Sol_140R2024R0015_Amd_0001.pdf
PDF 88 KB Posted
- Solicitation number
- 140R2024R0015
About this file
This is Amendment 01 to solicitation 140R2024R0015 for Phase II of the B.F. Sisk Dam Safety of Dams (SOD) Modifications project, issued by the Bureau of Reclamation's Mid-Pacific Region in Sacramento, CA.
The amendment extends the performance period from 1,095 days to 1,350 days and adds several new attachments to Section J, including: Virtual Site Visit Attendance (3DEC24), Virtual Presentation (3DEC24), In Person Site Visit Sign In Sheet (4DEC24), In Person Site Visit Agenda (4DEC24), Price Schedule in Excel format, and CAD Files (available via Kiteworks link upon email request to Roxana Ahola at rahola@usbr.gov with cc to Abelardo Lopez at aclopez@usbr.gov).
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140R2024R0015 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Sacramento CA 95825-1898 2800 Cottage Way, Room E-1815
R20
Division of Acquisition Services Regional Office Mid-Pacific Region Bureau of Reclamation
11/12/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
11/12/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
A. TITLE: B. F. Sisk Dam SOD Modifications, Phase II
B. PURPOSE: The purpose of this amendment is to incorporate various changes to solicitation documents.
C. DESCRIPTION: Amendment 01 Description of Changes:
1) Standard Form 1442, box 11 is revised from 1,095 to 1,350 days.
2) Section F number of days is revised from 1,095 to 1,350.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140R2024R0015/0001
3) Section J - New Incorporated Attachments:
Attachment 13 - Virtual Site Visit Attendance
3DEC24
Attachment 14 - Virtual Presentation 3DEC24
Attachment 15 - In Person Site Visit Sign In
Sheet 4DEC24
Attachment 16 - In Person Site Visit Agenda 4DEC24
Attachment 17 - Price Schedule in Excel
Attachment 18 - CAD Files (this attachment is available under separate cover. To request, please email Roxana Ahola at rahola@usbr.gov and cc: Abelardo (Carlos) Lopez at aclopez@usbr.gov to request the Kiteworks link.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .