01_140R3024R0025_Description_Specifications.pdf
PDF 17 MB Posted
- Solicitation number
- 140R3024R0025
About this file
This document is a Description and Specifications for the Hoover Dam Powerplant Station Service Replacement, a federal contract opportunity under Solicitation Number 140R3024R0025.
The key details are:
The project is for the replacement of the station service equipment at the Hoover Dam Powerplant, which is owned and operated by the Bureau of Reclamation, a civilian agency under the Department of the Interior. The required products and services include the design, engineering, procurement, installation, testing, and commissioning of new station service transformers, switchgear, and associated equipment. The contract is for a lump sum fixed price. Responses are due by March 24, 2023, and the contract is expected to be awarded by May 31, 2023. No set-asides or socioeconomic requirements are specified. The incumbent contractor is not named.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of the Interior August 2023
Hoover Dam Powerplant Station Service Replacement
Boulder Canyon Project, Arizona, Nevada
Lower Colorado Region
Station Service Replacement Boulder Canyon Project, Arizona, Nevada Solicitation No.
Table of Contents 00 01 10 - 1
SECTION C - DESCRIPTION / SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 10 Use of Site 01 14 12 Work Restrictions 01 14 30 Interruption of Service 01 31 19 Project Management and Coordination 01 32 10 Construction Program 01 33 00 Submittals 01 33 26 Electrical Drawings and Data 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 51 00 Temporary Utilities 01 54 20 Use of Government Cranes 01 55 00 Vehicular Access and Parking 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 32 Temporary Safety Fence 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 60 00 Product Requirements 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents
DIVISION 02 – EXISTING CONDITIONS
02 82 20 Removal and Disposal of Asbestos Containing Materials 02 83 33 Recycling of Equipment with Coatings Containing Regulated Metals
DIVISION 03 – CONCRETE
03 62 20 Nonshrink Grout for Equipment and Metalwork
DIVISION 26 – ELECTRICAL
26 05 02 Basic Electrical Materials and Methods
140R3024R0025
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Table of Contents 00 01 10 - 2
26 05 04 Electrical Demolition and Removal 26 05 20 Conductors and Cables 26 05 26 Grounding and Bonding 26 05 33 Raceways and Boxes 26 05 36 Cable Trays 26 05 80 Wiring Checkout and Tests 26 16 14 Secondary Unit Substation 26 20 10 Temporary Power Equipment 26 24 16 Panelboards 26 30 36 Resistive Load Bank
DIVISION 51 – INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors 51 00 10 Hoover Photographs 51 00 20 Breaker Requirements 51 00 30 Hazardous Materials Survey and Analytical Results 51 00 50 Electronic Media Release
DIVISION 52 - DRAWINGS
52 00 00 Drawings
END OF CONTENTS
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Summary of Work 01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. Work is located approximately 8 miles northeast of Boulder City, NV at Hoover Dam Powerplant in Clark County, Nevada and Mohave County, Arizona.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Removing existing station service equipment.
1. Disconnect existing connections to station service DSA, DSB, DSC, DSD, and
DSN.
2. Unmount existing equipment from station service equipment.
3. Demolition and disposal of cabinet MSB.
a. Disconnect and relocate loads:
1) Service Water Booster Pump #1 Via MSR.
2) Service Water Booster Pump #2 Via MSQ.
4. Perform cable testing of switchgear feeder conductors.
5. Remove and dispose station service equipment.
B. Furnish and install temporary power switchboard.
1. Connect main power to temporary switchboard.
2. Provide temporary power conductors to switchgear DSA, DSD, and DSN.
3. Split conductors to provide temporary power to each switchgear feeder breakers.
4. Arrange temporary cable run for main source and feeders to DSA, DSD, and
DSN.
C. Furnish and install new station service equipment.
1. Reconnect main source and feeders to new station service equipment.
2. Add MSB loads to DSD and DSN respectively.
3. Replace failed test cables with new cables.
4. Reinstall existing equipment and cable connections to new equipment.
D. Remove temporary power switchboard.
1. Remove and dispose of temporary power switchboard conductors.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Summary of Work 01 11 00 - 2
2. Remove and provide temporary cable trays and switchboard to Hoover Dam Power Plant.
E. Remove and replace panelboards and circuit breakers.
1. Remove and dispose of existing panelboards and breakers to be replaced.
2. Remove existing feed and loads from panelboards and/or breakers to be replaced.
3. Install new panelboards in location of old ones.
4. Replace existing feeder breakers for all panelboards to be replaced.
5. Replace existing feeder breakers with new one for existing loads.
6. Reconnect existing feed and feeder loads to new panelboards and feeder breakers.
F. Remove and replace 900kW load bank.
1. Remove existing connection from load bank to 2000A bolted switchgear.
2. Remove and dispose of existing 900kW load bank from concrete pad.
3. Install new 1000kW load bank in placed.
4. Replace and/or install new conductors for new 1000kW load bank.
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.
1.04 DEFINITIONS
A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 52:
1. CO: Contracting Officer.
2. COR: Contracting Officer’s Representative.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Summary of Work 01 11 00 - 3
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Summary of Work 01 11 00 - 4
This page intentionally left blank.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Use of Site 01 14 10 - 1
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:
1. For each Contractor use site on Government land.
a. Show use location and extent of impact. Uses include but are not limited to the following:
1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.
2) Parking areas, temporary roads, and haul routes.
3) Utilities including air, power, and water lines; fire hydrants; and compressor station.
4) First-aid and medical facilities.
5) Areas for processing, storing, and disposing of waste materials from construction operations.
6) Temporary fences.
b. Describe methods to preserve, protect, and repair, vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to jobsite, which are not to be removed and which do not interfere with work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.
c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near jobsite.
d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.
2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Use of Site 01 14 10 - 2
1.03 PROJECT CONDITIONS
A. Government land as shown on drawings may be used for required construction facilities.
1. Government Project Warehouse outside area is available for Contractor use.
2. Warehouse parking area is shown on drawings.
3. Contractor to maintain own security of Contractor utilized warehouse outside area, such as use of security fencing.
B. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.
C. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of COR.
D. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.
E. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by COR.
F. Transformer deck area outside of powerplant to be used for staging of materials. Deck area is 60 feet by 8 feet.
G. Access to Floor 2 for equipment and materials is available through the hatch cover located on Floor 3. Contractor to take off the hatch cover and use the available crane for equipment and materials to be lowered to Floor 2.
1. Hatch cover dimensions: 17 feet by 8-1/2 feet.
H. Space is available inside powerplant for Contractor work and storage areas. Coordinate with COR for exact locations within powerplant for available Contractor work locations and storage areas.
I. Provide COR 72-hour advance notice of deliveries being made. Warehouse deliveries are accepted Monday – Friday, 0730 -1530, except for federal holidays.
J. Door located by secondary unit substations DSD, DSA, and DSN may be removed by Contractor.
K. Section of drop ceiling may need to be removed to be able to install new equipment.
L. Mini office located by switchgear DSC is available for Contractor use.
M. Refer to Section 01 14 12 – Work Restrictions for additional onsite requirements.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Use of Site 01 14 10 - 3
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 RESTORATION
A. Restore Contractor use areas to pre-construction condition.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Work Restrictions 01 14 12 - 1
SECTION 01 14 12
WORK RESTRICTIONS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 WORK RESTRICTIONS
A. Bureau of Reclamation operates and maintains Hoover Dam and Powerplant.
B. Maintain Government access to the Hoover Powerplant and other facilities at all times.
C. Allowable Work Hours:
1. Monday through Thursday: 7:00 a.m. to 4:30 p.m.
2. Alternate work schedules may be allowed, including Fridays, Saturdays, night work, and extended shifts with a written notice 14-working days in advance of the proposed schedule and approval by the CO. Refer to Section 01 14 30 – Interruption of Service.
D. No work will be allowed during Federal holidays or Sundays.
E. Nameplate hanging tag will be issued by Government for each Contractor onsite vehicle used. The nameplate hanging tag shall be displayed hanging inside each vehicle.
F. Display Contractor company name on driver side of each onsite vehicle used.
G. While parked on the Transformer Deck, vehicle keys shall be left in each onsite vehicle used if it is necessary to move vehicle.
H. All onsite Contractor employees to wear PIV. Contractor to obtain PIVs. Contact COR to obtain PIV.
I. Obtain required permit for work in area. Coordinate with COR for obtaining required permit.
J. Access to Work Area:
1. Contractor personnel will be allowed to move about the work area unescorted during allowable work hours.
K. Provide a list of onsite Contractor employees every work day to Government inspector.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Work Restrictions 01 14 12 - 2
L. Access to the powerplant will remain locked outside of allowable working hours.
M. Powerplant access is via the dam portal road through the tunnel. Contractor employees shall park personal vehicles in the Government warehouse area parking lot. Refer to Section 01 14 10 – Use of Site. Up to 2 contractor vehicles may park on the Transformer Deck.
N. Contractor to provide temporary lighting for Contractor work area during replacement of Switchgear DSB and DSC.
1. Coordinate with COR for optimal plant operation days and times for performing this work during equipment outage.
O. Coordinate with COR for work on AM Panel in the machine shop area.
P. Photographs of the dam, powerplant and equipment are not allowed.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Interruption of Service 01 14 30 - 1
SECTION 01 14 30
INTERRUPTION OF SERVICE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include cost in prices offered in the Price Schedules for items of work for which interruption of services are required.
