This is a Detail Specifications document prepared by the City of Cleveland for the Michael J. Zone Neighborhood Resource & Recreation Center Locker Room, Entrance Lobby, and Restroom Improvements project. The City is soliciting a Design-Build contract that requires qualified contractors to provide architectural, engineering, and construction services to complete locker room improvements, entrance lobby enhancements, and restroom upgrades at the facility located at 6301 Lorain Road, Cleveland, Ohio 44102. Work shall be performed under a single General Construction contract on a gross price (Stipulated Sum) basis. The project will be constructed while the building remains occupied and operational, requiring contractors to coordinate with City personnel and maintain safe means of egress and life safety systems throughout construction. All bidders must examine the premises before submission and attend the mandatory Pre-Bid Conference to observe the scope of work and existing field conditions. Work must commence no later than 14 days after the Date of Commencement, with all work including punch-lists and close-out submittals completed by the Scheduled Completion Date. Construction activities and schedules require approval by the Architect and/or the Director's Designee prior to site entry.

The contract includes provisions for Alternate Items and Unit Price items, which bidders must price separately from the Base Bid. The Contractor bears sole responsibility for securing all required permits, licenses, and fees, including street and sidewalk closure permits. Contractors must contact the Ohio Utilities Protection Service (OUPS) at 1-800-362-2764 before commencing work and provide the reference file number to the project manager. The cost for all special inspections as required by the Ohio Building Code Section 1704 must be included in the Base Bid. Contractors shall provide full-color digital photographic documentation at preconstruction, weekly during construction, and at final completion, formatted as unaltered .jpg files with minimum 8-megapixel resolution. The City will provide field office space within the existing facility, and may allow use of existing toilet facilities, water service, and electrical power without metering charges if available; otherwise, the Contractor is responsible for providing these services independently.

View the file

Other files

File Type Posted
Michael_J._Zone_Neighborhood_Resource_&_Recreation_Center_Locker_Room,_Entrance_Lobby,_&_Restroom_Improvements_(Addendum_#2_Revision).pdf PDF
Michael_J._Zone_Neighborhood_Resource_&_Recreation_Center_Locker_Room,_Entrance_Lobby,_&_Restroom_Improvements_(Addendum_#1_Revision).pdf PDF
27_Criteria_Documents_&_Specifications.pdf PDF
26_Zone_NRRC_Locker_Room_Impmts_D-B_Traditional_RFP_Request_Memo_&_Mailing_List.pdf PDF
25_Wage_Theft_PDF_Version.pdf PDF
24_PW_RATES_-_COVER_LETTER_(2024.12.27).pdf PDF
23_PW_CERTIFIED_PAYROLL_REPORT_-_OHIO_(2024.12.27).pdf PDF
22_PW_INSTRUCTIONS_FOR_PREPARING_CERTIFIED_REPORTS_-_OHIO_(2024.12.27).pdf PDF
21_PW_THRESHOLD_LEVELS_-_OHIO_(2024.01.01).pdf PDF
20_PW_AFFIDAVIT_OF_COMPLIANCE_-_OHIO_(2024.12.27).pdf PDF
19_PW_NOTIFICATION_TO_EMPLOYEE_-_OHIO_(2024.12.27).pdf PDF
18_PW_CONTRACTOR_RESPONSIBILITY_-_OHIO_(2024.12.27).pdf PDF
17_Prev_Wage_Notification_(2024.12.27).pdf PDF
16_PW_NOTICE_-Valerie_Harvey_(2024.12.27).pdf PDF
14_PART_C_-_SUPPLEMENTAL_GENERAL_CONDITIONS__2025_09_16.pdf PDF
13_PART_B_-_General_Conditions_(final_8-28-25).pdf PDF
11_FORM_CWM-8_CONSTRUCTION_WASTE.pdf PDF
10_FORM_CWM-7_DEMOLITION_WASTE.pdf PDF
09_017419_CONSTRUCTION_WASTE_MANAGEMENT_AND_DISPOSAL.pdf PDF
08_City_of_Cleveland_Sustainable_Building_Policy_2013-04.pdf PDF
07_Cleveland_City-Wide_Asbestos_Policy_(2017.05.19).pdf PDF
06_2023_Reimbursables_Policy.pdf PDF
05_Design-Build_Agreement_Sample_for_MOCAP.pdf PDF
04_DASD_Minimum_Deliverables_(2026.06.04).pdf PDF
03_Subcontractor_Addition_and_Subtraction_Policy.pdf PDF
02_CCO_187-22.pdf PDF
01_NORTHERN_IRELAND_DISCLOSURE.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART D – DETAIL SPECIFICATIONS Page 1 of 6

