16-BP036 ALTERNATE BID PROPOSAL FORM.pdf
PDF 321 KB Posted
- Attached to
- BP036 Sitework Package 1- Package A
- Solicitation number
- CSP 26-041AL
- Issued by
- Fort Bend County, Texas
About this file
This is an Alternate Bid Proposal Form for Fort Bend Independent School District (FBISD) in Texas for Sitework Package 1 (CSP No. 26-041AL BP 036). FBISD seeks a contractor to provide a turnkey solution for site work renovations and repairs at multiple campuses, including repairs to site grading, sidewalks, storm drainage, irrigation, and parking lots. The project is anticipated to take 575 calendar days to complete from the executed contract and issuance of Notice to Proceed, though contractors may propose a lower completion timeline for consideration. Contractors must acknowledge receipt of all contract documents and addenda and certify that they have examined the site and locality conditions. The proposal remains open for 60 days after the proposal opening date, and selected contractors must sign the Agreement and submit contract security within 10 calendar days of the Owner's Notice of Award.
The proposal requires submission of a lump sum base bid amount, with provisions for multiple alternates including base bid adjustments, deviations requests, Settler Way stacking renovations, and irrigation system work at Goodman Elementary School and Highlands Elementary School. Liquidated damages are set at $1,000 per calendar day for failure to meet the substantial completion deadline and an additional $250 per calendar day for non-completion of punch list items and contract close-out within 60 calendar days after substantial completion. Contractors must include any specified allowances in their base bid and may propose unit prices for additional work. The contract documents were prepared by MWA Architects and dated December 12, 2025. All bidders must respond to all requests identified in the solicitation and clearly indicate acceptance or objection to the terms; no-bids are deemed non-responsive by FBISD.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RETURN THIS DOCUMENT IN CSP BID/PROPOSAL PACKAGE
ALTERNATE BID FORM – P a g e | 1
SECTION AC
PACKAGE “B” ALTERNATE BID PROPOSAL FORM – CSP STIPULATED SUM
CSP No: 26-041AL BP 036 BP Name: Sitework Package 1
FORT BEND INDEPENDENT SCHOOL DISTRICT
Submitted by:
Date: Phone Number:
Vendors are required to respond to all requests identified in the Solicitation and indicate their acceptance or objection to the terms of the Solicitation and these General Provisions must be clearly indicated in
Vendor’s Solicitation Response. No-bid is deemed non-responsive by FBISD.
Having examined Proposal and Contract Documents prepared by Fort Bend ISD and MWA Architects dated 12/12/2025 and having examined site conditions, the undersigned proposes to furnish all labor, equipment and materials and perform all work for the completion of the above-named project for the sum indicated below.
I. DESCRIPTION: FBISD is seeking a contractor to provide a turnkey solution for site work renovations and repairs at multiple campuses (BP036). The scope of work includes repairs to site grading, sidewalks, storm drainage, irrigation, and parking lots.
Undersigned agrees to complete the work for the lump sum amounts of:
Dollars
(Amount written in words governs)
(Amount in figures)
II. PROJECT TIMELINES – Refer to Section V. for the construction calendar days associated with alternates.
The District anticipates that this project will take 575 calendar days to complete. Contractor agrees the work will be substantially completed within 575 calendar days from executed contract and issuance of Notice to Proceed.
Should the Contractor anticipate lower calendar days to complete this project, please indicate below. The District will consider contractor proposed lower calendar days and incorporate into contract if deemed appropriate.
CONTRACTOR’S PROPOSED DAYS TO COMPLETE
BP 036 Base Proposal
ALTERNATE BID FORM – P a g e | 2
BP 036
BP 036
Alternates
Base Proposal and Alternates
(Enter only if LOWER than District’s proposed time)
III. LIQUIDATED DAMAGES:
The undersigned understands that liquidated damages as defined in the Supplementary Conditions will be included in the form of Agreement Between Owner and Contractor and that the contractor will be bound thereto.
Contractor accepts the provisions of the Contract as to liquidated damages in the event of failure to complete the work on time. Liquidated damages shall be the sum of $1,000.00 per day for each calendar day that Substantial Completion is delayed for each project.
Further, the Contractor acknowledges that additional liquidated damages in the sum of $250.00 per day for each calendar day shall be imposed for non-completion of punch list items and contract close-out within sixty (60) calendar days after Substantial Completion.
IV. ALLOWANCES:
Allowances are to be included in the Contractor’s base bid for each project in the following amounts:
A. $Add dollar amount . Add description of allowance
B. $Add dollar amount . Add description of allowance
Contractor should include allowance and markup in the base bid. Section 3.8 of the
Supplementary Conditions defines the procedures for markups.
V. ALTERNATES
Refer to Division 01 23 00 for administrative and procedural requirements of Alternates.