1.02 SUBMITTALS
A. Submit in accordance with Section 01 33 00 – Submittals.
B. RSN 01 14 30-1, Interruption of Service Request:
1. Area where work will be done (by number or other description).
2. Outline procedures for accomplishing work including:
a. Specific safety precautions to be taken.
b. Type and location of barricades.
c. Warning signs.
d. Protective grounds and devices to be used.
3. Commencement time of work.
4. Duration of work.
5. Number of personnel and their classification.
6. Description of equipment to be used.
7. Information indicating that required materials are on site or data indicating shipping dates of materials not on site.
1.03 PROJECT CONDITIONS
A. Coordinate and schedule interruption of services with COR:
1. Coordinate work with Government operations. Schedule at least 45 days in advance of the requested interruption of service.
2. No specific interruption of service request will be considered unless:
a. COR has reasonable assurance that materials and equipment required for work will be onsite.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Interruption of Service 01 14 30 - 2
b. Contractor will be prepared to perform work on date and during period of time requested for specific interruption of service.
3. Allowable time and available interruption of service periods will govern interruption of service requests, work scheduling, onsite delivery of materials, and required drawings and data submittals.
4. Interruption of service window available to Contractor:
a. Contractor to limit the interruption of service duration to reduce the time that station service loads are de-energized.
b. Limited to the time required to cutover loads to and from switchgear and temporary power equipment, perform wiring and checkout, Government inspection and testing, or for work performed by the Government.
c. Occur on only one switchgear at a time.
d. Switchgear DSA, DSD, DSN:
1) Limited to 5 days per switchgear.
2) Government will stop power generation on specific units to accommodate Contractor-requested and approved interruption of service for Switchgear DSA, DSD, and DSN only during October 1 through April 30.
e. Switchgear DSB and DSC:
1) Loads fed from this equipment do not require a power generation outage.
2) Interruption of service for this equipment will affect the office areas.
3) Begin de-energizing equipment on Thursday evening and have loads re-energized by 6:00 am on Monday morning.
4) Notify COR by 5:00 pm on Sunday if the schedule for re-energizing the loads will not be met.
5. Interruption of service scheduling will depend upon power demand requirements, generator availability, and related operating conditions.
a. Interruption of services may be scheduled during off-peak periods, nights, or weekends.
b. Government reserves right to schedule interruption of services for any period during 24-hour day, any day of week.
c. Contractor will be informed of type of interruption of services available and restrictions prior to start of construction.
B. Cut over loads may need to be performed on weekends.
C. Time between switchgear replacements may be used for breaker replacements.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Interruption of Service 01 14 30 - 3
D. When work cannot be performed during an approved interruption of service period, notify COR that interruption of service is not required.
E. Show construction interruption of services in the construction schedule.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Interruption of Service 01 14 30 - 4
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Project Management and Coordination 01 31 19 - 1
SECTION 01 31 19
PROJECT MANAGEMENT AND COORDINATION
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS Reclamation Safety and Health Standards including revisions posted at http://www.usbr.gov/safety/rshs/index.html
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 – Submittals.
B. RSN 01 31 19-1, Pre-Design Meeting Notification:
1. Provide confirmation to COR regarding requested date and time of meeting and indicate who will be attending and affiliations.
a. Provide copies of preliminary layout drawings.
1) Include drawings and design data for switchgear, panelboards, breakers, and temporary power equipment, including connections to existing equipment and accessories.
2) The submittal response for this RSN will be 25 days after the pre-design meeting.
3) Do not resubmit this information under this submittal. After pre-design meeting submit information under applicable Section.
C. RSN 01 31 19-2, Design Coordination Conference Confirmation:
1. Provide confirmation to COR regarding requested date and time of meeting and indicate who will be attending and affiliations.
D. RSN 01 31 19-3, Design and Progress Review Meeting Notification:
1. Provide confirmation to COR regarding requested date and time of meeting and indicate who will be attending and affiliations.
2. Schedule of future Design and Progress Review Meetings.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Project Management and Coordination 01 31 19 - 2
E. RSN 01 31 19-4, Daily Work Report.
1.04 PROJECT COORDINATION
A. The following meetings are considered significant, but do not relieve the Contractor from the responsibility of attending other meetings required by the specifications. The Preconstruction Conference described in clause 52.236-26 is a separate meeting requirement from the meetings in this section.
1. Pre-Design Meeting:
a. Date: No later than forty-five (45) days after receipt of Notice to Proceed and prior to performing any work on the required RSNs for the equipment listed below:
1) Switchgear.