PART D - DETAIL SPECIFICATIONS

D-1. SUMMARY OF WORK

A. GENERAL

1. This Section is applicable to all branches of Work

2. Project will be constructed under a single, General Construction contract on a gross price

(Stipulated Sum) basis.

3. All Construction Documents shall be reviewed by all trades and subcontractors since it is the purpose to cover, in a general way, the items involved in the construction work. The enumeration of specified items shall not be construed as a complete list of all the Work to be performed. The Contractor shall coordinate all trades and subcontractors.

4. All materials removed in the course of demolition shall become the property of the

Contractor and shall be removed from the site and properly disposed of at his sole expense, except as specified to be relocated and/or salvaged by the City.

5. Attendance of the Pre-Bid Conference may be mandatory. See Specification for further direction. If attendance is not mandatory, attendance at the Pre-Bid Conference is highly recommended in order to observe the scope of work and existing field conditions. Some of the work is categorized as Unit Price-based activities. The various Unit Price items are identified on the Drawings and/or within the Specifications. See Drawings and Technical

Specifications for additional information.

B. WORK COVERED BY THE CONTRACT DOCUMENTS

1. Work shall include the furnishing of all labor, materials, superintendence, equipment, tools, services for and incidental to the improvements proposed as are shown on the drawings and/or as specified by these specifications for the MICHAEL J. ZONE

NEIGHBORHOOD RESOURCE & RECREATION CENTER LOCKER ROOM IMPROVEMENTS. The project consists of improvements to the locker rooms, entrance lobby, and restrooms at

Michael J. Zone Neighborhood Resource & Recreation Center for the City of Cleveland.

The request is for a Design-Build Proposal from Contractors, which would include architectural, engineering, and related professional services, as well as construction and construction services to carry out the project through closeout, as indicated on the drawings, details and specifications.

D-2. SUMMARY OF WORK – ALTERNATES

A. GENERAL

1. All applicable requirements of all other portions of the Contract Documents apply to the work of any selected Alternates.

2. The Bid Schedule of Prices identifies each Alternate Item by number and describes the basic changes to be incorporated into the Work only when the Alternate Item is made a part of the Work by specific inclusion to the City-Contractor Agreement. The description of the Work as listed therein is not intended to be a complete specification of all work included. Conform to the Drawings and Technical Specifications for requirements.

3. Definitions and explanations: “Alternates” are defined in Part C. Selection may occur prior to award of Contract or may be deferred for possible selection at a date subsequent to signing of City-Contractor Agreement, in which case the Alternate will be made part of the Work by a written modification to the Contract.

4. Each contractor and subcontractor shall read the descriptions of each Alternate Item listed and determine the extent to which their work is affected.

5. Submit, in the space provided on the Schedule of Prices, an amount for each Alternate Item to be added to or deducted from the Base Bid. THE DOLLAR AMOUNT OF THE CONTRACT

AWARD (“BID PRICE”) SHALL BE BASED UPON THE SUM OF THE BASE BID AND ANY ALTERNATE

ITEMS ACCEPTED.

6. Each Alternate Item shall be complete in every detail for conformance with the Contract

Documents.

7. Include in the Alternate price the cost of all work for all trades, including modification of other related items, and overhead and profit for a single gross price.

