Attachment J-1

Specifications Renovations of Animal Rooms, Building 5A, Jefferson Laboratories

Project No. 2-3741-11 dated July 6, 2012

2-3741-11 RENOVATIONS OF ANIMAL ROOMS (304 Pages)

1308 MAIN STREET

LITTLE ROCK, AR 72202

(501) 378-0059 Phone

(501) 378-0415 Fax www.stuckarch.com

100% FINAL Submittal

Jefferson Laboratories of the FDA RReennoovvaattiioonn ooff AAnniimmaall RRoooommss

BBuuiillddiinngg 55AA Jefferson, Arkansas

July 6, 2012

Comm. #2-3741-11 http://www.stuckarch.com/

Stuck Associates Table of Contents Renovation of Animal Rooms July 6, 2012 Page 1 of 2 Building 5A Comm. No. 2-3741-11 Jefferson Laboratories of the FDA

TECHNICAL SPECIFICATIONS

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 10 00 Summary 01 30 00 Administrative Requirements 01 30 01 Submittal Log 01 32 16 Construction Progress Schedule 01 40 00 Quality Requirements 01 60 00 Product Requirements 01 70 00 Execution Requirements 01 78 00 Closeout Submittals

DIVISION 02 - SITE CONSTRUCTION

02 41 00 Demolition

DIVISION 03 - CONCRETE

03 30 00 Cast-In-Place Concrete

DIVISION 04 - MASONRY

04 05 11 Masonry Mortaring and Grouting 04 20 00 Unit Masonry

DIVISION 05 – METALS

05 50 00 Metal Fabrication

DIVISION 06 - WOOD AND PLASTICS

06 41 00 Custom Cabinets

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 00 Thermal Insulation 07 24 00 Exterior Insulation and Finish Systems 07 84 00 Firestopping 07 90 05 Joint Sealers

DIVISION 08 - DOORS AND WINDOWS

08 11 13 Hollow Metal Doors and Frames 08 13 00 Stainless Steel Doors and Frames 08 31 00 Access Doors & Panels 08 51 13 Aluminum Windows 08 71 00 Door Hardware

DIVISION 09 - FINISHES

09 00 00 Finish Schedule 09 21 16 Gypsum Board Assemblies 09 24 00 Portland Cement Plastering 09 44 00 Vinyl Flake Flooring With Vapor Barrier 09 51 00 Acoustical Ceilings 09 65 00 Resilient Flooring 09 68 00 Carpeting 09 90 00 Painting And Coating 09 96 00 Vinyl Flake Wall Coating 09 96 10 Epoxy Coating For Walls And Ceilings

Stuck Associates Table of Contents Renovation of Animal Rooms July 6, 2012 Page 2 of 2 Building 5A Comm. No. 2-3741-11 Jefferson Laboratories of the FDA

DIVISION 10 – SPECIALTIES

10 14 00 Signage 10 21 13.19 Plastic Toilet Compartments 10 26 01 Corner Guards 10 28 00 Toilet and Bath Accessories 10 44 00 Fire Protection Specialties 10 51 00 Lockers

DIVISION 11 – EQUIPMENT

11 45 01 Ice Machine 11 61 00 Fume Hoods

DIVISION 12 – FURNISHINGS

12 24 94 Roller Shades

DIVISION 13 – SPECIAL CONSTRUCTION – NOT USED

13 12 10 Pre-Engineered Buildings Components 13 12 20 Pre-Engineered Retrofit Roofing Systems

DIVISION 14 – CONVEYING EQUIPMENT – NOT USED

DIVISION 23 – MECHANICAL

23 00 10 Mechanical General 23 00 11 Demolition 23 00 15 Firestopping and Smoke Stopping 23 00 30 Electrical Requirements for Mechanical Equipment 23 00 60 Basic Piping 23 01 10 Valves 23 01 30 Piping Specialties 23 01 40 Mechanical Supporting Systems 23 01 60 Mechanical Systems Insulation 23 01 90 Identification 23 04 10 Plumbing Basics 23 04 20 Domestic Water System 23 04 30 Soil and Waste System 23 06 15 Steam Piping 23 06 20 Hydronic Piping 23 07 10 HVAC Sheet Metal 23 07 15 High Pressure Ductwork 23 08 53 Louver 23 08 60 Heat Recovery Air Handling System 23 08 61 Air Filters 23 08 62 AHU UV Lights 23 08 63 Variable Frequency Drives 23 08 95 Air Terminal Devices 23 09 71 Automatic Temperature Controls 23 09 90 Testing, Adjusting, and Balancing

DIVISION 26 – ELECTRICAL

26 00 10 Electrical – General Provisions 26 05 10 Wires and Cables (600 Volt Maximum) 26 05 33 Raceways, Boxes, Fittings and Supports 26 18 00 Wiring Devices 26 19 00 Miscellaneous Equipment 26 51 00 Lighting System

END OF SECTION

Stuck Associates Section 01 10 00 Renovation of Animal Rooms July 6, 2012 SUMMARY Building 5A Comm. No. 2-3741-11 Page 1 of 1 Jefferson Laboratories of the FDA

SECTION 01 10 00

SUMMARY

PART 1 GENERAL

1.01 PROJECT

A. Project Name: Building 5A, Renovation of Animal Rooms.

B. Owner's Name: Jefferson Laboratories of the FDA.

C. Architect's Name: Contracting Officer.

D. The Project consists of the selective demolition, new constrtuction, and alteration work in Building 5A for animal rooms, procedure room, and a change unit.

1.02 CONTRACT DESCRIPTION

A. Contract Type: A single prime contract based on a Stipulated Price.

1.03 WORK BY OWNER

1.04 OWNER OCCUPANCY

A. Jefferson Laboratories of the FDA intends to continue to occupy adjacent portions of the existing building during the entire construction period.

B. Cooperate with Jefferson Laboratories of the FDA to minimize conflict and to facilitate Jefferson Laboratories of the FDA's operations.

C. Schedule the Work to accommodate Jefferson Laboratories of the FDA occupancy.

1.05 CONTRACTOR USE OF SITE AND PREMISES

A. Construction Operations: Limited to areas noted on Drawings.

B. Provide access to and from site as required by law and by Jefferson Laboratories of the FDA:

1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered.

2. Do not obstruct roadways, sidewalks, or other public ways without permit.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

Stuck Associates Section 01 30 00 Renovation of Animal Rooms July 6, 2012 ADMINISTRATIVE REQUIREMENTS Building 5A Comm. No. 2-3741-11 Page 1 of 4 Jefferson Laboratories of the FDA

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

1.01 SECTION INCLUDES

A. Preconstruction meeting.

B. Progress meetings.

C. Construction progress schedule.

D. Coordination drawings.

E. Submittals for review, information, and project closeout.

F. Number of copies of submittals.

G. Submittal procedures.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 PRECONSTRUCTION MEETING

A. Jefferson Laboratories of the FDA, Contracting Officer, will schedule a meeting after Notice of Award.

B. Attendance Required:

1. Jefferson Laboratories of the FDA, Contracting Officer.

2. Contractor.

C. Agenda:

1. Execution of National Center for Toxicological Research - Contractor Agreement.

2. Submission of executed bonds and insurance certificates.

3. Distribution of Contract Documents.

4. Submission of list of Subcontractors, list of Products, schedule of values, and progress schedule.

5. Designation of personnel representing the parties to Contract, and Contracting Officer.

6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

7. Scheduling.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Contracting Officer, Jefferson Laboratories of the FDA, participants, and those affected by decisions made.

3.02 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the Work at maximum monthly intervals.

B. Make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

C. Attendance Required: Job superintendent, major Subcontractors and suppliers, Jefferson Laboratories of the FDA, Contracting Officerand others as appropriate to agenda topics for each meeting.

D. Agenda:

Comm. No. 2-3741-11 Page 2 of 4 Jefferson Laboratories of the FDA

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems which impede planned progress.

5. Review of submittals schedule and status of submittals.

6. Maintenance of progress schedule.

7. Corrective measures to regain projected schedules.

8. Planned progress during succeeding work period.

9. Coordination of projected progress.

10. Maintenance of quality and work standards.

11. Effect of proposed changes on progress schedule and coordination.

12. Other business relating to Work.

E. Record minutes and distribute copies within two days after meeting to participants, with two copies to Contracting Officer, Jefferson Laboratories of the FDA, participants, and those affected by decisions made.

3.03 CONSTRUCTION PROGRESS SCHEDULE - See Section 01 32 16

A. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

B. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

1. Include written certification that major contractors have reviewed and accepted proposed schedule.

C. Within 10 days after joint review, submit complete schedule.

D. Submit updated schedule with each Application for Payment.

3.04 COORDINATION DRAWINGS

A. Review drawings prior to submission to Contracting Officer.

3.05 SUBMITTALS FOR REVIEW

A. When the following are specified in individual sections, submit them for review:

1. Product data.

2. Shop drawings.

3. Samples for selection.

4. Samples for verification.

B. Submit to Contracting Officer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents.

C. Samples will be reviewed only for aesthetic, color, or finish selection.

D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 78 00 - CLOSEOUT

SUBMITTALS.

3.06 SUBMITTALS FOR INFORMATION

A. When the following are specified in individual sections, submit them for information:

1. Design data.

2. Certificates.

3. Test reports.

4. Inspection reports.

5. Manufacturer's instructions.

6. Manufacturer's field reports.

Comm. No. 2-3741-11 Page 3 of 4 Jefferson Laboratories of the FDA

C. production of submittal originally reviewed.

D. pecified in individual specification sections; one of which will be not be returned to Contractor unless specifically so stated.

3.09 B

B. smittal form. Revise submittals with original number and a

C. ent drawing and detail number, and

D.

tion of information r.

G. tem limitations which may be

J. ls as appropriate. Instruct parties to promptly report any

K. Submittals not requested will not be recognized or processed.

7. Other types indicated.

B. Submit for Contracting Officer's knowledge as contract administrator or for Jefferson Laboratories of the FDA. No action will be taken.

3.07 SUBMITTALS FOR PROJECT CLOSEOUT

A. When the following are specified in individual sections, submit them at project closeout:

1. Project record documents.

2. Operation and maintenance data.

3. Warranties.

4. Bonds.

5. Other types as indicated.

B. Submit for Jefferson Laboratories of the FDA's benefit during and after project completion.

3.08 NUMBER OF COPIES OF SUBMITTALS

A. Documents for Review:

1. Small Size Sheets, Not Larger Than 8-1/2 x 11 inches: Submit the number of copies which the Contractor requires, plus two copies which will be retained by the Contracting Officer.

B. Documents for Information: Submit two copies.

Documents for Project Closeout: Make one re Submit one extra of submittals for information.

Samples: Submit the number s retained by Contracting Officer.

1. After review, produce duplicates.

2. Retained samples will

SU MITTAL PROCEDURES

A. Transmit each submittal with approved form.

Sequentially number the tran sequential alphabetic suffix.

Identify Project, Contractor, Subcontractor or supplier; pertin specification section number, as appropriate on each copy.

Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordina is in accordance with the requirements of the Work and Contract Documents.

E. Schedule submittals to expedite the Project, and coordinate submission of related items.

F. For each submittal for review, allow 15 days excluding delivery time to and from the Contracto

Identify variations from Contract Documents and Product or sys detrimental to successful performance of the completed Work.

H. Provide space for Contractor and Contracting Officer review stamps.

I. When revised for resubmission, identify all changes made since previous submission.

Distribute copies of reviewed submitta inability to comply with requirements.

Comm. No. 2-3741-11 Page 4 of 4 Jefferson Laboratories of the FDA

Stuck Associates Section 01 30 01 Renovation of Animal Rooms July 6, 2012 SUBMITTAL LOG Building 5A Comm. No. 2-3741-11 Page 1 of 3 Jefferson Laboratories of the FDA

SECTION 01 30 01

SUBMITTAL LOG

SPEC

NO.

SPEC. SECTION

TITLE DESCRIPTION OF SUBMITTAL

SUBMIT FOR

REVIEW

SUBMIT FOR

INFORMATION

01 30 00 ADMINISTRTIVE REQUIREMENTS

Certificates X

01 32 16 CONSTRUCTION PROGRESS SCHEDULE

01 40 00 QUALITY REQUIREMENTS

Independent Agency Field Testing X

01 60 00 PRODUCT REQUIREMENTS

Product Data X Shop Drawings X Samples X

01 70 00 EXECUTION REQUIREMENTS

Field Report X

01 78 00 CLOSEOUT SUBMITTALS

Record Documents X Operation & Maintenance Data X

02 41 00 DEMOLITION

03 30 00 CAST-IN-PLACE-CONCRETE

Design Mix X Concrete Tests X Installation Instructions X

03 39 50 SEALING CONCRETE FLOORS

Materials Requirements X Installers Qualifications X

04 05 11 MASONRY MORTARING AND GROUTING

Test Report X

04 20 00 UNIT MASONRY

05 50 00 METAL FABRIATIONS

Certificate X

Comm. No. 2-3741-11 Page 2 of 3 Jefferson Laboratories of the FDA

SPEC. SECTION

TITLE DESCRIPTION OF SUBMITTAL

SUBMIT FOR

REVIEW

SUBMIT FOR

INFORMATION

07 21 00 THERMAL INSULATION

07 84 00 FIRESTOPPING

Manufacturer Qualifications X

07 90 05 JOINT SEALERS

Warranty X

08 11 13 HOLLOW METAL DOORS AND FRAMES

Manufacturer Qualifications

08 31 00 ACCESS DOORS AND PANELS

08 51 13 ALUMINUM WINDOWS

Shop Drawings X Samples X Warranty X Installation Instructions X

08 71 00 DOOR HARDWARE

Hardware Schedules X Product Data X Substitution Samples X Templates X Wiring Diagrams X

09 21 16 GYPSUM BOARD ASSEMBLIES

Installer Qualifications X

09 24 00 PORTLAND CEMENT PLASTERING

09 44 00 VINYL FLAKE FLOORING

Color Samples X Product Data X Maintenance Instructions X

09 66 00 VINYL FLAKE WALL COATING

Samples X

Comm. No. 2-3741-11 Page 3 of 3 Jefferson Laboratories of the FDA

SPEC. SECTION

TITLE DESCRIPTION OF SUBMITTAL

SUBMIT FOR

REVIEW

SUBMIT FOR

INFORMATION

09 66 10 Epoxy Coatings for Walls & Ceilings Product Data X Samples X

09 66 20 EPOXY COATINGS FOR HOLLOW DOORS

Samples X Maintenance Instructions X

Mock-Up X

09 90 00 PAINTS AND COATINGS

Samples X Manufacturer Qualifications X Installer Qualifications X Extra Materials X

