This document contains Questions and Answers related to Solicitation 140R3024R0025 for the Hoover Dam Powerplant Station Service Replacement. The solicitation is issued by the Department of the Interior's Bureau of Reclamation.

The key issues addressed in the Q&A include:

  • Concerns from vendors that the dimensional requirements for the new switchgear are too restrictive, as they have been unable to find compliant equipment from their suppliers. The agency has indicated the new equipment must not exceed the physical size of the existing equipment.
  • Requests for more detailed drawings and dimensions of the existing switchgear lineups DSB and DSC, which the agency has not provided. The vendor states this information is needed to verify they can submit a compliant proposal.
  • The agency has revised the minimum required workspace behind the switchgear enclosure from 42" to 36".

The vendor is requesting the solicitation be amended to provide the requested equipment dimension details and modify the requirements as needed to allow vendors to submit viable proposals.

View the file

Other files

File Type Posted
Sol_140R3024R0025_Amd_0004.pdf PDF
26_16_14_-_Secondary_Unit_Substation_0004.pdf PDF
Sol_140R3024R0025_Amd_0003.pdf PDF
01_140R3024R0025_Description_Specifications_Section_26_16_14_-_Secondary_Unit_Substation_0003.pdf PDF
140R3024R0025_Questions_and_Responses_13__15__16__19__24__and_63_0003.pdf PDF
01_140R3024R0025_Description_Specifications_Section_26_05_20_-_Conductors_and_Cables_0003.pdf PDF
00_140R3024R0025_Solicitation_Section_B_0003.pdf PDF
03b_140R3024R0025_Wage_Determinations_NV20240024_dated_07192024_0003.pdf PDF
00_140R3024R0025_Solicitation_Section_J_0003.pdf PDF
03a_140R3024R0025_Wage_Determinations_AZ20240006_dated_07192024_0003.pdf PDF
Sol_140R3024R0025_Amd_0002.pdf PDF
140R3024R0025_Questions_and_Responses_01_0002.pdf PDF
Sol_140R3024R0025_Amd_0001.pdf PDF
140R3024R0025_Switchgear_Site_Visit_Sign-In_Sheet_0001.pdf PDF
02_140R3024R0025_Drawings.pdf PDF
00_140R3024R0025_Hoover_Dam_Powerplant_Station_Service_Replacement_Boulder_Canyon_Project_Solicitation.pdf PDF
06_140R3024R0025_Small-Business-Subcontracting-Plan.docx DOCX document
07_140R3024R0025_Past_Performance_Questionnaire.doc DOC document
04b_140R3024R0025_SF25_Performance_Bond.pdf PDF
05_140R3024R0025_DI-137_Release_of_Claims.pdf PDF
03a_140R3024R0025_Wage_Determinations_AZ20240006_dated_03222024.pdf PDF
03b_140R3024R0025_Wage_Determinations_NV20240024_dated_01052024.pdf PDF
04a_140R3024R0025_SF24_Bid_Bond.pdf PDF
01_140R3024R0025_Description_Specifications.pdf PDF
04c_140R3024R0025_SF25A_Payment_Bond.pdf PDF
Sol_140R3024R0025.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140R3024R0025

Hoover Dam Powerplant Station Service

RFP 140R3024R0025

Questions and Responses 03

01) We have solicited five separate switchgear vendors, and they have all declined due to the dimensional restrictions.

We have tried to communicate this issue through the question and answer process, with no relief. A question was asked if wider switchgear would be acceptable. The answer was, “the details of the proposed switchgear should be included in the proposal and is the contractor’s responsibility to ensure proper fit and function. See RFP Description of Specifications, Section 26 16 14, 1.06.” Section 26 26 14 1.06.B states, “new equipment shall not exceed the physical size of the existing equipment. Maintain a minimum of 42” of workspace between the rear of the enclosure to the grounded surface.” This would indicate a wider switchgear is NOT acceptable.

We have been unable to obtain existing dimensions for lineups DSB and DSC (208V lineups). We submitted questions requesting details showing these existing dimensions. The answers provided were “DWG #45- D-1616 and 45-D-16332” and “The footprint is to remain the same as the existing equipment, see RFP Description of Specifications, Section 26 16 14 – 26, E. See Drawing #45-D-6005 through 45-D-60011, and 45-D-16382.” Drawing 45-D-16116 is not included in the drawing set. Drawing 45-D-16116 is an unscaled general equipment arrangement drawing showing location of each switchgear, in which dimensions cannot be derived. Drawings 45-D-16332 and 45-D-16382 show details for DSA & DSD (480), but do not apply to DSB and DSC. Drawings 45-D-6005 through 45-D-60011 are single line diagrams (no dimensions).

Dimensioned details for DSB and DSC must be provided to verify a viable proposal.

We request the solicitation be amended to provide the information requested and modified as necessary to allow industry manufacturers to submit compliant proposals.

a) TOPIC: 26 16 14

b) The minimum was revised to 36”. See revised Specifications.