8. Refer to Instructions to Bidders for a description of how Alternate Item prices affect award of the Contract.

9. Coordinate pertinent related work and modify surrounding work as required, to properly integrate the work under each Alternate Item and to provide the completed construction required by Contract Documents

D-3. SUMMARY OF WORK – UNIT PRICE ITEMS

A. GENERAL

PART D – DETAIL SPECIFICATIONS Page 2 of 6

1. Definition – a Unit Price is an amount incorporated in the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Bid Price by appropriate modification, if the Scope of Work or estimated quantities of Work required by the Contract

Documents is increased or decreased.

2. The Contractor shall include Unit Prices for each item listed in the Schedule of Prices. Unit

Prices are not part of the Bid Price.

3. All applicable requirements of all other portions of the Contract Documents apply to the work of this Section.

4. Each Unit Price item shall be complete in every detail for conformance with the Contract

Documents.

5. Unit Prices shall include the cost of all work for all trades, including modification of other related items, and overhead and profit for unit price item.

6. Coordinate pertinent related work and modify surrounding work as required to properly integrate the work under each Unit Price item and to provide the completed construction required by Contract Documents.

7. The City reserves the right to reject the Contractor’s measurement of work-in-place that involves use of established unit prices and have the work measured at the City’s expense.

D-4. SUMMARY OF WORK – ALLOWANCES

A. The Contractor shall include all the Allowances listed in the Schedule of Prices in his bid, in accordance with requirements of respective paragraphs as further defined in Part C –

Supplemental General Conditions.

B. Approval of the use of Allowance funds shall be in accordance with Part C – Supplemental

General Conditions.

D-5. EXAMINATIONS OF PREMISES

A. Before submitting a bid, each bidder shall visit and examine the premises and satisfy themself as to the existing conditions under which he will be obliged to operate or that will in any way affect the work to be done under this contract.

B. No requests for a change in contract cost or duration due to the Contractor’s error or negligence in identifying foreseeable existing conditions will be approved.

D-6. LOCATIONS

A. The particular site where the work will be done under this contract is as follows:

MICHAEL J. ZONE NEIGHBORHOOD RESOURCE & RECREATION CENTER

6301 LORAIN ROAD

CLEVELAND, OHIO 44102

D-7. APPLICABLE CODES

A. The current OHIO BUILDING CODE as administered and modified by the local authority having jurisdiction shall govern the Work. Additional regulatory constraints may apply. It is the

Contractor’s responsibility to comply with all applicable laws and regulations.

D-8. PERMITS

A. The Contractor shall bear sole responsibility to secure and pay for ALL fees, licenses, and permits required and/or needed to complete the work under this Contract.

B. The Contractor is not responsible to pay for plans examination fees for building permits, unless specifically identified in the Contract Documents.

C. The Contractor is responsible for any street and/or sidewalk closure permits. The Contractor shall notify the Project Manager of any street and/or sidewalk restrictions or closures in writing at least one (1) week in advance.

D-9. UTILITY PROTECTION

A. Indications of existing utilities are based on office records and site visits. The drawings do not purport to be 100% accurate and should not be construed as such. The City of Cleveland is not responsible for omissions from the contract of any services, structures, underground lines, nor misrepresentation as to the type or to the location. The Contractor must notify all of City’s utilities when his work is in progress. The Contractor will be responsible to have the service repaired as per the utility companies' policies if his labor force or equipment (including subcontractors) damages the utility or if the utility is damaged as a result of neglect or failure to provide adequate protection by the Contractor (including subcontractors).

PART D – DETAIL SPECIFICATIONS Page 3 of 6

B. Prior to the commencement of any contract work, the Contractor shall contact the Ohio Utilities

Protection Service (OUPS) at 1-800-362-2764 as required by Sections 3781.25 - 3781.32 of the Ohio

Revised Code (revised 3/14/89). Upon contacting OUPS, the Contractor will be given a reference file number. The Contractor shall be responsible to give that reference file number to the project manager / architect prior to construction. The General Contractor shall be responsible to contact

OUPS and assumes all responsibility for his employees and his subcontractors and their employees.

Work shall not commence until this requirement is met.