2) Temporary Power
3) Panelboards
4) Breakers
b. Location: Bureau of Reclamation, Hoover Powerplant Office, Hoover Powerplant, unless otherwise directed by the CO.
c. Meeting length: Anticipated to not exceed 3 days.
d. Purpose: Review with Government personnel electrical drawings, data, and technical requirements of all work required under this contract.
e. Attendees: Responsible engineering representatives who have been fully informed of specifications with respect to technical requirements, equipment to be furnished, and coordination necessary to complete electrical design. Include:
1) Project manager and project engineer from Contractor.
2) Representative from secondary unit substation manufacturer.
3) Representative from prime electrical subcontractor.
f. Electronic drawing file format (DWG) files of electrical design drawings included in these specifications are available. With at least 14 days notice, COR will make these files available to Contractor at pre-design meeting.
g. Provide following preliminary information at meeting:
1) Scope of work.
2) Proposed schedule.
3) Schedule of future Design and Progress Review Meetings. The
Contractor shall furnish a schedule of design and progress meetings.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Project Management and Coordination 01 31 19 - 3
4) Shipping, delivery, storage, installation, and on site assembly procedures. Include and provide:
a) Name and qualifications of manufacturer’s engineer if applicable to be onsite.
b) Considerations to address prevention of shipping damage.
5) Installation procedures in accordance with applicable specifications sections and drawings.
2. Design coordination conference.
a. Date: Approximately 120 days after receipt of Notice to Proceed.
b. Location: Hoover Powerplant Office, Hoover Dam Powerplant.
c. Purpose:
1) Review preliminary design documentation required under submittals:
a) RSN 26 16 14-1, Approval Drawings and Data in
Manufacturer’s Format.
b) RSN 26 16 14-2, Schematic Diagram Drawings in
Government Format.
c) RSN 26 20 10-1, Temporary Power Plan.
d) RSN 26 24 16-1, Approval Data.
e) RSN 26 24 16-2, Approval Layouts.
2) Review with Government personnel electrical drawings, data, and technical requirements of specifications.
3) Discuss interruption of services and project schedule.
4) Review plant and system operations.
5) Review bus modifications for temporary power connections.
6) Temporary power.
d. Attendees:
1) Responsible engineering representatives knowledgeable of technical requirements, equipment to be furnished, and coordination necessary to complete electrical design.
2) Representatives shall include:
a) Contractor.
b) Switchgear manufacturer.
c) Prime electrical subcontractor.
d) Installer of bus.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Project Management and Coordination 01 31 19 - 4
e. Within 30 calendar days after conclusion of conference, Government will furnish Contractor a letter regarding items discussed at conference with enclosed copies of all pertinent drawings and data marked with Government’s comments.
3. Design and Progress Review Meetings:
a. Location: Bureau of Reclamation, Hoover Powerplant Office, Hoover
Powerplant, unless otherwise directed by the CO.
b. Meetings length: Not to exceed 2 hours at each site.
c. Attendees:
1) Project manager and project engineer from Contractor.
2) COR, project managers and project engineers from Hoover
Powerplant.
3) One from prime electrical subcontractor.
d. Purpose:
1) Meet weekly, or any interval at the COR’s discretion, with COR to review progress made to the end date of the progress payment period.
2) Review with Government personnel electrical drawings, data, and technical requirements of specifications.
3) Schedule, Progress, and Coordination:
a) Review safety, progress made, schedule, project issues, submittals, Request for Information (RFI), and resolution necessary to meet specifications requirements.
b) Review dates that activities were started and completed, remaining duration, and percent complete.
c) Review submittals register, submittals currently in review and approval, and meeting submittals due dates or delivery time frames.
4) Discuss design and schedule.
1.05 DAILY WORK REPORT
A. Prepare written daily summary of work report. Include, as a minimum, the following:
1. Report of work performed during the day.
2. Upcoming planned work and associated work schedules.
3. Planned Contractor use of site and access.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Project Management and Coordination 01 31 19 - 5
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Project Management and Coordination 01 31 19 - 6
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Construction Program 01 32 10 - 1
SECTION 01 32 10
CONSTRUCTION PROGRAM
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Costs:
1. Developing Baseline Schedule: Include in lump sum price offered in Price
Schedule A for Mobilization and Preparatory Work.
2. Updating and Using Construction Program: Include as part of Contractor’s overhead.
1.02 DEFINITIONS
A. Schedule: The Critical Path Method (CPM) of planning and scheduling a construction project where activities are arranged based on activity relationships and network calculations determine when activities can be performed and the critical path of the project.
B. Project Calendar(s): Cross reference of numerical work days with calendar days. Project calendars serve as the basis for day/date conversion and assign work days and non-workdays.
C. Resources: Equipment, labor or crews, materials, subcontractors, fabricators, manufacturers, and consultants.
D. Out of Sequence Work: An activity that starts before its predecessor activities are completed.
1.03 REFERENCE STANDARDS
A. Associated General Contractors of America (AGC)
1. AGC Manual Construction Planning and Scheduling
Manual, 2004
1.04 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
1. Furnish database files in format compatible with Microsoft Project (release 2016 or newer).
2. Upon request, provide information and data used to develop and maintain the
Construction Program to the CO.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Construction Program 01 32 10 - 2
B. RSN 01 32 10-1, Representative Information:
1. Designation of authorized representative to develop and maintain Construction
Program. Include resume with training and experience.
C. RSN 01 32 10-2, Baseline Schedule:
1. Include:
a. Construction Program/Schedule database.
b. Definition of project calendars.
c. Gantt chart (Bar chart) for project on 11 by 17-inch print(s) and in portable document format (.pdf).
d. Activity report including logic constraints consisting of predecessors, successors, and constraint dates.
e. Tabular listings of resources and resource limitations used to produce baseline schedule. Correlate resources with schedule assumptions and offered price. Resource listings may be independent of schedule database.
f. Narrative explanation of project schedule development. Include impacts of resource limitations and weather conditions on project schedule development. Include planned number of work hours per day and hours per day for subcontractors.
D. RSN 01 32 10-3, Updated Schedule Reports:
1. This submittal is required for a proper invoice for progress payments in accordance with the clauses at FAR 52.232-27 - Prompt Payment for Construction Contracts and WBR 1452.232-82 - Other Invoice Requirements. In accordance with subparagraph (a)(i)(A) of the clause at FAR 52.232-27 - Prompt Payment for Construction Contracts, Government disapproval of this submittal will be considered failure of the Contractor to comply with contract requirements and payment due date may be delayed until 14 days after submittal contents are approved.
2. Include:
a. Construction Program database with updated activity and milestone data.
b. Definition of project calendars if revised from baseline calendars.
c. Gantt chart for project on 11 by 17-inch print(s) and in portable document format (.pdf).
d. Narrative report specifically stating status of project.
1) When negative float exists, cite specific actions and conditions which caused "behind schedule" condition and provide proposed course of action to complete the project within the specified delivery time. When float changed from previous month’s updated schedule, explain reason for change.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Construction Program 01 32 10 - 3
2) List of Contractor-initiated changes to current schedule stating reason for action taken and unresolved issues relating to the Construction Program. Government reserves the right to reject Contractor-initiated changes to current schedule which negatively impact Government action which was initiated on the basis of current schedule.
3) Discuss contract milestones and significant activities that were started, continued, or completed during the update period or scheduled during the next update period.
e. Submittal Register:
1) List submittals as listed in Table 01 33 00A.
2) Update Submittal Register monthly to include submittals and revised submittals. Register fields shall include RSN name and number, date submitted, date of response, status (e.g., approved, not approved, resubmittal required).
3) This register document is separate from scheduling database.
E. RSN 01 32 10-4, Time Impact Analysis:
1. Include:
a. Construction Program database with proposed revised activity and milestone data.
b. Proposed revised schedule due to change or delay. Highlight or list added, changed, or deleted activities.
c. Gantt chart for project on 11 by 17-inch print(s) and in portable document format (.pdf).
d. Narrative report explaining results and conclusions.
1.05 QUALIFICATIONS
A. Representative: Experienced in developing and maintaining construction schedules and knowledgeable of activities and progress on-site to develop and maintain accurate and reliable schedules.
1.06 GENERAL
A. Develop, maintain, and use Construction Program to plan, monitor, evaluate, and report accomplishment of work.
1.07 SCHEDULES
A. Prepare construction schedules using Critical Path Method outlined in AGC Manual. Use a computer software program to perform mathematical analysis of scheduling data.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Construction Program 01 32 10 - 4
1. Prepare schedule based on required sequence and interdependence of activities.
Logically sequence activities.
2. Prepare detailed activity network for accomplishing required work organized by Work Breakdown Structure (WBS). Utilize WBS in lieu of activity codes for organization of schedule. If activity codes are utilized in addition to WBS, use unique activity code names assigned as project codes rather than global codes.
3. Activities except “Award” shall have predecessor activities and activities except “Contract Complete” shall have successor activities.
4. Meet contract requirements; milestone(s) in accordance with the clause at FAR 52.211-10, Commencement, Prosecution, and Completion of Work; and relevant clauses and specification sections. Include interim milestone dates, Government interface dates, contract completion date, and other time or seasonal constraints specified in contract documents.
5. Include work of subcontractors, Government interfaces, and contract milestones.
6. Adjust Construction Program/schedule for seasonal weather conditions. Provide a narrative explaining the expected weather and plan for incorporation in schedule.
Consider work influenced by high or low ambient temperatures or precipitation.
Utilize Microsoft Project calendars to depict historical weather days that impact work. Assign weather calendars to work impacted by weather.
