This is a measure and payment roadway improvements specification document for the City of St. George, Utah's Roadway Improvements Various Locations Invitation for Bid (IFB) project. The document details 27 distinct line items covering the full scope of roadway construction and infrastructure improvements across multiple project locations. Items include traffic control, surveying, tree and concrete removal, utility relocation and reconstruction (signs, hydrants, water valves, manholes, and inlet boxes), roadway excavation and preparation, asphalt paving and milling, concrete curb and gutter installation, sidewalk construction, storm drainage infrastructure (including 18-inch HDPE and 24-inch RCP pipes), concrete driveway aprons, asphalt trails, and rock buffers and swales. The specification provides detailed descriptions of work scope, measurement units (lump sum, each, linear feet, or square feet), and payment schedules for each line item. The lump sum items for traffic control, survey, and mobilization include specific payment schedules tied to project completion percentages, with mobilization payments capped at 10% of total contract price.
Bidders are required to submit a bid bond equal to 5% of the total bid amount issued by a Utah-licensed surety company acceptable to the City of St. George. One hundred percent payment and performance bonds will be required upon contract award. All bid prices are to be submitted as contract unit prices for the respective measurement units, and payment for work items (except lump sum items with tiered schedules) is made upon completion of the work as a percentage of overall contract completion with each estimate. The City of St. George reserves the right to reject any or all proposals or waive any formality or technicality in the proposals submitted.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 13-sample - CERTIFICATE OF INSURANCE.pdf | ||
| 14-sample - CONSTRUCTION AGREEMENT.pdf | ||
| 17-6- ROADWAY IMPROVEMENTS VARIOUS LOCATIONS - 5.29.26.pdf | ||
| 7-NOTICE OF AWARD.docx | DOCX document | |
| 6-CONDITIONAL WAIVER RELEASE UPON FINAL PAYMENT.docx | DOCX document | |
| 8-GENERAL CONDITIONS rev 09.pdf | ||
| 5-PERFORMANCE BOND.docx | DOCX document | |
| 12-MAJOR SUBCONTRACTOR LISTING.pdf | ||
| 1-3- BID BOND.pdf | ||
| 9-1- INFORMATION FOR BIDDERS.pdf | ||
| 10-2- BID TERMS.pdf | ||
| 3-NOTICE TO PROCEED.docx | DOCX document | |
| 4-PAYMENT BOND.docx | DOCX document | |
| 2-CONDITIONAL WAIVER RELEASE UPON PROGRESS PAYMENT.docx | DOCX document | |
| 11-E-Verify Form.pdf | ||
| 16-4- SCOPE OF WORK ROADWAY IMPROVEMENTS.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2 Traffic Control Lump Sum
Payment shall be at the contract unit price per lump sum, which shall include furnishing, installing, maintaining, adjusting, and removing all traffic control devices and measures required for construction operations, and all labor, equipment, materials, and incidentals required to complete the item.
Contractor is responsible for submitting encroachment permit applications to city. The city will waive all fees associated with the encroachment permit. The lump sum price shall include traffic control for both locations.
Amount Paid When Paid
25% of the bid item amount With first estimate
Remaining portion of bid item paid as a percentage of the contract completed
With each subsequent estimate
3 Survey Lump Sum
Payment shall be at the contract unit price per lump su, which shall include construction staking, line and grade control, layout, replacement of disturbed control as required, coordination, and all labor, equipment, materials, and incidentals required to complete the item. The lump sum price shall include survey for both locations.
Amount Paid When Paid
25% of the bid item amount With first estimate
Remaining portion of bid item paid as a percentage of the contract completed
With each subsequent estimate
4 Remove Tree Each
Payment shall be at the contract unit price per each, which shall include cutting, grubbing, stump and roots removal to three feet (3’) below exiting ground, loading, hauling, disposal, backfilling of resulting voids, surface cleanup, and all labor, equipment, tools, and incidentals necessary to complete the item.
5 Remove Concrete Box Each
Payment shall be at the contract unit price per each, which shall include excavation as required, removal, hauling, disposal, backfill, compaction, cleanup, and all labor, equipment, materials, and incidentals required to complete the item.
Mobilization Lump Sum
Payment shall be at the contract unit price per lump sum, which shall include permits, bonds, insurance, project startup, movement of personnel and equipment to and from the site project signage, dust control, demobilization, and all incidentals necessary to complete the item. The lump sum price shall include mobilization for both locations.
Amount Paid When Paid
The lesser of 25% of Mobilization or 2.5% of contract With first estimate
The lesser of 50% of Mobilization or 5% of contract With any estimate following completion of 5% of contract
The lesser of 75% of Mobilization or 7.5% of contract With any estimate following completion of 10% of contract
The lesser of 100% of Mobilization or 10% of contract With any estimate following completion of 20% of contract
Amount bid in excess of 10% of contract price Project Acceptance-Final
6 Relocate Sign Each
Payment shall be at the contract unit price per each, which shall include removal and disposal of existing concrete sign base, post and footing work as required, resetting in new location, hardware, alignment, cleanup, and all labor, equipment, materials, and incidentals required to complete the item.
7 Relocate Hydrant Each
Payment shall be at the contract unit price per each, which shall include excavation, removal and reinstallation or replacement as required, pipe and fitting connections, valve work as required, testing, disinfection, backfill, compaction, cleanup, and all labor, equipment, materials, and incidentals required to complete the item.
8 Reconstruct Water Valve Each
Payment shall be at the contract unit price per each, which shall include excavation as needed, adjustment of valve box to finished grade, furnishing and placing collar material, setting lid to final grade, backfill, compaction, cleanup, and all labor, equipment, tools, materials, and incidentals necessary to complete the item.
9 Reconstruct Manhole Each
Payment shall be at the contract unit price per each, which shall include excavation as needed, adjustment of manhole to finished grade, furnishing and placing collar material, setting lid to final grade, backfill, compaction, cleanup, and all labor, equipment, tools, materials, and incidentals necessary to complete the item.
10 Reconstruct Curb Inlet Box Each
Payment shall be at the contract unit price per each, which shall include removal as required, reconstruction of the inlet box to grade, frame and grate work, pipe connection adjustments, backfill, compaction, cleanup, and all labor, equipment, materials, and incidentals required to complete the item.
11 Sawcut Asphalt Linear Feet
Payment shall be at the contract unit price per linear feet, which shall include layout, cutting asphalt pavement to the required line and depth, protection of adjacent surfaces, cleanup, and all labor, equipment, materials, and incidentals required to complete the item.
12 Roadway Excavation Lump Sum
Payment shall be at the contract unit price per lump sum, which shall include excavation, hauling, disposal or placement, grading, shaping, subgrade preparation within the excavation limits, cleanup, and all labor, equipment, materials, and incidentals required to complete the item.
13 Excavate, Stockpile & Place Rotomillings Lump Sum
Payment shall be at the contract unit price per lump sum, which shall include milling, hauling, stockpiling, rehandling, placement as road base, compaction, cleanup, and all labor, equipment, materials and incidentals required to complete the item.
14 3” Thick Asphalt Pavement Square Feet
Payment shall be at the contract unit price per square feet, which shall include hauling, placement, rolling, compaction, finishing, joints, cleanup, and all labor, equipment, materials, and incidentals required to complete the item.
15 Road Base Square Feet
Payment shall be at the contract unit price per square feet, which shall include hauling, placing, grading, watering as required, compaction, cleanup, and all labor, equipment, materials, and
16 Concrete Curb and Gutter Type HB30-7 Linear Feet
Payment shall be at the contract unit price per linear feet, which shall include excavation, subgrade preparation, untreated base course, forming, furnishing and placing concrete, finishing, curing, joints, and all incidentals necessary to complete the item.
17 Concrete Curb and Gutter Type RU-30 Linear Feet
Payment shall be at the contract unit price per linear feet, which shall include excavation, subgrade preparation, untreated base course, forming, furnishing and placing concrete, finishing, curing, joints, 18 Concrete Sidewalk Square Feet
Payment shall be at the contract unit price per square feet, which shall include excavation, subgrade preparation, untreated base course, furnishing and placing concrete, forming, finishing, curing, joints, 19 Detectable Warning Surface Each
Payment shall be at the contract unit price per each, which shall include surface preparation, furnishing and installation, fasteners or embedment as required, finishing, cleanup, and all labor, equipment, materials, and incidentals required to complete the item.
20 Curb Inlet Catch Basin Each
Payment shall be at the contract unit price per each, which shall include excavation, bedding, subgrade preparation, furnishing and installing the curb inlet structure, frame and grate or cover as specified, connection to storm drain pipe, concrete work, backfill, compaction, cleanup, and all labor, equipment, tools, materials, and incidentals necessary to complete the item.
21 Storm Drain Combination Box Each
Payment shall be at the contract unit price per each, which shall include excavation, bedding, subgrade preparation, furnishing and installing the combination storm drain box structure, frame and grate or cover as specified, pipe connections, concrete work, backfill, compaction, cleanup, and all labor, equipment, tools, materials, and incidentals necessary to complete the item.
22 18-inch HDPE Storm Drain Linear Feet
Payment shall be at the contract unit price per linear feet, which shall include, trench excavation, bedding, pipe, fittings, jointing, laying, alignment, testing if required, backfill, compaction, and all labor, equipment, materials, and incidentals necessary to complete the item.
23 24-inch RCP Storm Drain Linear Feet
Payment shall be at the contract unit price per linear feet, which shall include, trench excavation, bedding, pipe, fittings, jointing, laying, alignment, testing if required, backfill, compaction, and all labor, equipment, materials, and incidentals necessary to complete the item.
24 Concrete Driveway Apron Square Feet
Payment shall be at the contract unit price per square feet, which shall include excavation, subgrade preparation, untreated base course, concrete, forming, cutting, finishing, curing, joints, backfill, cleanup, and all labor, equipment, materials, and incidentals required to complete the item.
25 6-foot Asphalt Trail Linear Feet
Payment shall be at the contract unit price per linear feet, which shall include subgrade preparation, aggregate base course, asphalt paving, compaction, finishing, and all labor, equipment, materials, and
26 2-foot Rock Buffer Linear Feet
Payment shall be at the contract unit price per linear feet, which shall include excavation, grading, filter fabric if required, rock placement, shaping, cleanup, and all labor, equipment, materials, and incidentals
27 3-foot Rock Swale Linear Feet
Payment shall be at the contract unit price per linear feet, which shall include excavation, grading, filter fabric if required, rock placement, shaping, cleanup, and all labor, equipment, materials, and incidentals