D-10. SPACE FOR WORKING FACILITIES

A. The areas to be used by the Contractor shall be within the contract limit lines and within the property limit. THE CONTRACTOR SHALL NOT ENTER THE SITE UNTIL ALL CONSTRUCTION ACTIVITIES

AND SCHEDULES HAVE BEEN APPROVED BY THE ARCHITECT AND/OR THE DIRECTOR’S DESIGNEE. The

Contractor shall coordinate staging, dumpster, tool storage, and/or field office location with City prior to commencement of work at each project site.

B. FIELD OFFICE AND STORAGE

1. Provide field office within the existing facility in location to be determined by City. Field office must contain:

a. Meeting space for all attendees of project field meetings.

b. Complete set of plans and specifications, current including all revisions.

c. Copies of all RFIs, RFI responses, submittals, and product samples.

C. DUMPSTERS

1. Provide dumpsters of type and capacity as required. The Contractor must immediately empty and/or remove the dumpster(s) from the site when full or at minimum, on regularly scheduled intervals.

D-11. SCHEDULE, SITE RESTRICTIONS

A. SCHEDULE

1. The building and site will be occupied during demolition and construction activities. It is in the interest of the City to have the Contractor complete the proposed improvements as soon as possible.

2. The Contractor will be expected to utilize whatever manpower, methods, and means necessary to complete the Work on schedule.

3. The Contractor shall provide a detailed Construction Schedule indicating order of anticipated units to be worked on, starting times, completions times, activity dependencies, and critical path. The Contractor shall present the Construction Schedule at the Pre-

Construction Meeting for review and approval by the City.

a. Coordinate work with the City’s Project Manager and conduct construction operations in such a manner as to expedite the work.

b. A primary property contact will be identified at the Pre-Construction Meeting.

Notify this property contact and the Project Manager, in writing, at least 72 hours in advance in areas that may be required to be restricted from public access.

4. Coordinate and schedule all phases of the work with the Project Manager, the property contact, the Subcontractors, the Material Suppliers, and other parties as necessary to ensure the smooth and orderly transition of separate phases and to meet the schedule and requirements of the City.

a. Phase the work to allow for access to the site by the public, the City’s personnel, deliveries, and maintenance.

5. Coordinate delivery of materials and disposal of debris with the City. Remove at the end of each work day.

6. Perform routine work each day in a consistent manner, so that the City and the public can predict the time that noise or other inconveniences are likely to occur.

7. Do not proceed with the work when climactic conditions are outside of the respective manufacturer’s recommended limitations for installation.

B. SITE RESTRICTIONS

1. The City will occupy the site and conduct normal operations during the entire period of construction. Cooperate with the Project Manager and property contact in scheduling project operations to minimize conflict and to facilitate the City’s usage. The City retains the right to conduct other work, whether with the City’s own forces or with a separate

Contractor, on the Project site. The Contractor is responsible to coordinate his work with any additional work being performed.

a. The Contractor shall not have use of site and building except for the areas of work.

b. Maintain use of the site and building at all times. Maintain safe means of egress

PART D – DETAIL SPECIFICATIONS Page 4 of 6 and life safety systems from the building during construction. Schedule to complete work in the area of the building to allow access to the building at all times. Provide protection barriers as required for the safety of the occupants and public. Cooperate with the facility personnel and follow instructions.

i. Confine operations at site to areas permitted by law, ordinances, permits, Contract Documents, and City’s specific instructions.

ii. Do not unreasonably encumber site with materials or equipment. Staging area will be located as directed by City.

iii. Do not load structure with weight that will endanger structure. Loading determinations are part of Means and Methods and are the responsibility of the Contractor.

iv. Assume full responsibility for protection and safekeeping of tools and products stored on or off premises.

v. Move stored products which interfere with operations of building or the operations of other trades.

vi. Obtain and pay for use of additional storage or work areas needed for operations.

c. Assume full responsibility for protection and safety of the City’s personnel, visitors and the public.

i. Erect protective measures prior to the start of construction operations to shield persons and structures from damage, injury, and hazardous materials.

