This is a Project Manual for the State of California Department of General Services Real Estate Services Division, in partnership with the Department of Forestry and Fire Protection (CALFire), for the replacement of communication facilities in Humboldt and Shasta Counties, California. The project involves Phase V communication facilities replacement covering three mountain sites: Pratt Mountain, Bunchgrass Mountain, and Mt. Pierce. The work encompasses demolition of existing tower foundations, construction of new tower foundations, vault structures, HVAC systems, electrical systems, and antenna installations across all three locations. The project is organized into five books within the manual, with Book III specifically detailing specifications for Bunchgrass Mountain work. Project Director Courtney Wetsell manages the effort through the DGS Project Management and Development Branch, with GHD, Inc. serving as the consultant. The manual includes comprehensive specifications for structural work, concrete operations, masonry, metals, electrical systems, plumbing, site preparation, and erosion control across multiple divisions and sections.

The project specifications establish detailed requirements for materials, execution standards, and quality assurance across all construction disciplines. Concrete specifications require a minimum 4,500 psi compressive strength at 28 days with specific cement content of 765 pounds per cubic yard, water-cement ratios not exceeding 0.45, and retarders extending set time by two hours. Masonry work utilizes concrete block units meeting ASTM C90 standards with minimum 2,000 psi compressive strength, Type S mortar conforming to ASTM C270, and grout meeting ASTM C476 with 2,000 psi minimum compressive strength. Welding operations comply with AWS D1.1 Structural Welding Code standards. Field quality control includes independent testing laboratory services with minimum three concrete test cylinders per 75 cubic yards placed daily, maintaining material temperatures at minimum 50 degrees Fahrenheit during work and 48 hours after completion. All work must conform to the 2019 California Building Code, and contractors assume full responsibility for Federal, State, and local regulatory compliance including worker safety and proper disposal of demolished materials.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

08/14/26 Project Number: 1512A

STATE OF CALIFORNIA DEPARTMENT OF GENERAL SERVICES

REAL ESTATE SERVICES DIVISION

PROJECT MANAGEMENT AND DEVELOPMENT BRANCH

PROJECT MANUAL – Book III of V:

INTRODUCTORY INFORMATION

SPECIFICATIONS

FOR:

PHASE V COMMUNICATION FACILITIES

REPLACEMENT – GROUP A

1512B – BUNCHGRASS MTN.

DEPARTMENT OF FORESTRY AND FIRE

PROTECTION (CALFIRE)

HUMBOLT & SHASTA COUNTIES, CALIFORNIA

Courtney Wetsell, Project Director Telephone Number

279.799.4650 West

Sacramento, California Consultants: GHD

OFFICE OF THE STATE FIRE MARSHAL

APPROVED FIRE AND PANIC ONLY

01/12/26

Approval of this plan does not authorize or approve any omission or deviation from applicable regulations. Final approval is subject to field inspection. One set of approved plans shall be available on the project site at all times.

22-5731

PROJECT TITLE PAGE

RESDMSTR: 02/03/2014v1 00 01 01 - 1 01512A, B, E

DOCUMENT 00 01 01

PROJECT TITLE PAGE

Title: REPLACE COMMUNICATION FACILITIES, PHASE V – GROUP A:

1. PRATT MOUNTAIN

2. BUNCHGRASS MOUNTAIN

3. MT. PIERCE

Client Agency: DEPARTMENT OF FORESTRY AND FIRE

PROTECTION (CALFIRE)

Location: PRATT MOUNTAIN/ BUNCHGRASS

MOUNTAIN/ MT.PIERCE

HUMBOLDT & SHASTA COUNTIES,

CALIFORNIA

Project Number: 1512A, 1512B, 1512E

Project Director: Courtney Wetsell State of California Department of General Services Real Estate Services Division Project Management and Development Branch 707 Third Street, 4th Floor West Sacramento, California 95605 Telephone Number: 279.799.

Email: Courtney.Wetsell@dgs.ca.gov

Consultant: GHD, Inc.

Matt Weber, Project Manager 943 Reserve Drive Roseville, CA 95678 Telephone Number: (916) 296-3222 Email: Matt.Weber@ghd.com

CERTIFICATIONS PAGE

RESDMSTR: 02/03/2014v1 00 01 05 - 1 001512A, B, E

DOCUMENT 00 01 05

CERTIFICATIONS PAGE

PROJECT TITLE:

1. PRATT MOUNTAIN

2. BUNCHGRASS MOUNTAIN

3. MT. PIERCE

CLIENT AGENCY :

LOCATION:

PROJECT NUMBER :

OWNER :

PROJECT DIRECTOR :

CONSULTANT

REPLACE COMMUNICATION FACILITIES, PHASE V –

GROUP A:

DEPARTMENT OF FORESTRY AND FIRE PROTECTION

(CALFIRE)

A - PRATT MOUNTAIN

(Coordinates: 41°29'56.58"N, 124° 3'36.30"W)

B - BUNCHGRASS MTN.

(Coordinates: 41°29'56.58"N, 124° 3'36.30"W)

E - MT. PIERCE

(Coordinates: 41°29'56.58"N, 124° 3'36.30"W)

HUMBOLDT & SHASTA COUNTIES, CALIFORNIA

1512A, 1512B, 1512E

STATE OF CALIFORNIA

Courtney Wetsell Department of General Services Project Management and Development Branch 707 Third Street, 4th Floor West Sacramento, California 95605 Telephone Number: 279.799.4650 Email: Courtney.Wetsell@dgs.ca.gov

GHD, Inc. Matt.Weber@ghd.com

RESDMSTR: 02/03/2014v1 00 01 05 - 2 001512A, B, E

REGULATORY REVIEWS:

RESDMSTR: 02/03/2014v1 00 01 05 - 3 001512A, B, E

See Site Books 2, 3, & 4 for site Specific Regulatory Stamps

See Site Books 2, 3, & 4 for site Specific Regulatory Stamps

DSA ACCESS COMPLIANCE SFM

TABLE OF CONTENTS

RESDMSTR: 6/20/2025 00 01 10 - 1 1512A, B, E

DOCUMENT 00 01 10

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP

BOOK I

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

INTRODUCTORY INFORMATION

Pages Document 00 01 01 Project Title Page .......................................................................... 1 only 00 01 05 Certifications Page ........................................................................ 1 through 3 00 01 10 Table of Contents .......................................................................... 1 through 9 00 01 15 List of Drawings ............................................................................. 1 through 8

BIDDING REQUIREMENTS

Document 00 11 00 Invitation for Bids ........................................................................... 1 through 4 00 21 00 Instructions to Bidders ................................................................... 1 through 8 Appendix 00 21 00.01 Request for Bidding Interpretation ................................................. 1 only Document 00 22 00 Supplementary Instructions to Bidders .......................................... 1 only 00 22 10 DVBE Participation Program Requirements ................................... 1 through 3 00 41 00 Bid Form (Sample) ........................................................................ 1 through 10 00 43 13 Bidder’s Bond (Sample) ................................................................. 1 only 00 43 16 Certified Small Business Subcontractor(s) Summary (Sample) ..... 1 through 2 00 45 46 Payee Data Record (Sample) ........................................................ 1 through 2 00 91 13 Addendum (Sample)……………………………………………………1 through 3

