Sol_140PP027R0015_Amd_0002.pdf
PDF 208 KB Posted
- Attached to
- MORA-ADM NEW CAMP MUIR GUIDE BLDGS
- Solicitation number
- 140PP027R0015
- Issued by
- Not on record
About this file
This is Amendment 0002 to Solicitation 140PP027R0015, issued by the National Park Service (NPS) ConOps West 1 office in Denver, Colorado on November 2, 2026. The amendment is not extended and applies to the demolition and construction of climbing facilities at Camp Muir in Mount Rainier National Park (MORA). The contract is a firm fixed price award with a period of performance from January 15, 2027 to January 14, 2028.
The amendment includes questions and answers addressing project specifications. Question 1 clarifies helicopter flight day accounting: when both a medium-lift and light passenger helicopter operate on the same calendar day, it counts as one project flight day on the schedule but logs and bills as two separate aircraft days (one per tail number). An aggregate flight-hour limit applies outside the stated 8:00 AM to 4:00 PM operating window, with total flight hours capped by the overall project task order and standard DOI/OAS and FAA daily pilot limits (typically 7-8 flight hours per 24-hour period). Question 2 addresses structural steel fabricator qualifications: the government will accept an experienced structural steel fabricator without IAS AC172 accreditation if AWS D1.1-qualified welders, documented quality-control procedures, and independent third-party shop inspections are utilized. Key contacts include Contracting Officer Juan Roman (juan_roman@ios.doi.gov), Contract Specialist Janet Milson (janet_milson@ios.doi.gov), and Contracting Officer's Representative Josh Boisvert (josh_boisvert@nps.gov).
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Juan Roman
See continuation page
NPS ConOps West 1 1 Denver Federal Center, Building 85 P.O. Box 25287 Denver CO 80225-0287
PW1
140PP027R0015
11/02/2026
11/02/2026
1 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140PP027R0015/0002
Mount Rainier National Park (MORA)
Demolition/Construction of Climbing Facilities at Camp Muir. specifications.
QUESTIONS AND ANSWERS:
Question 1: The site-visit transcript, pages 4 and 6, describes nine helicopter flight days as a strong environmental planning allowance. If a medium-lift helicopter and a light passenger helicopter both operate on the same calendar day, does that count as one project flight day or two aircraft days? Please also clarify whether the allowance has an aggregate flight-hour limit beyond the stated 8 AM to 4
PM operating window.
Answer: Flight Days: Both helicopters operating on the same day counts as one project flight day on the schedule, but logs and bills as two separate aircraft days (one per tail number).
Flight-Hour Limits: Yes, an aggregate limit still applies outside the 8:00 AM ¿ 4:00 PM window. That window just sets the local operating timeframe¿total flight hours are still capped by the overall project task order and standard DOI/OAS and FAA daily pilot limits
(usually 7¿8 flight hours per 24-hour period).
Question 2: Section 05 12 00, Paragraphs 3.02.I and 3.03.C require structural steel fabricators to hold IAS AC172 accreditation. Would the government consider accepting an experienced structural steel fabricator without IAS AC172 accreditation, provided AWS D1.1-qualified welders, documented quality-control procedures, and independent third-party shop inspections are utilized?
Answer: Yes, In lieu of IAS AC172 accreditation, an experienced structural steel fabricator is acceptable with AWS
D1.1-qualified welders, documented quality-control procedures, and independent third-party shop inspections are utilized.
Continued...
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140PP027R0015/0002
Period of Performance: 01/15/2027 to
01/14/2028
FIRM FIXED PRICE
CO - Juan Roman juan_roman@ios.doi.gov
CS - Janet Milson janet_milson@ios.doi.gov
COR - Josh Boisvert josh_boisvert@nps.gov
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .