This document provides specifications for coatings for concrete to be used in the Hungry Horse Dam Drainage Sump Pump System Replacement project for the Bureau of Reclamation. The specifications include requirements for submittals such as product data, samples, qualifications, quality control plans, and testing reports for the coating materials. The coatings must meet MPI specification requirements and be delivered, stored, and applied according to the manufacturer's recommendations, including maintaining proper environmental conditions during surface preparation and curing. This project is being procured under solicitation number 140R1021B0008 for the replacement of drainage sump pumps at Hungry Horse Dam.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Hungry Horse Dam Drainage Sump Pump System Replacement Hungry Horse Project, Montana Amendment No. 001
Coatings for Concrete (Revised) 09 91 10 - 2
E. US. Green Building Council (USGBC)
1. Green Building Program (LEED) www.leedbuilding.org
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 09 91 10-1, Approval Data:
1. For each coating material:
a. Manufacturer’s product data, application, and MSDS sheets.
b. Supplier’s name, address, and phone number.
c. Identification of “Items to be coated” including sub-letter and sub-number listed in Coating Tabulations.
d. Manufacturer’s certification that material meets MPI specification requirements.
2. For each substituted coating material “equal” to specified product in Coating Tabulation:
a. List of not less than 3 similar successful material applications:
1) Project name, location, type of structure, and application dates.
2) Owner’s name, address, and telephone number.
b. Certification that material meets or exceeds specified requirements:
1) Manufacturer’s certification including technical representative’s signature and date of signature.
2) Independent laboratory’s certified test reports.
C. RSN 09 91 10-2, Final Approval Data:
1. For each coating material and thinner:
2. Purchase orders including order number, date, manufacturer’s designated product name, batch number(s), and quantity purchased.
D. RSN 09 91 10-3, Paint Chip Samples:
1. Color chip samples approximately 4 by 6 inch.
2. Label each sample. Include manufacturer’s designated product name; color; and gloss.
E. RSN 09 91 10-4 Qualifications:
1. Deleted
2. Coating applicator:
Hungry Horse Dam Drainage Sump Pump System Replacement Hungry Horse Project, Montana Amendment No. 001
Coatings for Concrete (Revised) 09 91 10 - 3
a. Deleted
b. List of not less than 3 comparable jobs for each coating type including owner’s name, address, and telephone number.
3. Deleted
F. RSN 09 91 10-5, Quality Control Plan:
1. Quality Control Manager:
a. Name and title.
2. Quality Control Procedure:
a. Quality control plan.
b. Procedure for addressing identified non-conformities.
G. RSN 09 91 10-6, Contractor Quality Testing Report:
1. Comprehensive report of daily quality control test reports.
1.04 DELIVERY, STORAGE, HANDLING
A. Deliver materials to jobsite in original, undamaged, unopened containers labeled with manufacturer’s name, designated product name, batch number, date of manufacture, and any special instructions.
B. Deliver materials in containers not larger than 5 gallons as packaged by manufacturer unless suitable equipment is provided at jobsite to handle and thoroughly mix materials in larger containers.
C. Store coating materials and thinners in accordance with the manufacturer's recommendations, and as a minimum, store off the ground, under cover, and at 50 to 95 degrees F.
D. Do not use coating material which has exceeded manufacturer’s specified storage stability period (shelf life).
1.05 AMBIENT CONDITIONS
A. Maintain environmental conditions to meet coating manufacturer’s requirements during surface preparation, coating application, and curing period. Provide heating or cooling,