CONTRACTING REQUIREMENTS

Document 00 52 00 Agreement (Sample) ..................................................................... 1 only 00 61 13 Performance Bond (Sample) ......................................................... 1 only 00 61 14 Payment Bond to Accompany Construction Contract (Sample) ..... 1 only 00 63 63 Construction Contract Change Order (Sample) ............................. 1 only 00 72 00 General Conditions of the Contract for Construction ...................... 1 through 31 00 73 00 Supplementary Conditions ............................................................. 1 through 13

SPECIFICATIONS GROUP

GENERAL REQUIREMENTS SUBGROUP

DIVISION 01 - GENERAL REQUIREMENTS

Section 01 10 00 Summary ....................................................................................... 1 through 8 01 21 00 Allowances .................................................................................... 1 through 2 01 25 00 Substitution Procedures ................................................................. 1 through 2

RESDMSTR: 6/20/2025 00 01 10 - 2 1512A, B, E

01 29 00 Payment Procedures ..................................................................... 1 through 4 01 31 00 Project Management and Coordination .......................................... 1 through 6 01 32 00 Construction Progress Documentation .......................................... 1 through 7 01 32 33 Photographic Documentation ........................................................ 1 through 3 01 33 00 Submittal Procedures .................................................................... 1 through 8 01 33 29.08 Buy Clean California Act Requirements ......................................... 1 through 2 01 40 00 Quality Requirements .................................................................... 1 through 6 01 50 00 Temporary Facilities and Controls ................................................. 1 through 7 01 56 39 Temporary Tree and Plant Protection ............................................ 1 through 5 01 57 23 Temporary Storm Water Pollution Control ..................................... 1 through 4 01 60 00 Product Requirements ................................................................... 1 through 5 01 64 00 Owner-furnished Products ............................................................. 1 through 3 01 73 00 Execution ...................................................................................... 1 through 7 01 74 19 Construction Waste Management and Disposal ............................ 1 through 5 Form 01 74 19.01 Construction Waste Estimate (A,B,& E) ......................................... 1 only 01 74 19.02 Waste Management Report (A, B & E) .......................................... 1 through 2 Section 01 74 20 Recycled Content Certification (A, B & E) ...................................... 1 through 3 Form 01 74 20.01 Recycled Content Certification Worksheet (Example) .................... 1 through 2 01 74 20.02 State Agency Buy Recycled Campaign Procurement Summary (Example) (A, B & E) ...................................................................................... 1 through 2 Section 01 75 00 Starting and Adjusting ................................................................... 1 through 3 01 77 00 Closeout Procedures ..................................................................... 1 through 12 Form STD 817 Prime Contractor’s Certifications – DVBE Subcontractor Report ... 1 through 5 01 77 00.01 Contractor’s Certification of Small Business Participation .............. 1 only 01 77 00.02 Contractor’ Certification of Small Business Participation ................ 1 only Section 01 79 00 Demonstration and Training .......................................................... 1 through 4

BOOK II - PRATT MTN.

DIVISION 02 – EXISTING CONDITIONS

Section 02 4000 Demolition ..................................................................................... 1 through 2 02 41 16 Groundwork for Structures ............................................................. 1 through 3

DIVISION 03 – CONCRETE

Section 03 10 00 Concrete Forming and Accessories ............................................... 1 through 5 03 20 00 Concrete Reinforcing ..................................................................... 1 through 3 03 30 00 Cast-In-Place Concrete ................................................................. 1 through 8

DIVISION 04 – MASONRY

Section 04 22 00 Concrete Unit Masonry .................................................................. 1 through 9

DIVISION 05 – METALS

Section 05 05 23 Metal Fastenings ........................................................................... 1 through 9 05 12 00 Structural Steel Framing ................................................................ 1 through 3 05 30 00 Metal Decking ................................................................................ 1 through 3 05 41 00 Steel Studs .................................................................................... 1 through 4

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

RESDMSTR: 6/20/2025 00 01 10 - 3 1512A, B, E

Section 06 10 00 Rough Carpentry ........................................................................... 1 through 2

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

Section 07 21 00 Thermal Insulation ......................................................................... 1 through 2 07 92 00 Joint Sealants ................................................................................ 1 through 4

DIVISION 08 – OPENINGS

Section 08 11 13 Standard Hollow Metal Doors ........................................................ 1 through 2 08 12 13 Hollow Metal Frames ..................................................................... 1 through 2 08 71 00 Door Hardware .............................................................................. 1 through 3

DIVISION 09 – FINISHES

Section 09 20 00 Plaster and Gypsum Board ............................................................ 1 through 2 09 54 53 Fiberglass Reinforced Panel .......................................................... 1 through 2 09 67 16 Epoxy Flooring .............................................................................. 1 through 3 09 91 00 Painting ......................................................................................... 1 through 7

DIVISION 13 – SPECIAL CONSTRUCTION

Section 13 36 13.13 Self-Supporting Steel Communications Tower ............................... 1 through 8 13 50 00 Antennas ....................................................................................... 1 through 17

DIVISION 15 – RESERVED (NOT USED)

DIVISION 16 – RESERVED (NOT USED)

DIVISION 17 – RESERVED (NOT USED)

DIVISION 18 – RESERVED (NOT USED)

DIVISION 19 – RESERVED (NOT USED)

FACILITY SERVICES SUBGROUP

DIVISION 20 – RESERVED (NOT USED)

DIVISION 22 – PLUMBING

Section 22 00 00 Plumbing ....................................................................................... 1 through 15

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

Section 23 00 00 Heating, Ventilating and Air Conditioning ....................................... 1 through 17 23 05 00 General Requirements for Mechanical Work ................................. 1 through 15

DIVISION 24 – RESERVED (NOT USED)

DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)

DIVISION 26 – ELECTRICAL

RESDMSTR: 6/20/2025 00 01 10 - 4 1512A, B, E

Section 26 01 00 Basic Electrical Requirements ....................................................... 1 through 9 26 01 26 Electrical Testing ........................................................................... 1 through 9 26 05 19 Low-Voltage Power Conductors and Cables .................................. 1 through 10 26 05 26 Grounding and Bonding ................................................................. 1 through 16 26 05 29 Electrical Hangers and Supports ................................................... 1 through 5 26 05 33.13 Conduit .......................................................................................... 1 through 10 26 05 33.16 Electrical Boxes ............................................................................. 1 through 3 26 05 36 Interior Cable Tray ......................................................................... 1 through 3 26 05 43 Underground Ducts and Structures ............................................... 1 through 6 26 05 48 Seismic Restraint for Electrical Equipment .................................... 1 only 26 05 53 Electrical Identification ................................................................... 1 through 7 26 24 16 Panelboards .................................................................................. 1 through 8 26 27 26 Wiring Devices .............................................................................. 1 through 7 26 27 26.10 Miscellaneous Electrical Devices ................................................... 1 through 4 26 28 16 Overcurrent Protection Devices ..................................................... 1 through 7 26 32 13 Standby System Generator Set ..................................................... 1 through 14 26 36 23 Automatic Transfer Switches ......................................................... 1 through 10 26 51 13 Interior Lighting .............................................................................. 1 through 9

