This document provides details on a federal contract solicitation. The solicitation number is 140R6021R0027 for the Glen Elder Dam Spillway Chute Replacement project located in Kansas. The Department of the Interior Bureau of Reclamation is the contracting agency seeking to replace the spillway chute at the Glen Elder Unit of the Solomon Division within the Pick-Sloan Missouri Basin Program. The amendment number is 0003 and pertains to required construction services for replacing infrastructure at the dam spillway. Interested vendors should review the solicitation and amendment for response due dates, award timing, and any other contractual requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R6021R0027_Amd_0003.pdf | ||
| Amendment_0002_0002.pdf | ||
| Sol_140R6021R0027_Amd_0002.pdf | ||
| Amendment_001_0001.pdf | ||
| Sol_140R6021R0027_Amd_0001.pdf | ||
| Solicitation_No_140R6021R0027_File_3_(51_00_50_Concrete_Core_Report).pdf | ||
| Solicitation_No_140R6021R0027_File_5_(53_20_00_Geologic_Logs).pdf | ||
| Solicitation_No_140R6021R0027_File_4_(52_00_00_Drawings).pdf | ||
| Solicitation_No_140R6021R0027_File_2_(51_00_40_Construction_Photos).pdf | ||
| Solicitation_No_140R6021R0027_File_1.pdf | ||
| Sol_140R6021R0027.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R6021R0027 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Billings MT 59107
R60
PO Box 36900 Regional Office Great Plains Region Bureau of Reclamation
08/13/20210003
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/14/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Gerri Voto-Braun
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Glen Elder Dam Spillway Chute Replacement, Glen Elder Unit, Solomon Division, Pick-Sloan Missouri Basin Program, Kansas
See attachment for changes incorporated by this amendment:
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Amendment No. 0003 Solicitation No. 140R6021R0027
Description of Changes:
1. Remove Foreword in its entirety and substitute therefor the attached revised Foreword.
2. Remove Table of Contents in its entirety and substitute therefor the attached revised Table of
Contents.
3. In Part I – The Schedule, remove Continuation of Section B – Supplies or Services and
Prices in its entirety and substitute therefor the attached Revised Section B.
4. In Part I – The Schedule, remove Specification Section 01 11 00 – Summary of Work in its entirety and substitute therefor the attached Revised Section 01 11 00.
5. In Part I – The Schedule, remove Specification Section 01 33 00 – Submittals in its entirety and substitute therefor the attached Revised Section 01 33 00.
6. In Part I – The Schedule, insert the attached new Specification Section 02 80 10 – General Requirements for Coatings Containing Hazardous Materials Abatement.
7. In Part I – The Schedule, insert the attached new Specification Section 02 83 35 – Removal and Disposal of Coatings and Equipment with Coatings Containing Regulated Metals.
8. In Part I – The Schedule, remove Specification Section 31 24 17 – Zone 2A Gravel Drain in its entirety and substitute therefor the attached Revised Section 31 24 17.
9. In Part I – The Schedule, insert the attached new Specification Section 35 21 10 – Flap Gates.
10. In Part I – The Schedule, remove Specification Section 52 00 00 – Drawings in its entirety and substitute therefor the attached Revised Section 52 00 00.
11. In Part I – The Schedule, in Section 52 00 00 – Drawings, remove the following drawings and substitute therefor the attached revised drawings:
Sheet No. Drawing No.
3 495-D-60003, Rev 1 dated 08/04/2021 8 495-D-60012, Rev 1 dated 08/05/2021 9 495-D-60013, Rev 1 dated 08/05/2021 11 495-D-60015, Rev 1 dated 05/05/2021 12 495-D-60016, Rev 1 dated 08/05/2021 20 495-D-60024, Rev 1 dated 08/10/2021 22 495-D-60026, Rev 1 dated 08/05/2021
Solicitation No. 140R6021R0027
23 245-D-60027, Rev 1 dated 08/05/2021 24 245-D-60028, Rev 1 dated 08/05/2021 25 245-D-60029, Rev 1 dated 08/05/2021 26 245-D-60030, Rev 1 dated 08/10/2021 27 245-D-60031, Rev 1 dated 08/10/2021 35 245-D-60039, Rev 1 dated 08/09/2021
12. In Part II – Contract Clauses, remove pages I-1and I-2 and substitute therefor the attached revised pages I-1 and I-2.
13. In Part IV – Representations and Instructions, remove page L-17 and substitute therefor the attached revised page L-17.
For convenience, essential changes on the revised solicitation pages are indicated by a vertical line within the margin, whereby the lines or paragraphs are changed from the previous version.
However, all portions of the revised solicitation pages shall apply whether changes thereon have been indicated or not.
Acknowledgement: See Block 11 on the Standard Form 30 regarding acknowledgement by offerors to this amendment. The Government requires acknowledgment by offerors to this amendment at the place designated for receipt of proposals. (Please see Block 19 on the Standard Form 1442.)
Receipt of Proposals: The hour and date for receipt of proposals remains the same; 2:00 PM MDT on August 20, 2021.
Third Party: If you have provided a copy of this solicitation to another company or individual, please forward this amendment accordingly.
Subcontracting Plan – A word version of the template for the subcontracting plan is included in this amendment and shall be used by large business concerns in the preparation of their draft subcontracting plan.
The final list of contractor questions and their respective answers are attached for information only.
i (Revised)
GLEN ELDER DAM SPILLAY CHUTE REPLACEMENT
GLEN ELDER UNIT, SOLOMON DIVISION
PICK-SLOAN MISSOURI BASIN PROJECT
KANSAS
FOREWORD
Work is located at Glen Elder Dam, approximately 2 miles southwest of Glen Elder, Kansas, in Mitchell County.
The work to be performed includes the following:
1. Development, improvement, and maintenance of access roads for construction.
2. Site development and mobilization of batch plant, certification, maintenance, and production of concrete.
3. Demolition of existing concrete chute, including sawcutting and hydrodemolition.
4. Concrete removal for concrete repairs.
5. Excavation of rock, common materials, and clay tile pipe demolition.
6. Shotcrete application to foundation.
7. Grouted anchor bar installation into existing concrete.
8. Rock anchor installation into foundation.
9. Gravel and sand filter material placement.
10. Drain pipe placement.
11. New concrete chute construction.
12. Concrete repairs.
13. Installation of standard and hydrophilic waterstop.
14. Unwatering of stilling basin, maintenance of unwatering systems, and removal of sediment and debris within the stilling basin.
15. Fabrication and installation of flap gates.
POINT OF CONTACT – The Contract Specialist for this action is Ms. Charlee Maurer. All questions and correspondence concerning this solicitation shall be directed to her via e-mail at camaurer@usbr.gov.
METHOD OF PROCUREMENT – This requirement is solicited as a Request For Proposal using the Federal Acquisition Regulation Part 15, Contracting by Negotiation.
ORGANIZED SITE VISIT – A virtual site visit will be held on July 30, 2021 at 2:00 PM MDT.
Prospective offerors interested in attending should contact Ms. Maurer via email. All offerors are strongly encouraged to attend this meeting.
CONTRACTOR QUESTIONS – The Government will not address questions received from prospective after 4:30 PM on August 2, 2021.
RECLAMATION SAFETY AND HEALTH STANDARDS (2014 EDITION) – For information regarding Bureau of Reclamation's publication "RECLAMATION SAFETY AND HEALTH ii (Revised)
STANDARDS" (2014 Edition at http://www.usbr.gov/ssle/safety/RSHS/rshs.html) which is applicable to work under this contract, see clause at "WBR 1452.223-81 SAFETY AND
HEALTH."
SYSTEM FOR AWARD MANAGEMENT (SAM) – Effective October 2018, all contractors interested in doing business with the Federal Government must be registered in the System for Award Management (SAM) database at the time they submit their offer.
Additionally, the contractors “DUNS and BRADSTREET” and banking information are required for the SAM registration and annual confirmation requirements must be accomplished through the SAM website at https://www.sam.gov. For assistance with registering in SAM, contact the Federal Services Desk at 1-866-606-8220.
INVOICE PROCESSING PLATFORM (IPP) – Payment requests for the anticipated contract or agreement must be submitted electronically through the U.S. Department of Treasury’s “Invoice Processing Platform” (IPP) System via the IPP website at https://www.ipp.gov. Contractors are required to use the IPP website to access and use IPP for submitting request for payment.
Registration assistance can be obtained by contacting the “IPP Production Helpdesk” via email ippgroup@bos.fbr.org or phone 1-866-973-3131. If the contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the contractor can submit a waiver request in writing to the Contractor Officer with its proposal. Note: Waivers will be on a case by case basis and not automatically granted as determined by the Contract Officer. Please see Paragraph G.3, DOI-AAAP-0028 for more specific information on the process for submitting invoices in IPP.
Table of Contents - 1 (Revised)
TABLE OF CONTENTS
PART I – THE SCHEDULE
SECTION A -- SOLICITATION, OFFER, AND AWARD, STANDARD FORM 1442
SECTION B -- PRICE SCHEDULE
SECTION C -- DESCRIPTION / SPECIFICATIONS
Division 01 General Requirements
01 11 00 Summary of Work 01 14 10 Use of Site 01 14 12 Work Restrictions and Limitations 01 14 20 Reservoir Operations 01 31 19 Project Management and Coordination 01 32 10 Construction Program 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 51 00 Temporary Utilities 01 52 10 Field Office and Laboratory 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 32 Temporary Safety Fence 01 57 15 Utility Line Investigations 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 50 Tree and Plant Protection 01 57 60 Protected Species 01 60 00 Product Requirements 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents
Division 02 Existing Conditions
02 21 30 Benchmarks 02 80 10 General Requirements for Coatings Containing Hazardous Materials Abatement 02 83 35 Removal and Disposal of Coatings and Equipment with Coatings Containing
Regulated Metals
Table of Contents - 2 (Revised)
Division 03 Concrete 03 11 10 Concrete Forming 03 15 12 PVC Waterstop 03 15 17 Hydrophilic Strip Waterstop 03 20 00 Concrete Reinforcing 03 20 30 Grouted Anchor Bars 03 30 00 Cast-In-Place Concrete 03 37 10 Shotcrete 03 81 10 Concrete Removal
Division 07 Thermal and Moisture Protection
07 21 20 Extruded Polystyrene Foam Insulation 07 92 00 Joint Sealants
Division 31 Earthwork 31 02 10 Water for Dust Abatement 31 03 33 Removal and Control of Water 31 11 00 Clearing and Grubbing 31 12 00 Removal of Stilling Basin Materials 31 14 10 Stripping 31 23 00 Excavation and Fill 31 23 02 Compacting Earth Materials 31 23 39 Disposal of Excavated Materials 31 24 13 Zone 2 Sand Filter Material 31 24 17 Zone 2A Gravel Drain 31 52 00 Cofferdams 31 68 00 Rock Anchors
Division 32 Exterior Improvements
32 15 10 Gravel Surfacing 32 91 20 Placing Topsoil 32 92 20 Seeding
Division 33 Utilities
33 46 36 HDPE Pipe Drains and Outfalls
Division 35 Waterway and Marine Construction
35 21 95 Steel Pipe
Division 51 Information Available to Offerors
51 00 00 Information Available to Offerors 51 00 20 Reservoir Water Surface Elevation Data 51 00 40 Construction Photographs 51 00 50 Concrete Core Report 51 40 00 Streamflow Records and Climatic Conditions
Table of Contents - 3 (Revised)
Division 52 Drawings 52 00 00 Drawings
Division 53 Geologic Investigations and Records
53 10 00 Geologic Investigations 53 20 00 Records of Geologic and Subsurface Investigations
SECTION D -- NOT USED
SECTION E -- INSPECTION AND ACCEPTANCE
E.1 52.246-12 Inspection of Construction ......................................................... E-1 E.2 52.246-21 Warranty of Construction .......................................................... E-2
SECTION F – DELIVERIES OR PERFORMANCE
F.1 52.211-10 Commencement, Prosecution, and Completion of Work .......... F-1 F.2 52.211-12 Liquidated Damages .................................................................. F-1 F.3 52.211-13 Time Extensions ......................................................................... F-1 F.4 52.211-18 Variation in Estimated Quantity ................................................ F-1 F.5 52.242-14 Suspension of Work ................................................................... F-2
SECTION G -- CONTRACT ADMINISTRATION DATA
G.1 1452.201-70 Authorities and Delegations ....................................................... G-1 G.2 WBR 1452.201-80 Contracting Officer’s Representative’s Authorities and Limitations .......................................................................... G-2 G.3 DOI-AAAP-0028 Electronic Invoicing and Payment Requirements – Invoice Processing Platform (IPP) .......................................................... G-3 G.4 DOI-AAAP-0050 Notice to Contractors – Contractor Performance Assessment Reporting System ....................................................................... G-4
SECTION H -- SPECIAL CONTRACT REQUIREMENTS–
H.1 MB-2 Payment for Technical Data ....................................................... H-1
PART II – CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
I.1 52.252-2 Clauses Incorporated by Reference (See Table) ........................ I-1 I.2 52.203-14 Display of Hotline Poster(s) ....................................................... I-4 I.3 52.204-21 Basic Safeguarding of Covered Contractor Information Systems .................................................................. I-5 I.4 52.215-8 Order of Precedence -- Uniform Contract Format ..................... I-6 I.5 52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns (Deviation 2019-01) IAW DOI-AAAP-150 ................................................................ I-7 I.6 52.219-28 Post-Award Small Business Program Rerepresentation ............ I-8 I.7 52.222-23 Notice or Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction ..................... I-12
Table of Contents - 4 (Revised)
I.8 52.223-3 ALT I Hazardous Material Identification and Material Safety Data – Alternate I ............................................................ I-13 I.9 52.225-11 Buy American–Construction Materials Under Trade Agreements ................................................................................ I-15 I.10 52.228-2 Additional Bond Security .......................................................... I-20 I.11 52.228-15 Performance and Payment Bonds – Construction ..................... I-20 I.12 52.232-5 Payments Under Fixed-Price Construction Contracts ............... I-22 I.13 52.232-27 Prompt Payment for Construction Contracts ............................. I-25 I.14 52.232-40 Providing Accelerated Payment to Small Business Subcontractors ............................................................................ I-33 I.15 52.236-1 Performance of Work by the Contractor .................................... I-34 I.16 52.236-2 Differing Site Conditions ........................................................... I-34 I.17 52.236-4 Physical Data ............................................................................. I-34 I.18 52.236-13 Accident Prevention ................................................................... I-35 I.19 52.236-21 ALT II Specifications and Drawings for Construction – Alternate II .... I-36 I.20 52.243-4 Changes ...................................................................................... I-37 I.21 52.252-6 Authorized Deviations in Clauses .............................................. I-38 I.22 1452.203-70 Restriction on Endorsements--Department of the Interior ......... I-38 I.23 1452.204-70 Release of Claims--Department of the Interior .......................... I-38 I.24 1452.215-70 Examination of Records by the Department of the Interior ....... I-38 I.25 1452.228-70 Liability Insurance -- Department of the Interior ...................... I-39 I.26 WBR 1452.209-82 Prohibition on Release of Information -- Bureau of Reclamation ............................................................................... I-39 I.27 WBR 1452.215-86 Intent to Incorporate Technical Proposal ................................... I-40 I.28 WBR 1452.215-87 Incorporation of Technical Proposal .......................................... I-40 I.29 WBR 1452.223-80 Asbestos-Free Warranty............................................................. I-40 I.30 WBR 1452.223-81 Safety and Health -- Bureau of Reclamation ............................. I-40 I.31 WBR 1452.223-82 Protecting Federal Employees and the Public from Exposure to Tobacco Smoke in the Federal Workplace -- Bureau of Reclamation ........................................................... I-41 I.32 WBR 1452.228-84 Certification or Representatives for Corporate Sureties --Bureau of Reclamation ............................................................ I-42 I.33 WBR 1452.231-81 Equipment Ownership and Operating Expense -- Bureau Of Reclamation .......................................................................... I-42 I.34 WBR 1452.232-80 Limitation of Funds ................................................................... I-44 I.35 WBR 1452.232-81 Payment for Mobilization and Preparatory Work – pay ALT I Alternative I ............................................................................... I-46 I-36 WBR 1452.232-82 Other Invoice Requirements ...................................................... I-48 I.37 WBR 1452.233-81 Claims Accounting -- Bureau of Reclamation ........................... I-48 I.38 WBR 1452.236-8 Other Contracts (Deviation) ....................................................... I-48 I.39 WBR 1452.236-84 Preservation of Cultural Resources -- Bureau of Reclamation .. I-48 I.40 WBR 1452.237-80 Security Requirements -- Bureau of Reclamation ..................... I-51 I.41 WBR 1452.243-80 Modification Proposals – Alternative IV – Bureau of ALT IV Reclamation ............................................................................... I-63
Table of Contents - 5 (Revised)
PART III – DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
Attachment No. 1 .............General Decision Number: KS20210037, Modification 01, July 30, 2021 Attachment No. 2 ………………..................................................... Standard Form 24 - Bid Bond Attachment No. 3 ………………............................................................................Form GP-PIV-1 Attachment No. 4 ……………….…………………OF-306 Declaration for Federal Employment Attachment No. 5 ………………………………………………….Subcontracting Plan Template
PART IV – REPRESENTATIONS AND INSTRUCTIONS
SECTION K -- REPRESENTATIONS, CERTIFICATIONS AND OTHER
STATEMENTS OF OFFERORS
K.1 52.204-8 Annual Representations and Certifications ...............................K-1 K.2 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment ..............................K-5 K.3 52.209-7 Information Regarding Responsibility Matters ........................K-8 K.4 52.209-12 Certification Regarding Tax Matters ........................................K-9 K.5 52.209-13 Violation of Arms Control Treaties or Agreements- Certification ..............................................................................K-11
SECTION L -- INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
L.1 52.204-7 System for Award Management ...............................................L-1 L.2 52.204-16 Commercial and Government Entity Code Reporting ..............L-2 L.3 52.204-22 Alternative Line Item Proposal .................................................L-4 L.4 52.211-1 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 ..............................................L-4 L.5 52.211-2 Availability of Specifications, Standards and Data Item Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST) ........................L-5 L.6 52.211-6 Brand Name or Equal ................................................................L-5 L.7 52.214-34 Submission of Offers in the English Language ........................L-6 L.8 52.214-35 Submission of Offers in U.S. Currency ....................................L-6 L.9 52.215-1 Instruction to Offerors – Competitive Acquisition ...................L-6 L.10 52.215-20 Requirements for Certified Cost or Pricing Data and Other Data Other Than Certified Cost or Pricing Data .............L-11 L.11 52.216-1 Type of Contract .......................................................................L-12 L.12 52.222-5 Construction Wage Rate Requirements – Secondary Site of the Work ........................................................................L-12 L.13 52.225-12 Notice of Buy American Requirement-Construction Materials Under Trade Agreements ..........................................L-12 L.14 52.228-1 Bid Guarantee ...........................................................................L-14 L.15 1452.233-2 Service of Protest – Department of the Interior (DEVIATION) ..........................................................................L-14 L.16 52.236-27 ALT I Site Visit (Construction) – Alternate I ......................................L-15
Table of Contents - 6 (Revised)
L.17 52.236-28 Preparation of Proposals – Construction...................................L-15 L.18 52.252-1 Solicitation Provisions Incorporated by Reference ...................L-15 L.19 52.252-5 Authorized Deviations in Provisions ........................................L-16 L.20 1452.215-71 Use and Disclosure of Proposal Information Department of the Interior ........................................................L-16 L.21 WBR 1452.215-80 Source Selection Evaluation Procedures -- Bureau of Reclamation ..............................................................................L-17 L.22 WBR 1452.215-81 Proposal Instructions -- Bureau of Reclamation .......................L-18 L.23 WBR 1452.233-82 Notice of Proposed Partnering -- Bureau of Reclamation ........L-24
L.24 WBR 1452.236-85 Instruction for Mobilization and Preparatory Work Schedule Line Item ...................................................................L-24
SECTION M -- EVALUATION FACTORS FOR AWARD
M.1 WBR 1452.215-82 Evaluation Factors for Award – Quality Predominance ............................................................................M-1 M.2 WBR 1452.225-82 Notice of World Trade Organization Government Procurement Agreement Evaluations – Bureau of Reclamation ....................M-3
END OF CONTENTS
Glen Elder Dam Spillway Chute Replacement Glen Elder Unit, Solomon Division Amendment No. 0003 Pick-Sloan Missouri Basin Program, Kansas Solicitation No. 140R6021R0027
Price Schedule Revised B - 1
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES
GLEN ELDER DAM SPILLWAY CHUTE REPLACEMENT
GLEN ELDER UNIT, SOLOMON DIVISION
PICK-SLOAN MISSOURI BASIN PROGRAM, KANSAS
B.1 PRICE SCHEDULE
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) Quantities in the Price Schedule s are estimated quantities for comparison of offers only.
Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated, no claim shall be made against the Government for overruns or underruns.
(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.
(e) Definitions:
(1) CLIN – Contract Line Item Number
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
1 WBR
1452.232-
Mobilization and Preparatory Work
For the lump sum of $
2 01 55 00 Temporary Roadways, Haul Routes, Batch Plant, and Parking
For the lump sum of $
3 02 21 30 Benchmarks For the lump sum of $
4 03 15 12 PVC Waterstops 9,920 lin ft $ $
5 03 15 17 Hydrophilic Strip Waterstop 1,910 lin ft $ $
Revised B - 2
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
6 03 20 00 Concrete Reinforcing 1,907,600 lbs
7 03 20 30 Installation of Anchor Bars 2,600 lin ft $ $
8 03 30 00 Cast-In-Place Concrete 13,220 yd3 $ $
9 03 30 00 Mud Mat Concrete 880 yd3 $ $
10 03 30 00 Test Slab Concrete 12 yd3 $ $
11 03 30 00 Concrete Batch Plant Installation
For the lump sum of $
12 03 37 10 Shotcrete 18,500 yd2 $ $
13 03 81 10 Concrete Removal 11,900 yd3 $ $
14 03 81 10 Saw Cut Existing Concrete, 2-inch Depth
1,910 ft $ $
15 03 81 10 Saw Cut Existing Concrete, Full Depth
2,840 ft $ $
16 03 81 10 Hydrodemolition, 6-Inch Calibration Setting
1,530 yd2 $
17 03 81 10 Hydrodemolition, 12-Inch
100 yd2 $
18 03 81 10 Hydrodemolition, 18-Inch
265 yd2 $
19 07 21 20 Extruded Polystyrene Foam Insulation
15,400 ft2 $ $
20 07 92 00 Joint Sealants For the lump sum of $
21 31 03 33 Removal and Control of Water
For the lump sum of $
22 31 12 00 Remove Material in Stilling Basin
19,600 yd3 $ $
23 31 23 00 Excavation for Existing Spillway Drainage Material and Backfill Removal
15,930 yd3 $ $
Revised B - 3
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
24 31 24 13 Zone 2 Sand Filter Material 5,800 yd3 $ $
25 31 24 17 Zone 2A Gravel Drain 7,600 yd3 $ $
26 31 52 00 Stilling Basin Cofferdam For the lump sum of $
27 31 68 00 Rock Anchors 1,400 ea $ $
28 32 91 20 Topsoil For the lump sum of
29 32 92 20 Seeding For the lump sum of $
30 33 46 36 8-inch-Diameter Nonperforated HDPE Pipe
72 lin ft $ $
31 33 46 36 8-inch-Diameter Perforated HDPE Pipe
7,310 lin ft $ $
32 35 21 10 Removal and Disposal of Existing Flap Gates
2 ea $ $
33 35 21 10 Flap Gates 2 ea $ $
34 35 21 95 Steel Pipe For the lump sum of $
TOTAL FOR PRICE SCHEDULE $_________________
END OF PRICES SCHEDULE
Revised B - 4
This page intentionally left blank.
Summary of Work
Revised 01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. Work is located at Glen Elder Dam, approximately 2 miles southwest of Glen Elder, Kansas, in Mitchell County.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Development, improvement, maintenance of access roads for construction.
B. Site development and mobilization of batch plant, certification, maintenance, and production of concrete.
C. Demolition of existing concrete chute, including sawcutting and hydrodemolition.
D. Concrete removal for concrete repairs.
E. Excavation of rock, common materials, and clay tile pipe demolition.
F. Shotcrete application to foundation.
G. Grouted anchor bar installation into existing concrete.
H. Rock anchor installation into foundation.
I. Gravel and sand filter material placement.
J. Drain pipe placement.
K. New concrete chute construction.
L. Concrete repairs.
M. Installation of standard and hydrophilic waterstop.
N. Unwatering of stilling basin, maintenance of unwatering systems, and removal of sediment and debris within stilling basin.
O. Fabrication and installation of flap gates.
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.
Summary of Work
Revised 01 11 00 - 2
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.
1.04 DEFINITIONS
A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 53:
1. CO: Contracting Officer.
2. COR: Contracting Officer’s Representative.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Submittals
Revised 01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-12 Decimal Inch Drawing Sheet Size and Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-14 United States National CAD Standards, Version 6
1.03 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittals: Considered "shop drawings" within the terms of the clause at FAR 52.236- 21, Specifications and Drawings for Construction.
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included in this section take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement Units: US Customary Units.
C. Drawings:
1. Minimum Identification in Title Block:
a. Contract number and title.
b. Contractor's or supplier's title and drawing number.
Revised 01 33 00 - 2
c. Date.
2. Provide space next to title block for review stamps.
3. Size: ANSI D size (22 inches by 34 inches).
4. Draw to scale using computer drafting.
a. In accordance with NIBS NCS.
b. Electronic file format: Compatible with AUTOCAD, Version 2020 or later.
c. Compile using "eTransmit" utility in AUTOCAD.
d. Government will provide electronic AutoCAD format template.
e. Title block and sheet format:
1) As shown on Standard Drawing 40-D-7102.
2) Government will supply template.
3) Government will supply specific title block information to be used.
f. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
D. Samples Submittals:
1. Label with complete manufacturer's product and color identification.
2. Include type and quantity of materials specified in the referenced section in each "set" of samples.
E. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
F. Certifications:
1. Certifications by a registered professional: Signed and sealed by registered professional.
2. Manufacturer's certifications: Signed by authorized representative of manufacturer.
Revised 01 33 00 - 3
G. Photographs:
1. Professional quality:
a. Include contract number, name of equipment, and view title.
b. Digital files in .jpeg or similar format.
H. Videos:
1. Digital file in MP4 format.
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in "Submittals Required" column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
C. Submit number of sets specified in "No. of sets to be sent:" columns in Table 01 33 00A - List of Submittals.
1. Electronic submittals:
a. In Portable Document Format (PDF).
1) Include RSN transmittal letter.
2) Optical Character Recognition (OCR).
3) 508 compliant.
4) RSNs having more than one requirement shall be bookmarked.
5) RSNs with requirements for files other than PDF (.XER, .PLF, .DWGs, etc.) shall be combined using WIN Zip.
b. Personally-Identifiable Information (PII) shall be encrypted using WINZip or Adobe Acrobat before transmitting electronically.
2. Submit electronic submittals via email or thumb drive based on size:
a. The Government can receive emails up to 25 MB. However, emails over 10 MB should be considered extra-large. Emailing of electronic submittals exceeding 10 MB should only occur after transmittal of extra-large size email has been verified.
b. Address email of electronic submittals less than extra-large size to:
1) sha-GPR-CONSTSVCS@usbr.gov
c. Electronic submittals that are too large to email shall be submitted on thumb drive.
Revised 01 33 00 - 4
d. Submittals received after 5:00 p.m. Mountain Time, shall be documented as received the next business day.
D. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for attached submittal.
3. Responsible code.
4. Identify submittal as initial or resubmittal.
E. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
a. Resubmitted drawings shall include a revision block with date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 14 days after receiving comments, unless otherwise directed.
4. Requirements for initial submittals apply to resubmittals.
5. Resubmittals shall be complete submittals without reference to the original submittal.
F. Submit each RSN under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned for resubmittal.
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 28 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return email date.
B. Time in Excess of Specified:
1. The CO may extend contract completion date to allow additional time for completing work affected by excess review time.
a. Time extension will extend the contract completion date based on the excess review time delay.
b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.
Revised 01 33 00 - 5
c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.
2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to extent that:
a. Approval was required under contract, and
b. Requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work; however, no such delay shall be deemed to be a "suspension order" as the term is used in that clause.
C. Submittal Response:
1. Response letter will indicate whether submittal is approved, not approved, acceptable, not acceptable, or acknowledged receipt.
a. Revise and resubmit submittals not approved or not acceptable.
b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.
1.07 TRANSMITTAL
A. Addresses for codes listed in Table 01 33 00A - List of Submittals:
1. CO: Bureau of Reclamation, Attention MB-5000, P.O. Box 36900, Billings, MT 59107-6900. Physical address: 2021 4th Avenue North, Billings, MT 59101.
2. COR: Bureau of Reclamation, Attention: MB-2600, P.O. Box 36900, Billings, MT 59107-6900. Physical address: 2021 4th Avenue North, Billings, MT 59101.
B. Email address for electronic submittals listed in Table 01 33 00A - List of Submittals:
sha-GPR-CONSTSVCS@usbr.gov.
1. Submit electronic submittals that are too large for email to the physical address above.
C. Submittals required by specifications, but not listed in Table 01 33 00A - List of Submittals:
1. Submit in accordance with this section.
2. Submit to COR unless otherwise specified.
Revised 01 33 00 - 6
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Revised 01 33 00 - 7
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
1 Reporting Executive Compensation and First Tier Subcontract Awards 52.204-10
Certification that executive compensation and subcontract awards were reported
Within 10 days of each report being submitted
CO 1 electronic 0
2 Equal Opportunity 52.222-26
Information required by Executive Order
112246 (SF-100)
Within 30 days following award
CO 1 electronic 0
3 Performance and Payment Bonds – Construction 52.228-15
Performance and Payment Bonds
Within 10 calendar days after award
CO 1 electronic 0
4 Release of Claims 1452.204-70
Release of Claims (DI-137) against the Government
After completion of the work and prior to final payment
CO 1 electronic 0
5 Insurance-work on a Government Installation 1452.228-70
1) Written certification that the required insurance has been obtained
2) Current certification of insurance for each subcontractor
Before commencing onsite work
CO 1 electronic
1 electronic
6 Liability Insurance 1452.228-70
Acceptable Certificate of Liability Insurance
Prior to commencement of work under the contract
CO 1 electronic 0
7 Payrolls and Basic Records 52.222-08
Copies of all payrolls
Weekly for each week of contract performance
COR 1 electronic encrypted
1 electronic encrypted
8 Labor Standards Data 52.222-11
List of subcontractors
Within 14 days after preconstruction meeting
COR 1 electronic
9 Labor Standards Data 52.222-11
Statement and acknowledgement Form (SF-1413) for each subcontract
Within 14 days after preconstruction meeting
COR 1 electronic
10 Deleted
Revised 01 33 00 - 8
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
11 Site Security GP-7 Employee information
Submitted at least 28 days prior to arrival on site.
Employees must be approved to perform on-site work
COR 0 1 electronic encrypted
12 Site Security GP-7 Equipment and vehicles to be brought on site
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic encrypted
13 Superintendence by the Contractor
Site Superintendent
Submitted and approved before mobilization
COR 0 1 electronic
01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan
Submitted and approved at least 28 days before mobilization
COR 1 electronic 1 electronic
01 31 19-1 Project Management and Coordination
Weekly Coordination Meeting Documentation
Weekly COR 0 1 electronic
01 32 10-1 Construction Program
Representative Information
Submitted within 14 days after preconstruction meeting and approved before mobilization
COR 1 electronic 1 electronic
01 32 10-2 Construction Program
Baseline Schedule
Submitted within 14 days after preconstruction meeting and approved before mobilization
COR 1 electronic 1 electronic
01 32 10-3 Construction Program
Updated Schedule Reports
Submitted and approved for monthly progress payments
COR 1 electronic 1 electronic
01 32 10-4 Construction Program
Time Impact Analysis
Within 28 days after the CO directs a contract change, with any proposal for a future modification, with any value engineering proposal, or with any request or claim for an equitable adjustment to the contract
COR 1 electronic 1 electronic
01 32 10-5 Construction Program
Schedule of Values
Submitted within 14 days after preconstruction meeting and approved before mobilization
COR 0 1 electronic
01 35 10-1 Safety Data Sheets Complete LHM and SDS
Submitted and approved at least 28 days before jobsite delivery of hazardous material
COR 0 1 electronic
Revised 01 33 00 - 9
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
01 35 10-2 Safety Data Sheets Updated LHM and
SDS
Submitted and approved at least 28 days before jobsite delivery of hazardous material not previously listed
COR 0 1 electronic
01 35 20-1 Safety and Health Safety Program Submitted and accepted at least 28 days before mobilization
COR 0 1 electronic
01 35 20-2 Safety and Health Monthly Accident Summary Reports
Monthly COR 0 1 electronic
01 35 20-3 Safety and Health Respirator User Documentation
Submitted and accepted at least 28 days before onsite work begins
COR 0 1 electronic encrypted
01 35 20-4 Safety and Health Crane Operation Certificates
Submitted and accepted at least 28 days before onsite work begins
COR 0 1 electronic
01 35 20-5 Safety and Health Exposure Assessment Form
Submitted and accepted at least 28 days before onsite work begins
COR 0 1 electronic
01 35 20-6 Safety and Health Other Training Certificates
Submitted and accepted at least 28 days before onsite work begins
COR 0 1 electronic
01 35 20-7 Safety and Health Pandemic Notification
Within 24 hours of positive test
COR 0 1 electronic
01 35 20-8 Safety and Health Employee Return to Work Documentation
Submitted and accepted before employee returns to work
COR 0 1 electronic
01 35 30-1 Contractor's Onsite Safety Personnel
Qualifications Submitted and accepted at least 28 days before onsite work begins
COR 0 1 electronic encrypted
01 35 30-2 Contractor's Onsite Safety Personnel
CIH Inspection Reports
Monthly COR 0 1 electronic
01 35 30-3 Contractor's Onsite Safety Personnel
Safety Inspection Reports
Weekly COR 0 1 electronic
01 46 00-1 Quality Procedures Contractor Quality Control Program
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 46 00-2 Quality Procedures Contractor's Daily Reports
Weekly COR 0 1 electronic
01 46 00-3 Quality Procedures Quality Control Supervisor Resume
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic encrypted
01 46 00-4 Quality Procedures Contractor’s Quality Testing Plan
Submitted and approved at least 28 days before mobilization
Revised 01 33 00 - 10
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
01 46 00-5 Quality Procedures Summary of Test Results
Monthly COR 0 1 electronic
01 46 20-1 Testing Agency Services
Testing Agency Services Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 46 20-2 Testing Agency Services
Certifications Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 51 00-1 Temporary Utilities
Water Consumption
Weekly COR 0 1 electronic
01 52 10-1 Field Office and Laboratory
Delivery Schedule and Site Layout
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 55 00-1 Vehicular Access and Parking
Temporary Access Roadway Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 55 00-2 Vehicular Access and Parking
Pre-Construction Video
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 55 00-3 Vehicular Access and Parking
Post-Construction Video
Within 7 days of completing construction
COR 0 1 electronic
01 55 00-4 Vehicular Access and Parking
Post-Restoration Video
Within 7 days of completing restoration
COR 0 1 electronic
01 55 20-1 Traffic Control Traffic Control Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 56 10-1 Protection of Existing Installations
Plan for Protecting Existing Installations
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 56 15-1 Protection of Existing Utilities
Utility Owner Acknowledgment
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 57 15-1 Utility Line Investigations
Locating Utility Lines Plans
Submitted and approved at least 28 days before beginning utility lines location work
COR 0 1 electronic
01 57 15-2 Utility Line Investigations
Utility Lines Information
Within 2 days after each utility line is located
COR 0 1 electronic
01 57 15-3 Utility Line Investigations
Permits Submitted and approved at least 28 days before beginning work in area of each utility line
COR 0 1 electronic
01 57 20-1 Environmental Controls
Copy of Applicable Air Quality Permit
Submitted and approved at least 28 days before mobilization
Revised 01 33 00 - 11
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
01 57 30-1 Water Pollution Control
Pollution Prevention Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 57 30-2 Water Pollution Control
Spill Prevention Control, and Countermeasure (SPCC) Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 57 50-1 Tree and Plant Protection
Protection Plan Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 71 20-1 Surveying Surveying Plan Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 71 20-2 Surveying Resumes Submitted and approved at least 28 days before beginning survey work; At least 28 days before personnel change
COR 0 1 electronic
01 71 20-3 Surveying Accuracy Check Results
Submitted and approved at least 28 days before beginning survey work
COR 0 1 electronic
01 71 20-4 Surveying Completed and Reduced Survey Notes
Within 7 days of completing and reducing notes
COR 0 1 electronic
01 71 20-5 Surveying Quantity Survey Notes and Computations
Submitted and approved for monthly progress payments
COR 0 1 electronic
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Plan
Submitted and approved at least 28 days before mobilization
COR 0 1 electronic
01 74 00-2 Cleaning and Waste Management
Waste Production and Disposal Records
Within 7 days of waste disposal
COR 0 1 electronic
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
Submitted and approved at least 28 days before beginning environmental assessment
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment (if required)
Within 14 days of completion of work
COR 0 1 electronic
01 78 30-1 Project Record Documents
Final As-built Drawings
Within 28 days of completion of work
COR 0
Revised 01 33 00 - 12
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
02 80 10-1 General Requirements for Coatings Containing Hazardous Materials Abatement
Resumes and Qualifications
Submitted and approved at least 28 days before beginning onsite work
02 80 10-2 General Requirements for Coatings Containing Hazardous Materials Abatement
Worker Protection Program
Submitted and approved at least 28 days before
02 80 10-3 General Requirements for Coatings Containing Hazardous Materials Abatement
Area Baseline Test Results
Within 7 days of collecting samples
COR 0 1 electronic
02 80 10-4 General Requirements for Coatings Containing Hazardous Materials Abatement
Working Level Test Results
Within 1 day of collecting samples
COR 0 1 electronic
02 80 10-5 General Requirements for Coatings Containing Hazardous Materials Abatement
Post Test Results for Cleaning Verification
Within 3 days of collecting samples
COR 0 1 electronic
02 83 35-1 Removal and Disposal of Coatings and Equipment with Coatings Containing Regulated Metals
Qualifications Submitted and approved at least 28 days before
Revised 01 33 00 - 13
Table 01 33 00A - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer's Representative.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Respon-sible code
No. of sets to be sent to:
CO COR
02 83 35-2 Removal and Disposal of Coatings and Equipment with Coatings Containing Regulated Metals
Coatings Removal Debris Abatement Plan
Submitted and approved at least 28 days before beginning…