ii. Protect building and ground surfaces from contamination, soiling, and damage during the work.

iii. Protect buildings, building interiors, building components, equipment, roads, approaches, parking areas, sidewalks, vehicles, trees, shrubs, and other plant materials from damage, staining, or defacing due to the work.

iv. Protect the installed work.

v. Provide temporary weatherproof protection to seal up openings and protect uncompleted work at the end of each work day and in the event of inclement weather.

d. Conduct Project operations to ensure the least inconvenience to the City and to the Public.

e. Where overhead work is performed, provide proper protection below.

f. Lock all vehicles and equipment when parked and unattended so as to prevent unauthorized use, damage, or theft. Do not leave such vehicles or equipment unattended with motor running or the ignition key in place.

g. Staging of materials and storage of vehicles, equipment, and materials shall be coordinated with facility personnel.

h. Comply with limitations on use of public streets and other requirements of authorities having jurisdiction.

i. Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to adjacent properties with City’s representative.

j. Smoking is not permitted within the building(s) or within 25 feet of entrances, operable windows, or outdoor air intakes.

C. SANITARY FACILITIES USE

1. Toilets: Use of City's existing toilet facilities will be permitted, if available, provided that the existing facilities are cleaned and maintained in a condition acceptable to City. At Final

Completion, restore these facilities to condition existing before initial use. If no public toilet facilities are available, the Contractor is responsible to provide their own toileting facilities for their workers, including Subcontractors.

D. WATER SERVICE USE

1. Use of water from City's existing water system is permitted if available without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations. If no water service is available, the Contractor is responsible to provide their own water service.

E. ELECTRICAL POWER SERVICE USE

1. Electric power from City's existing system is permitted if available without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations. Maintain equipment in a condition acceptable to the City. If no electric power is available, the Contractor is responsible to provide their own electrical service.

2. Connect to City's existing electric power service. Maintain equipment in a condition acceptable to City.

PART D – DETAIL SPECIFICATIONS Page 5 of 6

3. Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.

4. Provide superintendent with cellular telephone or portable two-way radio for use when away from field office.

F. EXISTING STAIR AND RAMP USAGE

1. Use of City's existing stairs and ramps will be permitted, provided stairs and ramps are cleaned and maintained in a condition acceptable to City and that use of stairs and ramps does not interfere with normal operations of the facility. Prior to Final Acceptance, restore stairs and ramps to condition existing before initial use.

2. Provide protective coverings, barriers, devices, signs, or other procedures to protect stairs and ramps and to maintain means of egress. If stairs and ramps become damaged, restore damaged areas so no evidence remains of correction work at no additional cost to City.

G. INSPECTION OF THE SCOPE OF WORK:

1. The Contractor shall inspect the site and become thoroughly familiar with the Contract

Documents prior to submitting bid and shall note other work that may be required as well as the nature of the conditions under which the work is to be performed. Submission of the bid shall confirm that the Contractor has fully investigated the site conditions all the related work to be done.

H. SPECIAL INSPECTIONS:

1. The Ohio Building Code (OBC) Section 1704 “Special Inspections” requires that one or more

Special Inspectors be employed to provide inspections during construction on the types of work listed in OBC Section 1704. It shall be the responsibility of the Contractor to engage one or more qualified testing firms to conduct these required inspections. The cost for all Special

Inspections shall be included in the Contractor’s Base Bid. The selection of the testing firm shall be approved by the City.

D-12. PHOTOGRAPHIC DOCUMENTATION

A. Contractor shall provide full-color, digital images, free of copyright or usage restrictions, in .jpg format, produced by a digital camera with minimum sensor size of 8 mega pixels, 4:3 aspect ratio, and at an image resolution of not less than 3264 × 2448 pixels.

B. Take photographs using the maximum range of depth of field, and that are in focus, to clearly show the Work. Photographs with blurry or out-of-focus areas will not be accepted.

C. Submit to the Architect and to the City digital images within five (5) days of taking photographs, exactly as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software. Maintain one set of images accessible in the field office at Project site, available at all times for reference. Identify images in the same manner as those submitted to Architect. Include date and time in file name for each image, unless noted otherwise.

1. Preconstruction Photographs: Before commencement of any work or demolition, take photographs of Project site and surrounding properties, including existing items to remain during construction, from different vantage points, as directed by Architect. Provide a minimum of twenty (20) color photographs.

2. Periodic Construction Photographs: Provide a minimum of ten (10) color photographs weekly. Select vantage points to show status of construction and progress since last photographs were taken.

3. Final Completion Construction Photographs: Provide minimum of twenty (20) color photographs after date of Substantial Completion for submission as project record documents. Architect will inform photographer of desired vantage points.

4. Other Photographs: Provide additional or incidental photographs as necessary to record project conditions, construction progress, etc., at the discretion of the Contractor or as requested by Architect and/or City.

D. Include Project Name, Architect, Contractor and date of image taken in metadata file tag. Label each digital image clearly and sequentially. Include vantage point, indicating location, direction

(by compass point), and elevation or story of construction.

D-13. TIME OF COMPLETION

A. Work shall begin no later than fourteen (14) days after Date of Commencement as defined in Part

C. All work required to achieve Final Acceptance, including punch-lists and close-out submittals, shall be completed by the Scheduled Completion Date as described in Part C.

B. All factors affecting the construction schedule, including but not limited to product lead times;

time for submission, review, and approval of submittals; foreseeable weather delays; permits;

inspections; testing; mobilization; punch list; and all close-out items shall be taken into

PART D – DETAIL SPECIFICATIONS Page 6 of 6 consideration by the bidders and become part of the construction schedule to be prepared by the Contractor after award of the Contract and presented at the Pre-Construction Meeting.

D-14. APPROVED EQUAL

A. The words "or approved equal" are implied in all cases throughout these Detail Specifications even though not expressly stated. All "or approved equal" items must be approved by the Architect and the Director and/or his designee before purchases are made by the Contractor.

D-15. CONTRACT DOCUMENTS

The Contract Documents comprise the following drawings:

CRITERIA DRAWING SET INCLUDING SPECIFICATIONS - RPMI:

GENERAL

G000 COVER SHEET

G100 DRAWING INDEX & CODE DATA

G101 MOUNTING HEIGHTS

DEMOLITION DRAWINGS

AD101a LEVEL 01 - DEMOLITION PLAN - LOCKER ROOMS

AD101b LEVEL 01 - DEMOLITION PLAN – RECEPTION

AD201a RCP - DEMOLITION PLAN - LOCKER ROOMS

AD201b RCP - DEMOLITION PLAN - RECEPTION

ARCHITECTURAL DRAWINGS

A101a LEVEL 01 - LOCKER ROOMS & RESTROOMS

A101b LEVEL 01 - RECEPTION DESK & LOBBY

A201a LEVEL 01 - RCP - LOCKER ROOMS & RESTROOMS

A201b LEVEL 01 - RCP - RECEPTION & CORRIDOR

A701 DOOR & WINDOW SCHEDULES

A801 INTERIOR ELEVATIONS

A802 INTERIOR ELEVATIONS

A803 INTERIOR ELEVATIONS

A804 INTERIOR ELEVATIONS

STRUCTURAL DRAWING

S001 STRUCTURAL NARRATIVE

MECHANICAL DRAWING

M001 MECHANICAL NARRATIVE

ELECTRICAL DRAWINGS

E001 ELECTRICAL GENERAL INFORMATION

E101 LIGHTING FLOOR PLAN

E201 ELECTRICAL FLOOR PLAN

E800 CRITERIA SPECIFICATIONS

SELECT EXISTING DRAWINGS INCLUDED FOR REFERENCE

FINISH COLOR BOARDS (2)

And the following Specifications:

PART "B" GENERAL CONDITIONS – CITY OF CLEVELAND

PART "C" SUPPLEMENTAL GENERAL CONDITIONS – CITY OF CLEVELAND

PART "D" DETAIL SPECIFICATIONS – CITY OF CLEVELAND