7. Define activities to level of detail resulting in their durations being no greater than 20 workdays.
a. Durations for administrative activities (e.g., submittals and reviews) fabrication, manufacturing, and typical level of effort activities (e.g., dewatering, storm water management) will not be subject to workday duration limitation.
8. Include separate activities for submittal preparation and submittal reviews when submittal addresses work that involves significant quantities, long lead times, is on the critical path or near critical path, or as requested by the COR. Assign Government submittal review activities to a seven-day calendar with durations as specified in Section 01 33 00 - Submittals. Include Required Submittal Number (RSN) in activity description.
9. Include separate activities for fabrication or manufacturing when work involves significant quantities, long lead times, is on the critical path or near critical path, or as requested by the COR
10. Include contract title, contract number, and Contractor’s name on transmittal cover sheet and each sheet of Gantt chart.
11. For each activity on Gantt chart, display activity identification number, activity description, planned or original duration, start date, finish date, total float, and calendar identification. Do not display early start and late start fields.
12. Include table of abbreviations used in the schedule, listed and defined alphabetically.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Construction Program 01 32 10 - 5
13. Use finish to start logic relationships between activities. Do not utilize start to start, finish to finish, or start to finish logic relationships. Do not use negative lead or lag times.
14. Use durations in units of whole workdays.
15. Provide best estimate of time required to complete activity considering quantity of work, work conditions, location of work, and planned resources for activity.
16. Equate durations of Government reviews and other identified actions to maximum number of calendar days specified in their respective paragraphs.
17. Establish workday calendar(s) and use these in the schedule to translate activity's workday duration into calendar dates. Use unique calendar names; do not use software default calendar names. Save calendars as project calendars, not global calendars.
B. Baseline Schedule:
1. Represents Contractor’s as-planned approach to accomplishing the work. Do not include actual start dates, percent completes, or actual finish dates.
C. Updated Schedule:
1. Meet monthly with COR at Government’s project office, or at a location approved by the COR, to review progress made to end date of progress payment period.
Establish dates that activities were started and completed and remaining duration for each activity started but not completed during the period.
a. Discuss and mutually agree upon changes to the schedule.
b. Out-of-sequence activities are not allowed. Revise logic to reflect change in work plan.
c. Finalize updated Construction Program database with mutually agreed upon changes.
2. Following receipt of executed contract modification, incorporate activity data stipulated in modification into current schedule for inclusion in next scheduled progress update. Provide appropriate logic relationships for revised activities.
3. Assign a unique project file name for each schedule update.
1.08 TIME IMPACT ANALYSIS
A. Provide time impact analysis for contract changes (e.g., change order, proposed modification, or value engineering change proposal) to support a claim or request for equitable adjustment to the contract due to delay or accelerated schedule.
B. The CO may use time impact analysis to determine if time extension or reduction to contract milestone dates is justified.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Construction Program 01 32 10 - 6
1. Time impact analysis is required for contract changes whether the Contractor’s current schedule milestone dates are the same as, earlier than, or later than, those required under the contract.
2. Changes, additions, or deletions to activities; activity durations; activity time frames; or activity predecessors and successors will not automatically determine that extension or reduction of contract time is warranted or due the Contractor.
3. Time extensions for performance will be considered only to the extent that the Contractor’s current scheduled milestone dates exceed contract milestone dates.
C. Float is not for exclusive use by or benefit of either the Government or the Contractor.
D. Perform time impact analyses using data in most recent approved schedule update prior to change or delay event.
1. Prepare proposed revised schedule and narrative description describing and highlighting changes or delays.
2. Prepare summary comparing results of two schedule analyses: One using current schedule data from last approved updated schedule prior to event requiring analysis, and one using proposed schedule data incorporating changes or delays.
a. Show contract milestones and activities whose periods of performance have shifted as result of change which affects production and/or manufacture schedules, material orders, construction seasons, and labor and/or equipment utilization.
b. For activities directly affected by change or delay, include the current and proposed items:
1) Activity description.
2) Types and quantities of major pieces of equipment, principal manpower, and pacing materials (materials that affect activity start, duration, or finish).
3) Activity duration.
4) Narrative containing rationale used in developing the proposed logic relationships and activity data.
c. Data date for impacted schedule used in comparison shall be the same as approved updated schedule data date.
d. Base schedule comparisons on status of work and available float at time the CO directs or proposes change to the work, the Contractor submits a value engineering change proposal, or when a delay occurs as shown in approved updated schedule.
1.09 REVIEW AND EVALUATION
A. Baseline Schedule:
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Construction Program 01 32 10 - 7
1. Within 21 calendar days after receipt of baseline schedule:
a. CO will approve or not approve proposed baseline schedule.
b. Upon request from the CO, meet with COR for a joint review of proposed baseline schedule.
c. If schedule is not approved, revise and resubmit within 7 calendar days following date of rejection letter.
