2
6"
"4 m in m a x m in m in
W6 x 9 steel post
W6 x 8.5 or
2' (min.) to outside edge of box culvert
" Ø Hole4
1" m in
" Ø Hole4
W6 x 9 steel post
W6 x 8.5 or inch diameter8
Attach guardrail post to box culvert with
8"
See Standard 617-32 for other details.
inch in length with resin-2 high-strength threaded rods 8
105 ksi. Rods, nuts, and washers have an electroplated strength of 125 ksi and a minimum yield strength of
" Thick8
NOTE:
NO SCALE ATTACHED TO BOX CULVERT
STEEL POSTS
MGS W-BEAM GUARDRAIL
617-38
:1
J u ly
S td p w w o r k
\d
\S td
.d g n
OFFICE OF FEDERAL LANDS HIGHWAY
U.S. DEPARTMENT OF TRANSPORTATION, FHWA
SPECIFICATION
APPROVED FOR USE
PROJECT
| QMI-1603949-C00 G001 |
| QMI-1603949-C00 C001 (1) |
| QMI-1603949-C00 C002 (1) |
| QMI-1603949-C00 C003 (1) |
| QMI-1603949-C00 C004 (1) |
| QMI-1603949-C00 C005 (1) |
| QMI-1603949-C00 C006 (1) |
| QMI-1603949-C00 C007 (1) |
| FHWA-Std |
| FLH Standard Drawings |
| 617-13: MGS and G4 W-Beam Guardrail, Installation in Rock |
| US Customary |
| 617-18: MGS W-Beam Guardrail, Back Slope Anchor Terminal Type MGS-BAT |
| Metric |
| Sheet 2 |
| 617-19: MGS and G4 W-Beam Guardrail, Type Flared Terminal and Grading |
| US Customary |
| 617-20: MGS and G4 W-Beam Guardrail, Type Tangent Terminal and Grading |
| US Customary |
| 617-32: MGS W-Beam Guardrail, Steel Posts |
| US Customary |
| 617-37: MGS W-Beam Guardrail Long-Span System |
| US Customary |
| 617-38: MGS W-Beam Guardrail Steel Posts Attached to Box Culvert |
| US Customary |
| FHWA-Std618 |
| FLH Standard Drawings |
| 617-18: MGS W-Beam Guardrail, Back Slope Anchor Terminal Type MGS-BAT |
| US Customary |
| Sheet 2 |
| 617-13: |
| Proj-Num: |
| NPS: |
| 617-19: |
| 617-20: |
| 617-32: |
| 617-37: |
| 617-38: |
| 617-18: |
| 617-18b: |
File details come from the government source that posted it. Updated .