11 63 60 STEAM STERILIZER LSR MODEL 121527

Shop Drawings X Field Report X Demonstration & Instruction Statement X

11 70 00 VACUUM BEDDING SYSTEM

Shop Drawings X Field Report X Demonstration & Instruction Statement X

DIVISION 23 - MECHANICAL

SPEC. SECTION

TITLE DESCRIPTION OF SUBMITTAL

SUBMIT FOR

REVIEW

SUBMIT FOR

INFORMATION

23 00 15 FIRESTOPPING AND SMOKE STOPPING

Product Data X

Installation Instructions X

Shop Drawings X

Statement of Qualifications X

23 00 60 BASIC PIPING

Product Data X

Welders Certificates X

23 01 10 VALVES

Product Data X

23 01 30 PIPING SPECIALTIES

Product Data X

23 01 40 MECHANICAL SUPPORTING SYSTEMS

Shop Drawings X

Product Data X

Installation Instructions X

Start Up Logs X

23 01 60 MECHANICAL SYSTEMS INSULATION

Product Data X

23 01 90 IDENTIFICATION

Valve Schedule X

23 04 10 PLUMBING BASICS

Product Data X

23 04 20 DOMESTIC WATER SYSTEM

Product Data X

23 04 30 SOIL AND WASTE SYSTEM

April 3, 2012 SUBMITTAL LOG-DIVISION 23 Building 5A

SPEC. SECTION

TITLE DESCRIPTION OF SUBMITTAL

SUBMIT FOR

REVIEW

SUBMIT FOR

INFORMATION

23 06 15 STEAM PIPING

Product Data X

Tests X

23 06 20 HYDRONIC PIPING

Product Data X

Tests X

23 07 10 HVAC SHEET METAL

Product Data X

Duct Sealant Product Data X

Duct Leak Tests X

23 07 15 HIGH PRESSURE DUCTWORK

Product Data X

Duct Sealant Product Data X

Duct Leak Tests X

23 08 53 LOUVERS

Product Data X

Test Data X

Maintenance Data X

23 08 60 HEAT RECOVERY AIR HANDLING UNIT

Shop Drawings X

Product Data X

Tests X

23 08 61 AIR FILTERS

Product Data X

23 08 62 AHU UV LIGHTS X

SPEC. SECTION

TITLE DESCRIPTION OF SUBMITTAL

SUBMIT FOR

REVIEW

SUBMIT FOR

INFORMATION

23 08 95 AIR TERMINAL DEVICES

Product Data X

23 09 71 AUTOMATIC TEMPERATURE CONTROLS

Product Data X

Shop Drawings X

23 09 90 TESTING, ADJUSTING & BALANCING

Instrument List X

Test List X

Certification X

Test and Balance Reports X

DIVISION 26 - ELECTRICAL

SPEC. SECTION

TITLE DESCRIPTION OF SUBMITTAL

SUBMIT FOR

REVIEW

SUBMIT FOR

INFORMATION

26 05 10 WIRES AND CABLES (600 VOLT MAXIMUM)

Product Data X

Shop Drawings X

26 05 33 RACEWAYS, BOXES, FITTINGS AND SUPPORTS

Product Data X

26 18 00 WIRING DEVICES

Product Data X

Shop Drawings X

26 19 00 MISCELLANEOUS EQUIPMENT

Product Data X

Shop Drawings X

26 51 00 LIGHTING SYSTEM

April 3, 2012 SUBMITTAL LOG-DIVISION 26 Building 5A Comm. No. 2-3741-11 Page 1 of 1 Jefferson Laboratories of the FDA

Stuck Associates Section 01 32 16 Renovation of Animal Rooms July 6, 2012 CONSTRUCTION PROGRESS SCHEDULE Building 5A Comm. No. 2-3741-11 Page 1 of 2 Jefferson Laboratories of the FDA

SECTION 01 32 16

CONSTRUCTION PROGRESS SCHEDULE

1.01 SECTION INCLUDES

A. Construction progress schedule, bar chart type.

1.02 SUBMITTALS

A. Within 10 days after date of Agreement, submit preliminary schedule defining planned operations for the first 60 days of Work, with a general outline for remainder of Work.

B. If preliminary schedule requires revision after review, submit revised schedule within 10 days.

C. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

1. Include written certification that major contractors have reviewed and accepted proposed schedule.

D. Within 10 days after joint review, submit complete schedule.

E. Submit updated schedule with each Application for Payment.

1.03 SCHEDULE FORMAT

A. Listings: In chronological order according to the start date for each activity. Identify each activity with the applicable specification section number.

B. Sheet Size: Multiples of 8-1/2 x 11 inches.

C. Scale and Spacing: To allow for notations and revisions.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 CONTENT

A. Show complete sequence of construction by activity, with dates for beginning and completion of each element of construction.

B. Identify each item by specification section number.

C. Show accumulated percentage of completion of each item, and total percentage of Work completed, as of the first day of each month.

D. Provide legend for symbols and abbreviations used.

3.02 BAR CHARTS

A. Include a separate bar for each major portion of Work or operation.

B. Identify the first work day of each week.

3.03 UPDATING SCHEDULE

A. Maintain schedules to record actual start and finish dates of completed activities.

B. Indicate progress of each activity to date of revision, with projected completion date of each activity.

C. Annotate diagrams to graphically depict current status of Work.

Stuck Associates Section 01 32 16 Renovation of Animal Rooms July 6, 2012 CONSTRUCTION PROGRESS SCHEDULE Building 5A Comm. No. 2-3741-11 Page 2 of 2 Jefferson Laboratories of the FDA

D. Identify activities modified since previous submittal, major changes in Work, and other identifiable changes.

E. Indicate changes required to maintain Date of Substantial Completion.

F. Submit reports required to support recommended changes.

Stuck Associates Section 01 40 00 Renovation of Animal Rooms July 6, 2012 QUALITY REQUIREMENTS Building 5A

SECTION 01 40 00

QUALITY REQUIREMENTS

1.01 SECTION INCLUDES

A. References and standards.

B. Control of installation.

C. Testing and inspection services.

D. Manufacturers' field services.

1.02 SUBMITTALS

A. Testing Agency Qualifications:

1. Prior to start of Work, submit agency name, address, and telephone number, and names of full time registered Engineer and responsible officer.

2. Submit copy of report of laboratory facilities inspection made by NIST Construction

Materials Reference Laboratory during most recent inspection, with memorandum of remedies of any deficiencies reported by the inspection.

B. Test Reports: After each test/inspection, promptly submit two copies of report to Contracting Officer and to Contractor.

