Questions_and_Answers_0001.pdf

PDF 153 KB Posted

Attached to
Archimedes pump construction for Topock Federal contract opportunity
Solicitation number
140R3024R0028
Issued by
Department of the Interior Bureau of Reclamation

About this file

This document contains Questions and Answers related to Solicitation No. 140R3024R00 for the construction of a 60 cfs pumping station. The solicitation is seeking offers for a firm fixed price contract, with an estimated magnitude between $10,000,000 and $15,000,000. Key details include: there is no power available at the site currently, but power lines may be installed at a later time; there are endangered species, such as the northern Mexican garter snake, that contractors must be aware of; normal work hours are from sunup to sundown, but exceptions can be granted for certain activities; the Superintendent, SSHO, and QC Manager positions can be held by the same individual as long as they meet the specified qualifications; the period of performance may be extended based on material/equipment lead times; and soil boring reports are available. The solicitation will be issued unrestricted, with a NAICS code of 237990 and a corresponding $45M small business size standard.

View the file

Other files for this federal contract opportunity

Other files attached to Archimedes pump construction for Topock, newest first.
File Type Posted
Questions_and_Answers_0008.pdf PDF
Sol_140R3024R0028_Amd_0008.pdf PDF
Revised_Page_M-4_0008.pdf PDF
Sol_140R3024R0028_Amd_0007.pdf PDF
Sol_140R3024R0028_Amd_0006.pdf PDF
Questions_and_Answers_0006.pdf PDF
Sol_140R3024R0028_Amd_0005.pdf PDF
Sol_140R3024R0028_Amd_0004.pdf PDF
Sol_140R3024R0028_Amd_0003.pdf PDF
Solicitation_No__140R3024R0028_Revised_Section_B_0003.pdf PDF
00_00_02_Dwgs-Amd1_TopockMarshPumpingPlant_11x17_09-05-2024_0003.pdf PDF
Specs-Amd1_TopockMarshPPFirebreakCanalPumpSta_09-05-2024_0003.pdf PDF
Sol_140R3024R0028_Amd_0002.pdf PDF
140R3024R0028_Sign_In_Sheet_0002.pdf PDF
Topock_Marsh_Pumping_Plant_Geotechnical_Report_2022_Part_2_0001.pdf PDF
FAR_52_211_01_0001.pdf PDF
Topock_Marsh_Pumping_Plant_Geotechnical_Report_2022_Part_3_0001.pdf PDF
Sol_140R3024R0028_Amd_0001.pdf PDF
Topock_Marsh_Pumping_Plant_Geotechnical_Report_2022_0001.pdf PDF
Soil_Borings_Information_-_Topock_Marsh_2010_0001.pdf PDF
Attachment_4_Wage_Determination_AZ20240014.pdf PDF
Attachment_1_Specifications.pdf PDF
Sol_140R3024R0028.pdf PDF
Attachment_8_Map_for_Site_Visit_Location.jpg JPG image
Attachment_2_06_00_00_02_Drawings.pdf PDF
Attachment_7_Subcontracting_Plan_Template.pdf PDF
Attachment_3_00_00_02A_Dwgs-B_Geology_and_Logs.pdf PDF
Attachment_5__DI-137_Release_of_Claims.pdf PDF
Attachment_6_Past_Performance_Questionnaire.pdf PDF
Solicitation_No__140R3024R0028.pdf PDF
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. 140R3024R00

Questions & Answers

1. Is power available at the site for use during construction for tools, trailers, exct.

There is no power available at the site.

2. If power is not available, is it anticipated that power will become available at some point, and when is it anticipated that power will be available?

At some point, power lines will be installed, however it is unknown at this time if and when power will become available at the site.

3. Are there any endangered or threatened species or plants in the area that we need to watch for or be trained on?

There are species to be aware of, one being the northern Mexican garter snake. We ask that people on site check around their vehicles to avoid harming the snake.

4. What are the acceptable work hours? Will special permission be given to work off hours for items like concrete work that will want to be placed during cooler times?

Normal working hours will be from sun- up to sun-down (daylight hours). Special permission will be granted to work outside of daylight hours, and these exceptions will be considered on a case-by-case basis when submitted with advance notice in writing to the Contracting Officer and Contracting Officer’s Representative.

5. Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?

No, they do not need to be separate individuals, however in Specification 01 35 30, requirements are listed for the Contractor's Onsite Safety Representative and Onsite Safety and Health Professional. These do not necessarily need to be separate individuals, but they must meet the stated criteria (e.g., shall be qualified by virtue of education, training, certification, and experience, and acceptable to Reclamation). See 01 35 30 for more specifics. Note that the Onsite Safety Representative is to be employed full-time on the job whereas the Onsite Safety and Health Professional is listed as part-time (and typically the qualifications of this position are more stringent). Also, the authorities, duties, and responsibilities are unique to each position though there is some overlap.

6. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

Yes, the period of performance can be extended if awardee provides valid information related to material/equipment lead times.

7. Are soil boring reports available? If not, it will be assumed that excavation will be clear of rocks and obstructions.

A Topock Marsh Pumping Plant, Geotechnical Report dated 2022, is available and attached.

Soil Boring Information, Topock Marsh, dated 2010, is available and attached.

File details come from the government source that posted it. Updated .