140R3025R0014_Attachment_2b_-_Task_Order_1_Price_Schedule_(1).xlsx
XLSX spreadsheet 15 KB Posted
- Attached to
- ROCKFALL MITIGATION HOOVER DAM - IDIQ
- Solicitation number
- 140R3025R0014
About this file
This document is a detailed Task Order 1 Price Schedule for a Rockfall Risk Mitigation project at Hoover Dam, covering the period from October 1, 2025 to September 30, 2026. The price schedule is part of an Indefinite Delivery/Indefinite Quantity (IDIQ) contract with the Department of the Interior Bureau of Reclamation, solicitation number 140R3025R0014. The comprehensive pricing breakdown includes four main sections: labor/crew rates, equipment costs, materials/activities, and mobilization/demobilization, with multiple line items for rope access crews, rock bolts, mesh, anchors, drilling equipment, support vehicles, and specialized mitigation materials. Currently, all unit rates are listed as $0.00, suggesting this is a template or preliminary pricing document pending final negotiation, with line items covering initial site inspection, night work, various rock bolt diameters, mesh installation, cable/rope work, and specialized rockfall mitigation equipment and materials.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Task Order 1
| Task Order 1 - Hoover Rockfall Mitigation | ||||||
| Unit rates based on Rockfall Risk Mitigation - IDIQ Schedule 1 (October 1, 2025 - September 30, 2026) | ||||||
| Item | Description | Comments | Quantity | Unit | Unit Rate | Total |
| 1-1 | Rope Access Crew - Day | Initial site inspection and set up | 8 | Crew Hrs | $0.00 | |
| 1-2 | Rope Access Crew - Night | 548 | Crew Hrs | $0.00 | ||
| 1-3 | 1 1/4" Diameter Rock Bolts | 112.0 | LF | $0.00 | ||
| 1-4 | 2" Diameter Rock Bolts | 220 | LF | $0.00 | ||
| 1-5 | 3mm Mesh | 989 | SF | $0.00 | ||
| 1-6 | 1/2" Diameter Stainless Steel Cable/Rope | 140 | LF | $0.00 | ||
| 1-7 | Anchors | 76 | EA | $0.00 | ||
| 1-8 | Rockfall Barrier System | 0 | LF | $0.00 | ||
| Sub Total | $0.00 |
| Item | Equipment Description | Number of Units | Quantity | Unit | Unit Rate | Total |
| 2-1 | Drill Rig-Wagon Drill (DTHH). Used to drill 2-in dia., 20-ft. long rock bolts and in areas with multiple bolts. | 1 | 22 | DAY | $0.00 | |
| 2-2 | Drill Rig- Hand Drill. Used to drill anchors and 1 1/4" dia. rock bolts. | 2 | 37 | DAY | $0.00 | |
| 2-3 | Grout Mixer and Pump | 1 | 22 | DAY | $0.00 | |
| 2-4 | Compressor (includes fuel; 5.5 gal/hr) | 1 | 55 | DAY | $0.00 | |
| 2-5 | Testing/stressing Equipment | 1 | 5 | DAY | $0.00 | |
| 2-6 | Rope Access Equipment (4 sets) | 4 | 55 | DAY | $0.00 | |
| 2-7 | Pick Up Truck | 2 | 55 | DAY | $0.00 | |
| 2-8 | Rubble Trailer | 1 | 55 | DAY | $0.00 | |
| 2-9 | Trailer (Flat Deck) | 1 | 55 | DAY | $0.00 | |
| 2-11 | Light Tower (includes fuel; 1.2 gal/hr) | 2 | 55 | DAY | $0.00 | |
| 2-12 | Telehandler Forklift 40' reach, 7000lb. with drill mast | 1 | 55 | DAY | $0.00 | |
| 2-13 | Telehandler Forklift (small, utility) | 1 | 55 | DAY | $0.00 | |
| 2-14 | Skidsteer | 0 | 55 | DAY | $0.00 | |
| 2-15 | ATV | 1 | 55 | DAY | $0.00 | |
| 2-16 | Portable Generator (includes fuel; 1 gal/hr) | 1 | 55 | DAY | $0.00 | |
| 2-17 | Rigging / Lifting Equipment | 1 | 55 | DAY | $0.00 | |
| Sub Total | $0.00 |
| Item | Other Materials/Activities Description | Quantity | Unit | Unit Rate | Total |
| 3-1 | Geobrugg Spike Plate | 58 | EA | $0.00 | |
| 3-2 | Temporary Rockfall Protection and Pedestrian Control (Fencing and Barricades) | 1 | EA | $0.00 | |
| 3-3 | Debris Removal (scaled material) | 55 | Crew Hrs | $0.00 | |
| Sub Total | $0.00 |
Sub Total $0.00
| Item | Mobilization/Demobilization | Quantity | Unit | Unit Rate | Total |
| 4-1 | Mobilization | 1 | EA | $0.00 |
Total $0.00