DIVISION 27 – COMMUNICATIONS

Section 27 53 19 Internal Cellular, Paging and Antenna Systems ............................. 1 only

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY (NOT USED)

DIVISION 29 – RESERVED (NOT USED)

SITE AND INFRASTRUCTURE SUBGROUP

DIVISION 30 – RESERVED (NOT USED)

DIVISION 31 – EARTHWORK

Section 31 01 50 Maintenance of Excavation Support and Protection ....................... 1 through 2 31 10 00 Site Preparation (Clearing and Grubbing) ...................................... 1 only 31 20 00 Earth Moving ................................................................................. 1 through 11 31 23 13 Subgrade Preparation ................................................................... 1 through 8 31 23 16.26 Rock Removal ............................................................................... 1 through 2 31 23 33 Trenching and Backfill ................................................................... 1 through 7 31 25 00 Erosion and Sedimentation Control ............................................... 1 through 5 31 25 13 Storm Water Pollution Prevention Plan .......................................... 1 through 2

DIVISION 32 – EXTERIOR IMPROVEMENTS

Section 32 11 23 Aggregate Base Courses ............................................................... 1 only 32 31 13 Chain Link Fence ........................................................................... 1 through 4

DIVISION 33 – UTILITIES (NOT USED)

DIVISION 34 – TRANSPORTATION (NOT USED)

RESDMSTR: 6/20/2025 00 01 10 - 5 1512A, B, E

DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION (NOT USED)

DIVISION 36 – RESERVED (NOT USED)

DIVISION 37 – RESERVED (NOT USED)

DIVISION 38 – RESERVED (NOT USED)

DIVISION 39 – RESERVED (NOT USED)

PROCESS EQUIPMENT SUBGROUP (NOT USED)

BOOK III – BUNCHGRASS MTN

DIVISION 02 – EXISTING CONDITIONS

Section 02 40 00 Demolition ..................................................................................... 1 through 2 02 41 16 Groundwork for Structures ............................................................. 1 through 3

DIVISION 03 – CONCRETE

Section 03 10 00 Concrete Forming and Accessories ............................................... 1 through 5 03 20 00 Concrete Reinforcing ..................................................................... 1 through 3 03 30 00 Cast-In-Place Concrete ................................................................. 1 through 8

DIVISION 04 – MASONRY

Section 04 22 00 Concrete Masonry Unit .................................................................. 1 through 9

DIVISION 05 – METALS

Section 05 05 23 Metal Fastenings ........................................................................... 1 through 9 05 12 00 Structural Steel Framing ................................................................ 1 through 3 05 30 00 Metal Decking ................................................................................ 1 through 3 05 41 00 Steel Studs .................................................................................... 1 through 4

DIVISION 06 – WOOD

Section 06 10 00 Rough Carpentry ........................................................................... 1 through 2

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

Section 07 21 00 Thermal Insulation ......................................................................... 1 through 2 07 92 00 Joint Sealants ................................................................................ 1 through 4

DIVISION 08 – WINDOWS AND DOORS

Section 08 11 13.13 Standard Hollow Metal Doors ........................................................ 1 through 2 08 12 13 Hollow Metal Frames ..................................................................... 1 through 2 08 71 00 Door Hardware .............................................................................. 1 through 3

DIVISION 09 – FINISHES

Section 09 20 00 Plaster Gypsum Board................................................................... 1 through 2

RESDMSTR: 6/20/2025 00 01 10 - 6 1512A, B, E

09 54 53 Fiberglass Reinforced Panel .......................................................... 1 through 2 09 67 16 Epoxy Flooring .............................................................................. 1 through 3 09 91 00 Painting ......................................................................................... 1 through 7

DIVISION 13 – SPECIAL CONSTRUCTION

Section 13 36 13.13 Self-Supporting Steel Communications Tower ............................... 1 through 8 13 50 00 Antennas ....................................................................................... 1 through 17

DIVISION 22 – PLUMBING

Section 22 00 00 Plumbing ....................................................................................... 1 through 14

DIVISION 23 – HEATING, VENTILATING AND AIR CONDITIONING

Section 23 00 00 Heating, Ventilating and Air Conditioning ....................................... 1 through 17 23 05 00 General Requirements for Mechanical Work ................................. 1 through 15

DIVISION 26 – ELECTRICAL

Section 26 01 00 Basic Electrical Requirements ....................................................... 1 through 9 26 01 26 Electrical Testing ........................................................................... 1 through 9 26 05 19 Low-Voltage Power Conductors and Cables .................................. 1 through 10 26 05 26 Grounding and Bonding ................................................................. 1 through 16 26 05 29 Electrical Hangers and Supports ................................................... 1 through 4 26 05 33.13 Conduit .......................................................................................... 1 through 10 26 05 33.16 Electrical Boxes ............................................................................. 1 through 3 26 05 36 Interior Cable Tray ......................................................................... 1 through 3 26 05 43 Underground Ducts and Structures ............................................... 1 through 6 26 05 48 Seismic Restraint for Electrical Equipment .................................... 1 only 26 05 53 Electrical Identification ................................................................... 1 through 7 26 24 16 Panelboards .................................................................................. 1 through 8 26 27 26 Wiring Devises .............................................................................. 1 through 7 26 27 26.10 Miscellaneous Electrical Devices ................................................... 1 through 4 26 28 16 Overcurrent Protection Devices ..................................................... 1 through 7 26 32 13 Stanby System Generator Set ....................................................... 1 through 15 26 36 23 Automatic Transfer Switches ......................................................... 1 through 10 26 51 13 Interior Lighting .............................................................................. 1 through 9

DIVISION 27 – COMMUNICATIONS

Section 27 53 19 Internal Cellular, Paging and Antenna Systems ............................. 1 only

DIVISION 31 – EARTHWORK

Section 31 01 50 Maintenance of Excavation Support and Protection ....................... 1 through 2 31 10 00 Site Preparation (Clearing and Grubbing) ...................................... 1 only 31 20 00 Earth Moving ................................................................................. 1 through 11 31 23 13 Subgrade Preparation ................................................................... 1 through 8 31 23 16.26 Rock Removal ............................................................................... 1 through 2 31 23 33 Trenching and Backfill ................................................................... 1 through 7 31 25 00 Erosion and Sedimentation Control ............................................... 1 through 5 31 25 13 Strom Water Pollution Prevention Plan .......................................... 1 through 2

RESDMSTR: 6/20/2025 00 01 10 - 7 1512A, B, E

DIVISION 32 – EXTERIOR IMPROVEMENTS

Section 32 11 23 Aggregate Base Courses ............................................................... 1 only 32 31 13 Chain Link Fence ........................................................................... 1 through 4

BOOK IV - MT. PIERCE

DIVISION 02 – EXISTING CONDITIONS

Section 02 40 00 Demolition ..................................................................................... 1 through 2 02 41 16 Groundwork for Structures ............................................................. 1 through 3

DIVISION 03 – CONCRETE

Section 03 10 00 Concrete Forming and Accessories ............................................... 1 through 5 03 20 00 Concrete Reinforcing ..................................................................... 1 through 3 03 30 00 Cast-In-Place Concrete ................................................................. 1 through 8

DIVISION 04 – MASONRY

Section 04 22 00 Concrete Masonry Units ................................................................ 1 through 9

DIVISION 05 – METALS

Section 05 05 23 Metal Fastenings ........................................................................... 1 through 9 05 12 00 Structural Steel Framing ................................................................ 1 through 3 05 30 00 Metal Decking ................................................................................ 1 through 3 05 41 00 Steel Studs .................................................................................... 1 through 4

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

Section 06 10 00 Rough Carpentry ........................................................................... 1 through 2

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

Section 07 21 00 Thermal Insulation ......................................................................... 1 through 2 07 92 00 Joint Sealants ................................................................................ 1 through 4

DIVISION 08 – OPENINGS

Section 08 11 13.13 Standard Hollow Metal Doors ........................................................ 1 through 2 08 12 13 Hollow Metal Frames ..................................................................... 1 through 2 08 71 00 Door Hardware .............................................................................. 1 through 3

DIVISION 9 – FINISHES

Section 09 20 00 Plaster Gypsum Board................................................................... 1 through 2 09 54 53 Fiberglass Reinforced Panel .......................................................... 1 through 2 09 67 16 Epoxy Flooring .............................................................................. 1 through 3 09 91 00 Painting ......................................................................................... 1 through 7

DIVISIOIN 13 – SPECIAL CONSTRUCTION

Section 13 36 13.13 Self-Supporting Steel Communications Tower ............................... 1 through 8

RESDMSTR: 6/20/2025 00 01 10 - 8 1512A, B, E

13 50 00 Antennas ....................................................................................... 1 through 18

DIVISION 22 – PLUMBING

Section 22 00 00 Plumbing ....................................................................................... 1 through 14

DIVISION 23 – HEATING, VENTILATING AND AIR CONDITIONING

Section 23 00 00 Heating, Ventilating and Air Conditioning ....................................... 1 through 17 23 05 00 General Requirements for Mechanical Work ................................. 1 through 15

DIVISION 26 – ELECTRICAL

Section 26 01 00 Basic Electrical Requirements ....................................................... 1 through 9 26 01 26 Electrical Testing ........................................................................... 1 through 9 26 05 19 Low-Voltage Power Conductors and Cables .................................. 1 through 10 26 05 26 Grounding and Bonding ................................................................. 1 through 16 26 05 29 Electrical Hangers and Supports ................................................... 1 through 4 26 05 33.13 Conduit .......................................................................................... 1 through 10 26 05 33.16 Electrical Boxes ............................................................................. 1 through 3 26 05 36 Interior Cable Tray ......................................................................... 1 through 3 26 05 43 Underground Ducts and Structures ............................................... 1 through 6 26 05 48 Seismic Restraint for Electrical Equipment .................................... 1 only 26 05 53 Electrical Identification ................................................................... 1 through 7 26 24 16 Panelboards .................................................................................. 1 through 8 26 27 26 Wiring Devices .............................................................................. 1 through 7 26 27 26.10 Miscellaneous Electrical Devices ................................................... 1 through 4 26 28 16 Overcurrent Protection Devices ..................................................... 1 through 7 26 32 13 Standby System Generator Set ..................................................... 1 through 14 26 36 23 Automatic Transfer Switches ......................................................... 1 through 10 26 51 13 Interior Lighting .............................................................................. 1 through 9

DIVISION 27 – COMMUNICATIONS

Section 27 53 19 Internal Cellular, Paging and Antenna System ............................... 1 only

DIVISION 31 – EARTHWORK

Section 31 01 50 Maintenance of Excavation Support and Protection ....................... 1 through 2 31 10 00 Site Preparation (Clearing and Grubbing) ...................................... 1 only 31 20 00 Earth Moving ................................................................................. 1 through 11 31 23 13 Subgrade Preparation ................................................................... 1 through 8 31 23 16.26 Rock Removal ............................................................................... 1 through 2 31 23 33 Trenching and Backfill ................................................................... 1 through 7 31 25 00 Erosion and Sedimentation Control ............................................... 1 through 5 31 25 13 Strom Water Pollution Prevention Plan .......................................... 1 through 2

DIVISION 32 – EXTERIOR IMPROVEMENTS

Section 32 11 23 Aggregate Base Courses ............................................................... 1 only 32 31 13 Chain Link Fence ........................................................................... 1 through 4

RESDMSTR: 6/20/2025 00 01 10 - 9 1512A, B, E

BOOK V - APPENDICES

A. Geotechnical Investigations:

A Pratt Final Geotechnical

Investigation 1 through 37

B Bunchgrass Final Geotechnical Investigation

1 through 39

E Pierce Final Geotechnical Investigation

1 through 52

B. Environmental Commitment Tables

A Pratt EC Table 1 through 6 B Bunchgrass EC Table 1 through 6 E Mt. Pierce EC Table 1 through 5

C. Miscellaneous Tower Equipment Information

1 Antenna Testing &

Analysis 1 through 11

2 Antenna Wrapping Procedure

1 through 5

3 Cal OES PSC & General Contractor Inspection and Acceptance Criteria

1 through 4

4 Grounding Requirement for Vault and Tower

1 through 13

5 Tower Install Coax - Waveguide

1 through 3

END OF DOCUMENT

LIST OF DRAWINGS

RESDMSTR: 02/03/2014 00 01 15 - 1 01512A, B, E

DOCUMENT 00 01 15

PRATT MTN. – INCREMENT 1

Sheet Number Description

GENERAL

PM -G001 COVER SHEET

PM -G002 DRAWING INDEX, DESIGN CRITERIA AND SITE ORIENTATION

PM -G003 ABBREVIATIONS AND SYMBOLS

CIVIL

PM -C101 EXISTING SITE DEMOLITION AND CONSTRUCTION

SEQUENCING PLAN

PM -C102 SITE AND GRADING PLAN

PM -C501 CIVIL SECTIONS AND DETAILS

PM-C502 COMMON SITE DETAILS

ARCHITECTURAL

PM -A101 VAULT FLOOR PLAN, ROOF PLAN AND BUILDING

ELEVATIONS

PM -A102 GENERATOR VAULT PLANS, ELEVATIONS AND SECTION

PM -A501 ARCHITECTURAL DETAILS

PM -A502 ARCHITECTURAL DETAILS

STRUCTURAL

PM -S001 STRUCTURAL NOTES

PM -S101 VAULT FOUNDATION AND ROOF FRAMING PLAN AND

SECTION

PM -S102 TOWER FOUNDATION PLAN AND ELEVATION

PM -S501 COMMON STRUCTURAL DETAILS

PM -S502 STRUCTURAL DETAILS

PM -S503 STRUCTURAL DETAILS

PM -S701 FEEDLINE BRIDGE

PM -S702 FEEDLINE BRIDGE

MECHANICAL

PM -M001 MECHANICAL SYMBOLS, LEGEND, ABBREVIATIONS, AND

GENERAL NOTES

PM -M101 LARGE VAULT – HVAC

PM -M102 GENERATOR VAULT – HVAC

PM -M501 MECHANICAL DETAILS

PM -M601 MECHANICAL SCHEDULES

RESDMSTR: 02/03/2014 00 01 15 - 2 01512A, B, E

ELECTRICAL

PM -E001 ELECTRICAL SYMBOLS LEGEND, ABBREVIATIONS AND

GENERAL NOTES

PM -E101 ELECTRICAL SITE PLAN

PM -E102 LARGE VAULT – LIGHTING, POWER, EQUIPMENT AND

GROUNDING

PM -E103 GENERATOR VAULT LIGHTING, POWER, EQUIPMENT AND

GROUNDING

PM -E104 LARGE VAULT INTERIOR ELEVATIONS – 1

PM -E105 LARGE VAULT INTERIOR ELECATIONS – 2

PM -E501 ELECTRICAL DETAILS – 1

PM -E502 ELECTRICAL DETAILS – 2

PM -E503 ELECTRICAL DETAILS – 3

PM -E504 ELECTRICAL DETAILS – 4

PM -E505 ELECTRICAL DETAILS – 5

PM -E506 ELECTRICAL DETAILS – 6

PM -E601 SINGLE LINE DIAGRAM AND LOAD CALCULATION

PM -E602 ELECTRICAL SCHEDULES – 1

PM -E603 ELECTRICAL SCHEDULES – 2

PM -E604 ALARM STATUS REPORTING SCHEMATICS

PM -E605 ALARM POINT DESCRIPTIONS

PM -E606 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF

CABLING – 1

PM -E607 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF

CABLING – 2

PM -E608 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF

CABLING – 3

PM -E609 SITE ANTENNA LAYOUT AND PRESSURIZATION

EQUIPMENT – 1

PM -E610 SITE ANTENNA LAYOUT AND PRESSURIZATION

EQUIPMENT – 2

PM-E611 -48VDC CRIS OES INTERCONNECT DIAGRAM

PM-E612 -48VDC MW OES INTERCONNECT DIAGRAM

PM-E613 +12VDC OES INTERCONNECT DIAGRAM

TOWER STRUCTURAL DRAWINGS

T-1 COVER SHEET & DRAWING INDEX

S-1 ELEVATION VIEW/NOTES

S-1.1 SST SECTION ALLOWABLE MEMBER FORCES

S-1.2 MONOPOLE SECTIONS ALLOWABLE FORCES

S-2 UPPER POLE

S-3 LOWER POLE

S-4 TOWER SECTION 13V - NESTED POLE

RESDMSTR: 02/03/2014 00 01 15 - 3 01512A, B, E

S-5 TOWER SECTION 13V

S-6 TOWER SECTION 15ST

S-6.1 TOWER SECTION 15ST CONT.

S-7 TOWER SECTION 17ST

S-7.1 TOWER SECTION 17ST CONT.

S-8 TOWER SECTION 19ST

S-9 TYPICAL GRATING/BRACING

S-10 TYPICAL HANDRAIL/DIAGONAL PIPE LIGHTING ROD

EXTENTSION, & SAFETY CLIMB KITS

S-11 CENTER MAST

S-12 COAX CAGE / CLIMBING LADDER, ANTI-CLIMB, & BUS BAR

S-13 ANTENNA LOCATION ELEVATION VIEWS

S-13.1 ANTENNA LOCATION PLAN VIEWS

S-14 FULLY LOADED FACE MOUNTED MICROWAVES

S-14.1 FULLY LOADED LEG MOUNTED MICROWAVES

S-14.2 FULLY LOADED VHF/UHF ANTENNA LOCATIONS

S-15 MW ICE BRIDGE DETAILS

S-15.1 MW ANTENNA ICE SHIELD DETAILS

S-16 MICROWAVE MOUNT KITS

S-17 UHF / VHF ANTENNA MOUNT KITS

S-18 LEG – ELEVATION ID PLATES

S-19 TOWER FOUNDATION SLAB/PIERS

RADIO AND MICROWAVE ANTENNA MOUNTING BRACKETS DRAWINGS

CO-TA1 COVER SHEET AND INDEX

CO-TA1.1 DSA 103

CO-TA2 TOWER STRUCTURAL NOTES

CO-TA3 SITE PRO BRACKET DETAILS

CO-TA5.2 TOWER ANTENNA MOUNTING DETAILS (AMPHENOL ANTEL)

CO-TA6 TOWER ANTENNA MOUNTING DETAILS

(ANDREW/COMMSCOPE)

CO-TA7.2 TOWER ANTENNA MOUNTING DETAILS (SINCLAIR)

CO-TA9 TOWER ANTENNA MOUNTING DETAILS (M2/KRECO)

CO-TA10 TOWER ANTENNA MOUNTING DETAILS

(COMMSCOPE/RFS/SINCLAIR)

CO-TA12 TOWER ANTENNA MOUNTING DETAILS (SCALA)

CO-TA18.1 TOWER ANTENNA MOUNTING DETAILS (TELEWAVE)

BUNCHGRASS MTN. – INCREMENT 2

GENERAL

BG-G001 COVER SHEET

BG-G002 DRAWING INDEX, DESIGN CRITERIA AND SITE ORIENTATION

BG-G003 ABBREVIATIONS AND SYMBOLS

CIVIL

BG-C101 EXISTING SITE DEMOLITION AND CONSTRUCTION

RESDMSTR: 02/03/2014 00 01 15 - 4 01512A, B, E

SEQUENCING PLAN

BG-C102 SITE AND GRADING PLAN

BG-C501 COMMON SITE DETAILS

BG-C502 COMMON SITE DETAILS

ARCHITECTURAL

BG-A101 VAULT FLOOR PLAN AND ROOF PLAN AND BUILDING

ELEVATIONS

BG-A501 ARCHITECTURAL DETAILS

BG-A502 ARCHITECTURAL DETAILS

STRUCTURAL

BG-S001 STRUCTURAL NOTES

BG-S101 VAULT FOUNDATION, ROOF FRAMING PLAN AND

SECTION

BG-S102 TOWER FOUNDATION PLAN AND ELEVATION

BG-S501 COMMON STRUCTURAL DETAILS

BG-S502 STRUCTURAL DETAILS

BG-S503 STRUCTURAL DETAILS

BG-S701 FEEDLINE BRIDGE

BG-S702 FEEDLINE BRIDGE

MECHANICAL

BG-M001 MECHANICAL SYMBOLS, LEGEND, ABBREVIATIONS, AND

GENERAL NOTES

BG-M101 MEDIUM VAULT – HVAC

BG-M501 MECHANICAL DETAILS

BG-M601 MECHANICAL SCHEDULES

ELECTRICAL

BG-E001 ELECTRICAL SYMBOLS LEGEND, ABBREVIATIONS AND

GENERAL NOTES

BG-E101 ELECTRICAL SITE PLAN

BG-E102 MEDIUM VAULT – LIGHTING, POWER, EQUIPMENT AND

GROUNDING

BG-E103 MEDIUM VAULT INTERIOR ELEVATIONS

BG-E501 ELECTRICAL DETAILS – 1

BG-E502 ELECTRICAL DETAILS – 2

BG-E503 ELECTRICAL DETAILS – 3

BG-E504 ELECTRICAL DETAILS – 4

BG-E505 ELECTRICAL DETAILS – 5

BG-E506 ELECTRICAL DETAILS – 6

BG-E601 SINGLE LINE DIAGRAM AND LOAD CALCULATION

BG-E602 ELECTRICAL SCHEDULES – 1

BG-E603 ELECTRICAL SCHEDULES – 2

BG-E604 ALARM STATUS REPORTING SCHEMATICS

BG-E605 ALARM POINT DESCRIPTIONS

BG-E606 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF

CABLING – 1

RESDMSTR: 02/03/2014 00 01 15 - 5 01512A, B, E

BG-E607 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF

CABLING – 2

BG-E608 SITE ANTENNA LAYOUT AND PRESSURIZATION

EQUIPMENT – 1

BG-E609 SITE ANTENNA LAYOUT AND PRESSURIZATION

EQUIPMENT – 2

BG-E610 -48VDC CRIS OES INTERCONNECT DIAGRAM

BG-E611 -48VDC MW OES INTERCONNECT DIAGRAM

BG-E612 +12VDC OES INTERCONNECT DIAGRAM

WESTERN UTILITY TELECOM, INC. DRAWING INDEX

T-1 COVER SHEET & DRAWING INDEX

S-1 ELEVATION VIEW/NOTES

S-1.1 SST SECTION ALLOWABLE MEMBER FORCES

S-1.2 MONOPOLE SECTION ALLOWABLE MEMBER FORCES

S-2 UPPER POLE

S-3 LOWER POLE

S-4 TOWER SECTION 13V NESTED POLE

S-5 TOWER SECTION 13V

S-6 TOWER SECTION 15ST

S-6.1 TOWER SECTION 15ST CONT.

S-7 TOWER SECTION 17ST

S-7.1 TOWER SECTION 17ST CONT.

S-8 TOWER SECTION 19ST

S-9 TYPICAL GRATING/BRACING

S-10 TYPICAL HAND RAIL/DIAGNOL PIPE LIGHTING ROD

EXTENSION, SAFETY & SAFETYCLIMB KITS

S-11 CENTER MAST

S-12 COAX CAGE/CLIMBING LADDER, ANTI-CLIMB, & BUS BAR

S-13 ANTENNA LOCATION ELEVATION VIEWS

S-13.1 ANTENNA LOCATION PLAN VIEWS

S-14 FULLY LOADED FACE MOUNTED MICROWAVES

S-14.1 FULLY LOADED LEG MOUNTED MICROWAVES

S-14.2 FULLY LOADED VHF/UHF ANTENNA LOCATIONS

S-15 MW ICE BRIDGE DETAILS

S-15.1 MW ANTENNA ICE SHIELD DETAILS

S-16 MICROWAVE MOUNT KITS

S-17 UHF/VHF ANTENNA MOUNT KITS

S-18 LEG/ELEVATION ID PLATES

S-19 TOWER FOUNDATION SLAB/PIERS

SATE OF CALIFORNIA

CO-TA1 COVER SHEET AND INDEX

CO-TA1.1 DSA 103

CO-TA2 TOWER STRUCTURAL NOTES

CO-TA3 SITE PRO BRACKET DETAILS

CO-TA5.2 TOWER ANTENNA MOUNTING DETAILS (AMPHENOL ANTEL)

CO-TA6 TOWER ANTENNA MOUNTING DETAILS

(ANDREW/COMMSCOPE)

CO-TA7.2 TOWER ANTENNA MOUNTING DETAILS (SINCLAIR)

RESDMSTR: 02/03/2014 00 01 15 - 6 01512A, B, E

CO-TA9 TOWER ANTENNA MOUNTING DETAILS (M2/KRECO)

CO-TA10 TOWER ANTENNA MOUNTING DETAILS

(COMMSCOPE/RFS/SINCLAIR)

CO-TA10.1 TOWER ANTENNA MOUNTING DETAILS (RFS/SINCLAIR)

CO-TA14.1 TOWER ANTENNA MOUNTING DETAILS (SCALA)

CO-TA18 TOWER ANTENNA MOUNTING DETAILS (TELEWAVE)

