U.S. Department of the Interior Bureau of Reclamation 2021 4th Ave. North Billings, MT 59101 FEBRUARY 2018

Solicitation No. 140R6018R0003

Pueblo Dam Contraction Joint Leak Repair

Fryingpan-Arkansas Project Colorado

U.S. Department of the Interior Bureau of Reclamation 2021 4th Ave. North Billings, MT 59101 FEBRUARY 2018

This page intentionally left blank.

Foreward - 1

PUEBLO DAM

BUTTRESS CONTRACTION JOINT TREATMENT

Fryingpan-Arkansas Project Colorado

FOREWORD

Work is located at Pueblo Dam, located approximately 8 miles west of Pueblo, Colorado, in Pueblo County.

A. The principal components of work to be performed under these specifications on the contraction joints between the buttresses 9-10, 6-7, 17-18, 18-19, 12-13, 13-14, 14-15, 15-16, 16-17, 19-20, 20-21, 3-4, 4-5, 5-6, 7-8, 8-9, 10-11, and 11-12, (18 joints total), include the following:

1. Preparation of concrete surfaces above and below the reservoir water surface (RWS) along the upstream face of the concrete dam:

a. Preparation includes power washing surface, removing asperities and repairing voids in concrete.

2. Attaching EPDM elastomeric membranes to the upstream face of the concrete dam (across contraction joints) above elevation 4888, using adhesives and temporary attachment devices for Zone 1:

a. Removal and disposal of temporary attachment devises (if applicable).

3. Underwater drilling into concrete dam for drop in anchors.

4. Fabrication and furnishing steel seal plates, anchors and miscellaneous metalwork.

5. Underwater installation of steel seal plates and EPDM sponge rubber seals (across contraction joints) to the upstream face of concrete dam below elevation 4890 for Zone 2.

6. Concrete coring and underwater installation of bottom seals in concrete dam (along contraction joints) below elevation 4870 for Zone 2.

The Government anticipates award of a firm fixed priced construction contract with one base period and two option periods, whereby each period will allow for a 9 month period of performance, (274 days for each period).

POINT OF CONTACT

The point of contact is Contract Specialist Darlene Dillon. All questions and correspondence concerning this solicitation shall be directed to her via email at ddillon@usbr.gov. To ensure all communication will be properly documented for record purposes, phone calls will not be accepted.

PROPOSAL CLOSING DATE

See Section “A”: “SOLICITATION, OFFER, AND AWARD, STANDARD FORM 1442” immediately following the “TABLE OF CONTENTS”

METHOD OF SUBMISSION OF PROPOSALS

See Section L of this Solicitation mailto:ddillon@usbr.gov

Foreward - 2

TYPE OF CONTRACT

This requirement is solicited as a “Request for Proposal (RFP) using the Federal Acquisition Regulation Sub Part 15, Contract by Negotiation Procedures. Results from this solicitation will be an anticipated award of a Firm Fixed Price Contract.

COMPETITION REQUIREMENTS

This acquisition is restricted to a Total Small Business set-aside.

RECLAMATION SAFETY AND HEALTH STANDARDS (2014) EDITION)

For information regarding the Bureau of Reclamation’s publication “RECLAMATION SAFETY AND HEALTH STANDARDS” (2014 Edition): http://www.usbr.gov/ssle/safety/RSHS/rshs.html, which is applicable to work under the anticipated contract. See Clause WBR 1452.223-81 SAFETY AND

HEALTH.

PRE PROPOSAL SITE VISIT

A pre-proposal organized site visit will be held TUESDAY, MARCH 27, 2018, at 10:00 AM MOUNTAIN (COLORADO) TIME ZONE. Prospective Offerors should make arrangement by contacting Larry Ketcham at telephone number 970-962-4510 Ex.502. Attendees are to provide and wear safety boots, hard hats, and safety vests.

SAM: Effective July 29, 2012, any contractor interested in doing business with the Government must register in the system for award management (SAM) database prior to award of a contract or agreement.

SAM is a Federal Government owned and operated FREE website that consolidates the Central Contractor Registration (CCR), the Online Representations and Certifications Application (ORCA), and the excluded parties list system (EPLS). The vendor’s DUNS and Bradstreet number and banking information are required for registration. Contractors may obtain information on registration and annual confirmation requirements via the SAM website at https://www.sam.gov/portal/public/sam or by the Federal Service Desk at telephone number 1-866-606-8220.

The Contractor's DUNS and Bradstreet number and banking information are required for registration.

Contractors may obtain information on registration and annual confirmation requirements via the SAM website, which can be accessed at https://www.sam.gov/portal/public/sam, or by telephone at the Federal Service Desk at 1-866-606-8220.

PAYMENTS: Payment requests for the anticipated contract must be submitted electronically through the U.S. Department of the Treasury’s Internet Payment Platform (IPP) System. The IPP website is https://www.ipp.gov. The contractor must use the IPP website to register, access, and use IPP for submitting requests for payment. Contractor assistance with enrollment can be obtained by contacting the IPP production helpdesk via email at ippgroup@bos.frb.org or at telephone number 1-866-973-3131.

If the contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the contractor must submit a waiver request in writing to the contracting officer with their proposal.

http://www.usbr.gov/ssle/safety/RSHS/rshs.html

Pueblo Dam Buttress Contraction Joint Treatment Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Table of Contents - 1

SECTION C - DESCRIPTION / SPECIFICATIONS

TABLE OF CONTENTS

SECTION A – Solicitation, Offer and Award, Standard Form 1442

SECTION B – Schedule

SECTION C -- Specifications

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 14 10 Use of Site 01 14 12 Work and Flow Restrictions 01 32 20 Construction Program 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 25 Marine Work 01 35 27 Underwater Work 01 35 30 Contractor’s Onsite Safety Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 56 10 Protection of Existing Installations 01 56 32 Temporary Safety Fence 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 60 00 Product Requirements 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents

DIVISION 03 - CONCRETE

03 15 17 Hydrophilic Strip Waterstop 03 15 20 Sponge Rubber Seal 03 81 11 Concrete Coring 03 81 14 Concrete Surface Preparation and Repair

DIVISION 05 - METALS

05 50 10 Steel Seal Plates

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Table of Contents - 2

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 13 50 Elastomeric Membrane (EPDM) Waterproofing

DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS

51 00 00 Information Available to Offerors 51 00 11 Leakage Data 51 00 12 Reservoir Data 51 00 90 Photographs

DIVISION 52 - DRAWINGS

52 00 00 Drawings

SECTION D – Packaging and Marketing Not Used

SECTION E – Inspection and Acceptance E.1 Material and Workmanship…………………………………………………E-1 E.2 Inspection and Construction ………………………………………………. E-1 E.3 Warranty of Construction …………………………………………..……... E-2

SECTION F – Deliveries or Performance F.1 Commencement, Prosecution, and Completion of Work ………………… F-1 F.2 Liquidated Damages – Construction ……………………………………..... F-1 F.3 Time Extensions ……………………………………………………………F-1 F.4 Variation in Estimated Quantity ………………………………………....... F-1 F.5 Suspension of Work ……………………………………………………...... F-2

SECTION G – Contract Administration Data G.1 Authorities and Delegations ……………………………………………….. G-1 G.2 Electronic Invoicing and Payment Requirements – Invoice Processing

Platform (IPP) ……………………………………………………………... G-2 G.3 Notice to Contractors – Contractor Performance Assessment Reporting

System ……………………………………………………………………... G-2

SECTION H – Special Contract Requirements H.1 Site Security ……………………………………………………………….. H-1

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Table of Contents - 3

PART II – CONTRACT CLAUSES

SECTION I – Contract Clauses I.1 Clauses Incorporated by Reference………………………………………... I-1 I.2 Commercial and Government Entity Code Maintenance………………….. I-3 I.3 Basic Safeguarding of Covered Contractor Information Systems………..... I-4 I.4 Order of Precedence – Uniform Contract Format ………………………….I-5 I.5 Option for Increased Quantity – Separately Priced Line Item……...……… I-6 I.6 Minimum Wages Under Executive Order 13658 …………………………..I-6 I.7 Estimate of Percentage of Recovered Material Content for EPA

Designated Items……………………………………………………………I-10 I.8 Buy American – Construction Materials Under Trade Agreements ……..... I-10 I.9 Bid Guarantee …………………………………………………………....... I-14 I.10 Additional Bond Security ………………………………………………..... I-15 I.11 Performance and Payment Bonds – Construction ………………………… I-15 I.12 Payments under Fixed-Price Construction Contracts……………………… I-16 I.13 Prompt Payment for Construction Contracts…….………………………… I-19 I.14 Performance of Work by the Contractor …………………………………...I-26 I.15 Differing Site Conditions …………………………………………………. I-26 I.16 Physical Data …………………………………………………………….... I-27 I.17 Accident Prevention ……………………………………………………….. I-27 I.18 Specifications and Drawings for Construction Alternate II ……………….. I-28 I.19 Changes …………………………………………………………………..... I-29 I.20 Authorized Deviations in Clauses ………………………………………..... I-30 I.21 Restriction on Endorsements – Department of the Interior …………….…. I-30 I.22 Release of Claims – Department of the Interior …………………………... I-30 I.23 Examination of Records by the Department of the Interior ……………….. I-30 I.24 Liability Insurance – Department of the Interior ……………………...…... I-30 I.25 Incorporation of Technical Proposal ……………………………………..... I-31 I.26 Employment Verification …………………………………………………..I-31 I.27 Asbestos-Free Warranty ……………………………………………………I-31 I.28 Safety and Health – Bureau of Reclamation …………………………...….. I-32 I.29 Protecting Federal Employees and the Public from Exposure to

Tobacco Smoke in the Federal Workplace – Bureau of Reclamation …….. I-32 I.30 Hazardous Substances …………………………………………………....... I-33 I.31 Nonconforming Hazardous Materials ……………………………………... I-33 I.32 Preservation, Packaging, Packing, Marking, and Labeling of

Hazardous Materials (HAZMAT) for Shipments …………………………. I-34 I.33 Certification of Representatives for Corporate Sureties—Bureau of Reclamation …………………………………………………………….. I-35 I.34 Equipment Ownership and Operating Expense – Bureau of

Reclamation ……………………………………………………………….. I-35 I.34 Equipment Ownership and Operating Expense—Bureau of Reclamation… I-35 I.35 Limitation of Funds ……………………………………………………….. I-37 I.36 Payment for Mobilization and Preparatory Work – Alternative 1 ………… I-38 I.37 Other Invoice Requirements ………………………………………………. I-40 I.38 Payment for Technical Data ………………………………………………..I-41

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Table of Contents - 4

I.39 Claims Accounting – Bureau of Reclamation …………………………….. I-41 I.40 Other Contracts (Deviation) ………………………………………...….…. I-41 I.41 Preservation of Cultural Resources-Bureau of Reclamation . . ................... I-41 I.42 Security Requirements—Bureau of Reclamation ……………….…………I-43 I.43 Modification Proposals – Alternative IV …………………………………. I-51

PART III – DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

SECTION J – Documents, Exhibits and Other Attachments General Decision Number CO180012, dated January 1, 2018 Standard Form 24 – Bid Bond Past Performance Questionnaire Subcontracting Percentage Worksheet

PART IV – REPRESENTATIONS AND INSTRUCTIONS

SECTION K – Representations, Certifications and Other Statements of Offerors

K.1 Annual Representations and Certifications ................................................... K-1 K.2 Information Regarding Responsibility Matters ………………………….... K-4 K.3 Certification Regarding Tax Matters …………………………………….... K-5

SECTION L – Instructions, Conditions and Notices to Bidders

L.1 System for Award Management ................................................................... L-1 L.2 Commercial and Government Entity Code Reporting................................... L-2 L.3 Alternative Line Item Proposal …………………………………………..... L-3 L.4 Availability of Specifications Listed in the GSA Index of Federal

Specifications, Standards and Commercial Item Descriptions, FPMR Part 101-29 ……………………………………………………….... L-3

L.5 Availability of Specifications, Standards, and Data Item Descriptions Listed in the Acquisition Streamlining and Standardization Information System (ASSIST) ..........................................................................................L-4

L.6 Submission of Offers in the English Language ............................................ L-4 L.7 Submission of Offers in U.S. Currency ........................................................ L-4 L.8 Instructions to Offerors – Competitive Acquisition ..................................... L-4 L.9 Requirements for Certified Cost or Pricing Data and Data Other Than

Certified Cost or Pricing Data …………………………………………… L-8 L.10 Type of Contract …………………………………………………………... L-9 L.11 Construction Wage Rate Requirements—Secondary Site of the Work…… L-10 L.12 Notice of Requirement for Affirmative Action to Ensure Equal

Employment Opportunity for Construction ……………………………….. L-10

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Table of Contents - 5

L.13 Subcontractor Responsibility Matters Regarding Compliance with Labor Laws ……………………………………………………………....... L-11

L.14 Notice of Buy American Requirement—Construction Materials Under Trade Agreements ......................................................................................... L-12

L.15 Site Visit (Construction) Alternate I.............................................................. L-13 L.16 Preparation of Proposals – Construction........................................................L-13

L.17 Authorized Deviations in Provisions ………………………………….…... L-13 L.18 Use and Disclosure of Proposal Information—Department of the

Interior ……………………………………………………………………...L-14 L.19 Source Evaluation and Selection Procedures – Bureau of Reclamation...….L-15 L.20 General Proposal Instructions – Bureau of Reclamation…...........................L-17 L.21 Technical Proposal Instructions – Bureau of Reclamation…………………L-18 L-22 Pricing Proposal Instructions – Bureau of Reclamation.....………………... L-19 L-23 Service of Protest -- Department of the Interior (Jul 1996)(Deviation) …... L-20 L-24 Notice of Proposed Partnering – Bureau of Reclamation …………………. L-21 L.25 Instruction for Mobilization and Preparatory Work Schedule Line Item …. L-21

SECTION M – Evaluation Factors for Award M.1 Evaluation of Options Exercised at Time of Contract Award……………....M-1 M.2 Evaluation Factors for Award – Quality Predominance—Bureau of Reclamation ………………………………………………………….......M-1 M.3 Notice of World Trade Organization Government Procurement

