Attachment_1.pdf

PDF 501 KB Posted

Attached to
15kV Electrical Switchgear Replacement
Solicitation number
14-223-SOL-00069
Issued by

About this file

Attachment 1 revised Section B.

View the file

Other files

File Type Posted
Amendment_3.pdf PDF
Attachment_3.pdf PDF
Attachment_2.pdf PDF
amendment_2.pdf PDF
Amendment_1.pdf PDF
Attachment_1_list_of_attendees.pdf PDF
Attachment_2_Revised_Section_B.pdf PDF
E-7.pdf PDF
Attachment_J-7_PAST_PERFORMANCE_EVALUATION_QUESTIONNAIRE.doc DOC document
M-3.pdf PDF
M-1.pdf PDF
E-3.pdf PDF
M-4.pdf PDF
E-10.pdf PDF
E-9.pdf PDF
E-6.pdf PDF
14-223-SOL-00069.pdf PDF
E-14.pdf PDF
E-15.pdf PDF
E-8.pdf PDF
Attachment_J-1_Specifications.pdf PDF
E-5.pdf PDF
E-2.pdf PDF
E-11.pdf PDF
Attachment_J-4_FDA_Form_3391.pdf PDF
M-2.pdf PDF
E-1.pdf PDF
E-13.pdf PDF
Attachment_J-3_U.S._Department_of_Labor_General_Decision_Number__AR140125.pdf PDF
Attachment_J-6_SAMPLE_CLIENT__LETTER.doc DOC document
COVER.pdf PDF
E-12.pdf PDF
E-4.pdf PDF
S-1.pdf PDF
Attachment_J-5_FDA_Form_3398.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART I- THE SCHEDULE

SECTION B- SUPPLIES OR SERVICES AND PRICES/COSTS

B-1 Purpose

Building 9 Medium Voltage (15KV) Switchgear Replacement, as detailed herein, at the U.S.

Food and Drug Administration (FDA) Jefferson Laboratories in Jefferson, AR.

B-2 Schedule of Items

Contract Line Item No.

Description Quantity Unit Price

Base: Installation of new 15kV electrical switchgear in Building 9 of the Jefferson Labs campus and removal of the existing 15kV electrical switchgear in Building 9 that currently supplies the campus medium voltage electrical distribution system. The construction will include phasing to allow for simultaneous operation of both the new switchgear and the existing switchgear to minimize the number and duration of electrical outages to the campus. Work shall be completed within 365 calendar days after the notice to proceed date (See SF 1442, Block 11 and Section F FAR Clause 52.211-10)

1 Job $

Option for Increased Quantity—Separately Priced Line Item. See FAR Clause 52.217-7 in Section I-2

Provide, install, test and connect new feeders between pad mounted switches VSS-C/C/I and VSS-I/I/C through an existing conduit system.

Work shall be completed within 90 calendar days of option exercise.

1 Job $

Provide and install HVAC system for Building 9.

Work shall be completed within 180 calendar days of option exercise.

1 Job $

Provide and install pad-mounted, switched, power factor correction 1200 kVA capacitor banks.

Work shall be completed within 180 days after

1 Job $

14-223-SOL-00069 Amendment 3

Contract Line Item No.

Description Quantity Unit Price option exercise.

Electrical Monitoring and Control System (EMCS) to control and monitor the main and tie circuit breakers in the new main switchgear and a total of 16 pad-mounted 15KV switches. The EMCS will monitor and display the position of each input and output switch and the status of the SF-6 gas container pressure on each pad-mounted switch assembly. Work shall be completed within 180 days after the option is exercised.

1 Job $

Remove Overhead & Poles. The contractor shall remove the overhead conductors and 7 power poles located on the east side of campus. Work shall be completed within 90 calendar days of option exercise.

1 Job $

Total Price CLINs 1-6

14-223-SOL-00069 Amendment 3

PART I- THE SCHEDULE
SECTION B- SUPPLIES OR SERVICES AND PRICES/COSTS