1. Include:

a. Date issued.

b. Project title and number.

c. Name of inspector.

d. Date and time of sampling or inspection.

e. Identification of product and specifications section.

f. Location in the Project.

g. Type of test/inspection.

h. Date of test/inspection.

i. Results of test/inspection.

j. Conformance with Contract Documents.

k. When requested by Contracting Officer, provide interpretation of results.

2. Test reports are submitted for Contracting Officer's knowledge as contract administrator or for the Jefferson Laboratories of the FDA, for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents.

C. Certificates: When specified in individual specification sections, submit certification by the manufacturer and Contractor or installation/application subcontractor to Contracting Officer, in quantities specified for Product Data.

1. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.

1.03 REFERENCES AND STANDARDS

A. For products and workmanship specified by reference to a document or documents not included in the Project Manual, also referred to as reference standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes.

B. Conform to reference standard of date of issue current on date of Contract Documents, except where a specific date is established by applicable code.

cts.

C. Obtain copies of standards where required by product specification sections.

D. Maintain copy at project site during submittals, planning, and progress of the specific work, until Substantial Completion.

E. Should specified reference standards conflict with Contract Documents, request clarification from Contracting Officer before proceeding.

F. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of Contracting Officer shall be altered from the Contract Documents by mention or inference otherwise in any reference document.

1.04 TESTING AND INSPECTION AGENCIES

A. Contractor shall employ and pay for services of an independent testing agency to perform other specified testing.

B. Employment of agency in no way relieves Contractor of obligation to perform Work in accordance with requirements of Contract Documents.

C. Contractor Employed Agency:

1. Laboratory: Authorized to operate in State in which Project is located.

2. Testing Equipment: Calibrated at reasonable intervals either by NIST or using an NIST established Measurement Assurance Program, under a laboratory measurement quality assurance program.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 CONTROL OF INSTALLATION

A. Monitor quality control over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce Work of specified quality.

B. Comply with manufacturers' instructions, including each step in sequence.

C. Should manufacturers' instructions conflict with Contract Documents, request clarification from Contracting Officer before proceeding.

D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.

E. Have Work performed by persons qualified to produce required and specified quality.

F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer.

G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement.

3.02 TESTING AND INSPECTION

A. Testing Agency Duties:

1. Provide qualified personnel at site. Cooperate with Contractring Officer and Contractor in performance of services.

2. Perform specified sampling and testing of products in accordance with specified standards.

3. Ascertain compliance of materials and mixes with requirements of Contract Documents.

4. Promptly notify Contracting Officer and Contractor of observed irregularities or non-conformance of Work or produ

5. Perform additional tests and inspections required by Contracting Officer.

6. Submit reports of all tests/inspections specified.

B. Limits on Testing/Inspection Agency Authority:

1. Agency may not release, revoke, alter, or enlarge on requirements of Contract Documents.

2. Agency may not approve or accept any portion of the Work.

3. Agency may not assume any duties of Contractor.

4. Agency has no authority to stop the Work.

C. Contractor Responsibilities:

1. Deliver to agency at designated location, adequate samples of materials proposed to be used which require testing, along with proposed mix designs.

2. Cooperate with laboratory personnel, and provide access to the Work and to manufacturers' facilities.

3. Provide incidental labor and facilities:

a. To provide access to Work to be tested/inspected.

b. To obtain and handle samples at the site or at source of Products to be tested/inspected.

c. To facilitate tests/inspections.

d. To provide storage and curing of test samples.

4. Notify Contracting Officer and laboratory 24 hours prior to expected time for operations requiring testing/inspection services.

5. Employ services of an independent qualified testing laboratory and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

6. Arrange with Jefferson Laboratories of the FDA's agency and pay for additional samples, tests, and inspections required by Contractor beyond specified requirements.

D. Re-testing required because of non-conformance to specified requirements shall be performed by the same agency on instructions by Contracting Officer. Payment for re testing will be charged to the Contractor by deducting testing charges from the Contract Price.

3.03 MANUFACTURERS' FIELD SERVICES

A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment as applicable, and to initiate instructions when necessary.

B. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers' written instructions.

3.04 DEFECT ASSESSMENT

A. Replace Work or portions of the Work not conforming to specified requirements.

B. If, in the opinion of Contracting Officer, it is not practical to remove and replace the Work, Contracting Officer will direct an appropriate remedy or adjust payment.

Stuck Associates Section 01 60 00 Renovation of Animal Rooms July 6, 2012 PRODUCT REQUIREMENTS Building 5A

SECTION 01 60 00

PRODUCT REQUIREMENTS

1.01 SECTION INCLUDES

A. General product requirements.

B. Transportation, handling, storage and protection.

C. Product option requirements.

D. Substitution limitations and procedures.

E. Spare parts and maintenance materials.

1.02 SUBMITTALS

A. Product Data Submittals: Submit manufacturer's standard published data. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information specific to this Project.

B. Shop Drawing Submittals: Prepared specifically for this Project.

C. Sample Submittals: Illustrate functional and aesthetic characteristics of the product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.

1. For selection from standard finishes, submit samples of the full range of the manufacturer's standard colors, textures, and patterns.

D. Indicate utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.

PART 2 PRODUCTS

2.01 NEW PRODUCTS

A. Provide new products unless specifically required or permitted by the Contract Documents.

B. Do not use products having any of the following characteristics:

1. Made outside the United States, its territories, Canada, or Mexico.

2. Made using or containing CFC's or HCFC's.

3. Made of wood from newly cut old growth timber.

2.02 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Use any product meeting those standards or description.