2. Do not proceed with onsite work, except mobilization and surveying, until baseline schedule has been approved by the Government.
B. Updated schedules:
1. Submit updated Construction Program schedule monthly.
2. Submit updated schedule at least seven days prior to the submission of each invoice request for progress payment.
3. If updated schedule is not approved, revise and resubmit updated schedule within
7 calendar days following date of rejection letter.
4. The COR will schedule pre-submittal meeting with the Contractor’s representative each month to review draft updated schedule prior to the Contractor submitting RSN 01 32 10-3, Updated Schedule Reports.
C. Failure to include elements of the work in schedules will not release Contractor from completing required work under the contract.
D. Performance will be evaluated by the Government using approved CPM schedules.
1.10 FAILURE TO COMPLY
A. Failure to comply with requirements of this Section shall be grounds for determination by the CO that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within specified time.
B. The CO may terminate the Contractor’s right to proceed with the work, or separable part of it, in accordance with default terms of this contract.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Construction Program 01 32 10 - 8
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Submittals 01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-2020 Decimal-inch Drawing Sheet Size and
Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-14 United States National CAD Standards, Version 6
1.03 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittal Types, as listed in Table 01 33 00A - List of Submittals:
1. A - Action:
a. Government will respond as to adequacy of submittal.
b. Action Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction.
2. I - Informational:
a. Government will acknowledge receipt of Informational submittals.
b. Government may reject an Informational submittal when the submittal does not satisfy contract requirements. Contractor shall correct mistakes or deficiencies in rejected Informational submittals and resubmit.
c. Informational Submittals: Considered “shop drawings” within terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction, except that approval by Government is not required.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Submittals 01 33 00 - 2
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement Units: US Customary Units.
4. Provide a unique transmittal number for each submittal.
C. Drawings:
1. Minimum Identification in Title Block:
a. Contract number and title.
b. Contractor’s or supplier’s company name.
c. Drawing title and number.
d. Date.
e. As shown on standard drawing 40-D-7102.
f. Title block and other Government blocks shall not be exploded, renamed, or modified unless directed by the CO.
g. Government will supply title block template in electronic drawing file format.
h. Use the Contents and Details text blocks in the title block to summarize the information provided on the drawing:
i. Contents: What is on the drawing.
j. Details: How the information is drawn
2. Reserve 3- by 3-inch space next to title block for review stamps.
3. Size:
a. D size (22 inches by 34 inches) as defined by ASME Y14.1.
b. Half size (11 inch by 17 inch).
4. Draw to scale using computer drafting:
a. In accordance with NIBS NCS.
b. Electronic drawing file format (DWG): Compatible with AutoCAD, Version 2015 or later.
c. Compile using “eTransmit” utility in AutoCAD.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Submittals 01 33 00 - 3
d. Include electronic file in portable document format (PDF) created from the electronic drawing file.
D. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
E. Certifications:
1. Certifications by a Registered Professional: Signed and sealed by registered professional.
2. Manufacturer’s Certifications: Signed by authorized representative of manufacturer.
F. Photographs:
1. Prints: Professional quality 8-inch by 10-inch color for each listed view.
a. Identify with adhesive labels on back.
1) Include contract number, name of equipment and view title.
2) Do not type directly on back of photograph.
2. Include negatives, or digital files on CD or DVD in .jpeg or similar format.
G. Manuals:
1. Copies:
a. Printed copies: Bound and indexed.
b. Electronic copies: Adobe pdf on CD or DVD discs.
1) Bookmark longer files to assist in navigating file.
2. Contents:
a. Parts identification lists, lists of special tools, and accessories.
b. Schematics and wiring diagrams.
c. Detailed instructions for installing, operating, lubricating, and maintaining equipment.
d. As-built drawings, photographs, and test records or reports if required by the specifications.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Submittals 01 33 00 - 4
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes listed items for RSNs with multiple parts.
C. Submit sets specified in “Sets to be sent:” columns in Table 01 33 00A - List of Submittals.
1. Electronic submittals:
a. In Portable Document Format (.pdf).
b. Include RSN transmittal letter.
c. Do not include Personally Identifiable Information (PII) in electronic submittals.
d. Submittal method (sized based):
1) Government can receive e-mails up to 10 MB. Receipt of e-mails exceeding 10 MB (extra-large) may be possible. Extra-large electronic submittals may occur only after the process and size limit for transmittal of extra-large electronic submittals have been verified by COR.
2) Submittals too large to be electronic transmittal: CD or DVD or by other means approved by the COR.
D. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for each attached submittal.
3. Responsible code.
4. Number of sets for each RSN.
5. Identify submittal as initial or resubmittal.
E. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 28 days after receiving the comments, unless otherwise directed.
4. Requirements for initial submittals apply to resubmittals.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Submittals 01 33 00 - 5
F. More than one RSN may be submitted under a transmittal letter, provided responsible code is same.
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 28 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.
B. Time in Excess of Specified:
1. CO may extend contract completion date to allow additional time for completing work affected by excess review time.
a. Time extension will be to extent that excess review time caused delay to contract completion date.
b. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.
2. No time extension will be allowed if Contractor fails to make complete action submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to the extent that:
a. Approval was required under the contract, and.
b. Requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of clause at FAR
52.242-14, Suspension of Work; however, no such delay shall be deemed to be a “suspension order” as term is used in that clause.
C. Return of Submittals:
1. Return of submittals will be by electronic response or hard copy, as applicable.
2. Action Submittals: 1 set of submittals required for action will be returned either approved, approved with comments or not approved.
a. Revise and resubmit submittals not approved.
b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Submittals 01 33 00 - 6
3. Informational Submittals: Government will acknowledge Informational submittals.
a. Informational submittals will not be returned when they satisfy contract requirements.
b. Informational submittals that do not satisfy contract requirements may be returned for resubmittal or additional information may be requested.
1.07 HARD COPY TRANSMITTALS
A. Addresses for codes listed in Table 01 33 00A – List of Submittals:
1. Contracting Officer, Bureau of Reclamation, Attn: LC-1000, Lower Colorado
Regional Office, 500 Fir Street, Boulder City, NV 89005-2403.
2. Contracting Officer’s Representative, Bureau of Reclamation, Attn: LC-1000, Lower Colorado Regional Office, 500 Fir Street, Boulder City, NV 89005-2403.
3. Technical Service Center, Bureau of Reclamation, Attn: 86-68160, P.O. Box
25007, Denver CO 80225-0007; Express Mail: Sixth and Kipling, Building 67, Room 152.
B. Electronic submittals listed in Table 01 33 00A – List of Submittals:
1. Government contact information will be provided to the Contractor after award.
C. Send original transmittal letter with appropriate number of sets to office listed in “Responsible Code” column in Table 01 33 00A – List of Submittals.
1. Responsible codes starting with “86-6” are located in Technical Service Center.
Send these submittals to the TSC address shown above.
D. Send copy of transmittal letter with appropriate number of sets to offices that are not responsible code, but show “Sets to be sent” in Table 01 33 00A – List of Submittals.
E. When “Sets to be sent” is 0, send a copy of transmittal letter to that office.
F. Submittals required by specifications, but not listed in Table 01 33 00A – List of Submittals:
1. Submit in accordance with this section.
2. Submit to COR, unless otherwise specified.
PART 2 PRODUCTS
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Submittals 01 33 00 - 7
PART 3 EXECUTION
Not Used
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative, and TSC indicates Technical Service Center.
Sets to be sent: **
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code CO COR TSC
01 14 10-1 Use of Site Land Use And Landscape Rehabilitation Plan
At least 28 days before use of Government land
A COR Electronic
01 14 30-1 Interruption of Service
Interruption of Service Request
At least 45 days before each interruption of service request
A COR Electronic
01 31 19-1 Project Management and Coordination
Pre-Design Meeting Notification
At least 15 days before pre-design meeting
A COR Electronic
01 31 19-2 Project Management and Coordination
Design Coordination Conference Confirmation
At least 28 days before design coordination conference
I COR Electronic
01 31 19-3 Project Management and Coordination
Design and Progress Review Meeting Notification
At least 14 days before beginning design and progress review meeting
I COR Electronic
01 31 19-4 Project Management and Coordination
Daily Work Report Daily I COR Electronic
01 32 10-1 Construction Program
Representative Information
Within 7 days after receipt of Notice of Award
I COR Electronic
01 32 10-2 Construction Program
Baseline Schedule Within 21 days after receipt of Notice to Proceed
A COR 1 3 3
01 32 10-3 Construction Program
Updated Schedule Reports
With monthly requests for progress payments.
A COR Electronic
Boulder Canyon Project, Arizona, Nevada Solicitation No.
Submittals 01 33 00 - 8
Table 01 33 00A. - List of Submittals
* Submittal Types: A - Action, I - Information ** CO indicates Contracting Officer, COR indicates Contracting Officer’s Representative, and TSC indicates Technical Service Center.
Sets to be sent: **
RSN
Clause or
Section Title
Submittals required Due date or delivery time
Type
Respon-sible code CO COR TSC
01 32 10-4 Construction Program
Time Impact Analysis
Within 28 days after the CO directs a contract change with schedule impacts.
Or
With proposal for future modification, value engineering proposal, or request or claim for equitable adjustment to the contract.
A COR Electronic