MT. PIERCE – INCREMENT 3

GENERAL

MP-G001 COVER SHEET

MP-G002 DRAWING INDEX, DESIGN CRITERIA AND SITE ORIENTATION

MP-G003 ABBREVIATIONS AND SYMBOLS

CIVIL

MP-C101 EXISTING SITE DEMOLITION AND CONSTRUCTION

SEQUENCING

MP-C102 SITE AND GRADING PLAN

MP-C501 CIVIL SECTIONS AND DETAILS

MP-C502 COMMON SITE DETAILS

ARCHITECTURAL

MP-A101 VAULT FLOOR PLAN, ROOF PLAN AND BUILDING

ELEVATIONS

MP-A102 GENERATOR VAULT PLANS, ELEVATIONS AND SECTION

MP-A501 ARCHITECTURAL DETAILS

MP-A502 ARCHITECTURAL DETAILS

CIVIL

MP-S001 STRUCTURAL NOTES

MP-S101 VAULT FOUNDATION AND ROOF FRAMING PLAN AND

SECTION

MP-S102 TOWER FOUNDATION PLAN AND ELEVATION

MP-S501 COMMON STRUCTURAL DETAILS

MP-S502 STRUCTURAL DETAILS

MP-S503 STRUCTURAL DETAILS

MP-S701 FEEDLINE BRIDGE

MP-S702 FEEDLINE BRIDGE

MECHANICAL

MP-M001 MECHANICAL SYMBOLS, LEGEND, ABBREVIATIONS, AND

GENERAL NOTES

MP-M101 LARGE VAULT – HVAC

MP-M102 GENERATOR VAULT – HVAC

RESDMSTR: 02/03/2014 00 01 15 - 7 01512A, B, E

MP-M501 MECHANICAL DETAILS

MP-M601 MECHANICAL SCHEDULES

ELECTRICAL

MP-E001 ELECTRICAL SYMBOLS LEGEND, ABBREVIATIONS AND

GENERAL NOTES

MP-E101 ELECTRICAL SITE PLAN

MP-E102 LARGE VAULT – LIGHTING, POWER, EQUIPMENT AND

GROUNDING

MP-E103 GENERATOR VAULT – LIGHTING, POWER, EQUIPMENT AND

GROUNDING

MP-E104 LARGE VAULT – INTERIOR ELEVATIONS – 1

MP-E105 LARGE VAULT – INTERIOR ELEVATIONS – 2

MP-E501 ELECTRICAL DETAILS – 1

MP-E502 ELECTRICAL DETAILS – 2

MP-E503 ELECTRICAL DETAILS – 3

MP-E504 ELECTRICAL DETAILS – 4

MP-E505 ELECTRICAL DETAILS – 5

MP-E506 ELECTRICAL DETAILS – 6

MP-E601 SINGLE LINE DIAGRAM AND LOAD CALCULATION

MP-E602 ELECTRICAL SCHEDULES – 1

MP-E603 ELECTRICAL SCHEDULES – 2

MP-E604 ALARM STATUS REPORTING SCHEMATICS

MP-E605 ALARM POINT DESCRIPTIONS

MP-E606 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF

CABLING – 1

MP-E607 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF

CABLING – 2

MP-E608 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF

CABLING – 3

MP-E609 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF

CABLING – 4

MP-E610 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF

CABLING – 5

MP-E611 SITE ANTENNA LAYOUT AND PRESSURIZATION

EQUIPMENT – 1

MP-E612 SITE ANTENNA LAYOUT AND PRESSURIZATION

EQUIPMENT – 2

PM-E613 -48VDC CRIS OES INTERCONNECT DIAGRAM

PM-E614 -48VDC MW OES INTERCONNECT DIAGRAM

PM-E615 +12VDC OES INTERCONNECT DIAGRAM

TOWER STRUCTURAL SHEETS

T-1 COVER SHEET/DRAWING INDEX

S-1 ELEVATION VIEW/NOTES

S-1.1 SST SECTION ALLOWABLE MEMBER FORCES

S-1.2 MONOPOLE SECTION ALLOWABLE MEMBER FORCES

S-2 UPPER POLE

S-3 LOWER POLE

S-4 TOWER SECTION 13V – NESTED POLE

RESDMSTR: 02/03/2014 00 01 15 - 8 01512A, B, E

S-5 TOWER SECTION 13V

S-6 TOWER SECTION 15ST

S-6.1 TOWER SECTION 15ST CONT.

S-7 TOWER SECTION 17ST

S-7.1 TOWER SECTION 17ST CONT.

S-8 TOWER SECTION 19ST

S-9 TYPICAL GRATING/BRACING

S-10 TYPICAL HAND RAIL/DIAGANOL PIPE, LIGHTING ROD

EXTENSION, & SAFETY CLIMB KITS

S-11 CENTER MAST

S-12 COAX CAGE/CLIMBING LADDER, ANTI-CLIMB, & BUS BAR

S-13 ANETNNA LOCATION ELEVATION VIEWS

S-13.1 ANTENNA LOCATION PLAN VIEWS

S-14 FULLY LOADED FACE MOUNTED MICROWAVES

S-14.1 FULLY LOADED LEG MOUNTED MICROWAVES

S-14.2 FULLY LOADED VHF/UHF ANTENNA LOCATIONS

S-15 MW ICE BRIDGE DETAILS

S-15.1 MW ANTENNA ICE SHIELD DETAILS

S-16 MICROWAVE MOUNT KITS

S-17 UHF/VHF ANTENNA MOUNT KITS

S-18 LEG/ELEVATION ID PLATES

S-19 TOWER FOUNDATION SLAB/PIERS

STRUCTURAL DETAILS FOR RADIO AND MICROWAVE ANTENNA MOUNTING

BRACKETS

CO-TA1 COVER SHEET AND INDEX

CO-TA1.1 DSA 103

CO-TA2 TOWER STRUCTURAL NOTES

CO-TA3 SITE PRO BRACKET DETAILS

CO-TA4 TOWER ANTENNA MOUNTING DETAILS (ANDREW)

CO-TA5.2 TOWER ANTENNA MOUNTING DETAILS (AMPHENOL ANTEL)

CO-TA6 TOWER ANTENNA MOUNTING DETAILS

(ANDREW/COMMSCOPE)

CO-TA6.1 TOWER ANTENNA MOUNTING DETAILS

(ANDREW/COMMSCOPE)

CO-TA7 TOWER ANTENNA MOUNTING DETAILS (HUSTLER/ANTENNA

EXPERT/DIAMOND)

CO-TA7.2 TOWER ANTENNA MOUNTING DETAILS (SINCLAIR)

CO-TA9 TOWER ANTENNA MOUNTING DETAILS (M2/KRECO)

CO-TA10 TOWER ANTENNA MOUNTING DETAILS

(COMMSCOPE/RFS/SINCLAIR)

CO-TA11.2 TOWER ANTENNA MOUNTING DETAILS (DB SPECTRA/SCALA)

CO-TA13 TOWER ANTENNA MOUNTING DETAILS (SCALA)

CO-TA14 TOWER ANTENNA MOUNTING DETAILS (SCALA)

CO-TA14.1 TOWER ANTENNA MOUNTING DETAILS (SCALA)

CO-TA15 TOWER ANTENNA MOUNTING DETAILS (SINCLAIR)

CO-TA17 TOWER ANTENNA MOUNTING DETAILS (SINCLAIR)

CO-TA18 TOWER ANTENNA MOUNTING DETAILS (TELEWAVE)

END OF DOCUMENT

CALFIRE REPLACE TELECOM DEMOLITION

PHASE V - BUNCHGRASS 02 40 00 - 1 DGS PROJECT 1512

11/29/22 GHD: REV. 1

SECTION 02 40 00

DEMOLITION

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Furnish labor, materials, and equipment necessary for demolition, dismantling, and removal of existing tower foundation, and miscellaneous items or debris as indicated, specified, and required for completion of the Contract.

1.02 RELATED SECTIONS

A. Division 01: General Requirements.

B. Section 31 10 00: Site Preparation (Clearing and Grubbing).

C. Section 31 23 16.26: Rock Removal.

D. Section 31 23 33: Trenching and Backfill.

E. Section 32 11 23: Aggregate Base Courses.

1.03 REFERENCES

A. Perform work in accordance with requirements of the General Condition, Supplementary Conditions, and Division 1, General Requirements.

B. American National Standards Institute (ANSI), latest edition:

1. ANSI A10.6 American National Standard Safety Requirements for Demolition.

1.04 TIMING AND SCHEDULING OF WORK

A. Timing: No demolition or removal of work shall commence until the State has been notified at least 48 hours in advance of proposed start of removal and such times have been approved.

1.05 REGULATORY REQUIREMENTS

A. Contractor Responsibility: Contractor shall assume full responsibility and liability for compliance with applicable Federal, State, and local regulations pertaining to work practices, hauling, disposal of demolished materials, and protection of workers and other persons at the site and persons occupying areas adjacent to site.

PART 2 - PRODUCTS

2.01 GENERAL REQUIREMENTS

A. Materials resulting from the demolition shall become Contractor’s property and Contractor shall be responsible for their removal and proper disposal.