B. Products Specified by Naming One or More Manufacturers: Use a product of one of the manufacturers named and meeting specifications, no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions:

Submit a request for substitution for any manufacturer not named.

2.03 SPARE PARTS AND MAINTENANCE PRODUCTS

A. Provide spare parts, maintenance, and extra products of types and in quantities specified in individual specification sections.

B. Deliver to Project site; obtain receipt from Contracting Officer prior to final payment.

PART 3 EXECUTION

Stuck Associates Section 01 60 00 Renovation of Animal Rooms July 6, 2012 PRODUCT REQUIREMENTS Building 5A on.

3.01 SUBSTITUTION PROCEDURES

A. Instructions to Bidders specify time restrictions for submitting requests for substitutions during the bidding period. Comply with requirements specified in this section.

B. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents.

C. A request for substitution constitutes a representation that the submitter:

1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product.

2. Will provide the same warranty for the substitution as for the specified product.

3. Will coordinate installation and make changes to other Work which may be required for the

Work to be complete with no additional cost to Jefferson Laboratories of the FDA.

4. Waives claims for additional costs or time extension which may subsequently become apparent.

D. Substitution Submittal Procedure:

1. Submit three copies of request for substitution for consideration. Limit each request to one proposed substituti

2. Submit shop drawings, product data, and certified test results attesting to the proposed product equivalence. Burden of proof is on proposer.

3. The Contracting Officer will notify Contractor in writing of decision to accept or reject request.

3.02 TRANSPORTATION AND HANDLING

A. Transport and handle products in accordance with manufacturer's instructions.

B. Promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and products are undamaged.

C. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage.

3.03 STORAGE AND PROTECTION

A. Store and protect products in accordance with manufacturers' instructions.

B. Store with seals and labels intact and legible.

C. Store sensitive products in weather tight, climate controlled, enclosures in an environment favorable to product.

D. For exterior storage of fabricated products, place on sloped supports above ground.

E. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products.

F. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.

G. Arrange storage of products to permit access for inspection. Periodically inspect to verify products are undamaged and are maintained in acceptable condition.

Stuck Associates Section 01 70 00 Renovation of Animal Rooms July 6, 2012 EXECUTION REQUIREMENTS Building 5A Comm. No. 2-3741-11 Page 1 of 7 Jefferson Laboratories of the FDA ch equipment.

SECTION 01 70 00

EXECUTION REQUIREMENTS

1.01 SECTION INCLUDES

A. Examination, preparation, and general installation procedures.

B. Requirements for alterations work, including selective demolition, except removal, disposal, and/or remediation of hazardous materials and toxic substances.

C. Cutting and patching.

D. Surveying for laying out the work.

E. Cleaning and protection.

F. Starting of systems and equipment.

G. Demonstration and instruction of Jefferson Laboratories of the FDA personnel.

1.02 SUBMITTALS

A. Survey work: Submit name, address, and telephone number of Surveyor before starting survey work.

1. On request, submit documentation verifying accuracy of survey work.

2. Submit a copy of site drawing signed by the Land Surveyor, that the elevations and locations of the work are in conformance with Contract Documents.

3. Submit surveys and survey logs for the project record.

B. Cutting and Patching: Submit written request in advance of cutting or alteration which affects:

1. Structural integrity of any element of Project.

2. Integrity of weather exposed or moisture resistant element.

3. Efficiency, maintenance, or safety of any operational element.

4. Visual qualities of sight exposed elements.

5. Work of Jefferson Laboratories of the FDA or separate Contractor.

1.03 QUALIFICATIONS

A. For survey work, employ a land surveyor registered in Jefferson, Arkansas and acceptable to Contracting Officer. Submit evidence of Surveyor's Errors and Omissions insurance coverage in the form of an Insurance Certificate.

1.04 PROJECT CONDITIONS

A. Ventilate enclosed areas to assist cure of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.

B. Dust Control: Execute work by methods to minimize raising dust from construction operations.

Provide positive means to prevent air-borne dust from dispersing into atmosphere.

1.05 COORDINATION

A. Coordinate scheduling, submittals, and work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later.

B. Verify that utility requirements and characteristics of new operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, su

Comm. No. 2-3741-11 Page 2 of 7 Jefferson Laboratories of the FDA

C. Coordinate space requirements, supports, and installation of mechanical and electrical work which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.

E. Coordinate completion and clean-up of work of separate sections.

F. After Jefferson Laboratories of the FDA occupancy of premises, coordinate access to site for correction of defective work and work not in accordance with Contract Documents, to minimize disruption of Jefferson Laboratories of the FDA's activities.

PART 2 PRODUCTS

2.01 PATCHING MATERIALS

A. New Materials: As specified in product sections; match existing products and work for patching and extending work.

B. Type and Quality of Existing Products: Determine by inspecting and testing products where necessary, referring to existing work as a standard.

C. Product Substitution: For any proposed change in materials, submit request for substitution described in Section 01 60 00.

PART 3 EXECUTION

3.01 EXAMINATION

A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent work.

Start of work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural support or attachment of new work being applied or attached.

C. Examine and verify specific conditions described in individual specification sections.

D. Verify that utility services are available, of the correct characteristics, and in the correct locations.

E. Prior to Cutting: Examine existing conditions prior to commencing work, including elements subject to damage or movement during cutting and patching. After uncovering existing work, assess conditions affecting performance of work. Beginning of cutting or patching means acceptance of existing conditions.

