This is a Special Instructions to Vendors document issued by Broward County, Florida for the Aviation Department's Separated Shared Use Path - Phase 1 project at North Perry Airport (HWO). The solicitation is for development and construction of a separated shared use pathway as a fixed-price, definite quantity contract. Vendors must submit responses electronically through BPRO by the specified closing date and time. The county will award the contract to the lowest responsive and responsible bidder based on total bid price. Vendors are required to perform at least 30 percent of the total contract price themselves without subcontracting, and any work requiring licensure must be performed by appropriately licensed or registered contractors or subcontractors.
Licensing requirements mandate that vendors possess either a Florida State Certified General Contractor license, a Florida State Certified General Builder license, or a Broward County General Building Contractor Class "A" or Class "B" license at the time of submittal, with proof required within three business days of request or the vendor may be deemed nonresponsive. The solicitation includes two pass-through allowances totaling $400,000: $300,000 for Utilities Resolution and $100,000 for Unforeseen Conditions and Wildlife Mitigation, with actual payment based only on costs incurred and subject to Contract Administrator authorization. Prevailing wage rates apply to this non-federally funded construction project valued at $250,000 or more, requiring compliance with Broward County Code Section 26-5 and Federal Register wage standards. No Small Business Enterprise or Community Business Enterprise set-asides apply to this solicitation.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL INSTRUCTIONS TO VENDORS
QUOTATION REQUEST OR INVITATION TO BID
Separated Shared Use Path – Phase 1
A. Scope This fixed contract is for a separated shared use pathway at the North Perry Airport (HWO) for the Aviation Department in accordance with the Specifications and Requirements.
B. Contract Type
Definite Quantity Contracts. This solicitation is for a definite quantity of goods or services. Purchase order(s) for the quantity(ies) stated in the solicitation will be issued to the Vendor after notification of award and receipt of all required documents or as otherwise stated in the solicitation.
The Contract, including Standard Terms and Conditions, Contract Supplemental Conditions (as applicable), Contract General Conditions, Contract Supplemental General Conditions (as applicable), Specification Package, and Drawings.
C. Office of Economic and Small Business Requirements
A SBE/CBE Reserve or CBE Goal is not applicable to this solicitation.
D. Funding Requirements (ex. Grant, State, or Federal) Not applicable to this solicitation.
E. Specifications and Requirements Specifications and Requirements and Drawings included apply to this solicitation.
F. Requests for Approved Equals
G. Vendor Responsibilities The Vendor will be responsible for the provision, installation (if applicable, per Specifications and Requirement, and performance of all equipment, materials, services, etc. offered in their submittal. The Vendor is not relieved of responsibility for the performance of all equipment furnished, or of ensuring timely delivery of materials, equipment, etc., even if the equipment or materials are not of their own manufacture.
The Vendor must itself perform, without subcontracting or other forms of outsourcing, work that constitutes at least 30 percent of the total contract price.
H. Fiscal Year End
I. Basis of Award Award of this contract will be made to the lowest responsive, responsible bidder on a total bid price (sum of all items) basis.
J. Multiple Awards
K. Price Adjustment/Escalation
L. Maintenance and Service Requirements
M. Licensing Requirements Proof of licensing should be returned with the Vendor’s submittal. If not provided with submittal, the Vendor must submit within three business days after the County’s request. Vendors may be deemed nonresponsive for failure to fully comply with stated timeframes.
In order to be considered a responsible and responsive Vendor for the scope of work set forth in this solicitation, the Vendor must possess the license(s) indicated below (including any specified State registration, if applicable) at the time of solicitation submittal. Any certificate of competency that meets or exceeds the licensing requirements specified herein, as determined in the sole and absolute discretion of the County, will be considered responsible and responsive to the licensing requirements of this solicitation.
CERTIFIED GENERAL CONTRACTOR
State of Florida License: OR
CERTIFIED GENERAL BUILDER
OR
Broward County: GENERAL BUILDING CONTRACTOR CLASS “A” [Must be registered with the State]
OR
GENERAL BUILDING CONTRACTOR CLASS “B”
[Must be registered with the State]
Any work performed under this contract that requires licensure or registration must be performed by a licensed or registered contractor or subcontractor, as applicable.
Joint Venture submittal requirements (If applicable):
A Joint Venture should submit satisfactory proof with its submittal that the Joint Venture, or at least one of the Joint Venture partners, shall be required to possess one of the above licenses (including any specified State registration, if applicable) at the time of submittal. If not submitted with its response, the Joint Venture must submit such proof within three business days of County’s written request. A Joint Venture may be deemed non-responsive for failure to comply within stated timeframes.
If a Joint Venture is recommended for contract award, it must either 1) submit satisfactory proof that the Joint Venture holds the specified license (if applicable) or that a licensed contractor has qualified the Joint Venture, or
2) provide satisfactory proof it applied for the specified license (if applicable) or the licensee has applied to qualify the Joint Venture, within three business days of County’s written request. The license or qualification, as applicable, in the name of the Joint Venture, must be effective prior to contract execution.
Additional submittal requirements (for construction services only):
A Joint Venture proposer should submit satisfactory proof with its submittal that the Joint Venture complies with all applicable legal requirements, including but not limited to, Section 489.119, Florida Statutes and Rule 61G4- 15.0022, Florida Administrative Code, at time of submittal. If not submitted with its response, the Joint Venture must submit such proof within three business days of County’s written request. A Joint Venture may be deemed non-responsive for failure to comply within stated timeframes.
N. Certification Requirements
O. Permits and Fees
P. Allowances This solicitation includes pass-thru allowances. It is not necessary to add your allowance amounts into your bid prices. The County will add the allowance amount to the bid offer.
The solicitation includes a allowance amount of $ 300,000.00 for the below item(s):
Utilities Resolution: $300,000 Unforeseen Conditions, & Wildlife Mitigation: $100,000
The following shall apply to payment of allowances:
1. The allowance amount is an estimate only; payment is not guaranteed and is only paid based on actual costs incurred by the Vendor for the identified allowance.
2. The Contract Administrator or designee must authorize use of any allowances (per Specifications and
Requirements) prior to Vendor incurring costs related to an allowance amount.
3. No markup or additional fees are allowed on payment of allowance items. This includes, but is not limited to, overhead, profit, “runner’s fees”, etc.
4. Allowances for Permit Fees: payment for permit fees does not include licenses, permit expediting services, re-inspection fees, and expired permit fees. Proof of permit fee(s) shall be submitted with Vendor’s invoice for payment.
5. Allowance for Parts on a Pass Thru: Vendor must charge the County the same invoice prices as it is charged by its suppliers. A copy of the Vendor’s invoice(s) from supplier(s) for approved parts and materials shall be submitted with the Vendor’s invoice for payment. In cases where the Vendor manufactures its own parts, Vendor will charge the County a price no higher than it charges its most favored customer.
Q. Public Bid Disclosure Act
In compliance with the Public Bid Disclosure Act, Section 218.80, Florida Statutes, each permit, license, impact, inspection, and/or certificate of occupancy fee that will be payable by the Vendor to the County by virtue of this work/project (before or during construction) is set forth below, and includes the dollar amount or the percentage method or unit method to be paid of all permits, licenses, and/or fees.
The using agency will be responsible for paying for any and all permit, license, impact, inspection, and/or certificate of occupancy fees imposed on the work by Broward County. This does not alleviate the Vendor from the obligation to file any necessary applications or obtain any necessary permits or licenses.
Licenses, permits, and fees that may be required by the State of Florida, State agencies, or other local governmental entities are not included in the above list.
R. Recycling Preference
S. Prevailing Wage Rates Section 26-5 of the Broward County Code of Ordinances provides that in all non-federally funded construction procurement activity of $250,000 or more, the rate of wages and fringe benefit payments for all laborers, mechanics, and apprentices shall not be less than those payments for similar skills in classifications of work in like industries as determined by the Secretary of Labor and as published in the Federal Register (latest revision). The applicable Prevailing Wage Rate Tables are included in the solicitation.
T. Liquidated Damages Refer to Contract (BCF170), Summary of Terms and Conditions and Article 3.3.
U. Payment Refer to Contract (BCF 170).
V. Additional Information/Instructions
Form Date 7/17/26
| A. Scope |
| B. Contract Type |
| C. Office of Economic and Small Business Requirements |
| D. Funding Requirements (ex. Grant, State, or Federal) |
| E. Specifications and Requirements |
| F. Requests for Approved Equals |
| G. Vendor Responsibilities |
| H. Fiscal Year End |
| I. Basis of Award |
| J. Multiple Awards |
| K. Price Adjustment/Escalation |
| L. Maintenance and Service Requirements |
| M. Licensing Requirements |
| N. Certification Requirements |
| O. Permits and Fees |
| Q. Public Bid Disclosure Act |
| R. Recycling Preference |
| S. Prevailing Wage Rates |
| T. Liquidated Damages |
| U. Payment |
| V. Additional Information/Instructions |