CALFIRE REPLACE TELECOM DEMOLITION

PHASE V - BUNCHGRASS 02 40 00 - 2 DGS PROJECT 1512

11/29/22 GHD: REV. 1

PART 3 - EXECUTION

3.01 EXAMINATION

A. Examine existing structures and appurtenances to determine full extent of demolition required for completed work.

B. Contractor shall coordinate with local utility companies, before the demolition of any building or structure, for the removal of existing electrical services. See plans for utility company contacts.

3.02 DEMOLITION

A. Perform demolition work in accordance with ANSI A10.6 and the Contract Documents.

B. Remove items designated for demolition within the limits of work indicated and as required to perform Work of this Contract.

C. Foundations for tower structure shall be demolished and removed from site or chipped as necessary to be below new foundation grade.

D. After demolition, backfill holes with spoils excavated from that site per Section 31 23 16.26, Rock

Removal; fill materials per Section 31 23 33, Trenching and Backfill; or gravel per Section 32 11 23, Aggregate Base Courses. Rough grade to smooth out differences.

3.03 REMOVAL, DISPOSAL AND CLEAN-UP

A. Remove demolished structures and materials from site to approved disposal sites.

B. Nothing to be demolished or removed from site shall be burned on site.

3.04 FIELD QUALITY CONTROL

A. Perform demolition work using workers skilled in demolition of buildings, using appropriate tools and equipment, under supervision of a competent foreman at all times.

END OF SECTION

CALFIRE REPLACE TELECOM GROUNDWORK FOR STRUCTURES

PHASE V - BUNCHGRASS 02 41 16 - 1 DGS PROJECT 1512

011/29/22 GHD: REV. 1

SECTION 02 41 16

GROUNDWORK FOR STRUCTURES

1.01 SECTION INCLUDES

A. Excavation and backfilling for tower foundation.

1.02 QUALITY ASSURANCE

A. Perform groundwork for structures in accordance with Geotechnical Investigation Reports located in Book II of the Project Manual.

2.01 FILL MATERIAL

A. Provide suitable imported material consisting of soil, mineral aggregates or blend thereof, or suitable excavated material may be used. Fill material shall be approved for use by State. Materials shall compact to hard unyielding surface and thereafter remain stable. Remove stones, bricks or other objects that may puncture waterproofing membranes; also remove wood and rubbish throughout material.

2.02 EXCESS EXCAVATION AND WASTE

A. Remove from site, dispose of off premises unless otherwise indicated.

3.01 EXCAVATION

A. General: Excavate for foundation, to lines and levels indicated or required. Finish bottom of excavations to true, level surface with steps and offsets in foundation located as required. Exercise care when excavating for lower foundation so as to not disturb soil under higher adjacent foundation.

B. Make excavation of sufficient size to provide ample room for construction of forms and shoring.

C. Hand digging will be required if excavating near existing ducts or other utilities that are to remain.

D. Soft, Spongy, or Unsuitable Bearing Material: Remove soft, spongy, or unsuitable bearing material down to solid bearing. See General Conditions.

E. Existing Utilities: Exercise extreme care when excavating near utility lines to avoid damage thereto. Notify the State when utilities not shown on plans are encountered; do not proceed with work in such areas until written instructions are received from the State.

F. Changes in the Work: Pursuant to provisions of the General Conditions, changes in work required by conditions encountered during excavation and comprehensive grading operations and payment, therefore, will be made in accordance with applicable provisions of the General Conditions.

PHASE V - BUNCHGRASS 02 41 16 - 2 DGS PROJECT 1512

011/29/22 GHD: REV. 1

G. Shoring: Provide as required, in conformity with Sections 1540 through 1547, Subchapter 4, Article 6, Construction Safety Orders, Title 8, Industrial Relations.

3.02 PLACING FILL AND BACKFILL

A. Remove vegetation, large stones, soft spots, and objectionable material from existing ground surface. Excavate or fill to required subgrade. Fill and compact soft spots. Prior to placing fill material, thoroughly disc and bond plow entire areas to depth of 8 inches. Thoroughly re-compact scarified subgrade to relative compaction of 90 percent as determined by ASTM Test Method No.

D 1557.

B. Remove wood, rocks, and other rubbish from excavations before placing material. Do not place material against concrete until concrete has reached its 28-day strength. Place material in horizontal layers 3 inches or less in depth before compaction, and thoroughly tamp, roll, or otherwise compact. Place material to limits and grades designated on plans, or if not designated, to original natural ground level.

C. Refer to Geotechnical Investigation Report for Engineered Fill located in Book II of the Project

Manual.

3.03 GENERAL SITE GRADING

A. General site grading is included hereunder. Grade areas within grading limits indicated, to new contours, cross sections and finish grades shown. Except as otherwise indicated, remove vegetation, wood, and other rubbish from areas to be graded.

B. Rough grade areas and treat subsoil in excavated areas and areas requiring 12 inches of fill or less by chiseling to minimum depth of 12 inches.

C. Use chiseling equipment having teeth spaced 12 inches apart maximum. Construct swales to provide drainage from all areas to drainage outfalls (new or existing). Compact by rolling with grading equipment or by other means to produce required results.

D. Grade finish surfaces smooth and even, finish flush with surfaced areas, sidewalks, concrete pads, tops of curbs, manholes, drains, valve boxes, etc., unless otherwise indicated. Adjust tops of existing pull boxes as required to meet finish grades. Finish surfaces shall be clean, free from undesirable vegetation, stones, wood, etc., and suitable for subsequent landscape work.

3.04 ROCK EXCAVATION

A. This item of work shall consist of removing rock, boulder outcroppings, and rock masses if encountered during excavation/trenching operations.

B. The use of explosives for rock disintegration is not approved.

C. The Contractor shall personally verify site conditions of rock removal and note irregularities affecting work of this item.

D. The Contractor by beginning this work item means acceptance of existing conditions.

E. The Contractor shall coordinate the removal and disposal of excavated material from site with State's representative's permission and coordination.

PHASE V - BUNCHGRASS 02 41 16 - 3 DGS PROJECT 1512

011/29/22 GHD: REV. 1

F. When rock is uncovered that cannot be removed by mechanical means, the Contractor shall notify the State's representative for a determination of method of rock removal.

CALFIRE REPLACE TELECOM CONCRETE FORMING AND ACCESSORIES

PHASE V - BUNCHGRASS 03 10 00 - 1 DGS PROJECT 1512

SECTION 03 10 00

CONCRETE FORMING AND ACCESSORIES

1.01 DESCRIPTION

A. Work Included:

1. Formwork for cast-in-place concrete, with shoring, bracing, and anchorage.

2. Openings for other affected work.

3. Form accessories.

4. Stripping forms.

B. Work Installed but Specified Elsewhere:

1. Section 05 12 00: Structural Steel Framing.

C. Related Sections:

1. Section 03 20 00: Concrete Reinforcing.

2. Section 03 30 00: Cast-In-Place Concrete.

D. System Description:

1. Design, engineer, and construct formwork, shoring, and bracing to meet design and code requirements, so that resultant concrete conforms to required shapes, lines, and dimensions.

A. Source Quality Control:

1. Construct and erect concrete formwork and shoring in accordance with ACI 301…