3.02 PREPARATION

A. Prepare surfaces and remove surface finishes to provide for proper installation of new work and finishes.

B. Clean substrate surfaces prior to applying next material or substance.

C. Seal cracks or openings of substrate prior to applying next material or substance.

D. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.

3.03 LAYING OUT THE WORK

A. Promptly notify Contracting Officer of any discrepancies discovered.

Comm. No. 2-3741-11 Page 3 of 7 Jefferson Laboratories of the FDA

B. Establish elevations, lines and levels. Locate and lay out by instrumentation and similar appropriate means:

1. Grid or axis for structures.

2. Building foundation, column locations, ground floor elevations.

C. Periodically verify layouts by same means.

D. Maintain a complete and accurate log of control and survey work as it progresses.

3.04 GENERAL INSTALLATION REQUIREMENTS

A. Install products as specified in individual sections, in accordance with manufacturer's instructions and recommendations, and so as to avoid waste due to necessity for replacement.

B. Make neat transitions between different surfaces, maintaining texture and appearance.

C. When existing finished surfaces are cut so that a smooth transition with new work is not possible, terminate existing surface along a straight line at a natural line of division and make recommendation to Contracting Officer.

3.05 ALTERATIONS

A. Drawings showing existing construction and utilities are based on casual field observation and existing record documents only.

1. Verify that construction and utility arrangements are as shown.

2. Report discrepancies to Contracting Officer before disturbing existing installation.

3. Beginning of alterations work constitutes acceptance of existing conditions.

B. Separate areas in which alterations are being conducted from other areas that are still occupied.

C. Remove existing work as indicated and as required to accomplish new work.

1. Remove items indicated on drawings.

2. Relocate items indicated on drawings.

3. Where new surface finishes are to be applied to existing work, perform removals, patch, and prepare existing surfaces as required to receive new finish; remove existing finish if necessary for successful application of new finish.

4. Where new surface finishes are not specified or indicated, patch holes and damaged surfaces to match adjacent finished surfaces as closely as possible.

D. Services (Including but not limited to HVAC, Plumbing, Fire Protection, Electrical, and Telecommunications): Remove, relocate, and extend existing systems to accommodate new construction.

1. Maintain existing active systems that are to remain in operation; maintain access to equipment and operational components; if necessary, modify installation to allow access or provide access panel.

2. Where existing systems or equipment are not active and Contract Documents require reactivation, put back into operational condition; repair supply, distribution, and equipment as required.

3. Where existing active systems serve occupied facilities but are to be replaced with new services, maintain existing systems in service until new systems are complete and ready for service.

a. Disable existing systems only to make switchovers and connections; minimize duration of outages.

b. Provide temporary connections as required to maintain existing systems in service.

4. Verify that abandoned services serve only abandoned facilities.

5. Remove abandoned pipe, ducts, conduits, and equipment, including those above accessible ceilings; remove back to source of supply where possible, otherwise cap stub and tag with identification; patch holes left by removal using materials specified for new construction.

Comm. No. 2-3741-11 Page 4 of 7 Jefferson Laboratories of the FDA nish.

ther work.

E. Protect existing work to remain.

1. Prevent movement of structure; provide shoring and bracing if necessary.

2. Perform cutting to accomplish removals neatly and as specified for cutting new work.

3. Repair adjacent construction and finishes damaged during removal work.

4. Patch as specified for patching new work.

F. Adapt existing work to fit new work:

1. When existing finished surfaces are cut so that a smooth transition with new work is not possible, terminate existing surface along a straight line at a natural line of division and make recommendation to Contracting officer

2. Where removal of partitions or walls results in adjacent spaces becoming one, rework floors, walls, and ceilings to a smooth plane without breaks, steps, or bulkheads.

3. Where a change of plane of 1/4 inch or more occurs in existing work, submit recommendation for providing a smooth transition for Contracting Officer'sContracting Officer review and request instructions.

G. Patching: Where the existing surface is not indicated to be refinished, patch to match the surface finish that existed prior to cutting. Where the surface is indicated to be refinished, patch so that the substrate is ready for the new fi

H. Refinish existing surfaces as indicated:

1. Where rooms or spaces are indicated to be refinished, refinish all visible existing surfaces to remain to the specified condition for each material, with a neat transition to adjacent finishes.

2. If mechanical or electrical work is exposed accidentally during the work, re-cover and refinish to match.

3. Patch as specified for patching new work.

I. Clean existing systems and equipment.

J. Remove demolition debris and abandoned items from alterations areas and dispose of off-site;

do not burn or bury.

K. Do not begin new construction in alterations areas before demolition is complete.

L. Comply with all other applicable requirements of this section.

3.06 CUTTING AND PATCHING

A. Whenever possible, execute the work by methods that avoid cutting or patching.

B. Perform whatever cutting and patching is necessary to:

1. Complete the work.

2. Fit products together to integrate with other work.

3. Provide openings for penetration of mechanical, electrical, and other services.

4. Match work that has been cut to adjacent work.

5. Repair areas adjacent to cuts to required condition.

6. Repair new work damaged by subsequent work.

C. Execute cutting and patching including excavation and fill to complete the work, to uncover work in order to install improperly sequenced work, to remove and replace defective or non-conforming work, to remove samples of installed work for testing when requested, to provide openings in the work for penetration of mechanical and electrical work, to execute patching to complement adjacent work, and to fit products together to integrate with o

D. Execute work by methods to avoid damage to other work, and which will provide appropriate surfaces to receive patching and finishing. In existing work, minimize damage and restore to original condition.