Alternate No. 1 Base Bid Adjustment
The undersigned agrees to complete all base bid work and adjust the final base bid lump sum amount as follows:
1. Add ☐ Deduct ☐ No Change ☐ Not Applicable ☐
2. Dollars
(Amount written in words governs)
Amount written in figures
3. Add ☐ Deduct ☐ No. of calendar days to adjust the Contract Time for this alternate:
ALTERNATE BID FORM – P a g e | 3
Alternate No. 2 Deviations Request Form
If Bidder proposes to use any substitution or deviations from the base bid use Alternate No. 2 via the
Deviations Form in section 00 21 13 Instructions to Bidders. If the owner elects to proceed with
Alternate No. 2, the undersigned agrees to complete the ADDITIVE work for the lump sum amount of:
(Amount written in words governs)
Alternate No. 3 Settler Way Stacking Renovations: Add stacking lanes parking spaces and entry aprons to the south drive as shown in drawing x-C2.0. Partial demolition of existing conditions shall be included as indicated.
If the owner elects to proceed with Alternate No. 3 the undersigned agrees to complete the
ADDITIVE work for the lump sum amounts of:
(Amount written in words governs)
Alternate No. 4 for schools Goodman Elementary School and Highlands Elementary School only: At areas indicated to receive irrigation, demolish the existing bed and salvage the landscaping plant materials along the building face to expose the existing weepholes; provide 2’-0” wide 3000 psi concrete mow strip where indicated. Re-grade area ensuring positive drainage to existing catch basins.
Re-install salvaged plant materials, provide irrigation for all reinstalled planting beds. Irrigation systems shall include either Hunter or Rainbird components (do not mix) smart controllers and rain sensors.
Contractor shall field locate the irrigation tap and meter.
If the owner elects to proceed with Alternate No. 4 the undersigned agrees to complete the
ADDITIVE work for the lump sum amounts of:
Dollars
(Amount written in words governs)
2. Amount written in figures
ALTERNATE BID FORM – P a g e | 4
VI. UNIT PRICES – ALTERNATE BID
UNIT PRICES – Add Description
01 ☐ add description add unit
02 ☐ add description add unit
03 ☐ add description add unit
04 ☐ add description add unit
05 ☐ add description add unit
VII. CHANGES IN THE WORK
The undersigned understands that changes in the work shall be performed in accordance with the
Supplementary Conditions.
VIII. PROPOSAL EVALUATION WAIVER
By submitting a Proposal, the proposer indicated below agrees to waive any claim it has or may have against the Owner, Architect, Engineers, Consultants and their respective employees, arising out of or in connection with the administration, evaluation, or recommendation of any proposal.
The proposer further agrees the Owner reserves the right to waive any requirements under the proposal documents or the Contract Documents, acceptance or rejection of any proposals, and recommendation or award of the contract.
It is understood that the right is reserved by the Owner to reject any or all proposals, or waive any informalities in Receipt of Proposals.
The undersigned certifies that the amounts contained in this Competitive Sealed Proposal have been carefully checked and are submitted as correct and final; and additionally, agrees to comply with all provisions of the Proposal Form.
The undersigned CONTRACTOR proposes and agrees, if this Proposal is accepted, to enter into an Agreement with OWNER in the form included in the Contract Documents to complete all work as specified or indicated in the Contract Documents for the Contract Price and within the Contract
Time indicated in this Proposal and in accordance with the Contract Documents.
CONTRACTOR accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Proposal Security. This Proposal will remain open for sixty (60) days after the day of Proposal opening. CONTRACTOR will sign the
Agreement and submit the Contract Security and other documents required by the Contract documents within ten (10) calendar days after the date of the OWNER'S Notice of Award.
In submitting this Proposal, CONTRACTOR represents, as more fully set forth in the Agreement, that:
(a) Contractor has examined copies of all the Contract Documents and of the following addenda, receipt of which is hereby acknowledged, and also copies of the Advertisement or Invitation to
Submit Proposal.
ALTERNATE BID FORM – P a g e | 5
ADD-01 dated
ADD-03 dated
ADD-05 dated
ADD-07 dated
Total # pgs
Total # pgs
Total # pgs
Total # pgs
ADD-02 dated
ADD-04 dated
ADD-06 dated
ADD-08 dated
Total # pgs
Total # pgs
Total # pgs
Total # pgs
(b) CONTRACTOR has examined the site and locality where the work is to be performed, the legal requirements (federal, state and local laws, ordinances, rules and regulations) and the conditions effecting cost, progress or performance of the work and has made such independent investigations as CONTRACTOR deems necessary.
(c) This PROPOSAL is genuine and not made in the interest of or on behalf of any undisclosed person, firm or corporation and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation; CONTRACTOR has not directly or indirectly induced or solicited any other Contractor to submit a false or sham Proposal;
CONTRACTOR has not solicited or induced any person, firm or a corporation to refrain from submitting a proposal; and CONTRACTOR has not sought by collusion to obtain for himself any advantage over any other Contractor or over OWNER.
Type of Proposer’s Organization:
(Corporation, Co-Partnership, Individual, etc.)
Proposer:
(Print or Type)
Title of Office:
Legal Address:
Signature of Proposer
Zip Code: Tel:( )
ATTEST:
(Secretary, if Proposer is a Corporation
ALTERNATE BID FORM – P a g e | 6 Revised 1/30/24
SEAL:
(If Corporation)