Agreement Evaluations—Bureau of Reclamation ………………………….M-5

END OF CONTENTS

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Table of Contents - 6

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

PART I -- THE SCHEDULE

This Page Intentionally Left Blank

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0040356345

Bureau of Reclamation

Great Plains Region

Regional Office PO Box 36900

R60

Billings MT 59107

8. ADDRESS OFFER TO

DOI Bureau of Reclamation 2021 4th Ave North Billings, MT 59101 Attn: GP-5000 Gerri Voto-Braun, Contracting Officer

Darlene Dillon 406-247-7820

1x 02/14/2018

140R6018R0003

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Pueblo Dam -- Buttress Contraction Joint Treatment, Fryingpan-Arkansas Project, Colorado

The estimated overall price range for this work, which is inclusive of Schedule A, Optional Schedule B, and Optional Schedule C, is more than $10,000,000 U.S. Dollars.

The set-aside for this solicitation is Total Small Business.

The North American Industrial Classification Code is 237990 Other Heavy and Civil Engineering.

The Small Business Size Standard is $36.5 Million.

Proposals will be received at the Bureau of Reclamation Great Plains Regional Office, at the address identified in Blocks 7 and 8 above. Individuals delivering proposals in person are required to present a valid identification and shall allow adequate time to pass through security.

Taxpayer Identification Number: _______________________________________________ Data Universal Numbering System: ______________________________________________ Commercial and Government Entity Code: _______________________________________

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See Paragraph F.1.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 274 calendar days and complete it within ________________ ________________ calendar days after receiving

04/16/2018

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time

__160_________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected .

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

Bureau of Reclamation Great Plains Region

Regional Office PO Box 36900

R60

Billings MT 59107

Gerri Voto-Braun

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

The Invoice Processing Platform https://www.ipp.gov

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140R6018R0003

00010

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Pueblo Dam -- Buttress Contraction Joint Treatment

- Schedule A (See CLINS 1-6)

Pueblo Dam Buttress Contraction Joint Treatment

- Optional Schedule B (See CLINS 1-6)

Pueblo Dam Buttress Contraction Joint Treatment

- Optional Schedule C (See CLINS 1-6)

AU1 $____________

00020

00030

1 AU $____________

1 AU $_______________

SECTION B – PRICE SCHEDULE

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Schedule B - 1

CONTINUATION OF

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

Pueblo Dam Buttress Contraction Joint Treatment

Fryingpan-Arkansas Project Colorado

B.1 SCHEDULE(S)

(a) Offers will be considered for award on the following Price Schedules, but no offer will be considered for award on only a part of the Price Schedules.

(1) Offerors shall complete Price Schedules A, B, and C.

(2) Offers will be evaluated based on the total of Price Schedules A, B, and C.

(3) Price Schedules B, and C are optional price schedules.

(4) The Government reserves the right to exercise optional Price Schedule B up to one (1) year following the completion of contraction joint 9-10.

(5) The Government has determined that if optional Price Schedule B is not awarded, the Government will not award optional Price Schedule C.

(6) The Government reserves the right to exercise optional Price Schedule C any time during the year following the date optional Price Schedule B was exercised.

(b) Offers are subject to the terms and conditions of this solicitation.

(c) Quantities in the Price Schedules are estimated quantities for comparison of offers only.

Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated Quantity, does not apply to lump sum items.

(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.

(e) Definitions:

(1) Schedule A – Includes contraction joints between buttresses, 6-7, 9-10, 17-18, and 18-19.

(2) Schedule B – Includes contraction joints between buttresses 12-13, 13-14, 14-15, 15-16, 16-17, 19-20, 20-21.

Schedule

B - 2

(3) Schedule C – Includes contraction joints between buttresses 3-4, 4-5, 5-6, 7-8, 8-9, 10-11, 11-12.

(4) Zone 1 – Upstream concrete dam face, along buttress contraction joints from elevation 4888.00 up to 4921.75 on non-overflow buttresses, and from elevation

4888.00 up to and across ogee spillway crest 5-feet downstream from formed drain access cover on overflow buttresses.

(5) Zone 2 – Upstream concrete dam face, along buttress contraction joints from elevation 4890.00 down to foundation fillet or embankment contact (elevation varies) on both non-overflow and overflow buttresses.

(6) CLIN – Contract Line Item Number.

(7) Fiscal Year – Federal Fiscal Year, beginning October 1, through September 30.

PRICE SCHEDULE A

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

1 WBR

1452.232 -81

Mobilization and Preparatory Work

For the lump sum of $

2 03 15 17 Furnish and Install Bottom Seals

8 each $ $

3 03 81 14 Concrete Surface Preparation (Zone 1 and Zone 2)

1,800 ft2 $ $

4 03 81 14 Concrete Repair (Zone 1 and Zone 2)

40 ft2 $ $

5 05 50 10 Furnish and Install Zone 2 Seal Assemblies

480 lin-ft $ $

6 07 13 50 Furnish and Install Zone 1 Seal Assembly

138 lin-ft $ $

TOTAL FOR PRICE SCHEDULE A $_________________

B - 3

OPTIONAL PRICE SCHEDULE B

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

1 WBR

1452.232 -81

Mobilization and Preparatory Work

For the lump sum of $

2 03 15 17 Furnish and Install Bottom Seals

14 each $ $

3 03 81 14 Concrete Surface Preparation (Zone 1 and Zone 2)

3,000 ft2 $ $

4 03 81 14 Concrete Repair (Zone 1 and Zone 2)

72 ft2 $ $

5 05 50 10 Furnish and Install Zone 2 Seal Assemblies

820 lin-ft $ $

6 07 13 50 Furnish and Install Zone 1

210 lin-ft $ $

TOTAL FOR OPTIONAL PRICE SCHEDULE B $_________________

B - 4

OPTIONAL PRICE SCHEDULE C

CLIN Section Supplies or Services Quantity and Unit

Unit Price

Amount

1 WBR

1452.232 -81

Mobilization and Preparatory Work

For the lump sum of $

2 03 15 17 Furnish and Install Bottom Seals

14 each $ $

3 03 81 14 Concrete Surface Preparation (Zone 1 and Zone 2)

2,800 ft2 $ $

4 03 81 14 Concrete Repair (Zone 1 and Zone 2)

68 ft2 $ $

5 05 50 10 Furnish and Install Zone 2 Seal Assemblies

760 lin-ft $ $

6 07 13 50 Furnish and Install Zone 1

210 lin-ft $ $

TOTAL FOR OPTIONAL PRICE SCHEDULE C $_________________

TOTAL FOR PRICE SCHEDULES A, B, and C $_________________

END OF SECTION

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

SECTION C

THE SPECIFICATIONS

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Summary of Work 01 11 00 - 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.01 LOCATION

A. Work is located at Pueblo Dam, located approximately 8 miles west of Pueblo, Colorado, in Pueblo County.

1.02 PRINCIPAL COMPONENTS OF WORK

A. The principal components of work to be performed under these specifications on the contraction joints between the buttresses 9-10, 6-7, 17-18, 18-19, 12-13, 13-14, 14-15, 15-16, 16-17, 19-20, 20-21, 3-4, 4-5, 5-6, 7-8, 8-9, 10-11, and 11-12, (18 joints total), include the following:

1. Preparation of concrete surfaces above and below the reservoir water surface (RWS) along the upstream face of the concrete dam:

a. Preparation includes power washing surface, removing asperities and repairing voids in concrete.

2. Attaching EPDM elastomeric membranes to the upstream face of the concrete dam (across contraction joints) above elevation 4888, using adhesives and temporary attachment devices for Zone 1:

a. Removal and disposal of temporary attachment devises (if applicable).

3. Underwater drilling into concrete dam for drop in anchors.

4. Fabrication and furnishing steel seal plates, anchors and miscellaneous metalwork.

5. Underwater installation of steel seal plates and EPDM sponge rubber seals (across contraction joints) to the upstream face of concrete dam below elevation 4890 for Zone 2.

6. Concrete coring and underwater installation of bottom seals in concrete dam (along contraction joints) below elevation 4870 for Zone 2.

1.03 SPECIFICATIONS REQUIREMENTS

A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.

B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.

C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within the sentence or phrase.

Summary of Work

01 11 00 - 2

1.04 DEFINITIONS

A. When the specifications use a word or term defined in the Federal Acquisition Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.

1.05 ACRONYMS

A. The following acronyms apply to specifications Divisions 1 through 52:

1. CO: Contracting Officer.

2. COR: Contracting Officer’s Representative.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

Use of Site 01 14 10 - 1

SECTION 01 14 10

USE OF SITE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR):

1. Cleaning Manual-2012 Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition

Available online at:

http://www.usbr.gov/mussels/prevention

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:

1. For each Contractor use site on Government land:

a. Show use location and extent of impact. Uses include but are not limited to the following:

1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.

2) Parking areas, temporary roads, and haul routes.

3) Utilities including air, power, and water lines; fire hydrants; and compressor station.

4) First-aid and medical facilities.

5) Areas for processing, storing, and disposing of waste materials from construction operations.

6) Temporary fences.

b. Describe methods to preserve, protect, and repair if damaged, vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to the jobsite, which are not to be removed and which do not http://www.usbr.gov/mussels/prevention http://www.usbr.gov/mussels/prevention

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Use of Site 01 14 10 - 2 interfere with the work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.

c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near the jobsite.

d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.

2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.

C. RSN 01 14 10-2, Schedule for Contractor Use of Reservoir and Boat Ramps:

1. Submit schedule of dates for accessing the boat ramps.

1.04 PROJECT CONDITIONS

A. Government land as shown on drawings may be used for required construction facilities.

B. Use of existing boat ramps and reservoir access shall be coordinated with Government Agencies (Colorado Parks and Wildlife, and Bureau of Reclamation), prior to use.

C. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.

D. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of the COR.

E. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.

F. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by the COR.

G. Use of campground areas for housing by Contractor employees is not allowed.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 CLEANING

A. Construction Equipment and Watercraft:

1. Before bringing on site, clean construction equipment and watercraft to remove dirt, vegetation, other organic material, and mussels to prevent introduction of noxious weeds, and invasive plant and animal species.

01 14 10 - 3

2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in USBR Cleaning Manual.

3. The COR will inspect construction equipment following procedures described in USBR Cleaning Manual before allowing the equipment on site.

4. Contractor shall comply with all Colorado Parks and Wildlife regulations on site.

3.02 RESTORATION

A. Restore Contractor use areas to pre-construction condition.

01 14 10 - 4

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Work and Flow Restrictions 01 14 12 - 1

SECTION 01 14 12

WORK AND FLOW RESTRICTIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedules for other items of work.

1.02 WORK AND FLOW RESTRICTIONS

A. The Contractor shall fully complete work on contraction joint 9-10 prior to beginning work on any other contraction joints. All Zone 1 and Zone 2 seal assemblies shall be installed, including bottom seals.

B. Pueblo Reservoir and Park are open to the public for boating, camping and fishing year round. The Lake Pueblo Park is open to the public 24 hours a day throughout the year and accessed by Thatcher Blvd. (Hwy 96), or Nichols Road (South and North entrances to park). A lighter volume of public activity is anticipated to and from the Pueblo Reservoir and State Park during the winter season than what occurs during summer season.

C. The “Annual Operating Plan” for the Fryingpan-Arkansas Project, which includes Pueblo Reservoir, is prepared each year by the Pueblo Dam Field Office Water Scheduling Staff.

In this annual report the previous year’s operations are reviewed and documented. These operating plans usually indicate that Pueblo Reservoir’s content will be at its lowest level near the end of September. Normally, Pueblo Reservoir’s storage content will be at its highest level in April or May. Pueblo Reservoir’s storage content decreases as the irrigation demand increases during the summer.

D. Continuous operation of Reclamation’s facilities, other utilities, and roadways are of critical importance during construction. The Contractor is required to schedule and conduct construction activities to enable existing facilities to operate continuously.

Under no circumstances will the Contractor be allowed to proceed with work affecting a facility’s operation without obtaining advanced approval from the COR.

E. The following operational data presented below is approximate, and releases will vary from month to month and year to year depending on multiple factors. A better estimation of expected and real time flow releases can be provided to the Contractor by the Pueblo Dam Field Office Water Scheduling Group once the time and duration of the underwater work has been determined.

1. River Outlet Works and Spillway Outlet Works: Water deliveries to the Arkansas River are made year round through the River Outlet Works and Spillway Outlet Works. Releases are also made year round to the Southern Delivery System

Work and Flow Restrictions

01 14 12 - 2

(SDS), through the River Outlet Works intake. The River Outlet Works intake structure is located on buttress No. 16. The Spillway Outlet Works intake structures are located on buttress No.’s 9, 11 and 13.

a. Yearly Average Flow (from 1996 to present) = 518 ft3/s.

b. Yearly Average Maximum Flow (from 1996 to present) = 3,250 ft3/s.

c. Maximum Recorded Flow (from 1996 to present) = 5,832 ft3/s.

1) Flow rates can vary month to month and year to year based on snow pack, delivery requirements, storm events and other factors.

2) Historically, the maximum yearly flow rates occur in the spring months.

2. South Outlet Works: Municipal water deliveries are made year round through the South Outlet Works multi-level intake structure located on buttress No. 7.

a. Yearly Average Flow (from 2002 up to 2009) = 104 ft3/s.

1) Flow rates vary month to month and year to year dependent upon demand.

2) Historically, the maximum yearly flow rates occur in the spring and summer months.

3. Fish Hatchery Outlet Works: Water deliveries to the fish hatchery located immediately downstream from Pueblo Dam are made year round through the Fish Hatchery multi-level intake structure located on buttress No. 8.

a. Yearly Average Flow (from 2002 to present) = 28 ft3/s.

b. Yearly Average Maximum Flow (from 2002 to present) = 35 ft3/s.

c. Maximum Recorded Flow (from 2002 to present) = 46 ft3/s.

1) Flow rates vary month to month and year to year dependent upon hatchery requirements.

2) Historically, the flow rates are highest in the summer months.

4. Bessemer Ditch Outlet Works: Irrigation water deliveries are made through the Bessemer Ditch Outlet Works intake structure located on the right embankment dam. The Bessemer Ditch typically only operates during the spring months (March and April). Flow rates shown below are taken only from months operating.

a. Yearly Average Flow (from 1996 to present) = 85 ft3/s.

b. Yearly Average Maximum Flow (from 1996 to present) = 238 ft3/s.

c. Maximum Recorded Flow (from 1996 to present) = 286 ft3/s.

F. Historical reservoir elevation data, and reservoir elevation exceedance curves are included in Section 51 00 11 - Leakage Data.

01 14 12 - 3

G. The maximum historic reservoir elevation to date at Pueblo Dam is 4888.35. The spillway crest elevation is 4898.7. The spillway is an uncontrolled ogee crest overflow spillway, and has never operated since construction of Pueblo Dam.

H. Flood operations at Pueblo Dam vary during the year, and are subject to change based on expected inflow and reservoir elevation. Typically, when the reservoir elevation exceeds the top of seasonal conservation, and/or when the total discharge downstream from Pueblo Dam is approximately 6,000 cubic feet per second, the reservoir enters flood operations. The top of seasonal conservation pool from April 15 through October 31 is El. 4880.38, and from November 1 through April 14 is El. 4893.80.

1. Reservoir Elevation and Reservoir Work Restrictions (below water and boat or barge work):

a. The Contractor is not allowed to perform reservoir work when the reservoir is in flood operations, unless otherwise approved by the CO.

b. Reservoir work includes: all work performed below the reservoir water surface (diving operations), including work from boats, barges or other floating work platforms.

2. Reservoir Elevation and Dam Work Restrictions (above water work).

a. The Contractor is not allowed to perform dam work when the reservoir is in flood operations, unless otherwise approved by the CO.

b. Dam Work includes: work performed above water including work performed from the top of dam and platforms supported by the dam.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

01 14 12 - 4

Construction Program

01 32 20 - 1

SECTION 01 32 20

CONSTRUCTION PROGRAM

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Developing Baseline Schedule: Include in lump sum prices offered in the Price Schedules for mobilization and preparatory work.

2. Updating and Using Construction Program: Include as an element of Contractor’s overhead.

1.02 DEFINITIONS

A. Schedule: The Critical Path Method (CPM) of planning and scheduling a construction project where activities are arranged based on activity relationships and network calculations determine when activities can be performed and the critical path of the project.

B. Project Calendar(s): Cross reference of numerical work days with calendar days. The project calendar serves as the basis for the day/date conversion and assigns work days and non-workdays.

1.03 REFERENCE STANDARDS

A. Associated General Contractors of America (AGC):

1. AGC Manual-04 Construction Planning and Scheduling Manual

1.04 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals:

1. Furnish database files in format compatible with Oracle Primavera P6 Professional Project Management (release 6.2 or newer) or Microsoft Project (release 2010 or newer).

2. Furnish schedule and analysis data on CD-ROM disc.

3. Upon request, provide information and data used to develop and maintain the Construction Program to the CO.

B. RSN 01 32 20-1, Baseline Schedule:

1. Include:

a. Construction Program/Schedule database.

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Construction Program 01 32 20 - 2

b. Definition of project calendars.

c. Gantt chart (Bar chart) for project.

d. Activity report including all logic constraints consisting of predecessors, successors, and constraint dates.

C. RSN 01 32 20-2, Updated Schedule:

1. Include:

a. Construction Program database with updated activity and milestone data.

b. Definition of project calendars if revised from baseline calendars.

c. Gantt chart for project.

d. Narrative report specifically stating status of project.

1) If negative float exists, cite specific actions and conditions which caused the "behind schedule" condition and provide proposed course of action to complete the project within the specified delivery time.

2) List of Contractor-initiated changes to the current schedule stating the reason for the action taken and any unresolved issues relating to the Construction Program. Government reserves the right to reject Contractor-initiated changes to the current schedule which negatively impact any Government action which was initiated on the basis of the current schedule.

1.05 SCHEDULE

A. Develop, maintain, and use approved Construction Program to plan, monitor, report, and evaluate accomplishment of work.

B. Prepare construction schedules using Critical Path Method outlined in AGC Manual.

C. Failure to include any element of the work will not release Contractor from completing all required work under the contract.

D. Construction Program:

1. Prepare detailed activity network for accomplishing required work organized by work breakdown structure.

2. Prepare schedule based on required sequence and interdependence of activities.

3. Include work of subcontractors, Government interfaces, and contract milestones.

4. Include contract title, contract number, and Contractor's name on each sheet.

5. Adjust Construction Program/schedule for seasonal weather conditions.

6. Define activities to a level of detail resulting in their durations being no greater than 20 workdays unless otherwise accepted by CO.

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Construction Program 01 32 20 - 3

a. Durations for administrative activities (e.g., submittals and reviews, fabrication, manufacturing), or other specific activities identified in the contract will not be subject to the workday limitation.

7. Use durations in units of whole workdays.

8. Include activities for Government reviews and approvals of submittals that are critical to the project completion data.

9. Update schedule with changes directed by contract modifications or approved changes to sequencing.

E. Baseline Schedule:

1. Represents Contractor’s as-planned approach to accomplishing the work.

2. Include planned start and completion dates for features of work.

F. Updated Schedule:

1. Enter actual progress.

2. Assign a unique project file name for each schedule update.

G. Contract Change or Delay:

1. Submit a time impact evaluation within 14 days of contract change or delay, showing effects of change order or delay on the progress schedule.

2. Time extensions for performance will be considered only to the extent that the Contractor’s current scheduled milestone dates exceed the contract milestone dates.

H. Float is not for the exclusive use by or benefit of either the Government or the Contractor.

I. If in the opinion of the CO, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the CO:

1. The CO may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

2. Costs for actions required to improve progress will be the responsibility of the Contractor.

1.06 FAILURE TO COMPLY

A. Failure to comply with the requirements of this section shall be grounds for a determination by the CO that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the specified time.

Construction Program

01 32 20 - 4

B. The CO may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Submittals 01 33 00 - 1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedules for other items of work.

1.02 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME Y14.1-2005(2010) Decimal Inch Drawing Sheet Size and Format

B. National Institute of Building Sciences (NIBS)

1. NIBS NCS-2011 United States National CAD Standards, Version 5

1.03 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

1.04 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.

B. General:

1. Prepare in English.

2. Label with contract number and title and RSN.

3. Measurement Units: US Customary Units.

C. Drawings:

1. Minimum Identification in Title Block:

a. Contract number and title.

b. Contractor’s or supplier’s title and drawing number.

c. Date.

2. Reserve 3- by 3-inch space next to title block for review stamps.

Submittals

01 33 00 - 2

3. Print Size: D size (22 inches by 34 inches).

4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.

a. Computer drafted drawings:

1) In accordance with NIBS NCS.

2) Electronic file format: Compatible with AutoCAD, Version 2013 or later.

3) Compile using “eTransmit” utility in AutoCAD.

b. Drawing prepared with drafting equipment, when allowed: Lettering shall be neat.

5. Drawings Designated as “Government Format” in Specifications:

a. Computer drafted.

b. Government will provide electronic AutoCAD format template.

c. Title block and sheet format:

1) As shown on Standard Drawing 40-D-7102.

2) Government will supply template.

3) Government will supply specific title block information to be used.

6. Final Drawings:

a. Computer drafted.

b. Government will supply electronic AutoCAD format template.

c. Show as-built changes, including revision dates, made during installation.

Indicate changes by clouding.

7. Electronic Files: On CD or DVD discs.

D. Samples Submittals:

1. Label with complete manufacturer's product and color identification.

2. Include type and quantity of materials specified in the referenced section in each “set” of samples.

3. Samples: Representative of product to be installed.

4. Label each sample, sample kit with contract number and title.

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Submittals 01 33 00 - 3

E. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

a. Identify manufacturer's name, type, model, size, and characteristics.

b. Illustrate that product or equipment meets requirements of specifications.

c. Mark items to be furnished in a manner that will photocopy (no highlighter).

d. Strike through items that do not apply.

F. Certifications:

1. Certifications by a registered professional: Signed and sealed by registered professional.

2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.

1.05 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.

B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

C. Submit sets specified in “Sets to be sent:” columns in Table 01 33 00A - List of Submittals.

1. Electronic Submittals:

a. In Portable Document Format (.pdf).

b. Include RSN transmittal letter.

c. Do not include Personally Identifiable Information (PII) in electronic submittals.

d. Submittal method (size based):

1) Government can receive e-mails up to 10 MB. Receipt of e-mails exceeding 10 MB (extra-large) may be possible. E-mailing of extra-large electronic submittals may occur only after size limit for transmittal of extra-large e-mail has been verified.

2) Electronic media for submittals too large to e-mail: CD or DVD.

D. Include the following information in transmittal letters:

1. Contract number and title.

2. RSN for each attached submittal.

Fryingpan-Arkansas Project, Colorado Solicitation No. 140R6018R0003

Submittals 01 33 00 - 4

3. Responsible code.

4. Number of sets for each RSN.

5. Identify submittal as initial or resubmittal.

E. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 7 days after receiving comments, unless otherwise directed.

4. Requirements for initial submittals apply to resubmittals.

F. Submit each RSN under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned for resubmittal.

1.06 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require 28 days for review of each submittal or resubmittal, unless otherwise specified.

2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.

B. Time in Excess of Specified:

1. CO may extend contract completion date to allow additional time for completing work affected by excess review time.

a. Rime extension will be to extent that excess review time caused delay to contract completion date.

b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.

c. Concurrent days of…

This is the start of the file's text. The full file is on GovTribe.