Comm. No. 2-3741-11 Page 5 of 7 Jefferson Laboratories of the FDA dition.

E. Employ original installer to perform cutting for weather exposed and moisture resistant elements, and sight exposed surfaces.

F. Cut rigid materials using masonry saw or core drill. Pneumatic tools not allowed without prior approval.

G. Restore work with new products in accordance with requirements of Contract Documents.

H. Fit work air tight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces.

I. At penetrations of fire rated walls, partitions, ceiling, or floor construction, completely seal voids with fire rated material in accordance with Section 07 84 00, to full thickness of the penetrated element.

J. Patching:

1. Finish patched surfaces to match finish that existed prior to patching. On continuous surfaces, refinish to nearest intersection or natural break. For an assembly, refinish entire unit.

2. Match color, texture, and appearance.

3. Repair patched surfaces that are damaged, lifted, discolored, or showing other imperfections due to patching work. If defects are due to condition of substrate, repair substrate prior to repairing finish.

K. Refinish surfaces to match adjacent finish. For continuous surfaces, refinish to nearest intersection or natural break. For an assembly, refinish entire unit.

L. Make neat transitions. Patch work to match adjacent work in texture and appearance. Where new work abuts or aligns with existing, perform a smooth and even transition.

3.07 PROGRESS CLEANING

A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly con

B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing the space.

C. Broom and vacuum clean interior areas prior to start of surface finishing, and continue cleaning to eliminate dust.

D. Collect and remove waste materials, debris, and trash/rubbish from site periodically and dispose off-site; do not burn or bury.

3.08 PROTECTION OF INSTALLED WORK

A. Provide special protection where specified in individual specification sections.

B. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage.

C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.

D. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials.

E. Prohibit traffic or storage upon waterproofed or roofed surfaces. If traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer.

F. Remove protective coverings when no longer needed; reuse or recycle plastic coverings if possible.

Comm. No. 2-3741-11 Page 6 of 7 Jefferson Laboratories of the FDA

3.09 SYSTEMS STARTUP

A. Coordinate schedule for start-up of various equipment and systems.

B. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions which may cause damage.

C. Verify tests, meter readings, and specified electrical characteristics agree with those required by the equipment or system manufacturer.

D. Verify that wiring and support components for equipment are complete and tested.

E. Execute start-up under supervision of applicable Contractor personnel and manufacturer's representative in accordance with manufacturers' instructions.

F. Submit a written report that equipment or system has been properly installed and is functioning correctly.

3.10 DEMONSTRATION AND INSTRUCTION

A. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shutdown of each item of equipment at scheduled time, at equipment location.

B. For equipment or systems requiring seasonal operation, perform demonstration for other season within six months.

C. Provide a qualified person who is knowledgeable about the Project to perform demonstration and instruction of owner personnel.

3.11 ADJUSTING

A. Adjust operating products and equipment to ensure smooth and unhindered operation.

3.12 FINAL CLEANING

A. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces.

B. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned.

C. Clean filters of operating equipment.

D. Clean debris from roofs, gutters, downspouts, and drainage systems.

E. Clean site; sweep paved areas, rake clean landscaped surfaces.

F. Remove waste, surplus materials, trash/rubbish, and construction facilities from the site;

dispose of in legal manner; do not burn or bury.

3.13 CLOSEOUT PROCEDURES

A. Make submittals that are required by governing or other authorities.

B. Notify Contracting Officer when work is considered ready for Substantial Completion.

C. Submit written certification that Contract Documents have been reviewed, work has been inspected, and that work is complete in accordance with Contract Documents and ready for Contracting Officer's review.

D. Correct items of work listed in executed Certificates of Substantial Completion and comply with requirements for access to Jefferson Laboratories of the FDA-occupied areas.

Comm. No. 2-3741-11 Page 7 of 7 Jefferson Laboratories of the FDA

E. Notify Contracting Officer when work is considered finally complete.

F. Complete items of work determined by Contracting Officer's final inspection.

Stuck Associates Section 01 78 00 Renovation of Animal Rooms July 6, 2012 CLOSEOUT SUBMITTALS Building 5A

SECTION 01 78 00

CLOSEOUT SUBMITTALS

1.01 SECTION INCLUDES

A. Project Record Documents.

B. Operation and Maintenance Data.

C. Warranties and bonds.

1.02 SUBMITTALS

A. Project Record Documents: Submit documents to Contracting Officer with claim for final Application for Payment.

B. Operation and Maintenance Data:

1. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of Work. Contracting Officer will review draft and return one copy with comments.

2. For equipment, or component parts of equipment put into service during construction and operated by Jefferson Laboratories of the FDA, submit completed documents within ten days after acceptance.

3. Submit 1 copy of completed documents 15 days prior to final inspection. This copy will be reviewed and returned after final inspection, with Contracting Officer's comments. Revise content of all document sets as required prior to final submission.

4. Submit four sets of revised final documents in final form within 10 days after final inspection.

C. Warranties and Bonds:

1. For equipment or component parts of equipment put into service during construction with

Jefferson Laboratories of the FDA's permission, submit documents within ten days after acceptance.

2. Make other submittals within ten days after Date of Substantial Completion, prior to final Application for Payment.

3. For items of Work for which acceptance is delayed beyond Date of Substantial Completion, submit within ten days after acceptance, listing the date of acceptance as the beginning of the warranty…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .