About this file
This is an Information for Bidders document from the City of St. George, Utah, for the 250 West Reconstruction project spanning from Blackridge Drive to Tech Ridge Parkway. The project involves road reconstruction work, with bids published on July 20, 2026. A mandatory pre-bid meeting is scheduled for July 29, 2026, at 2:00 p.m. at City Hall Community Development Conference Room; failure to attend will result in automatic disqualification. Questions are due by August 5, 2026, with bid submission closing on August 11, 2026, via sgcity-utah.bonfirehub.com. The City intends to commence construction within 20 calendar days of the Notice of Award and complete the project within 90 calendar days from the Notice to Proceed. Bidders must commit to these timelines before submitting proposals and must complete all work within a maximum of 60 calendar days for full road closure.
Each bid must include Work Qualification documentation demonstrating a minimum of three similar past projects (10 points), St. George City past performance evaluations (10 points), a comprehensive Bid Schedule covering all work per plans and specifications (50 points), and a detailed Construction Schedule in PDF format demonstrating resources and ability to meet the 90-day timeline (30 points). A 5 percent bid bond payable to the City is required; bid bonds of the three lowest responsible bidders will be retained until award, with the successful bidder's bond retained until performance and payment bonds are executed. Performance and payment bonds, each equal to 100 percent of the contract price, must be obtained from a corporate surety approved by the City. Award will be made to the lowest responsible bidder meeting all specified criteria and requirements. The selected contractor must execute the agreement and obtain all required bonds, insurance certificates, and legal work status documentation within 10 calendar days of receiving the Notice of Award.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INFORMATION FOR BIDDERS
The City of St. George, hereinafter called “CITY,” shall receive BIDS for the following:
Project: _250 West Reconstruction (Blackridge Dr. to Tech Ridge Parkway)_______________
Project Address: __250 West and Blackridge Drive ________________________________
1. BID TIMELINE:
BID PUBLISHING DATE: _July 20, 2026 ______________________________________
PRE-BID MEETING DATE, TIME & LOCATION: _July 29, 2026 at 2:00 pm
City Hall Community Development Conference Room__________________________
MANDATORY: YES___X___ NO_______________
Failure to attend a mandatory Pre-Bid meeting will result in automatic disqualification
QUESTIONS DUE DATE: __August 5, 2026______________________________
SUBMISSION CLOSE DATE: _August 11, 2026_____________________________
2. All BIDS must be submitted via sgcity-utah.bonfirehub.com. Any BID may be edited or withdrawn prior to the above scheduled time for the opening of BIDS. Any BID received after the time and date specified shall not be considered. No BIDDER may withdraw a BID within 60 days after the actual date of the opening thereof. Should there be reasons why the contract cannot be awarded within the specified period, the time may be extended by mutual agreement between the CITY and the BIDDER.
3. Each BID must be accompanied by Work Qualification, Bid Schedule, and Construction
Schedule. Contractors will be ranked and project awarded based on the following item criterion.
1. Work Qualification – A minimum of three (3) past projects that are similar in nature. 10 points possible
2. St. George City past performance evaluations (internal review only). 10 points possible
3. Bid Schedule shall include all work called for by the plans and specifications and bidding documents. In the case of a discrepancy in the extension of a line item, the unit price shall govern. BIDDERS must satisfy themselves of the accuracy of the estimated quantities, where given, by examination of the site and a review of the drawings and specifications including ADDENDA. After BIDS have been https://sgcity-utah.bonfirehub.com/ submitted, the BIDDER shall not assert that there was a misunderstanding concerning the quantities of WORK or of the nature of the WORK to be done.
UNIT PRICES as called for in the BID Schedule shall be submitted to cover all additions and deductions in the scope of the WORK. CITY has the right to reduce or remove items from the project. 50 points possible
4. Construction Schedule – The contractors proposed schedule shall demonstrate resources and ability to meet contract time in 90 calendar days. There will be a maximum of 60 calendar days for full road closure. Construction schedule shall be submitted in PDF format. 30 points possible
4. Bid Schedules are included in the Requested Information for a Base Bid and any alternates. It is the CITY'S intent to award this contract based upon the Base Bid. The CITY, in consultation with the ENGINEER, shall add bid items at the City’s sole discretion. The low bid shall be considered to be the bid which has the lowest base bid items selected by the
CITY for inclusion in the final Agreement.
5. The CONSTRUCTION SCHEDULE is particularly important to the CITY. The BID shall include a construction schedule prepared using spreadsheet or scheduling software, showing all main work categories, including at least clearing and grubbing, grading, and drainage, building construction, building interiors, concrete work, and asphalt paving.
6. It is the CITY'S intention to commence construction within 20 calendar days of the Notice of
Award and to complete the project no later than 90 Calendar Days from the Notice to
Proceed. BIDDER'S must be able to commit to these dates before submitting Bids.
7. The CITY shall provide to BIDDERS prior to BIDDING, all information which is pertinent to, and delineates and describes, the land owned, and rights-of-way acquired or to be acquired.
CONTRACT DOCUMENTS INCLUDING BONDS:
1. The CONTRACT DOCUMENTS contain the provisions required for the construction of the project. Information obtained from an officer, agent, or employee of the CITY or any other person shall not affect the risks or obligations assumed by the CONTRACTOR or relieve him from fulfilling any of the conditions of the contract.
2. Each BID must be accompanied by a BID bond payable to the CITY for five percent of the total amount of the BID. As soon as the BID prices have been compared, the CITY will return the BONDS of all except the three lowest responsible BIDDERS. The BID BOND of the successful BIDDER will be retained until the payment BOND and performance BOND have been executed and approved and the Notice to Proceed has been issued, after which the BID BOND will be returned. A certified check may be used in lieu of a BID BOND.
3. A performance BOND and a payment BOND, each in the amount of 100 percent of the
CONTRACT PRICE, with a corporate surety approved by the CITY, will be required for the faithful performance of the contract.
4. Attorneys-in-fact who sign BID BONDS, payment BONDS or performance BONDS must file with each BOND a certified copy of their power of attorney with the effective date.
AWARDING CONTRACT:
1. The CITY may waive any informalities, minor defects, or reject any and all BIDS.
2. The CITY may make such investigations as it deems necessary to determine the ability of the
BIDDER to perform the WORK, and the BIDDER shall furnish to the CITY all such information and data for this purpose as the CITY may request. The CITY reserves the right to reject any BID if the evidence submitted by, or investigation of, such BIDDER fails to satisfy the CITY that such BIDDER is properly qualified to carry out the obligations of the
Agreement and to complete the Agreement and to complete the WORK contemplated therein.
3. The BIDDER, by evidence of the submission of the BID, acknowledges that BIDDER and
BIDDER’S subcontractors meet or exceed the specified requirements for related project experience and insurances, and that should the CITY discover at any time evidence to the contrary, BIDDER agrees to withdraw BIDDER’S BID and to allow the CITY to award the
CONTRACT to the next lowest responsible BIDDER. BIDDER must have the proper contractor’s license for this type of project prior to bidding on the project. It is solely
BIDDER’S responsibility to comply with all applicable federal, state, and local laws, regulations, and ordinances that affect this project.
4. Award will be made to the lowest responsible BIDDER as determined by the City using the criteria contained in City ordinances governing the award of contracts. The BID shall be awarded on the condition that the BIDDER provides all required documents prior to the
NOTICE TO PROCEED being issued. Failure to provide the required documents shall be considered a default on the Contract and may result in the CITY awarding the Contract to another BIDDER in addition to other legal remedies.
5. The party to whom the contract is awarded will be required to execute the Agreement and obtain the performance BOND, the payment BOND, the Certificate of Legal Work
Status for the BIDDER and all Subcontractors and the certificate of insurance within ten (10) calendar days from the date when NOTICE OF AWARD is delivered to the BIDDER. The
NOTICE OF AWARD shall be accompanied by the necessary Agreement and BOND forms.
The bid shall be awarded on the condition that the BIDDER provides all required documents prior to the NOTICE TO PROCEED being issued. Failure to provide the required documents shall be considered a default on the Contract and may result in the City
Awarding the CONTRACT to another BIDDER in addition to other legal remedies.
6. In case of failure of the BIDDER to execute the Agreement or is found to be ineligible or becomes ineligible to meet all the requirements for the project, the CITY may at its option consider the BIDDER in default, in which case the BID BOND accompanying the proposal shall become the property of the CITY.
7. Upon receipt of acceptable performance BOND, payment BOND, insurance certificates and
Agreement signed by the party to whom the Agreement was awarded, the CITY shall sign the Agreement and return to such party an executed duplicate of the Agreement. Should the
CITY not execute the Agreement, the BIDDER may by WRITTEN NOTICE withdraw the
BIDDER’S signed Agreement. Such notice of withdrawal shall be effective upon receipt of the notice by the CITY.
8. The NOTICE TO PROCEED shall be issued immediately upon the following occurring:
providing the executed Agreement to the CITY, providing the performance and payment
BONDS to City, and providing the insurance certificates to City. Should there be reasons why the City wants to delay and the NOTICE TO PROCEED cannot be issued within such period the time may be extended by mutual agreement between the CITY and
CONTRACTOR. If the NOTICE TO PROCEED has not been issued within the ten (10) day period or within the period mutually agreed upon, the CONTRACTOR may terminate the Agreement without further liability on the part of either party.
9. All applicable laws, ordinances, and the rules and regulations of all authorities having jurisdiction over construction of the project shall apply to the contract throughout.
10. Each BIDDER is responsible for inspecting the site and for reading and being thoroughly familiar with the CONTRACT DOCUMENTS. Failure or omission of any BIDDER to do any of the foregoing shall in no way relieve any BIDDER from any obligation in respect to his BID.
File details come from the government source that posted it. Updated .