Attachment_1_Amendment_No_0004_0004.pdf
PDF 1 MB Posted
- Attached to
- FKC Middle Reach Capacity Correction Project Phase Federal contract opportunity
- Solicitation number
- 140R2020R0009
About this file
This document provides a submittal register for the FKC Middle Reach Capacity Correction Project Phase 1 solicitation issued by the Department of the Interior Bureau of Reclamation. The register outlines fourteen required submittals including construction constraints and sequencing plans, a land use and landscape rehabilitation plan, environmental mitigation and compliance training logs, and a detailed schedule of values. Submittals are due to the construction engineer and government approved reviewer within timeframes ranging from 14 days to 60 days following contract award or before starting certain onsite work. One hard copy of each submittal is to be provided using the construction document management system. The register specifies the responsible party, review authority, and number of copies required for each submittal item.
View the file
Other files for this federal contract opportunity
Show all 50
FKC Middle Reach Capacity Correction Project Phase has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No: 140R2020R0009 Specifications No. 20-C0907
STANTEC/184031016 SUBMITTALS
FKC MIDDLE REACH CAPACITY CORRECTION PROJECT PHASE 1 PAGE 01 33 00 - 12
Table 01 33 00A – List of Submittals *CE indicates Construction Engineer, OGR indicates Onsite Government Representative, GAR indicates Government Approved Reviewer, and FWA indicates Friant Water Authority. One hard copy of each CDMS RSN shall be sent to the CE.
RSN Section Title Submittals Required
Due Date or Delivery Time
Responsible Code
No. of sets to be sent to:*
CE OGR GAR FWA
01 14 00-8 Construction Constraints and Sequencing
Permanent Piping Connection at new Roadway Siphons
Submitted at least 2 months before scheduled activity and approved before starting associated work
GAR CDMS
01 14 00-9 Construction Constraints and Sequencing
Permanent Piping Connection at canal conflicts at the new Canal
Submitted at least 2 months before scheduled activity and approved before starting associated work
GAR CDMS
01 14 00-10 Construction Constraints and Sequencing
Utility Removal Plan
Submitted at least 2 months before scheduled activity and approved before starting associated work
GAR CDMS
01 14 00-11 Construction Constraints and Sequencing
Pothole Plan Submitted within 60 days of NTP and approved before starting onsite work
GAR CDMS
01 14 00-12 Construction Constraints and Sequencing
Pothole Report Submitted within 30 days after potholing is conducted
GAR CDMS
01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan
Submitted and approved before starting onsite work
CE CDMS
01 29 73-1 Schedule of Values
Detailed Schedule of Values
Submitted and approved before first payment
CE CDMS
01 30 00-1 Environmental Mitigation and Compliance
WEAT and Paleontological Resources Awareness Training Logs
Submitted within 7 days of completing training for all construction personnel
CE CDMS
01 30 00-2 Environmental Mitigation and Compliance
Clean Construction Equipment
Submitted at least 60 days before starting onsite construction
CE CDMS
Attachment 1 Amendment No 0004 swolfert Text Box Submitted within 14 Days following the date of the Post Award conference.