Attachment_17_-_Price_Schedule_in_Excel_0001.xlsx
XLSX spreadsheet 13 KB Posted
- Solicitation number
- 140R2024R0015
About this file
This is a price schedule template in Excel format for Phase II of the B.F. Sisk Dam SOD Modifications project managed by the Bureau of Reclamation. The schedule contains 59 Contract Line Item Numbers (CLINs) covering various construction and maintenance activities including mobilization, site security, traffic control, environmental protection, excavation work, and infrastructure components.
Key elements include significant earthwork operations (14 million cubic yards of Zone 8 miscellaneous fill), drainage system installations, monitoring equipment, and environmental management tasks such as dust control and stormwater pollution prevention. The schedule also encompasses specialized items like Tule Elk herd management, dewatering systems, and slope stability monitoring. Items are priced either as lump sum amounts or unit prices with specific quantities, such as 780 acres of clearing and grubbing, 502 linear feet of temporary inclinometer casings, and various volumes of different fill materials and construction aggregates.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| PRICE SCHEDULE | |||||
| CLIN | Section | Supplies or Services | Quantity and Unit | Unit Price | Amount |
| 1 | WBR 1452.232-81 | Mobilization and Preparatory Work | For the lump sum of | $ | |
| 2 | 01 31 30 | Contract Document Management System (CDMS) | For the lump sum of | $ | |
| 3 | 01 35 50 | Site Security | For the lump sum of | $ | |
| 4 | 01 52 10 | Government Field Office Maintenance | For the lump sum of | $ | |
| 5 | 01 52 14 | Government Field Laboratory Facility Maintenance | For the lump sum of | $ | |
| 6 | 01 55 28 | Temporary Post-Mounted Traffic Signs | For the lump sum of | $ | |
| 7 | 01 56 32 | Temporary Safety Fence | For the lump sum of | $ | |
| 8 | 01 56 34 | Exclusion Fence | For the lump sum of | $ | |
| 9 | 01 57 30 | Stormwater Pollution Prevention Plan (SWPPP) General Requirements | For the lump sum of | $ | |
| 10 | 01 83 13 | Project Monitoring | For the lump sum of | $ | |
| 11 | 02 01 80 | Tule Elk Herd Management | For the lump sum of | $ | |
| 12 | 05 50 00 | Metal Fabrications (Miscellaneous Metalwork) | For the lump sum of | $ | |
| 13 | 10 14 54 | New Post-Mounted Project Signs | For the lump sum of | $ | |
| 14 | 31 02 10 | Water for Dust Abatement | For the lump sum of | $ | |
| 15 | 31 02 30 | Dust Palliative | For the lump sum of | $ | |
| 16 | 31 03 33 | Unwatering | For the lump sum of | $ | |
| 17 | 31 03 33 | Temporary Observation Sumps | 3 sumps | $ | $ |
| 18 | 31 03 33 | Dewatering Sumps | 9 sumps | $ | $ |
| 19 | 31 03 33 | Supplementary Dewatering Sumps Materials | 3 sumps | $ | $ |
| 20 | 31 03 33 | Supplementary Dewatering Sumps Installation/Removal | 3 sumps | $ | $ |
| 21 | 31 03 33 | Dewatering Sump Operation | For the lump sum of | $ | |
| 22 | 31 09 10 | Abandoning and Removing Existing Instrumentation | For the lump sum of | $ | |
| 23 | 31 09 12 | Temporary Inclinometer Casings | 502 lin ft | $ | $ |
| 24 | 31 09 13 | Slope Stability Monitoring Service | For the lump sum of | $ | |
| 25 | 31 09 22 | Protecting Existing Instrumentation | For the lump sum of | $ | |
| 26 | 31 09 25 | Vibrating-Wire Piezometers | 8 vibrating-wire pie- zometers | $ | $ |
| 27 | 31 11 00 | Clearing and Grubbing | 780 acres | $ | $ |
| 28 | 31 14 10 | Stripping | 700,000 yd3 | $ | $ |
| 29 | 31 23 11 | General Excavation | 86,000 yd3 | $ | $ |
| 30 | 31 23 14 | Excavation of Rock Blanket Material | 310,000 yd3 | $ | $ |
| 31 | 31 23 17 | Excavation of Shear Key | 120,000 yd3 | $ | $ |
| 32 | 31 23 21 | Stockpiling of Riprap | 50,000 yd3 | $ | $ |
| 33 | 31 23 22 | Constructing Haul Roads | For the lump sum of | $ | |
| 34 | 31 23 25 | Relocating Existing Maintenance Yard Equipment | For the lump sum of | $ | |
| 35 | 31 23 70 | Controlled Low Strength Material | 100 yd3 | $ | $ |
| 36 | 31 24 13 | Zone 1, Impervious Fill | 4,700 yd3 | $ | $ |
| 37 | 31 24 14 | Zone 9A, Sand Filter | 50 yd3 | $ | $ |
| 38 | 31 24 14 | Zone 9C, Separator | 310,000 yd3 | $ | $ |
| 39 | 31 24 15 | Zone 11, Gravel Drain | 440,000 yd3 | $ | $ |
| 40 | 31 24 16 | Zone 8, Miscellaneous Fill | 14,000,000 yd3 | $ | $ |
| 41 | 31 24 17 | Zone 10, Shear Key Rockfill | 47,000 yd3 | $ | $ |
| 42 | 31 24 18 | Downstream Rock Blanket Material | 270,000 yd3 | $ | $ |
| 43 | 31 32 32 | Non-Woven Geotextile | 4,200 yd2 | $ | $ |
| 44 | 32 10 16 | Remove Existing Asphalt Pavement and Base Course | 660 yd3 | $ | $ |
| 45 | 32 11 23 | Aggregate Base Course | 500 yd3 | $ | $ |
| 46 | 32 12 22 | Asphalt Concrete Pavement | 500 yd3 | $ | $ |
| 47 | 32 12 30 | Gonzaga Road Maintenance | For the lump sum of | $ | |
| 48 | 32 15 10 | Gravel Surfacing | 6,000 yd2 | $ | $ |
| 49 | 32 31 10 | Chain Link Fence | 220 lin ft | $ | $ |
| 50 | 32 31 10 | Removal and Disposal of Existing Chain Link Fence | 300 lin ft | $ | $ |
| 51 | 32 91 19 | Topsoil | 920 acres | $ | $ |
| 52 | 32 92 20 | Restoration and Revegetation | 920 acres | $ | $ |
| 53 | 33 05 16 | Precast Concrete Box Culvert | For the lump sum of | $ | |
| 54 | 33 05 31 | Inspection Wells | For the lump sum of | $ | |
| 55 | 33 29 04 | Removing Existing Toe Drain Pipes | 250 lin ft | $ | $ |
| 56 | 33 46 36 | 12-inch Diameter Perforated HDPE Pipe | 870 lin ft | $ | $ |
| 57 | 33 46 36 | 12-inch Diameter Nonperforated HDPE Pipe | 470 lin ft | $ | $ |
| 58 | 33 46 36 | Drain Cleanouts | 2 drain cleanouts | $ | $ |
| 59 | 33 46 42 | Weir Boxes | For the lump sum of | $ |